Drainage assembly on mine roadway roof

By designing the drainage components on the top plate of the mine tunnel, and using multiple sets of drainage and diversion components, multi-point drainage and filtering diversion of water on the top plate of the tunnel tunnel is achieved, solving the problem that the existing technology cannot deal with severe water seepage in a timely manner. Reduces safety hazards.

CN222276739UActive Publication Date: 2024-12-31INNER MONGOLIA GAOERQI MINING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420926291.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-29
Publication Date
2024-12-31
Estimated Expiration
2034-04-29

AI Technical Summary

Technical Problem

The seepage of the top plate of the mine tunnel is random and irregular in cycles. The existing methods cannot deal with severe seepage in time on rainy days, resulting in safety hazards.

Method used

A mine tunnel roof drainage assembly is designed, including a drainage assembly fixed to the tunnel roof. It is equipped with multiple sets of drainage parts and guides. The drainage parts are inserted into the rock layer through the roof, and the guides filter and transport water flow. , combined with arc plate and precipitation box, realize multi-point drainage and filtration diversion.

Benefits of technology

It speeds up the drainage speed, reduces the probability of safety hazards, can diversion when water seeps slightly, and quickly deal with it when water seeps severely on rainy days.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222276739U_ABST
    Figure CN222276739U_ABST
Patent Text Reader

Abstract

The utility model discloses a drainage assembly on a mine roadway roof, which comprises a roadway roof fixed in a roadway, and is characterized in that the inner side surface of the roadway roof is fixedly connected with a drainage assembly, a plurality of drainage piece groups are sequentially arranged in the drainage assembly from front to back, and the drainage piece groups penetrate through the roadway roof; the drainage assembly is arranged in the roadway roof and inserted into a rock layer on the top of the roadway roof, the drainage piece sets can conduct drainage and collection on water in the rock layer on the upper portion of the roadway roof, flow guide pieces are fixedly connected to the two sides of the drainage assembly respectively, and the flow guide pieces can conduct filtering, flow guiding and conveying on the water in the drainage assembly. Water in a rock layer on the upper portion of a roadway roof can be drained and collected, multi-point drainage and collection are formed, drainage is accelerated, and the probability of potential safety hazards is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical field:

[0001] The utility model relates to the field of roof drainage components, in particular to a drainage component on a roof of a mine tunnel. Background technology:

[0002] The stability of mines and hydrological conditions are constantly changing, resulting in random and irregular distribution of water seepage points on the roof of mine tunnels, posing a safety hazard to tunnel workers and equipment. When tunnel water seepage is slight, plugging is usually used to deal with it. However, when tunnel water seepage is severe on rainy days, timely measures cannot be taken. Some methods include laying impermeable boards on the top of the tunnel to divert the seepage to both sides. The drainage effect is slow and it is still easy to pose a safety hazard to tunnel workers and equipment. Utility model content:

[0003] To this end, the utility model provides a drainage component on the roof of a mine tunnel to overcome the problem that the prior art usually adopts a plugging method to deal with slight tunnel water seepage, but cannot take timely measures when the tunnel water seepage is serious on rainy days. Some methods include laying impermeable plates on the top of the tunnel to guide the seepage to both sides, but the drainage effect is slow and it is easy to bring safety hazards to tunnel workers and equipment.

[0004] The utility model is implemented by the following technical solutions:

[0005] A drainage assembly on a mine tunnel roof comprises a tunnel roof fixed in the tunnel, and is characterized in that a drainage assembly is fixedly connected to the inner side surface of the tunnel roof, and a plurality of drainage component groups are sequentially arranged in the drainage assembly from front to back, the drainage component groups pass through the tunnel roof and are inserted into the rock layer at the top of the tunnel roof, and the drainage component groups can drain and collect water in the rock layer on the upper part of the tunnel roof, and the drainage components are fixedly connected to guide components on both sides of the drainage assembly, and the guide components can filter, divert and transport the water in the drainage assembly.

[0006] Preferably, the drainage assembly includes a plurality of drainage members sequentially arranged at the lower inner portion of the tunnel roof, and baffles are fixedly connected to both sides of each drainage member, and the baffles are fixedly connected to the tunnel roof.

[0007] Preferably, the drainage member comprises a plurality of arc-shaped plates fixedly connected in sequence, and an arc-shaped groove is fixedly provided in each arc-shaped plate, and the inner surface of the arc-shaped groove is mirror-polished, and a drainage member group is arranged in each arc-shaped plate.

[0008] Preferably, the guide member group includes a plurality of guide members, which are uniformly arranged in sequence above the arc plate, and the plurality of guide members pass through the tunnel roof in a radial shape and are inserted into the rock layer on the upper part of the tunnel roof, and the guide members are fixedly connected to the tunnel roof.

