Ultrahigh concrete pumping pump pipe fixing device

By combining the adjusting plate and screw nut structure, the problem of fixing dual-pump pipelines was solved, achieving stable fixing of pipelines of different sizes and improving construction efficiency and stability.

CN222334689UActive Publication Date: 2025-01-10CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP 1ST ENG +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421281169.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2025-01-10
Estimated Expiration
2034-06-06

AI Technical Summary

Technical Problem

Existing technologies make it difficult to simultaneously fix dual pumping pipelines, affecting construction progress and quality.

Method used

The positions of the first and second adjustment plates are adjusted by the first and second installation components, respectively. The pumping pipes are embedded through the first and third installation slots, and the dual pumping pipes are fixed by the screw and nut structure.

Benefits of technology

It enables stable fixing of dual pumping pipelines of different sizes, improving installation stability and construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222334689U_ABST
    Figure CN222334689U_ABST
Patent Text Reader

Abstract

The utility model provides an ultrahigh pump concrete pump pipe fixing device, which belongs to the technical field of pipeline installation and comprises a connecting plate group, a first fixing plate, a first adjusting plate, a first installation component, a second fixing plate, a second adjusting plate and a second installation component. The connecting plate group comprises a first connecting plate and a second connecting plate, and the first connecting plate is vertically connected with the second connecting plate; a first mounting groove is formed in the first fixing plate in a penetrating manner, and the first fixing plate is connected with one side of the second connecting plate; a second mounting groove is formed in the first adjusting plate in a penetrating manner, and the second mounting groove of the first adjusting plate is opposite to the first mounting groove; according to the device, the positions of the first adjusting plate and the second adjusting plate are adjusted through the first mounting assembly and the second mounting assembly correspondingly, so that the effect of adjusting according to double pumping pipelines of different sizes can be achieved, and then the purpose of fixing the double pumping pipelines at the same time is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of pipeline installation, and in particular relates to a super-high pumping concrete pump pipe fixing device. Background Art

[0002] Pumped concrete is the process of transporting and pouring concrete mixtures along a delivery pipe using a concrete pump or pump truck. Currently, in the construction of super-high main towers, in order to avoid factors such as discontinuous tower column concrete pouring due to pump pipe failure and quality defects, as well as to avoid progress being affected by pump pipe replacement, a dual pumping pipeline arrangement is adopted for the main tower concrete.

[0003] In a patent application with application number 202122970934.6, an ultra-high pumping concrete pump pipe support frame is proposed, and the support chassis of the ultra-high pumping concrete pump pipe support frame is provided with symmetrically distributed closing plates, and the closing plates are arc-shaped structures, so that the pump pipe can be flipped and clamped through the closing plates and connecting hinges, and a magnetic block with an arc-shaped structure is provided on one side of the support chassis, so that when the pump pipe is installed, it can be magnetically adsorbed through the magnetic block, making the installation more convenient.

[0004] However, the above technical solution is not convenient for fixing the dual pumping pipelines at the same time, and therefore a device capable of fixing the dual pumping pipelines at the same time is urgently needed. Utility Model Content

[0005] Based on the above technical problems, the utility model provides an ultra-high pumping concrete pump pipe fixing device, which adjusts the positions of a first adjustment plate and a second adjustment plate respectively through a first mounting component and a second mounting component, thereby achieving the function of being able to adjust dual pumping pipes according to different sizes respectively, thereby achieving the purpose of fixing the dual pumping pipes at the same time.

[0006] The specific technical solution is:

[0007] A super-high pumping concrete pump pipe fixing device comprises: a connecting plate group, a first fixing plate, a first adjusting plate, a first mounting assembly, a second fixing plate, a second adjusting plate and a second mounting assembly; the connecting plate group comprises a first connecting plate and a second connecting plate, the first connecting plate is vertically connected to the second connecting plate; the first fixing plate is provided with a first mounting groove through it, and the first fixing plate is connected to one side of the second connecting plate; the first adjusting plate is provided with a second mounting groove through it, and the second mounting groove of the first adjusting plate is opposite to the first mounting groove; the first mounting assembly comprises two first screws and four first nuts, one end of the two first screws is respectively connected to the two sides of the top surface of the first adjusting plate, and the other ends of the two first screws are respectively passed through the second connecting plate On both sides of the connecting plate, four first nuts are respectively sleeved on the outside of the two first screws, and the four first nuts are all in contact with the side walls of the second connecting plate; the second fixing plate is penetrated by a third mounting groove, and the second fixing plate is connected to the other side of the second connecting plate; the second adjusting plate is penetrated by a fourth mounting groove, and the fourth mounting groove of the second adjusting plate is opposite to the third mounting groove; the second mounting assembly includes two second screws and four second nuts, one ends of the two second screws are respectively connected to the two sides of the top surface of the second adjusting plate, the other ends of the two second screws respectively pass through the two sides of the second connecting plate, the four second nuts are respectively sleeved on the outside of the two second screws, and the four second nuts are all in contact with the side walls of the second connecting plate.

