Road surface crack pouring device for road maintenance
By using sealing and sliding components in the road maintenance pavement filling device, the problem of insufficient cement slurry pressure due to large gap width is solved, the cement slurry filling effect is achieved when the cement slurry penetrates into the gap, and the quality of the road maintenance is improved.
Patent Information
- Application Number
- CN202420517677.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2034-03-18
AI Technical Summary
When the gap width of the existing seam filling devices are large, the cement slurry pressure is limited and cannot penetrate deep into the gap, resulting in poor grouting effect and affecting the road maintenance effect.
A highway maintenance pavement seam filling device is designed, using sealing components and sliding components. The sealing components are separated by rubber rings and annular groove sliding blocks. The sliding components are adjusted by sliding components of the conical barrel and arc-shaped conduit, combined with the addition of The pressure pump increases the pressure and depth guidance of the cement slurry.
Regional filling of different gaps is achieved, ensuring that cement slurry penetrates deep into the gaps, improving the filling effect, and smoothing the surface overflow through rubber rings, improving the quality of filling of highway maintenance.
Smart Images

Figure CN222251672U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway maintenance equipment, in particular to a highway maintenance pavement crack filling device. Background Art
[0002] After a highway is built and opened to traffic, its quality will gradually decline due to the wear and impact of wheels, erosion and weathering by natural forces such as rainstorms, floods, sandstorms, ice and snow, sunlight, ice melting, as well as human damage and certain defects left over from construction. Therefore, after a highway is built and opened to traffic, maintenance measures must be taken and it must be continuously updated and improved. Highway maintenance must repair damaged parts in a timely manner, otherwise it will lead to increased investment in repair projects, shorten the service life of the highway, and cause losses to road users.
[0003] When cracks appear on a road due to the squeezing of heavy-loaded vehicles, the two sides of the road will separate and gaps will appear on the road. If the gaps are not dealt with in time, the scope of road damage will expand. Therefore, it is necessary to use grouting devices to deal with the gaps on the road in time.
[0004] When using existing grouting devices, a conical gun head is often inserted into the gap, and then high-strength cement slurry is poured into the gap through a pipe and the conical gun head until the gap is filled with cement slurry and overflows on the road surface. A fence is set outside the grouting part, and the fence is recovered after the cement slurry solidifies to complete the grouting operation. In actual use, it is found that due to the difference in the width of highway gaps, after the conical gun head is inserted into the gap, if the gap width is significantly larger than the gun head width, the pressure of the cement slurry filled is limited and cannot flow deep into the gap, resulting in poor grouting effect, which in turn leads to limited highway maintenance grouting effect. For this reason, we propose a highway maintenance pavement grouting device. Utility Model Content
[0005] The purpose of the utility model is to provide a road maintenance pavement grouting device to solve the problem raised in the above background technology that if the gap width is significantly larger than the gun head width, the pressure of the cement slurry filled in is limited and cannot flow deep into the gap, resulting in poor grouting effect, which in turn leads to limited highway maintenance grouting effect.
[0006] To achieve the above purpose, the utility model provides the following technical solution: a road maintenance pavement grouting device, comprising:
[0007] A grouting box for storing cement slurry used in grouting operations, wherein the outer wall of the grouting box is connected to a cement slurry delivery pipe, and a joint ring is welded and fixed to the end of the cement slurry delivery pipe, and the inner circumference of the joint ring is configured with a threaded groove;
[0008] A threaded ring is screwed and fixed to a joint ring, an arc-shaped conduit is welded and fixed at the end of the threaded ring, a conical barrel is slidably penetrated inside the arc-shaped conduit, a threaded ring is integrally formed on the outer circumference of the arc-shaped conduit, a road surface bonding sheet is screwed on the outer circumference of the threaded ring, a sealing assembly is arranged at the bottom of the road surface bonding sheet, and a sliding assembly is arranged between the conical barrel and the arc-shaped conduit.
[0009] Preferably, the sealing assembly includes a rubber ring attached to the bottom of the road surface bonding sheet and an annular groove constructed at the bottom of the road surface bonding sheet, a sliding block is slidably arranged in the annular groove, a vertical rod is fixed to the bottom of the sliding block, and a rubber sheet is bonded to the bottom end of the vertical rod.
[0010] Preferably, the sliding assembly includes vertical grooves symmetrically arranged on the inner circumference of the arc-shaped tube, and limiting rods are inserted and fixed in the vertical grooves. Limiting rings are slidably arranged between the outer circumferences of the limiting rods, and the conical gun barrel is fixed on the inner circumference of the limiting rings. A spring is sleeved on the outer circumference of the limiting rods, and the bottom of the spring abuts against the surface of the limiting ring.