[0009] Preferably, the guide member is a tapered steel pipe, and a drill bit is fixed to the front end of the tapered steel pipe. A plurality of guide holes are annularly fixed on the outer wall of the tapered steel pipe, and a filter screen is fixed in the guide holes.

[0010] Preferably, the guide member includes a sedimentation box, and a sedimentation box is fixed on both sides of each arc plate, and the sedimentation box is arranged on both sides of the tunnel roof. The side ends of the sedimentation box are fixedly connected with a drainage pipe, and the drainage pipe is fixed on the side of the tunnel. The bottom of the drainage pipe passes through the cover plate and is inserted into the drainage trough. The bottom surface of the drainage trough is set with an inclined surface, and a cover plate is fixed on the top of the drainage trough.

[0011] Preferably, the sedimentation box includes a plurality of partitions fixedly arranged in sequence inside, and the heights of the plurality of partitions are successively reduced, and the plurality of partitions divide the sedimentation box into a plurality of sedimentation tanks, a plurality of through holes are fixed on the top of each partition, a discharge pipe is fixed at the bottom of each sedimentation tank, a valve is fixed on the discharge pipe, and a threaded pipe is fixed at the bottom of the discharge pipe.

[0012] The advantages of the utility model are as follows: by installing a plurality of drainage component groups in the drainage assembly, the water in the rock layer on the upper part of the tunnel roof can be drained and collected to form multi-point drainage and collection, thereby accelerating drainage and reducing the probability of potential safety hazards. Description of the drawings:

[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0014] Figure 1 It is a schematic diagram of the structure of the utility model;

[0015] Figure 2 It is a side cross-sectional structural schematic diagram of the utility model;

[0016] Figure 3 It is a schematic diagram of the local structure of the utility model.

[0017] In the figure: tunnel roof 1, drainage parts 2, baffles 3, curved plates 4, tapered steel pipes 5, drill bits 6, sedimentation boxes 7, drainage pipes 8, drainage troughs 9, and discharge pipes 10. Specific implementation method:

[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0019] like Figure 1 , Figure 2 , Figure 3 As shown, the drainage assembly on the roof of a mine tunnel includes a tunnel roof 1 fixed in the tunnel, and the inner side of the tunnel roof 1 is fixedly connected to the drainage assembly, and a plurality of drainage component groups are arranged in sequence from front to back in the drainage assembly, the drainage component group passes through the tunnel roof 1, and is inserted into the top rock layer of the tunnel roof 1, and the drainage component group can drain and collect water in the upper rock layer of the tunnel roof, and the two sides of the drainage assembly are respectively fixedly connected with guide components, and the guide components can filter, guide and transport the water in the drainage assembly.

[0020] During use, multiple groups of drainage components drain the water in the rock layer on the upper part of the tunnel roof in multiple directions and collect it into the drainage component. The water in the drainage component is then filtered and diverted to the collection area outside the mine tunnel through the diversion components to complete the drainage operation on the mine tunnel roof. It can divert water when the tunnel seepage is slight, and it can also speed up the diversion operation when the tunnel seepage is serious on rainy days, effectively reducing the probability of safety hazards.

[0021] The drainage assembly includes a plurality of drainage components 2 sequentially arranged at the lower inner part of the road roof 1 , and baffles 3 are fixedly connected to both sides of each drainage component 2 , respectively, and the baffles 3 are fixedly connected to the roadway roof 1 .

[0022] The drainage member 2 includes a plurality of arc-shaped plates 4 which are fixedly connected in sequence, and an arc-shaped groove is fixedly provided in each arc-shaped plate 4 , and the inner surface of the arc-shaped groove is mirror-polished, and a drainage member group is arranged in each arc-shaped plate 4 .

[0023] During use, the drainage component group can drain water into the drainage component 2, because each arc-shaped plate 4 is fixedly provided with an arc-shaped groove, so that multiple drainage component groups can divert the water flow into multiple arc-shaped plates 4 to achieve drainage operation.

[0024] The guide member group includes a plurality of guide members, which are uniformly arranged in sequence above the arc plate 4, and the plurality of guide members pass through the tunnel roof 1 in a radial shape and are inserted into the rock layer on the upper part of the tunnel roof. The guide members are fixedly connected to the tunnel roof 1.

[0025] The flow guide member adopts a tapered steel pipe 5, and a drill bit 6 is fixed to the front end of the tapered steel pipe 5. A plurality of flow guide holes are annularly fixed on the outer wall of the tapered steel pipe 5, and a filter screen is fixed in the flow guide holes.

