Advanced mold injection device for TBM (Tunnel Boring Machine) gripper shoe part and TBM
By installing monitoring, formwork installation and grouting systems at the TBM boot site, the hole walls are automatically closed and concrete is poured, which solves the problems of low grouting efficiency and major safety hazards in manual sealing, and achieves efficient and safe advance support.
Patent Information
- Application Number
- CN202420095331.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-15
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2034-01-15
AI Technical Summary
During TBM construction, when the surrounding rock is broken, soft rock, collapse cavity and other poor geology, manual sealing and grouting efficiency is low and there are safety risks of high altitude operations.
Design a leading mold injection device for TBM boot support, including monitoring system, template installation system and grouting system. The hole wall situation is monitored in real time through the camera, and the hole wall is automatically closed and concrete is poured using the formwork displacement component and the nozzle displacement component. , achieve advanced support.
It improves the efficiency of mold sealing and grouting, reduces the safety hazards of construction workers, reduces the intensity of high-altitude operations, and ensures the personal safety of workers.
Smart Images

Figure CN222228564U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of tunneling equipment, and in particular to an advanced injection molding device for a TBM support shoe and a TBM. Background Art
[0002] Full-face hard rock tunnel boring machines (TBMs) are currently widely used in tunnel projects such as railways, highways, mining, and hydropower construction. During TBM excavation, the support shoes provide stable support for the tunnel boring machine to ensure that the cutterhead of the tunnel boring machine has a normal excavation posture. During the excavation process, due to the complex and changeable geological conditions, it is necessary to advance the detection of unfavorable geological sections when approaching unfavorable geological sections to reduce construction risks and construction difficulties. However, advance detection cannot detect all unfavorable geological conditions. It often happens that during TBM construction, the surrounding rock at the support shoe position is broken and cavities appear, which makes it impossible for the surrounding rock to provide support pressure and propulsion reaction force to the TBM support shoe. Therefore, mold sealing grouting is required.
[0003] At present, during TBM construction, when encountering unfavorable geological conditions such as broken surrounding rock, soft rock, collapsed cavity, etc. at the TBM support shoe location, the manual sealing and grouting method is adopted.
[0004] However, manual mold sealing and grouting construction has low efficiency and involves high-altitude operations during the construction process, posing great safety hazards. Utility Model Content
[0005] The present application provides an advanced molding device and a TBM for a TBM support shoe part, so as to solve the technical problems of low efficiency of sealing and grouting of the existing TBM support shoe part and great potential safety hazards.
[0006] A first aspect of an embodiment of the present application provides an advanced molding device for a TBM support shoe part, comprising a monitoring system, a template installation system and a grouting system;
[0007] The monitoring system is used to be arranged on the main beam of the TBM, and the monitoring system includes a camera and a display, wherein the camera is electrically connected to the display, the camera is used to photograph the hole wall to be supported by the support shoe of the TBM, and the display is used to display the content photographed by the camera;
[0008] The template installation system includes a grouting template and a template displacement component, the template displacement component is used to be arranged on the main beam, the output end of the template displacement component is connected to the grouting template, and the template displacement component is configured to drive the grouting template to move so that the grouting template closes the hole wall to be grouted;
[0009] The grouting system includes a nozzle and a nozzle displacement assembly. The nozzle displacement assembly is used to be arranged on the main beam. The output end of the nozzle displacement assembly is connected to the nozzle. The nozzle displacement assembly is configured to drive the nozzle to move so that the nozzle is aligned with the grouting port of the grouting template. The nozzle is used to pour concrete.
[0010] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, the template displacement assembly includes a slider, a guide rail and a travel cylinder, the guide rail is arranged on the main beam, and the direction of the guide rail is the same as the length direction of the main beam, the slider is slidably connected to the guide rail, the grouting template is arranged on the slider, the travel cylinder is connected to the slider, and the travel cylinder is configured to drive the slider to move on the guide rail.
[0011] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, the template displacement assembly also includes a tightening cylinder and at least one guide column, at least one guide sleeve is arranged on the grouting template, and each of the guide columns is sleeved in each of the guide sleeves in a one-to-one manner, the tightening cylinder is arranged on the slider, and the output end of the tightening cylinder is connected to the grouting template, and the tightening cylinder is configured to drive the grouting template to move along the length direction of the guide column so that the grouting template is close to or away from the hole wall to be grouted.