[0011] Preferably, a booster pump is installed on the outer periphery of the cement slurry delivery pipe, and the booster pump is arranged at one end of the cement slurry delivery pipe close to the grouting box.
[0012] Preferably, the thread ring is arranged on the outer periphery of the arc-shaped conduit close to one end of the bottom of the arc-shaped conduit.
[0013] Preferably, both ends of the rubber sheet are configured in a wedge shape.
[0014] Preferably, the annular groove is arranged on the inner side of the rubber ring.
[0015] Compared with the prior art, the beneficial effects of the utility model are:
[0016] 1. The utility model provides a sealing component, which can separate the gap from the side close to the edge of the gap during the grouting operation on the highway, thereby regionalizing the grouting and ensuring the sealing effect of the grouting area, so that the poured cement slurry has a certain pressure so that the cement slurry can penetrate deep into the gap, thereby improving the grouting effect, and in the process of slow movement, the cement slurry overflowing on the highway surface can be smoothed with the help of a rubber ring.
[0017] 2. The utility model provides a sliding component, and during actual operation, the bottom of the conical barrel can be telescopically adjusted, thereby meeting the needs of grouting operations in road gaps of different depths, and conveniently guiding the cement slurry to a deeper position in the gap, thereby assisting in improving the grouting effect of the gap. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0019] Figure 2 It is a structural schematic diagram of the arc-shaped guide tube and the tapered barrel in the utility model;
[0020] Figure 3 It is a schematic diagram of the structure of the road surface bonding sheet of the utility model in an inverted state;
[0021] Figure 4 It is a cross-sectional view of the arc-shaped conduit in the utility model.
[0022] In the figure: 1. grouting box; 2. cement slurry delivery pipe; 3. booster pump; 4. joint ring; 5. threaded ring; 6. arc-shaped guide tube; 7. threaded ring; 8. road surface bonding sheet; 9. rubber ring; 10. annular groove; 11. sliding block; 12. vertical rod; 13. rubber sheet; 14. tapered barrel; 15. limit ring; 16. limit rod; 17. spring. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] Example
[0025] See also Figure 1-Figure 4 A road maintenance pavement grouting device shown in the figure comprises a grouting box 1 for storing cement slurry used for grouting operation, the outer wall of the grouting box 1 is connected to a cement slurry delivery pipe 2, a joint ring 4 is welded and fixed at the end of the cement slurry delivery pipe 2, the inner circumference of the joint ring 4 is structured with a threaded groove, a threaded ring 5 screwed and fixed to the joint ring 4, an arc-shaped conduit 6 is welded and fixed at the end of the threaded ring 5, a tapered gun barrel 14 is slidably penetrated inside the arc-shaped conduit 6, a threaded ring 7 is integrally formed on the outer circumference of the arc-shaped conduit 6, the threaded ring 7 is arranged on the outer circumference of the arc-shaped conduit 6 near one end of the bottom of the arc-shaped conduit 6, a pavement bonding sheet 8 is screwed on the outer circumference of the threaded ring 7, a sealing component is arranged at the bottom of the pavement bonding sheet 8, and a sliding component is arranged between the tapered gun barrel 14 and the arc-shaped conduit 6.
[0026] Specifically, the sealing assembly includes a rubber ring 9 adhered to the bottom of the road surface bonding sheet 8 and an annular groove 10 constructed at the bottom of the road surface bonding sheet 8, the annular groove 10 is arranged on the inner side of the rubber ring 9, and a sliding block 11 is slidably arranged in the annular groove 10, and a vertical rod 12 is fixed to the bottom of the sliding block 11, and a rubber sheet 13 is bonded to the bottom end of the vertical rod 12. The rubber sheet 13 has a certain elastic deformation ability. After the rubber sheet 13 is inserted into the gap in the road, the edge side of the rubber sheet 13 can be deformed to one side to ensure that the edge side of the rubber sheet 13 is tightly fitted with the gap, thereby separating the internal space of the gap, and distributing and filling the separated intervals, thereby greatly improving the filling effect.