[0008] In addition, the ultra-high pumping concrete pump pipe fixing device in the above technical solution provided by the utility model may also have the following additional technical features:

[0009] In the above technical solution, it also includes: two first circular holes and two second circular holes; the two first circular holes are respectively arranged on both sides of the second connecting plate, and the two first screws pass through the two first circular holes respectively; the two second circular holes are respectively arranged on both sides of the second connecting plate, and the two second screws pass through the two second circular holes respectively; wherein the two second circular holes are respectively located below the two first circular holes and the first fixed plate.

[0010] In the above technical solution, it also includes: a first reinforcing plate and a second reinforcing plate; one end of the first reinforcing plate is connected to the top of the first connecting plate, and the other end of the first reinforcing plate is connected to the top of one side of the second connecting plate; one end of the second reinforcing plate is connected to the bottom end of the first connecting plate, and the other end of the second reinforcing plate is connected to the bottom end of the other side of the second connecting plate.

[0011] In the above technical solution, the first fixing plate, the first adjusting plate, the second fixing plate and the second adjusting plate are all steel plates with a thickness of 2 cm.

[0012] In the above technical solution, the diameters of the first screw and the second screw are both 20 mm.

[0013] In the above technical solution, it also includes: four mounting holes; the mounting holes are elliptical, and the four mounting holes are evenly arranged on the first connecting plate.

[0014] Compared with the prior art, the utility model of a super-high pumping concrete pump pipe fixing device has the following beneficial effects:

[0015] 1. By embedding the two pumping pipes into the first mounting groove and the third mounting groove respectively, and using the first mounting assembly and the second mounting assembly to adjust the positions of the first adjustment plate and the second adjustment plate respectively, the dual pumping pipes of different sizes can be adjusted respectively, thereby achieving the purpose of fixing the dual pumping pipes at the same time.

[0016] 2. The double-nut fixing structure is adopted to improve the stability when installing the first adjustment plate and the second adjustment plate. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of an ultra-high pumping concrete pump pipe fixing device and a pumping pipeline after installation of the utility model;

[0018] Figure 2 This is a front view of a super-high concrete pump pipe fixing device of the utility model;

[0019] Figure 3 This is a schematic diagram of the structure of the first adjustment plate and the second adjustment plate of the utility model after being assembled;

[0020] Figure 4 It is a schematic diagram of the structure after the first adjustment plate and the second adjustment plate of the utility model are separated;

[0021] in, Figures 1 to 4 The corresponding relationship between the reference numerals and component names in the figure is:

[0022] 10 first connecting plate, 11 second connecting plate, 12 first fixing plate, 13 first mounting groove, 14 first adjusting plate, 15 second mounting groove, 16 first screw rod, 17 first nut, 18 second fixing plate, 19 third mounting groove, 20 second adjusting plate, 21 fourth mounting groove, 22 second screw rod, 23 second nut, 24 first circular hole, 25 second circular hole, 26 first reinforcing plate, 27 second reinforcing plate, 28 mounting hole, 29 pumping pipe. DETAILED DESCRIPTION

[0023] The following is a combination of specific implementation cases and attached Figure 1-4 The present invention is further described below, but the present invention is not limited to these embodiments.