[0012] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, the template displacement assembly also includes a buffer spring assembly, and the tightening cylinder is connected to the grouting template through the buffer spring assembly.
[0013] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, the nozzle displacement assembly includes a support frame and a manipulator, the support frame is arranged on the main beam, the manipulator is arranged on the support frame, and the nozzle is connected to the output end of the manipulator.
[0014] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, the nozzle displacement assembly also includes a swivel mechanism, and the manipulator is rotatably connected to the support frame through the swivel mechanism.
[0015] In the preferred technical solution of the advance molding device for the TBM support shoe part, a saddle frame and a compensating cylinder are also included. The saddle frame is used to install the support shoe of the TBM, and the compensating cylinder is arranged on the main beam. The output end of the compensating cylinder is connected to the saddle frame.
[0016] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, it also includes a hydraulic control system, and the traveling cylinder and the compensating cylinder are respectively connected to the hydraulic control system, and the hydraulic control system is configured to control the traveling cylinder and the compensating cylinder to extend and retract synchronously when the compensating cylinder is extended and retracted.
[0017] In the preferred technical solution of the above-mentioned advance molding device for the TBM support shoe part, the monitoring system also includes an operating room and a protection platform, the operating room is arranged on the main beam, the protection platform is arranged on the upper surface of the operating room, the camera is arranged on the lower surface of the protection platform, and the display is arranged in the operating room.
[0018] A second aspect of an embodiment of the present application provides a TBM, comprising a main beam, on which is provided an advanced injection molding device for a TBM support shoe portion as described in any one of the above items.
[0019] The present application provides an advance molding device and TBM for the TBM support shoe part, wherein the advance molding device for the TBM support shoe part includes a monitoring system, a template installation system and a grouting system. The advance molding device for the TBM support shoe part of the present application first observes the condition of the cave wall to be supported by the support shoe of the TBM through the monitoring system. If there is a cavity in the cave wall to be supported and the surrounding rock has fallen off, the grouting template is used to seal the cave wall at this position through the template installation system, and then concrete is poured into the grouting port of the grouting template through the grouting system to achieve the sealing grouting of the cave wall at this position, completing the advance support, and facilitating the subsequent TBM support shoe part to support this place. Since the present application observes the cave wall to be supported by the support shoe of the TBM in advance through the monitoring system, there is no need for manual observation here, which improves the observation efficiency and ensures personal safety, and reduces safety hazards; at the same time, the template installation system and the grouting system are used to perform sealing grouting, and the efficiency of sealing grouting is high compared with manual construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0021] Figure 1 A schematic structural diagram of an advance molding device for a TBM support shoe provided in an embodiment of the present application;
[0022] Figure 2 for Figure 1 A schematic diagram of the structure from another angle;
[0023] Figure 3 Another structural schematic diagram of the advance molding device for the TBM support shoe part provided in the embodiment of the present application;
[0024] Figure 4 for Figure 1 Structural diagram of the middle template installation system;
[0025] Figure 5 for Figure 4 A schematic diagram of the structure from another angle;
[0026] Figure 6 for Figure 2 Schematic diagram of the structure of the grouting system;
[0027] Figure 7 for Figure 2 The structural diagram of the monitoring system;
[0028] Figure 8 A schematic structural diagram of an operating room in an advance molding device for a TBM support shoe portion provided in an embodiment of the present application.
[0029] Description of reference numerals:
[0030] 100- monitoring system, 110- camera, 120- display, 130- operation room, 140- protection platform, 200- template installation system, 210- grouting template, 220- template displacement assembly, 221- slider, 222- guide rail, 223- walking cylinder, 224- tightening cylinder, 225- guide column, 226- buffer spring assembly, 300- grouting system, 310- nozzle, 320- nozzle displacement assembly, 321- support frame, 322- manipulator, 323- slewing mechanism, 400- main beam, 500- support shoe, 600- guide sleeve, 700- saddle frame, 800- compensation cylinder, 900- cave wall, 1000- thrust cylinder.
[0031] The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments. DETAILED DESCRIPTION
[0032] Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The implementation methods described in the following exemplary embodiments do not represent all implementation methods consistent with the present application. On the contrary, they are merely examples of devices and methods consistent with some aspects of the present application as detailed in the attached claims. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.
