Diversion system

By setting up diversion steel pipes and rainwater wells in the foundation pit excavation construction, the conflict between foundation pit excavation and existing rainwater pipelines is solved, the construction process is simplified, the construction period is saved, and the cost is reduced, and the normal operation of rainwater pipelines is achieved.

CN222252400UActive Publication Date: 2024-12-27武汉城建建设工程有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420946072.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-06
Publication Date
2024-12-27
Estimated Expiration
2034-05-06

AI Technical Summary

Technical Problem

During the excavation and construction of foundation pits, the existing concrete stormwater pipeline conflicts with the foundation pit space. The traditional method requires relocation of the stormwater pipeline, resulting in high construction period and cost, affecting the project progress and cost.

Method used

Design a flow diversion system, including setting up steel sheet pile support lines on both sides of the planned drainage pipe and erecting diversion steel pipes between them. The new rainwater well is located at the connection between the concrete rainwater pipe and the flow diversion steel pipe to ensure that the length of the flow diversion steel pipe is greater than the support. The spacing and elevation of the wire guards are consistent with the existing rainwater pipelines to achieve flow diversion.

Benefits of technology

This flow diversion system simplifies the construction process, does not need to first relocate the drainage pipeline, saves construction period, and passes through the support structure through the flow diversion steel pipe, achieving the normal operation of existing rainwater pipelines and reducing project costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222252400U_ABST
    Figure CN222252400U_ABST
Patent Text Reader

Abstract

The flow guide system is used for transforming an existing concrete rainwater pipeline erected on the upper portion of a planned drainage pipeline, the flow guide system comprises steel sheet pile supporting lines, a newly-built rainwater well and a flow guide steel pipe, and the steel sheet pile supporting lines are arranged on the two sides of the planned drainage pipeline. The flow guide steel pipe is erected between the two steel sheet pile supporting lines, and the newly-built catch basin is arranged on the outer sides of the steel sheet pile supporting lines and located at the joint of an existing concrete rainwater pipeline and the flow guide steel pipe. According to the diversion system, the steel sheet pile supporting lines are arranged on the two sides of the planned drainage pipeline to protect the drainage pipeline, the diversion steel pipes are erected on the steel sheet pile supporting lines, and the diversion system is communicated with the newly-built catch basin through the diversion steel pipes, so that communication between the existing concrete rainwater pipeline and the diversion steel pipes is achieved; therefore, communication between the existing concrete rainwater pipeline on the upper portion of the planned drainage pipeline and the flow guide pipe is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of construction water supply and drainage, and more specifically, to a diversion system. Background Art

[0002] When excavating the foundation pit, there will be a problem of spatial conflict between the excavated foundation pit and the existing concrete rainwater pipes, and the existing concrete rainwater pipes cannot be abolished during the construction period. The current traditional construction method is to relocate the rainwater pipes within the affected area and move them out of the foundation pit. However, the relocation period of rainwater pipes is long and the cost is high, which directly affects the construction period and cost of the entire project.

[0003] In order to solve the above-mentioned foundation pit excavation construction problems, it is urgent to invent a diversion system to solve the above-mentioned technical problems. Utility Model Content

[0004] The utility model provides a diversion system to solve the problem in the prior art that when excavating a foundation pit, the excavation of the foundation pit will involve spatial conflicts with existing power pipelines, and the function of the existing concrete rainwater pipe cannot be abolished during the construction period.

[0005] According to one aspect of the utility model, a diversion system is provided for transforming an existing concrete rainwater pipe erected on the upper part of a planned drainage pipe, the diversion system comprising a steel sheet pile support line, a newly built rainwater well and a diversion steel pipe, the steel sheet pile support lines are arranged on both sides of the planned drainage pipe, the diversion steel pipe is erected between the two steel sheet pile support lines, the newly built rainwater well is arranged on the outside of the steel sheet pile support lines, and the newly built rainwater well is located at the connection between the existing concrete rainwater pipe and the diversion steel pipe.

[0006] Preferably, based on the above solution, the length of the guide steel pipe is greater than the distance between the two steel sheet pile support lines.

[0007] Preferably, based on the above scheme, the distance between the steel sheet pile support lines is 4-5m.

[0008] Preferably, based on the above scheme, the elevation of the guide steel pipe is consistent with the elevation of the existing concrete rainwater pipe.

[0009] The utility model provides a diversion system, which protects the drainage pipe by arranging steel sheet pile support lines on both sides of the planned drainage pipe, and sets up diversion steel pipes on the steel sheet pile support lines, which are connected with the newly built rainwater well through the diversion steel pipes, thereby realizing the connection between the existing concrete rainwater pipe on the upper part of the planned drainage pipe and the diversion pipe.

[0010] Compared with the prior art, the beneficial effects of the present invention are:

[0011] (1) The utility model has a simple shape and does not require the relocation of existing drainage pipelines, thus saving the entire project construction period.