[0024] A super-high pumping concrete pump pipe fixing device, comprising: a connecting plate group, a first fixing plate 12, a first adjusting plate 14, a first mounting assembly, a second fixing plate 18, a second adjusting plate 20 and a second mounting assembly; the connecting plate group comprises a first connecting plate 10 and a second connecting plate 11, and the first connecting plate 10 is vertically connected to the second connecting plate 11; the first fixing plate 12 is penetrated by a first mounting groove 13, and the first fixing plate 12 is connected to one side of the second connecting plate 11; the first adjusting plate 14 is penetrated by a second mounting groove 15, and the second mounting groove 15 of the first adjusting plate 14 is opposite to the first mounting groove 13; the first mounting assembly comprises two first screw rods 16 and four first nuts 17, one end of the two first screw rods 16 are respectively connected to the two sides of the top surface of the first adjusting plate 14, and the other ends of the two first screw rods 16 respectively pass through the second connecting plate On both sides of 11, four first nuts 17 are respectively sleeved on the outside of the two first screws 16, and the four first nuts 17 are all in contact with the side walls of the second connecting plate 11; the second fixing plate 18 is penetrated by a third mounting groove 19, and the second fixing plate 18 is connected to the other side of the second connecting plate 11; the second adjusting plate 20 is penetrated by a fourth mounting groove 21, and the fourth mounting groove 21 of the second adjusting plate 20 is opposite to the third mounting groove 19; the second mounting assembly includes two second screws 22 and four second nuts 23, one ends of the two second screws 22 are respectively connected to the two sides of the top surface of the second adjusting plate 20, the other ends of the two second screws 22 respectively pass through the two sides of the second connecting plate 11, the four second nuts 23 are respectively sleeved on the outside of the two second screws 22, and the four second nuts 23 are all in contact with the side walls of the second connecting plate 11.

[0025] With the above structure, by respectively embedding the two pumping pipes 29 into the first mounting groove 13 and the third mounting groove 19, and using the first mounting assembly and the second mounting assembly to respectively adjust the positions of the first adjustment plate 14 and the second adjustment plate 20, the dual pumping pipes 29 of different sizes can be adjusted respectively, thereby achieving the purpose of simultaneously fixing the dual pumping pipes 29. And by adopting a double nut fixing structure, the stability when installing the first adjustment plate 14 and the second adjustment plate 20 is improved.

[0026] Specifically, after the first connecting plate 10 is fixed at a specified position by using a fixing member, multiple positions of the dual pumping pipeline 29 are fixed from bottom to top, and the first nut 17 and the second nut 23 are tightened, thereby completing the installation of the dual pumping pipeline 29.

[0027] Specifically, the interval between two adjacent first connecting plates 10 is 4.5 m.

[0028] In an embodiment of the utility model, it also includes: two first circular holes 24 and two second circular holes 25; the two first circular holes 24 are respectively arranged on both sides of the second connecting plate 11, and the two first screw rods 16 pass through the two first circular holes 24 respectively; the two second circular holes 25 are respectively arranged on both sides of the second connecting plate 11, and the two second screw rods 22 pass through the two second circular holes 25 respectively; wherein, the two second circular holes 25 are respectively located below the two first circular holes 24 and the first fixing plate 12.

[0029] The positions of the first screw 16 and the second screw 22 are guided respectively through the first circular hole 24 and the second circular hole 25, so as to facilitate determining the positions of the first screw 16, the second screw 22, the first adjustment plate 14 and the second adjustment plate 20, so that when they are installed on the second connecting plate 11, the second mounting groove 15 and the fourth mounting groove 21 of the first adjustment plate 14 and the second adjustment plate 20 are respectively relative to the first mounting groove 13 and the third mounting groove 19 of the first fixing plate 12 and the second fixing plate 18.

[0030] In an embodiment of the utility model, it also includes: a first reinforcing plate 26 and a second reinforcing plate 27; one end of the first reinforcing plate 26 is connected to the top of the first connecting plate 10, and the other end of the first reinforcing plate 26 is connected to the top of one side of the second connecting plate 11; one end of the second reinforcing plate 27 is connected to the bottom end of the first connecting plate 10, and the other end of the second reinforcing plate 27 is connected to the bottom end of the other side of the second connecting plate 11.

[0031] The first reinforcing plate 26 and the second reinforcing plate 27 strengthen the connection strength between the first connecting plate 10 and the second connecting plate 11, thereby improving the stability of the device.

[0032] In the embodiment of the present invention, the first fixing plate 12 , the first adjusting plate 14 , the second fixing plate 18 and the second adjusting plate 20 are all steel plates with a thickness of 2 cm.

[0033] In the embodiment of the present invention, the diameters of the first screw 16 and the second screw 22 are both 20 mm.