[0026] During use, multiple diversion pieces are used to penetrate the tunnel roof 1 in a radial shape, so that the diversion and collection effect in multiple directions can be achieved. At the same time, a drill bit 6 is fixed on the front end of the conical steel pipe 5, which can make it easy to insert the diversion piece into the rock layer on the upper part of the tunnel roof. During drainage, the diversion hole can achieve the diversion effect on the water flow.

[0027] The guide member includes a sedimentation box 7, and a sedimentation box 7 is fixed on both sides of each arc plate 4. The sedimentation box 7 is arranged on both sides of the tunnel roof 1. The side ends of the sedimentation box 7 are fixedly connected with a drainage pipe 8, and the drainage pipe 8 is fixed on the side of the tunnel. The bottom of the drainage pipe 8 passes through the cover plate and is inserted into the drainage groove 9. The bottom surface of the drainage groove 9 is set with an inclined surface, and a cover plate is fixed on the top of the drainage groove 9.

[0028] The sedimentation box 7 includes a plurality of partitions fixedly arranged in sequence, and the heights of the plurality of partitions are successively reduced, and the plurality of partitions divide the sedimentation box 7 into a plurality of sedimentation tanks, a plurality of through holes are fixed on the top of each partition, a discharge pipe 10 is fixed at the bottom of each sedimentation tank, a valve is fixed on the discharge pipe 10, and a threaded pipe is fixed at the bottom of the discharge pipe 10.

[0029] During use, a plurality of partitions with successively lowered heights are used in the sedimentation box 7 to achieve a stepped sedimentation effect, so that the water flow can complete a certain degree of sedimentation in each sedimentation tank, preventing debris in the water flow from clogging the drain pipe 8. The drain pipe 8 can divert the water flow into the drainage trough 9. At the same time, because the bottom surface of the drainage trough 9 is set with an inclined surface, the water can be diverted and transported to the collection area outside the mine tunnel.

[0030] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A drainage assembly on a mine tunnel roof, comprising a tunnel roof fixed in the tunnel, characterized in that: A drainage component is fixedly connected to the inner side surface of the tunnel roof, and a plurality of drainage component groups are arranged in sequence from front to back in the drainage component. The drainage component group passes through the tunnel roof and is inserted into the rock layer at the top of the tunnel roof, and the drainage component group can drain and collect water in the rock layer on the upper part of the tunnel roof. Guide components are fixedly connected on both sides of the drainage component, and the guide components can filter, divert and transport the water in the drainage component.

2. The drainage assembly on the mine tunnel roof according to claim 1, characterized in that: The drainage assembly includes a plurality of drainage components sequentially arranged in the lower part of the tunnel roof, and baffles are fixedly connected to both sides of each drainage component, and the baffles are fixedly connected to the tunnel roof.

3. The drainage assembly on the mine tunnel roof according to claim 2, characterized in that: The drainage member comprises a plurality of arc-shaped plates which are fixedly connected in sequence, and an arc-shaped groove is fixedly provided in each arc-shaped plate, and the inner surface of the arc-shaped groove is mirror-polished, and a drainage member group is arranged in each arc-shaped plate.

4. The drainage assembly on the mine tunnel roof according to claim 3, characterized in that: The guide member group includes a plurality of guide members, which are uniformly arranged in sequence above the arc plate, and the plurality of guide members pass through the tunnel roof in a radial shape and are inserted into the rock layer on the upper part of the tunnel roof. The guide members are fixedly connected to the tunnel roof.

5. The drainage assembly on the roof of a mine tunnel according to claim 4, characterized in that: The flow guide member adopts a conical steel pipe, and a drill bit is fixed on the front end of the conical steel pipe. A plurality of flow guide holes are annularly fixed on the outer wall of the conical steel pipe, and a filter screen is fixed in the flow guide hole.

6. The drainage assembly on the roof of a mine tunnel according to claim 5, characterized in that: The guide member includes a sedimentation box, and each arc plate is fixed with a sedimentation box on both sides. The sedimentation box is arranged on both sides of the tunnel roof. The side ends of the sedimentation box are fixedly connected with a drainage pipe, and the drainage pipe is fixed on the side of the tunnel. The bottom of the drainage pipe passes through the cover plate and is inserted into the drainage trough. The bottom surface of the drainage trough is set with an inclined surface, and the top of the drainage trough is fixed with a cover plate.

7. The drainage assembly on the roof of a mine tunnel according to claim 6, characterized in that: The sedimentation box includes a plurality of partitions fixedly arranged in sequence, and the heights of the plurality of partitions are successively reduced, and the plurality of partitions divide the sedimentation box into a plurality of sedimentation tanks, a plurality of through holes are fixed on the top of each partition, a discharge pipe is fixed at the bottom of each sedimentation tank, a valve is fixed on the discharge pipe, and a threaded pipe is fixed at the bottom of the discharge pipe.