[0033] It should be noted that all directional indications in the embodiments of the present application (such as up, down, left, right, front, back, etc.) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0034] In this application, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0035] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present application, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or a scheme that satisfies both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in the field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection required by this application.
[0036] As mentioned in the background technology, full-face hard rock tunnel boring machines (TBM) are currently widely used in tunnel projects such as railways, highways, mining, and hydropower construction. During TBM excavation, the support shoes provide stable support for the tunnel boring machine to ensure that the cutter head of the tunnel boring machine has a normal excavation posture. During the excavation process, due to the complex and changeable geological conditions, when approaching a poor geological section, it is necessary to advance the detection of the poor geological section to reduce construction risks and construction difficulties. However, advance detection cannot detect all poor geological conditions. It often happens that during TBM construction, the surrounding rock at the support shoe position is broken and cavities appear, which makes it impossible for the surrounding rock to provide support pressure and propulsion reaction force to the TBM support shoe. Therefore, mold sealing grouting is required.
[0037] At present, during TBM construction, when encountering unfavorable geological conditions such as broken surrounding rock, soft rock, collapsed cavity, etc. at the TBM support shoe location, the manual sealing and grouting method is adopted.
[0038] However, manual mold sealing and grouting construction has low efficiency and involves high-altitude operations during the construction process, posing great safety hazards.
[0039] In order to solve the technical problems of low efficiency of sealing and grouting of the existing TBM support shoe part and great safety hazards, the present application proposes an advanced molding device and TBM for the TBM support shoe part, wherein the advanced molding device for the TBM support shoe part includes a monitoring system, a template installation system and a grouting system; the monitoring system is arranged on the main beam of the TBM, the monitoring system includes a camera and a display, the camera is electrically connected to the display, the camera is used to photograph the hole wall to be supported by the TBM support shoe, and the display is used to display the content photographed by the camera; the template installation system includes a grouting template and a template displacement assembly, the template displacement assembly is arranged on the main beam, the output end of the template displacement assembly is connected to the grouting template, and the template displacement assembly is configured to drive the grouting template to move so that the grouting template closes the hole wall to be grouted; the grouting system includes a nozzle and a nozzle displacement assembly, the nozzle displacement assembly is arranged on the main beam, the output end of the nozzle displacement assembly is connected to the nozzle, the nozzle displacement assembly is configured to drive the nozzle to move so that the nozzle is aligned with the grouting port of the grouting template, and the nozzle is used to pour concrete.
[0040] The advance molding device for the TBM support shoe part of the present application first observes the condition of the cave wall to be supported by the support shoe of the TBM through the monitoring system. If there is a cavity in the cave wall to be supported and the surrounding rock is detached, the grouting template is used to seal the cave wall at this position through the template installation system, and then the concrete is poured into the grouting port of the grouting template through the grouting system to achieve the sealing grouting of the cave wall at this position, completing the advance support, and facilitating the subsequent TBM support shoe part to support this place. Since the present application observes the cave wall to be supported by the support shoe of the TBM in advance through the monitoring system, there is no need for manual observation here, which improves the observation efficiency, ensures personal safety, and reduces safety hazards; at the same time, the template installation system and the grouting system are used to perform sealing grouting, which further improves the efficiency of sealing grouting compared to manual construction, reduces the high intensity of construction personnel, and ensures the personal safety of workers.
[0041] The following specific embodiments are combined with the accompanying drawings to describe the technical solution of the application in detail. The following specific embodiments can be combined with each other, and the same or similar concepts or processes may not be described in detail in some embodiments.
[0042] Reference Figures 1 to 8 As shown, Figure 1 A schematic structural diagram of an advance molding device for a TBM support shoe provided in an embodiment of the present application; Figure 2 for Figure 1 A schematic diagram of the structure from another angle; Figure 3Another structural schematic diagram of the advance molding device for the TBM support shoe part provided in the embodiment of the present application; Figure 4 for Figure 1 Structural diagram of the middle template installation system; Figure 5 for Figure 4 A schematic diagram of the structure from another angle; Figure 6 for Figure 2 Schematic diagram of the structure of the grouting system; Figure 7 for Figure 2 The structural diagram of the monitoring system; Figure 8 A schematic structural diagram of an operating room in an advance molding device for a TBM support shoe portion provided in an embodiment of the present application.
