Hanging beam device
By designing a double-layer rotatable lifting beam device to connect to the driving, the lifting capacity is improved to 1,200 tons, solving the problem that the existing technology cannot meet the high tonnage lifting, and achieving cost savings and improvements in rotational capacity.
Patent Information
- Application Number
- CN202420455355.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-08
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2034-03-08
AI Technical Summary
The existing maximum lifting truck can only lift 700 tons, which cannot meet the lifting needs of 852 tons Guohe No. 1 evaporator. The existing solutions are high in cost or low in usage.
A lifting beam device is designed, including main beam, end beam, short beam and slewing mechanism, which is connected to the driving through a double-layer rotatable structure of the main beam and end beam, which improves the lifting capacity, and uses the slewing mechanism to cooperate with the ground forklift to achieve 360-degree rotation. Reduce costs.
The lifting capacity has been improved to 1,200 tons, saving costs, and 360-degree rotation has been achieved, meeting the lifting needs of large-scale products, and improving the lifting capacity of the factory.
Smart Images

Figure CN222225710U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of lifting equipment slings, and in particular relates to a hanging beam device. Background Art
[0002] The Guohe No. 1 evaporator weighs 852 tons after completion, with a total length of about 26 meters, an upper outer diameter of φ6398mm, and a lower outer diameter of φ4869mm. After the product is assembled, it needs to be transferred multiple times at different workstations and rotated at different angles to meet the final machining requirements after water pressure. To complete the manufacturing of this target product, a lifting capacity of no less than 852 tons is an indispensable condition, but the existing maximum lifting crane is 700 tons, which cannot meet the lifting requirements of this product.
[0003] To meet the lifting requirements of target products, there are two main existing solutions / techniques:
[0004] One is to add a large-tonnage crane of at least 900 tons to perform lifting and horizontal rotation. However, the plan to add a large-tonnage crane of 900 tons requires a one-time investment of about 12 million yuan, with only two target products, a low crane utilization rate and a high investment cost.
[0005] The second is to design and manufacture a non-standard rotating platform of at least 900 tons, drive the target product to rotate horizontally through the rotating platform, and then use a large-tonnage truck crane to lift it. However, the rotating platform occupies a large production area in the workshop, the number of target products is small, the utilization rate is low, and the height position of the truck crane in the workshop is limited. Utility Model Content
[0006] In order to overcome the above-mentioned shortcomings of the prior art, the purpose of the utility model is to provide a hanging beam device.
[0007] The technical solution adopted by the utility model to solve its technical problems is:
[0008] A beam hanging device comprises a main beam, an end beam, a short beam and a slewing mechanism;
[0009] The short beam is rotatably matched with the main beam through the slewing mechanism, and a hanging rope seat assembly for connecting a hanging rope is provided on the short beam;
[0010] One end of the main beam is provided with a rope seat for connecting the crane suspension rope, and the other end is rotatably matched with the end beam, and the end beam and the main beam are arranged vertically relative to each other;
[0011] Rope seats for connecting the crane suspension ropes are provided at both ends of the end beam.
[0012] Preferably, the slewing mechanism comprises a hook fork, the upper end of the hook fork is rotatably cooperated with the main beam, the lower end of the hook fork extends into the short beam, and the lower end of the hook fork is provided with a hanging shaft, and the hanging shaft is connected to the short beam.
[0013] Preferably, the upper end of the hook fork is a cylinder, and a thrust spherical roller bearing and a slewing support bearing are provided on the upper end of the hook fork, and the thrust spherical roller bearing and the slewing support bearing are provided on the main beam.
[0014] Preferably, the side wall of the short beam is provided with a through hole corresponding to the hanging shaft, and the hanging shaft is inserted and arranged along the radial direction of the hook fork.
[0015] Preferably, the rope seat assembly includes a fixed axis passing through the short beam, the side wall of the short beam is provided with a rope seat body, the rope seat body cooperates with the fixed axis, the rope seat body is provided with a rope groove, a bolt member is provided at the notch of the rope groove, and one end of the bolt member is connected to the side wall of the short beam.
[0016] Preferably, the short beam is in the shape of an inverted triangle structure, and the rope seat assembly is symmetrically arranged at both ends of the bottom of the short beam.
[0017] Preferably, a matching groove is provided at the other end of the main beam, and the end beam matches with the matching groove.
[0018] Preferably, a rotating shaft is provided at the other end of the main beam, one end of the rotating shaft is located in the matching groove, and a rotating groove matching with the rotating shaft is provided at the middle position of the end beam.
[0019] Preferably, a plurality of pulley members are provided on the rope seat.
[0020] Preferably, balance and eccentric weight indicator needles are provided on the main beam and the short beam.