[0027] Specifically, the sliding assembly includes vertical grooves symmetrically arranged on the inner circumference of the arc-shaped guide tube 6, and limit rods 16 are inserted and fixed in the vertical grooves. A limit ring 15 is slidably arranged between the outer circumferences of the limit rods 16, and the conical gun barrel 14 is fixed on the inner circumference of the limit ring 15. A spring 17 is sleeved on the outer circumference of the limit rod 16, and the bottom of the spring 17 abuts against the surface of the limit ring 15. Under the coordinated action of the spring 17, the limit ring 15 and the limit rod 16, the bottom of the conical gun barrel 14 can be inserted into the deepest part of the gap, thereby ensuring that the grouting in the gap is complete and the quality of the grouting is guaranteed.
[0028] Specifically, a booster pump 3 is installed on the outer periphery of the cement slurry delivery pipe 2, and the booster pump 3 is arranged at one end of the cement slurry delivery pipe 2 close to the grouting box 1. The booster pump 3 is used to drive the cement slurry in the cement slurry delivery pipe 2 to flow toward the side of the tapered gun barrel 14.
[0029] Specifically, both ends of the rubber sheet 13 are constructed in a wedge shape, and the two sides of the rubber sheet 13 are relatively thin, which facilitates elastic deformation so that the rubber sheet 13 fits in the gap.
[0030] It should be noted that the utility model is a road maintenance pavement grouting device. The sliding block 11 is rotated in advance to move the rubber sheet 13 to a suitable position at the bottom of the road surface bonding sheet 8, and then the conical barrel 14 is inserted into the gap. The two sides of the rubber sheet 13 are elastically deformed to keep in close contact with the inner wall of the gap, thereby separating the gap. At this time, the conical barrel 14 is located in a smaller space, and the booster pump 3 is started to transport the cement slurry in the grouting box 1 to the gap through the cement slurry delivery pipe 2. When the cement slurry in the gap on one side is filled, the road surface bonding sheet 8 is moved together with the rubber sheet 13 to the side away from the smaller gap, and the above operation is repeated. During the movement of the road surface bonding sheet 8, the cement slurry overflowing on the road surface can be smoothed by the rubber ring 9.
[0031] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A road maintenance pavement grouting device, characterized in that: include: A grouting box (1) for storing cement slurry used in grouting operations, wherein the outer wall of the grouting box (1) is connected to a cement slurry delivery pipe (2), a joint ring (4) is welded and fixed to the end of the cement slurry delivery pipe (2), and the inner circumference of the joint ring (4) is configured with a threaded groove; A threaded ring (5) is screwed and fixed to a joint ring (4), an arc-shaped conduit (6) is welded and fixed to the end of the threaded ring (5), a conical gun barrel (14) is slidably penetrated inside the arc-shaped conduit (6), a threaded ring (7) is integrally formed on the outer circumference of the arc-shaped conduit (6), a road surface bonding sheet (8) is screwed on the outer circumference of the threaded ring (7), a sealing component is arranged at the bottom of the road surface bonding sheet (8), and a sliding component is arranged between the conical gun barrel (14) and the arc-shaped conduit (6).
2. A road maintenance pavement caulking device according to claim 1, characterized in that: The sealing assembly comprises a rubber ring (9) attached to the bottom of a road surface bonding sheet (8) and an annular groove (10) constructed at the bottom of the road surface bonding sheet (8), a sliding block (11) is slidably arranged in the annular groove (10), a vertical rod (12) is fixed to the bottom of the sliding block (11), and a rubber sheet (13) is bonded to the bottom end of the vertical rod (12).
3. A road maintenance pavement caulking device according to claim 1, characterized in that: The sliding assembly comprises vertical grooves symmetrically arranged on the inner circumference of the arc-shaped guide tube (6), wherein limit rods (16) are inserted and fixed in the vertical grooves, and a limit ring (15) is slidably arranged between the outer circumferences of the limit rods (16), and the conical gun barrel (14) is fixed on the inner circumference of the limit ring (15), and a spring (17) is sleeved on the outer circumference of the limit rod (16), and the bottom of the spring (17) abuts against the surface of the limit ring (15).
4. A road maintenance pavement caulking device according to claim 1, characterized in that: A booster pump (3) is installed on the outer periphery of the cement slurry delivery pipe (2), and the booster pump (3) is arranged at one end of the cement slurry delivery pipe (2) close to the grouting box (1).
5. A road maintenance pavement caulking device according to claim 1, characterized in that: The threaded ring (7) is arranged on the outer periphery of the arc-shaped conduit (6) near one end of the bottom of the arc-shaped conduit (6).
6. A road maintenance pavement caulking device according to claim 2, characterized in that: Both ends of the rubber sheet (13) are configured in a wedge shape.
7. A road maintenance pavement caulking device according to claim 2, characterized in that: The annular groove (10) is arranged on the inner side of the rubber ring (9).