Fabricated floor slab mounting structure based on BIM (Building Information Modeling) technology

By adopting BIM technology in prefabricated buildings, using components such as clamps, screws and steel frames, the problem of large installation errors is solved, and the precise positioning and stable fixation of the floor slabs are achieved, and the construction efficiency is improved.

CN222252690UActive Publication Date: 2024-12-27HENAN ZHONGKE STEEL STRUCTURE CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420098590.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-16
Publication Date
2024-12-27
Estimated Expiration
2034-01-16

AI Technical Summary

Technical Problem

The existing prefabricated building floor slab installation structure has problems such as large installation errors during the installation process, which affects the installation efficiency.

Method used

Adopt the prefabricated floor slab installation structure based on BIM technology, including the base frame, clamp, screw, clamp, sound-absorbing and cushioning pad and steel frame. The clamps are used to adapt to the wall panel surfaces of different verticalities, adjust the preload force, and combine multiple types of Fixed method to eliminate installation errors and achieve precise positioning.

Benefits of technology

It effectively eliminates the error between the wall panel and the floor panel, improves construction efficiency and installation stability, and ensures the precise positioning and stable fixation of the floor panel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222252690U_ABST
    Figure CN222252690U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type floor installation structure based on the BIM technology, and belongs to the technical field of house building. The fabricated floor slab mounting structure based on the BIM technology further comprises a clamping block fixedly arranged on the upper side of the bottom frame. The upper end of each clamping block is slidably connected with a second screw rod. Each second screw is in threaded connection with an adjusting nut on the upper end face of the corresponding clamping block. The lower end of each second screw is fixedly connected with a clamping plate. Sound-absorbing cushioning pads are arranged at the lower ends of the inner sides of the four clamping blocks; the upper end of the sound-absorbing cushioning pad is fixedly connected with the mounting frame; a plurality of steel bar frames are arranged on the inner side of the mounting frame; the two ends of the steel bar frame penetrate through the mounting frame to be clamped with the wallboards; by arranging the clamping blocks, the clamping blocks can adapt to the surfaces of wallboards with different perpendicularity, when the bottom frame is fixed to the surfaces of the wallboards, the clamping blocks are properly bent, the situation that gaps between the installation frame and the wallboards and gaps between the sound-absorbing and cushioning pads and the wallboards are too large in the installation process are avoided, the clamping plates abut against the surfaces of the floors so as to eliminate installation and manufacturing errors, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of house construction, and more specifically relates to an assembled floor slab installation structure based on BIM technology. Background Art

[0002] BIM technology is a digital tool used in engineering design, construction, and management. By integrating the digital and information models of buildings, it is shared and transmitted throughout the life cycle of project planning, operation, and maintenance, so that engineering and technical personnel can correctly understand and efficiently respond to various building information, provide a basis for collaborative work for the design team and all parties involved in the construction, including construction and operation units, and play an important role in improving production efficiency, saving costs, and shortening construction periods. Prefabricated buildings are buildings assembled on site from prefabricated parts and components. Prefabricated buildings have outstanding characteristics such as energy saving and environmental protection, fast construction, controllable costs, safety and durability. Therefore, prefabricated buildings based on BIM technology have high production efficiency and corresponding component cost reduction due to the standardization of design and informatization of management, standard components, and corresponding reduction in component costs. With the digital management of the factory, the cost performance of the entire prefabricated building will become higher and higher. Using BIM technology, analyzing the stress during floor slab installation and collecting feedback on technical issues, and designing a floor slab installation structure that is easy to install and adjust and reduces the impact of installation errors on construction is an important and indispensable research direction for prefabricated buildings.

[0003] For example, a prefabricated building floor installation structure with patent application number CN202022052572.8 includes a bottom plate layer, grooves are provided on both sides of the bottom end of the bottom plate layer, and a fixing mechanism is connected in each groove. Each fixing mechanism runs through the bottom plate layer, the sound insulation board and the steel bar layer. The bottom plate layer, the sound insulation board and the steel bar layer constitute the floor plate, and the bottom end of each fixing mechanism is connected to a connecting block, and the bottom end of each connecting block is connected to a fixing plate, and the upper ends of the fixing plates are connected to a slide frame on both sides, and each connecting block is connected to a slider on both sides, and each slider is connected to the slide frame, and the bottom end of each fixing plate is connected to a side plate, and each side plate is connected to a fixing bolt. The utility model adjusts the spacing between the two side plates so that the opposite sides of the two side plates are in contact with the wall, and then fixes the side plates to the wall by fixing bolts, thereby fixing the floor plate, and the floor plate installation is simple.

[0004] Although the above-mentioned prefabricated building floor installation structure is simple to install, there is still a problem of large installation error during installation, which affects the installation efficiency. Utility Model Content

[0005] In order to solve the above technical problems, the utility model provides a prefabricated floor installation structure based on BIM technology, which improves construction efficiency, accurately positions, and eliminates errors between wall panels and floor panels.