[0043] In the embodiments of this application, refer to Figure 1 and Figure 2 As shown, a first aspect of an embodiment of the present application provides an advanced molding device for a TBM support shoe part, comprising a monitoring system 100, a template installation system 200 and a grouting system 300.
[0044] The monitoring system 100 is used to be set on the main beam 400 of the TBM. The monitoring system 100 includes a camera 110 and a display 120. The camera 110 is electrically connected to the display 120. The camera 110 is used to photograph the cave wall supported by the support shoe 500 of the TBM, and the display 120 is used to display the content photographed by the camera 110.
[0045] The template installation system 200 includes a grouting template 210 and a template displacement assembly 220. The template displacement assembly 220 is used to be set on the main beam 400. The output end of the template displacement assembly 220 is connected to the grouting template 210. The template displacement assembly 220 is configured to drive the grouting template 210 to move so that the grouting template 210 closes the hole wall to be grouted.
[0046] The grouting system 300 includes a nozzle 310 and a nozzle displacement assembly 320. The nozzle displacement assembly 320 is used to be set on the main beam 400. The output end of the nozzle displacement assembly 320 is connected to the nozzle 310. The nozzle displacement assembly 320 is configured to drive the nozzle 310 to move so that the nozzle 310 is aligned with the grouting port of the grouting template 210. The nozzle 310 is used to pour concrete.
[0047] The monitoring system 100 of the present application is used to photograph the cave wall 900 supported by the support shoe 500 of the TBM. By observing the content photographed by the camera 110 on the display 120, the operator can see the surrounding rock conditions of the cave wall 900 supported by the support shoe 500 of the TBM, thereby eliminating the need for manual observation of the surrounding rock conditions at the cave wall 900, thereby ensuring personal safety.
[0048] If the cave wall 900 to be supported has a cavity and surrounding rock falling off, the template displacement assembly 220 of the template installation system 200 drives the grouting template 210 to move, so as to close the cave wall 900 at this position with the grouting template 210 .
[0049] After the grouting template 210 closes the cave wall 900 at this position, the position of the nozzle 310 is adjusted through the nozzle displacement assembly 320 of the grouting system 300, so that the nozzle 310 is aligned with the grouting port of the grouting template 210, and then concrete is poured into the grouting port of the grouting template 210 through the nozzle 310, thereby achieving the sealing grouting of the cave wall 900 at this position, completing the advanced support, and facilitating the subsequent TBM support shoe 500 to support this place.
[0050] Since the present application uses the monitoring system 100 to observe in advance the cave wall 900 supported by the support shoe 500 of the TBM, there is no need for manual observation there, which improves the observation efficiency, ensures personal safety, and reduces safety hazards; at the same time, the mold sealing and grouting are carried out through the formwork installation system 200 and the grouting system 300, which further improves the efficiency of the mold sealing and grouting compared to manual construction, reduces the high work intensity of the construction personnel, and ensures the personal safety of the workers.
[0051] It should be noted that the TBM gripper shoes 500 are generally provided in two groups, and the present application provides two advance injection molding devices for the TBM gripper shoe parts, and the two advance injection molding devices for the TBM gripper shoe parts correspond one to one to the two groups of TBM gripper shoes 500.
[0052] In another embodiment, referring to Figure 1 , Figure 4 and Figure 5 As shown, the template displacement assembly 220 includes a slider 221, a guide rail 222 and a travel cylinder 223. The guide rail 222 is set on the main beam 400, and the direction of the guide rail 222 is the same as the length direction of the main beam 400. The slider 221 is slidably connected to the guide rail 222. The grouting template 210 is set on the slider 221. The travel cylinder 223 is connected to the slider 221. The travel cylinder 223 is configured to drive the slider 221 to move on the guide rail 222.
[0053] Because the moving direction of the TBM's support shoe 500 is the length direction of the TBM's main beam 400, that is, only the displacement of the grouting template 210 in the length direction of the main beam 400 needs to be changed to ensure that the grouting template 210 covers all the cave walls 900 to be supported by the support shoe 500. When the cave wall 900 to be supported by the support shoe 500 needs to be grouted, the cave wall 900 to be supported by the support shoe 500 at this time is the cave wall 900 to be grouted. In this embodiment, the slider 221 is driven to move on the guide rail 222 by the travel cylinder 223, so that the grouting template 210 is displaced along the length direction of the main beam 400, ensuring that the grouting template 210 can be aligned with the cave wall 900 to be grouted, thereby facilitating the grouting template 210 to close the cave wall 900 to be grouted.