[0034] In the embodiment of the utility model, it further comprises: four mounting holes 28 ; the mounting holes 28 are elliptical, and the four mounting holes 28 are evenly arranged on the first connecting plate 10 .

[0035] By setting the mounting hole 28 to be elliptical, when the first connecting plate 10 is installed at a specified position using a fixing, the fixing can have a certain range of lateral movement in the mounting hole 28, thereby being able to fine-tune the position of the first connecting plate 10 according to actual needs.

[0036] Implementation process: By embedding the two pumping pipes 29 into the first mounting groove 13 and the third mounting groove 19 respectively, and using the first mounting assembly and the second mounting assembly to adjust the positions of the first adjustment plate 14 and the second adjustment plate 20 respectively, the dual pumping pipes 29 of different sizes can be adjusted respectively, thereby achieving the purpose of fixing the dual pumping pipes 29 at the same time. And by adopting a double nut fixing structure, the stability of the first adjustment plate 14 and the second adjustment plate 20 when installing is improved.

[0037] In the description of the present invention, the term "plurality" refers to two or more than two. Unless otherwise clearly defined, the orientation or positional relationship indicated by the terms "upper" and "lower" is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention. The terms "connection", "installation", "fixation", etc. should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0038] In the description of the present invention, the terms "one embodiment", "some embodiments", "specific embodiments", etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In the present invention, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0039] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A super high concrete pump pipe fixing device, characterized in that: include: A connecting plate group, the connecting plate group comprising a first connecting plate and a second connecting plate, the first connecting plate being vertically connected to the second connecting plate; A first fixing plate, wherein a first mounting groove is formed through the first fixing plate, and the first fixing plate is connected to one side of the second connecting plate; A first adjustment plate, wherein a second mounting groove is formed through the first adjustment plate, and the second mounting groove of the first adjustment plate is opposite to the first mounting groove; A first mounting assembly, wherein the first mounting assembly comprises two first screws and four first nuts, one end of the two first screws are respectively connected to two sides of the top surface of the first adjustment plate, the other ends of the two first screws respectively pass through two sides of the second connecting plate, the four first nuts are respectively sleeved on the outside of the two first screws, and the four first nuts are all in contact with the side wall of the second connecting plate; A second fixing plate, wherein a third mounting groove is formed through the second fixing plate, and the second fixing plate is connected to the other side of the second connecting plate; A second adjustment plate, wherein a fourth mounting groove is formed through the second adjustment plate, and the fourth mounting groove of the second adjustment plate is opposite to the third mounting groove; The second mounting assembly includes two second screws and four second nuts, one end of the two second screws are respectively connected to the two sides of the top surface of the second adjustment plate, the other ends of the two second screws pass through the two sides of the second connecting plate respectively, the four second nuts are respectively sleeved on the outside of the two second screws, and the four second nuts are all in contact with the side wall of the second connecting plate.

2. The ultra-high pumping concrete pump pipe fixing device according to claim 1 is characterized in that: Also includes: Two first circular holes, the two first circular holes are respectively arranged on both sides of the second connecting plate, and the two first screw rods respectively pass through the two first circular holes; Two second circular holes, the two second circular holes are respectively arranged on both sides of the second connecting plate, and the two second screw rods respectively pass through the two second circular holes; The two second circular holes are respectively located below the two first circular holes and the first fixing plate.

3. The ultra-high pumping concrete pump pipe fixing device according to claim 2 is characterized in that: Also includes: A first reinforcing plate, one end of which is connected to the top of the first connecting plate, and the other end of which is connected to the top of one side of the second connecting plate; A second reinforcing plate, one end of the second reinforcing plate is connected to the bottom end of the first connecting plate, and the other end of the second reinforcing plate is connected to the bottom end of the other side of the second connecting plate.

4. The ultra-high pumping concrete pump pipe fixing device according to claim 3 is characterized in that: The first fixing plate, the first adjusting plate, the second fixing plate and the second adjusting plate are all steel plates with a thickness of 2 cm.

5. The ultra-high pumping concrete pump pipe fixing device according to claim 4 is characterized in that: The diameters of the first screw and the second screw are both 20 mm.

6. The ultra-high pumping concrete pump pipe fixing device according to claim 5 is characterized in that: Also includes: Four mounting holes, each of which is elliptical, are evenly arranged on the first connecting plate.

Citation Information

Patent Citations

  • Ultrahigh pump pipe supporting frame for pumping concrete

    CN216666683U