[0012] (2) Use a newly built diversion steel pipe as the diversion section. Its length is greater than the distance between the steel sheet pile support lines, and it can span the support structure in one span. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the technical solutions of the embodiments of the present utility model, the following is a brief introduction to the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0014] Figure 1 It is a structural schematic diagram of the flow diversion system of the utility model;

[0015] Figure 2 It is a side view of the flow diversion system of the utility model;

[0016] Description of Figure Numbers:

[0017] Existing concrete rainwater pipe 1, planned drainage pipe 2, steel sheet pile support line 31, newly built rainwater well 32, and diversion steel pipe 33. DETAILED DESCRIPTION

[0018] The following is a further detailed description of the specific implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0019] It should be understood that when used in this specification and the appended claims, the term "comprising" indicates the presence of described features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections.

[0020] In order to simplify the drawings, only the parts related to the utility model are schematically shown in each figure, and they do not represent the actual structure of the product. In addition, in order to simplify the drawings and facilitate understanding, in some figures, only one of the parts with the same structure or function is schematically drawn or marked. In this article, "one" not only means "only one", but also means "more than one".

[0021] It should be further understood that the term “and / or” used in the specification and appended claims refers to any combination and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0022] In the embodiments shown in the drawings, the directions (such as up, down, left, right, front and back) used to explain the structure and movement of the various components of the present invention are not absolute but relative. These descriptions are appropriate when the components are in the positions shown in the drawings. If the description of the positions of the components changes, the directions also change accordingly.

[0023] In addition, in the description of the present application, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0024] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the specific implementation methods of the utility model will be described below with reference to the accompanying drawings. Obviously, the accompanying drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings and other implementation methods can be obtained based on these drawings without creative work.

[0025] See also Figure 1 , and combined with Figure 2 As shown, a diversion system of the utility model is used to transform an existing concrete rainwater pipe 1 installed on the upper part of a planned drainage pipe 2.

[0026] That is, when designing and planning the construction of the drainage pipe 2, it is necessary to set steel sheet pile support lines 31 at both ends of the planned drainage pipe 2 to facilitate the excavation of the foundation pit and protect the construction of the planned drainage pipe 2. During the construction, there is a concrete rainwater pipeline on the upper part. During the construction, in order to ensure that the function of the existing concrete rainwater pipeline 1 cannot be abolished during the construction, the utility model provides the following solution.

[0027] A diversion system of the utility model includes a steel sheet pile support line 31, a newly built rainwater well 32 and a diversion steel pipe 33, the steel sheet pile support line 31 is arranged on both sides of the planned drainage pipe 2, the diversion steel pipe 33 is erected between the two steel sheet pile support lines 31, the newly built rainwater well 32 is arranged on the outside of the steel sheet pile support line 31, and the newly built rainwater well 32 is located at the connection between the existing concrete rainwater pipe 1 and the diversion steel pipe 33.

[0028] It should be noted that the length of the guide steel pipe 33 of the utility model is greater than the distance between the two steel sheet pile support lines 31, and the distance between the steel sheet pile support lines 31 is 4-5m, and the elevation of the guide steel pipe 33 is consistent with the elevation of the existing concrete rainwater pipe 1.

[0029] The utility model has a simple structure and is easy to operate. By constructing a new diversion section, the problem of not destroying the existing drainage system when a new drainage pipeline 2 is planned is effectively solved.

[0030] A diversion system of the utility model is provided by arranging steel sheet pile support lines 31 on both sides of a planned drainage pipe 2 to protect the drainage pipe, and setting up a diversion steel pipe 33 on the steel sheet pile support line 31, which is connected with a newly built rainwater well 32 through the diversion steel pipe 33, thereby realizing the connection between the existing concrete rainwater pipe 1 on the upper part of the planned drainage pipe 2 and the diversion pipe, and ensuring the normal operation of the existing concrete rainwater pipe 1 during construction.

[0031] Compared with the prior art, the beneficial effects of the present invention are:

[0032] 1. The utility model has a simple shape and does not require the relocation of existing drainage pipelines, thus saving the entire project construction period.

[0033] 2. The utility model uses a newly built diversion steel pipe 33 as a diversion section, the length of which is greater than the distance between the steel sheet pile support lines 31, and can cross the support structure in one span.

[0034] Finally, the method of this application is only a preferred implementation scheme and is not intended to limit the protection scope of the utility model. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model should be included in the protection scope of the utility model.

Claims

1. A diversion system for transforming an existing concrete rainwater pipe installed on the upper part of a planned drainage pipe, characterized in that: The diversion system includes a steel sheet pile support line, a newly built rainwater well and a diversion steel pipe. The steel sheet pile support line is arranged on both sides of the planned drainage pipe, the diversion steel pipe is erected between the two steel sheet pile support lines, the newly built rainwater well is arranged on the outside of the steel sheet pile support line, and the newly built rainwater well is located at the connection between the existing concrete rainwater pipe and the diversion steel pipe.

2. A flow guiding system according to claim 1, characterized in that: The length of the guide steel pipe is greater than the distance between the two steel sheet pile support lines.

3. A flow guiding system according to claim 1, characterized in that: The distance between the steel sheet pile support lines is 4-5m.

4. A flow guiding system according to claim 1, characterized in that: The elevation of the diversion steel pipe is consistent with the elevation of the existing concrete rainwater pipe.