[0054] In certain embodiments, reference Figure 4 and Figure 5 As shown, the template displacement assembly 220 also includes a tightening cylinder 224 and at least one guide column 225. At least one guide sleeve 600 is provided on the grouting template 210. Each guide column 225 is sleeved in each guide sleeve 600 in a one-to-one manner. The tightening cylinder 224 is provided on the slider 221. The output end of the tightening cylinder 224 is connected to the grouting template 210. The tightening cylinder 224 is configured to drive the grouting template 210 to move along the length direction of the guide column 225 so that the grouting template 210 is close to or away from the cave wall 900 to be grouted.
[0055] In this embodiment, the grouting template 210 is driven to move along the length direction of the guide column 225 by the tightening cylinder 224, so that the grouting template 210 can be pressed against the hole wall 900 to be grouted. When the grouting template 210 needs to be repositioned, the grouting template 210 is moved away from the hole wall 900 to be grouted by the tightening cylinder 224, that is, the grouting template 210 is contracted, so that the grouting template 210 is moved to the next position.
[0056] In one embodiment, referring to Figure 4 and Figure 5 As shown, the template displacement assembly 220 also includes a buffer spring assembly 226 , and the tightening cylinder 224 is connected to the grouting template 210 via the buffer spring assembly 226 .
[0057] In this embodiment, the tensioning cylinder 224 is connected to the grouting template 210 through the buffer spring assembly 226, so as to prevent the vibration of the main beam 400 and the tensioning cylinder 224 during the operation of the TBM from causing excessive shaking of the grouting template 210, thereby affecting the sealing and grouting construction, thereby improving the stability and safety of the construction and reducing the impact of vibration on grouting during the excavation process.
[0058] In other possible embodiments, refer to Figure 2 and Figure 6As shown, the nozzle displacement assembly 320 includes a support frame 321 and a manipulator 322 . The support frame 321 is disposed on the main beam 400 , the manipulator 322 is disposed on the support frame 321 , and the nozzle 310 is connected to the output end of the manipulator 322 .
[0059] In this embodiment, the position of the nozzle 310 is adjusted by the manipulator 322 so that the nozzle 310 can be aligned with the grouting port of the grouting template 210 .
[0060] In another possible embodiment, referring to Figure 6 As shown, the nozzle displacement assembly 320 also includes a swivel mechanism 323, and the manipulator 322 is rotatably connected to the support frame 321 through the swivel mechanism 323. Since the manipulator 322 is rotatably connected to the support frame 321, the range of movement of the manipulator 322 is increased, ensuring that the nozzle 310 can be aligned with the grouting port of the grouting template 210.
[0061] In some possible embodiments, reference Figure 1 As shown, a saddle frame 700 and a compensating cylinder 800 are also included. The saddle frame 700 is used to install the TBM support shoe 500. The compensating cylinder 800 is arranged on the main beam 400, and the output end of the compensating cylinder 800 is connected to the saddle frame 700.
[0062] During the excavation process of the TBM, the propulsion cylinder 1000 of the TBM extends, and when the main beam 400 of the TBM moves forward, the shoe 500 on the saddle frame 700 needs to abut against the cave wall 900, that is, the shoe 500 and the saddle frame 70 are stationary relative to the cave wall 900, and the compensation cylinder 800 will extend. The expansion and contraction amount of the travel cylinder 223 can be adjusted by the expansion and contraction amount of the compensation cylinder 800, so as to ensure that the grouting template 210 and the cave wall 900 are relatively stationary, and prevent the grouting template 210 from moving out of the cave wall 900 to be grouted.
[0063] In another embodiment, a hydraulic control system is also included, and the traveling cylinder 223 and the compensation cylinder 800 are respectively connected to the hydraulic control system. The hydraulic control system is configured to control the traveling cylinder 223 and the compensation cylinder 800 to extend and retract synchronously when the compensation cylinder 800 extends and retracts.
[0064] In this embodiment, the hydraulic control system is used to synchronize the extension and retraction of the traveling cylinder 223 and the compensation cylinder 800. When the compensation cylinder 800 is extended, the hydraulic control system controls the synchronous extension of the traveling cylinder 223, thereby ensuring that the grouting template 210 and the cave wall 900 are relatively still, so that the template can be assembled and grouting can be performed synchronously during excavation, and the quality of the spray mix can be guaranteed.