[0021] Compared with the prior art, the beneficial effects of the utility model include:
[0022] The lifting beam device of the present application has a double-layer rotatable structure, which is connected to two cranes with lifting capacities through the lifting rope seats of the main beam and the end beam. This can improve the overall lifting capacity. For example, the lifting capacities of a heavy-span crane of 700 tons and a double-trolley crane of 350 tons can be combined to increase the maximum heavy-span lifting capacity from 700 tons to 1,200 tons. Compared with the solution of adding a crane of more than 900 tons, it greatly saves costs.
[0023] The slewing mechanism is also set up. When adjusting the rotation, the crane is used to lift the beam device. The beam device lifts the workpiece. When it is close to the ground, it can cooperate with the ground forklift and the sling to pull one end of the workpiece for traction. With the assistance of the forklift, the workpiece can be pulled to achieve a 360-degree rotation and U-turn, and can achieve forward and reverse rotation. Compared with the motor-driven automatic rotation solution, it also saves costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0025] Figure 1 It is a schematic diagram of the utility model connected with the bracket.
[0026] Figure 2 It is a schematic diagram of the end beam of the utility model.
[0027] Figure 3 It is a schematic diagram of the connection between the slewing mechanism and the short beam of the utility model.
[0028] Figure 4 This is a structural diagram of the rope seat assembly of the utility model
[0029] Figure 5 It is a schematic diagram of the hanging rope scheme of the utility model.
[0030] Figure 6 It is a three-dimensional schematic diagram of the utility model.
[0031] in:
[0032] 1-main beam, 2-end beam, 3-short beam, 4-hook fork, 5-hanging shaft, 6-thrust spherical roller bearing, 7-slewing support bearing, 8-fixed shaft, 9-hanging rope seat, 10-bolt part, 11-matching groove, 12-rotating shaft part, 13-rotating groove, 14-hanging rope seat, 15-balance and eccentric weight indicator needle, 16-workpiece, 17-bracket, 18-long rope, 19-short rope, 20-shackle. DETAILED DESCRIPTION
[0033] In order to more clearly understand the above-mentioned purposes, features and advantages of the utility model, the utility model is described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that, in the absence of conflict, the embodiments of the present application and the features in the embodiments can be combined with each other. In the following description, many specific details are set forth in order to fully understand the utility model, and the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0034] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention.
[0035] Example:
[0036] like Figure 1-6 As shown, in this embodiment, a beam hanging device is provided, including a main beam 1, an end beam 2, a short beam 3 and a slewing mechanism;
[0037] The short beam 3 is rotatably matched with the main beam 1 through a slewing mechanism. A rope seat assembly for connecting a rope is provided on the short beam 3. The connecting rope is used to connect a workpiece 16, namely, a steam generator.
[0038] A rope seat 14 for connecting a crane suspension rope is provided at one end of the main beam 1, and the other end is rotatably matched with the end beam 2, and the end beam 2 is vertically arranged relative to the main beam 1;
[0039] Both ends of the end beam 2 are provided with rope seats 14 for connecting the crane suspension ropes.
[0040] The lifting beam device of the present application has a double-layer rotatable structure, which is connected to two cranes with lifting capacities through the rope seat 14 of the main beam 1 and the rope seat 14 of the end beam 2. This can improve the overall lifting capacity. For example, the lifting capacities of a heavy-span 700-ton crane and a 350-ton double-trolley crane can be combined to increase the maximum heavy-span lifting capacity from 700 tons to 1,200 tons. Compared with the solution of adding a crane of more than 900 tons, it greatly saves costs.
[0041] The slewing mechanism is also provided. When adjusting the rotation, the crane is used to lift the beam device. The beam device lifts the workpiece. When the workpiece is close to the ground, the ground forklift and the sling can be used to pull one end of the workpiece. With the assistance of the forklift, the workpiece 16 can be pulled to achieve a 360-degree rotation and U-turn, and forward and reverse rotation can be achieved. Compared with the motor-driven automatic rotation solution, it also saves costs.
[0042] When the hanging beam device is stored, the bracket 17 can be used for support.
[0043] The slewing mechanism of the present application includes a hook fork 4, the upper end of the hook fork 4 is rotatably matched with the main beam 1, the lower end of the hook fork 4 extends into the short beam 3, and the lower end of the hook fork 4 is provided with a hanging shaft 5, which is connected to the short beam 3.
[0044] Specifically, the upper end of the hook fork 4 is a cylinder, and a thrust spherical roller bearing 6 and a slewing support bearing 7 are provided on the upper end of the hook fork 4 . The thrust spherical roller bearing 6 and the slewing support bearing 7 are provided on the main beam 1 .
[0045] Specifically, the side wall of the short beam 3 is provided with a through hole corresponding to the hanging shaft 5 , and the hanging shaft 5 is inserted and arranged along the radial direction of the hook fork 4 .
[0046] Specifically, the rope seat assembly includes a fixed shaft 8 passing through the short beam 3, and the side wall of the short beam 3 is provided with a rope seat body 9, the rope seat body 9 cooperates with the fixed shaft 8, the rope seat body 9 is provided with a rope groove, and a bolt member 10 is provided at the notch of the rope groove, and one end of the bolt member 10 is connected to the side wall of the short beam 3.