[0006] The utility model discloses an assembled floor installation structure based on BIM technology, comprising a base frame; the base frames are in two pairs; the outer side of each base frame is fixedly connected to a wall panel; a screw rod is arranged at the lower end of each base frame; each base frame is threadedly connected to the wall panel through a screw rod; each screw rod is located at the outer side of the base frame and is threadedly connected to a locking nut; it also comprises a clamping block fixedly arranged on the upper side of the base frame; the upper end of each clamping block is slidably connected to a screw rod; each screw rod is threadedly connected to an adjusting nut on the upper end surface of the clamping block; the lower end of each screw rod is fixedly connected to a clamping plate; sound-absorbing and shock-absorbing pads are arranged at the lower ends of the inner sides of four clamping blocks; the upper ends of the sound-absorbing and shock-absorbing pads are fixedly connected to an installation frame; a plurality of steel bars are arranged at the inner side of the installation frame; the two ends of the steel bars pass through the installation frame to clamp the wall panel.

[0007] Preferably, two pairs of code plates are fixedly arranged at the lower end of the sound-absorbing and shock-absorbing pad; each of the code plates corresponds to an adjacent base frame; and each of the code plates is fixedly connected to the base frame.

[0008] Preferably, each of the clamping plates is a high-elastic rubber plate.

[0009] Preferably, the code plate is a multi-layer high-density shock-absorbing and sound-absorbing sponge plate.

[0010] Preferably: a sleeve is provided at the connection between each of the steel reinforcement frames and the installation frame.

[0011] Compared with the prior art, the beneficial effects of the present invention are:

[0012] (1) By setting the clamping block, the clamping block can adapt to the wall panel surface with different verticality. When the base frame is fixed on the wall panel surface, the clamping block is appropriately bent to avoid excessive gap between the installation frame, sound-absorbing and shock-absorbing pad and the wall panel during installation, so that the clamping plate presses against the floor surface to eliminate installation and manufacturing errors and improve construction efficiency;

[0013] (2) By setting the clamp and the screw, the preload force on the floor slab during installation can be adjusted; the deformation of the clamp block is appropriately adjusted, the clamp is matched with the lower end of the clamp block, and then the code plate and the base frame are welded, and finally the steel frame is combined with the installation frame and the wall panel to fix the floor slab in multiple ways, eliminating installation errors and making the floor slab installation stable; the code plate and the base frame are welded after docking, and the positioning is precise to eliminate the error between the wall panel and the floor slab. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0015] Figure 2 It is a schematic diagram of the main structure of the utility model.

[0016] Explanation of the numbers in the figure: 10, base frame; 11, locking nut; 12, screw one; 13, clamp block; 14, wall panel; 15, clamp plate; 16, adjusting nut; 17, screw two; 18, installation frame; 19, steel frame; 20, sound-absorbing and shock-absorbing pad; 21, code plate. DETAILED DESCRIPTION

[0017] Specific embodiment 1: Please refer to Figure 1-2 A prefabricated floor installation structure based on BIM technology includes a base frame 10; the base frames 10 are in two pairs; each base frame 10 is fixedly connected to a wall panel 14 on the outside; a screw 12 is arranged at the lower end of each base frame 10; each base frame 10 is threadedly connected to the wall panel 14 through a screw 12; each screw 12 is located on the outer side of the base frame 10 and is threadedly connected to a locking nut 11; it also includes a clamping block 13 fixedly arranged on the upper side of the base frame 10; each clamping block 13 is slidably connected to a screw 2 17 at the upper end; each screw 2 17 is threadedly connected to an adjusting nut 16 on the upper end surface of the clamping block 13; each screw 2 17 is threadedly connected to an adjusting nut 16 at the lower end A clamping plate 15 is fixedly connected; a sound-absorbing and shock-absorbing pad 20 is arranged at the lower inner end of the four clamping blocks 13; the upper end of the sound-absorbing and shock-absorbing pad 20 is fixedly connected to the mounting frame 18; a plurality of steel frames 19 are arranged inside the mounting frame 18; both ends of the steel frames 19 pass through the mounting frame 18 to clamp the wall panel 14; by arranging the clamping blocks 13, the clamping blocks 13 can adapt to the surfaces of the wall panels 14 with different verticalities. When the base frame 10 is fixed on the surface of the wall panel 14, the clamping blocks 13 are appropriately bent to avoid excessive gaps between the mounting frame 18, the sound-absorbing and shock-absorbing pad 20 and the wall panel 14 during installation, so that the clamping plates 15 are pressed against the floor surface to eliminate installation and manufacturing errors and improve construction efficiency.

[0018] See also Figure 2 Two pairs of code plates 21 are fixedly arranged at the lower end of the sound-absorbing and shock-absorbing pad 20; each of the code plates 21 corresponds to the adjacent base frame 10; each of the code plates 21 is fixedly connected to the base frame 10; by setting the clamping plate 15 and the screw rod 17, the pre-tightening force of the floor during installation can be adjusted; the deformation of the clamping block 13 is appropriately adjusted, the clamping plate 15 cooperates with the lower end of the clamping block 13, and then the code plates 21 and the base frame 10 are welded, and finally the steel frame 19 is combined with the installation frame 18 and the wall panel 14 to fix the floor in a variety of fixing methods, thereby eliminating the installation error and making the floor installation stable; the code plates 21 are welded after being docked with the base frame 10, and the positioning is precise, thereby eliminating the error between the wall panel 14 and the floor.