[0065] In other possible embodiments, refer to Figure 1 , Figure 2 , Figure 7 and Figure 8 As shown, the monitoring system 100 also includes an operation room 130 and a protection platform 140. The operation room 130 is arranged on the main beam 400, the protection platform 140 is arranged on the upper surface of the operation room 130, the camera 110 is arranged on the lower surface of the protection platform 140, and the display 120 is arranged in the operation room 130.
[0066] In this embodiment, the operator in the operating room 130 observes the content captured by the camera 110 on the display 120, so as to observe the cave wall 900 supported by the support shoe 500 of the TBM. The protection platform 140 protects the camera 110 and the operating room 130 to prevent the upper surrounding rock from falling.
[0067] In another possible embodiment, the protection platform 140 abuts against the cave wall 900 to prevent the surrounding rock above the protection platform 140 from falling into the grouting area.
[0068] Reference Figure 1 , Figure 2 and Figure 3 As shown, the second aspect of the embodiment of the present application provides a TBM, including a main beam 400, on which is provided any one of the above-mentioned advance molding devices for the TBM support shoe part.
[0069] The TBM provided in the present application is provided with any of the above-mentioned advance molding devices for the TBM support shoe part on the main beam 400, wherein the advance molding device for the TBM support shoe part includes a monitoring system 100, a template installation system 200 and a grouting system 300; the monitoring system 100 is arranged on the main beam 400 of the TBM, the monitoring system 100 includes a camera 110 and a display 120, the camera 110 is electrically connected to the display 120, the camera 110 is used to photograph the cave wall 900 supported by the support shoe 500 of the TBM, and the display 120 is used to display the content photographed by the camera 110; the template installation system 200 includes a grouting template 210 and a mold The plate displacement component 220, the template displacement component 220 is arranged on the main beam 400, the output end of the template displacement component 220 is connected to the grouting template 210, and the template displacement component 220 is configured to drive the grouting template 210 to move so that the grouting template 210 closes the hole wall 900 to be grouted; the grouting system 300 includes a nozzle 310 and a nozzle displacement component 320, the nozzle displacement component 320 is arranged on the main beam 400, the output end of the nozzle displacement component 320 is connected to the nozzle 310, and the nozzle displacement component 320 is configured to drive the nozzle 310 to move so that the nozzle 310 is aligned with the grouting port of the grouting template 210, and the nozzle 310 is used to pour concrete.
[0070] The advance molding device for the TBM support shoe part of the present application first observes the situation of the cave wall 900 supported by the support shoe 500 of the TBM through the monitoring system 100. If there is a cavity and surrounding rock detachment in the cave wall 900 to be supported, the grouting template 210 is used to close the cave wall 900 at this position through the template installation system 200, and then concrete is poured into the grouting port of the grouting template 210 through the grouting system 300 to achieve the sealing grouting of the cave wall 900 at this position, completing the advance support, and facilitating the subsequent TBM support shoe 500 to support this place. Since the present application observes the cave wall 900 supported by the support shoe 500 of the TBM in advance through the monitoring system 100, there is no need for manual observation here, which improves the observation efficiency and ensures personal safety, and reduces safety hazards; at the same time, the template installation system 200 and the grouting system 300 are used to perform sealing grouting, which further improves the efficiency of sealing grouting compared with manual construction, reduces the high work intensity of construction personnel, and ensures the personal safety of workers.
[0071] Those skilled in the art will readily appreciate other embodiments of the present application after considering the description and practicing the contents disclosed herein. The present application is intended to cover any modification, use or adaptation of the present application, which follows the general principles of the present application and includes common knowledge or customary techniques in the art that are not disclosed in the present application. The description and examples are intended to be exemplary only, and the true scope and spirit of the present application are indicated by the following claims.
[0072] It should be understood that the present application is not limited to the precise structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present application is limited only by the appended claims.