[0047] Specifically, the short beam 3 is in the shape of an inverted triangle structure, and the rope seat assemblies are symmetrically arranged at the two ends of the bottom of the short beam 3 .
[0048] The hanging rope connected to the hanging rope seat assembly of the present application adopts a hanging rope scheme of long rope 18 and short rope 19. Combined with the overall height of the workshop, the target product country and the diameter of the No. 1 evaporator, the height of the cross-domain obstacle, the height of the hanging beam itself, the safety angle of the hanging rope and other comprehensive factors are analyzed to draw a simulation diagram of the hanging rope setting. At the same time, in order to reduce the difficulty of hanging the hanging rope at high altitude, the hanging rope is finally set to a length configuration scheme of a 5m short rope 19 and a 16m long rope 18. The hanging rope connection is completed by a shackle 20 above the side of the workpiece 16 and in a position accessible by a forklift, which not only facilitates the connection of the hanging rope, but also avoids the shackle from crushing the surface of the workpiece 16. Due to the limitation of the lifting height requirement, a very long hanging rope cannot be used, and the hanging beam is lowered to the ground near the side of the workpiece 16 for hooking; if a shorter hanging rope is used, it is difficult to hang it on the hook on the other side because the hanging rope is bulky. Therefore, the hanging rope on the hanging rope seat assembly of the present application is designed as a combination of a long rope 18 and a short rope 19.
[0049] Specifically, a matching groove 11 is provided at the other end of the main beam 1 , and the end beam 2 matches with the matching groove 11 .
[0050] Specifically, a rotating shaft 12 is provided at the other end of the main beam 1 , one end of the rotating shaft 12 is located in the matching groove 11 , and a rotating groove 13 matching with the rotating shaft 12 is provided at the middle position of the end beam 2 .
[0051] Specifically, the rope seat 14 is provided with a plurality of pulley members.
[0052] Specifically, balance and eccentric weight indicator needles 15 are provided on the main beam 1 and the short beam 3, which are used to observe the balance state of the lifting.
[0053] To sum up, the structure of the present application has the effects of low investment and excellent lifting effect. Combined with the company's existing two cranes with 700 tons and 350 tons double trolleys, the lifting capacity is increased to 1,200 tons, which not only meets the lifting needs of the products, but also improves the large-scale lifting capacity of the factory.
[0054] The above description is only a preferred embodiment of the present invention and does not constitute any form of limitation to the present invention. Therefore, any modification, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A beam hanging device, characterized in that: It includes main beam, end beam, short beam and slewing mechanism; The short beam is rotatably matched with the main beam through the slewing mechanism, and a hanging rope seat assembly for connecting a hanging rope is provided on the short beam; One end of the main beam is provided with a rope seat for connecting the crane suspension rope, and the other end is rotatably matched with the end beam, and the end beam and the main beam are arranged vertically relative to each other; Rope seats for connecting the crane suspension ropes are provided at both ends of the end beam.
2. The beam suspension device according to claim 1, characterized in that: The slewing mechanism comprises a hook fork, the upper end of the hook fork is rotatably matched with the main beam, the lower end of the hook fork extends into the short beam, and a hanging shaft is provided at the lower end of the hook fork, and the hanging shaft is connected to the short beam.
3. The hanging beam device according to claim 2, characterized in that: The upper end of the hook fork is a cylinder, and a thrust spherical roller bearing and a slewing support bearing are arranged on the upper end of the hook fork. The thrust spherical roller bearing and the slewing support bearing are arranged on the main beam.
4. The hanging beam device according to claim 2, characterized in that: The side wall of the short beam is provided with a through hole corresponding to the hanging shaft, and the hanging shaft is inserted and arranged along the radial direction of the hook fork.
5. The hanging beam device according to claim 1, characterized in that: The rope seat assembly includes a fixed shaft passing through the short beam, a rope seat body is provided on the side wall of the short beam, the rope seat body cooperates with the fixed shaft, the rope seat body is provided with a rope groove, a bolt member is provided at the notch of the rope groove, and one end of the bolt member is connected to the side wall of the short beam.
6. The beam suspension device according to claim 5, characterized in that: The short beam is in the shape of an inverted triangle structure, and the rope seat components are symmetrically arranged at two ends of the bottom of the short beam.
7. The beam suspension device according to claim 1, characterized in that: The other end of the main beam is provided with a matching groove, and the end beam matches with the matching groove.
8. The beam suspension device according to claim 7, characterized in that: A rotating shaft is provided at the other end of the main beam, one end of the rotating shaft is located in the matching groove, and a rotating groove matching with the rotating shaft is provided at the middle position of the end beam.
9. The hanging beam device according to claim 1, characterized in that: A plurality of pulley members are arranged on the rope seat.
10. The hanging beam device according to claim 1, characterized in that: Balance and eccentric weight indicator needles are arranged on the main beam and the short beam.