[0019] See also Figure 2 Each of the clamping plates 15 is a high-elastic rubber plate.

[0020] See also Figure 1 The code plate 21 is a multi-layer high-density shock-absorbing and sound-absorbing sponge plate.

[0021] See also Figure 2A sleeve is provided at the connection between each of the steel reinforcement frame 19 and the installation frame 18 .

[0022] See also Figure 2 The clamp block 13 is a high-toughness C-shaped steel with aluminum-iron alloy as the main raw material.

[0023] During operation, first fix the base frame 10 on the wall panel 14, tighten the locking nut 11, so that the screw 12 can press the locking nut 11 on the base frame 10, and firmly fix the base frame 10 on the wall panel 14, and then weld the clamping block 13 on the base frame 10; first fix the installation frame 18 with the sound-absorbing and shock-absorbing pad 20, and then use the crane and the lifting ears set on the installation frame 18, and then adjust the position of the sound-absorbing and shock-absorbing pad 20 so that the code plate 21 is aligned with the base frame 10. 14, and then weld the code plate 21 and the base frame 10 together, then adjust the adjusting nut 16 and the clamping block 13 to level the installation frame 18; tighten the adjusting nut 16, and the clamping plate 15 presses the upper surface of the installation frame 18, so that the installation frame 18 and the sound-absorbing and shock-absorbing pad 20 are fixed under the action of the pre-tightening force; insert the steel frame 19 into the installation frame 18 and the wall panel 14, and use the steel frame 19 to fix the installation frame 18 and the sound-absorbing and shock-absorbing pad 20 on the wall panel 14. After completing the installation of the assembled floor of the steel structure, other floor materials can be laid faster and safer, and other construction processes can be carried out.

[0024] For example, certain words are used in the specification and claims to refer to specific components. Those skilled in the art should understand that hardware manufacturers may use different terms to refer to the same component. This specification and claims do not use differences in names as a way to distinguish components, but use differences in the functions of components as the criteria for distinction. For example, "including" mentioned throughout the specification and claims is an open term, so it should be interpreted as "including but not limited to". "Approximately" means that within an acceptable error range, those skilled in the art can solve the technical problem within a certain error range and basically achieve the technical effect.

[0025] It should be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a product or system including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such product or system. In the absence of more restrictions, the elements defined by the sentence "including one..." do not exclude the existence of other identical elements in the product or system including the elements.

[0026] The above description shows and describes several preferred embodiments of the present application, but as mentioned above, it should be understood that the present application is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the application concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art do not deviate from the spirit and scope of the present application, and should be within the scope of protection of the claims attached to the present application.

Claims

1. An assembled floor installation structure based on BIM technology, comprising a base frame (10); the base frames (10) are provided in two pairs; the outer side of each base frame (10) is fixedly connected to a wall panel (14); a screw rod (12) is provided at the lower end of each base frame (10); each base frame (10) is threadedly connected to the wall panel (14) via a screw rod (12); each screw rod (12) is located on the outer side of the base frame (10) and is threadedly connected to a locking nut (11); characterized in that: It also includes a clamping block (13) fixedly arranged on the upper side of the base frame (10); the upper end of each clamping block (13) is slidably connected to a screw rod (17); each screw rod (17) is threadedly connected to an adjusting nut (16) on the upper end surface of the clamping block (13); the lower end of each screw rod (17) is fixedly connected to a clamping plate (15); sound-absorbing and shock-absorbing pads (20) are arranged on the inner lower end surfaces of the four clamping blocks (13); the upper ends of the sound-absorbing and shock-absorbing pads (20) are fixedly connected to a mounting frame (18); a plurality of steel bars (19) are arranged inside the mounting frame (18); and both ends of the steel bars (19) pass through the mounting frame (18) to clamp the wall panel (14).

2. The assembled floor installation structure based on BIM technology according to claim 1 is characterized in that: Two pairs of code plates (21) are fixedly arranged at the lower end of the sound-absorbing and shock-absorbing pad (20); each of the code plates (21) corresponds to an adjacent bottom frame (10); and each of the code plates (21) is fixedly connected to the bottom frame (10).

3. The assembled floor installation structure based on BIM technology according to claim 1 is characterized in that: Each of the clamping plates (15) is a highly elastic rubber plate.

4. The assembled floor installation structure based on BIM technology according to claim 2 is characterized in that: The code plate (21) is a multi-layer high-density shock-absorbing and sound-absorbing sponge plate.

5. The assembled floor installation structure based on BIM technology according to claim 1 is characterized in that: A sleeve is provided at the connection between each steel bar frame (19) and the installation frame (18).

Citation Information

Patent Citations

  • Fabricated building floor slab mounting structure

    CN213926968U