Claims
1. A pre-molding device for TBM support shoe parts, characterized in that: It comprises a monitoring system (100), a template installation system (200) and a grouting system (300); The monitoring system (100) is used to be arranged on the main beam (400) of the TBM, and the monitoring system (100) comprises a camera (110) and a display (120), wherein the camera (110) is electrically connected to the display (120), the camera (110) is used to photograph the cave wall to be supported by the support shoe (500) of the TBM, and the display (120) is used to display the content photographed by the camera (110); The template installation system (200) comprises a grouting template (210) and a template displacement component (220), wherein the template displacement component (220) is used to be arranged on the main beam (400), an output end of the template displacement component (220) is connected to the grouting template (210), and the template displacement component (220) is configured to drive the grouting template (210) to move so that the grouting template (210) closes the hole wall to be grouted; The grouting system (300) comprises a nozzle (310) and a nozzle displacement assembly (320); the nozzle displacement assembly (320) is used to be arranged on the main beam (400); the output end of the nozzle displacement assembly (320) is connected to the nozzle (310); the nozzle displacement assembly (320) is configured to drive the nozzle (310) to move so that the nozzle (310) is aligned with the grouting port of the grouting template (210); and the nozzle (310) is used to pour concrete.
2. The advanced injection molding device for TBM gripper shoe according to claim 1 is characterized in that: The template displacement assembly (220) comprises a slider (221), a guide rail (222) and a travel cylinder (223); the guide rail (222) is arranged on the main beam (400), and the direction of the guide rail (222) is the same as the length direction of the main beam (400); the slider (221) is slidably connected to the guide rail (222); the grouting template (210) is arranged on the slider (221); the travel cylinder (223) is connected to the slider (221), and the travel cylinder (223) is configured to drive the slider (221) to move on the guide rail (222).
3. The advanced injection molding device for TBM gripper shoe according to claim 2 is characterized in that: The template displacement assembly (220) further comprises a tightening oil cylinder (224) and at least one guide column (225); at least one guide sleeve (600) is arranged on the grouting template (210); each of the guide columns (225) is sleeved in each of the guide sleeves (600) in a one-to-one correspondence; the tightening oil cylinder (224) is arranged on the slider (221); an output end of the tightening oil cylinder (224) is connected to the grouting template (210); the tightening oil cylinder (224) is configured to drive the grouting template (210) to move along the length direction of the guide column (225) so as to move the grouting template (210) close to or away from the hole wall to be grouted.
4. The advanced injection molding device for TBM gripper shoe according to claim 3 is characterized in that: The template displacement assembly (220) further comprises a buffer spring assembly (226), and the tightening cylinder (224) is connected to the grouting template (210) via the buffer spring assembly (226).
5. The advanced molding device for TBM gripper shoe according to claim 1 is characterized in that: The nozzle displacement assembly (320) comprises a support frame (321) and a manipulator (322); the support frame (321) is arranged on the main beam (400); the manipulator (322) is arranged on the support frame (321); and the nozzle (310) is connected to an output end of the manipulator (322).
6. The advanced injection molding device for TBM gripper shoe according to claim 5, characterized in that: The nozzle displacement assembly (320) further comprises a rotating mechanism (323), and the manipulator (322) is rotatably connected to the support frame (321) via the rotating mechanism (323).
7. The advanced injection molding device for TBM gripper shoe according to claim 2, characterized in that: It also includes a saddle frame (700) and a compensation cylinder (800), wherein the saddle frame (700) is used to install the support shoe (500) of the TBM, and the compensation cylinder (800) is arranged on the main beam (400), and the output end of the compensation cylinder (800) is connected to the saddle frame (700).
8. The advanced injection molding device for TBM gripper shoe according to claim 7, characterized in that: The invention also comprises a hydraulic control system, wherein the travel cylinder (223) and the compensation cylinder (800) are respectively connected to the hydraulic control system, and the hydraulic control system is configured to control the travel cylinder (223) and the compensation cylinder (800) to synchronously extend and retract when the compensation cylinder (800) retracts and retracts.
9. The advance molding device for TBM gripper shoe according to any one of claims 1 to 8, characterized in that: The monitoring system (100) further comprises an operating room (130) and a protection platform (140), wherein the operating room (130) is arranged on the main beam (400), the protection platform (140) is arranged on the upper surface of the operating room (130), the camera (110) is arranged on the lower surface of the protection platform (140), and the display (120) is arranged in the operating room (130).
10. A TBM, comprising a main beam (400), characterized in that: The main beam (400) is provided with an advance molding device for the TBM support shoe part according to any one of claims 1 to 9.