Hoisting buffer locking device and pipeline detection machine equipment

By designing a lifting buffer locking device on the pipeline detection robot, the impact force of the buffer cylinder and locking cylinder transfer and locking cable is used to solve the impact problem when the end of the pipeline detection robot cable touches the limit, and the impact is achieved. The buffering of force and the stable fixation of the cable avoid structural damage and cable breakage.

CN222361829UActive Publication Date: 2025-01-17NORTHWEST ENGINEERING CORPORATION LIMITED
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421260878.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2025-01-17
Estimated Expiration
2034-06-04

AI Technical Summary

Technical Problem

In a pipe detection robot under a full load state, the end of the cable is easily touched at the pipe limit, causing the impact force to be transmitted to the robot or hoisting equipment, which may damage the limiter or cause the cable to break.

Method used

A lifting buffer locking device is designed, including a pulling mechanism and a buffering platform, which transfers and locks the impact force of the cable through multiple buffer cylinders and locks cylinders to avoid structural damage and cable breakage.

Benefits of technology

Effectively buffer impact force, prevent structural damage to the robot and hoisting equipment, and ensure stable and fixed cables to avoid cable breakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222361829U_ABST
    Figure CN222361829U_ABST
Patent Text Reader

Abstract

The utility model relates to a hoisting buffer locking device and pipeline detection machinery equipment, which are suitable for hoisting a pipeline detection robot and comprise a traction mechanism at least provided with a cable guide wheel suitable for winding and guiding a cable; the buffering platform is suitable for installing the traction mechanism, the cable penetrates through the center of the buffering platform and surrounds the cable, a plurality of buffering air cylinders are arranged on the buffering platform to transfer impact force borne by the cable, and a plurality of locking air cylinders are further arranged on the buffering platform to lock or loosen the cable. And the cable bypasses the wire guide wheel and then penetrates through the hoisting buffer locking device to be connected with the pipeline detection robot. When the end portion of a cable on the side of the pipeline detection robot touches the limiting position, the buffering air cylinder in the hoisting buffering locking device can effectively transfer impact force to the buffering air cylinder for buffering, structural damage to hoisting equipment and the robot is avoided, or the situation that the cable is snapped due to sudden stopping of the robot is avoided. And after buffering and resetting, a locking air cylinder in the hoisting buffering locking device can clamp and fix the end part of the cable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of underwater detection equipment for urban pipe networks, and specifically relates to a lifting buffer locking device and a pipeline detection machine and equipment. Background Art

[0002] The pipeline inspection robot is a special robot developed for maintenance and repair operations such as inspection, spraying, interface welding, and foreign matter cleaning of oil, gas, liquid and other pipelines. It can enter complex and changeable non-structural pipeline environments that are beyond the reach of humans. Through the non-destructive testing devices and operating devices it carries, it can perform online inspection, cleaning, and maintenance of working pipelines to ensure the safety of the pipelines and unimpeded operation.

[0003] However, when lifting a pipeline inspection robot in a fully loaded working state, there was no buffer device in the past, and the cable end of the pipeline inspection robot was easy to touch the pipeline limit. After touching the pipeline limit, due to the large weight of the pipeline inspection robot in a fully loaded state and the large inertia of the lifting process itself, the impact force will be transmitted to the pipeline inspection robot or the lifting equipment. The inertia of the pipeline robot will damage the limiter, or the cable reel will not stop in time, causing the cable to break. Utility Model Content

[0004] The utility model aims to provide a lifting buffer locking device and a pipeline detection machine and equipment to overcome the above technical defects.

[0005] In order to solve the above technical problems, the utility model provides a lifting buffer locking device suitable for lifting a pipeline inspection robot, comprising:

[0006] A pulling mechanism having at least a wire pulley suitable for winding and guiding the cable;

[0007] The buffer platform is suitable for installing the pulling mechanism. The cable passes through the center of the buffer platform and surrounds the cable. A plurality of buffer cylinders are arranged on the buffer platform to transfer the impact force on the cable, and a plurality of locking cylinders are also arranged to lock or release the cable.

[0008] The buffer platform includes:

[0009] An upper buffer platform, a plurality of buffer cylinders are installed on the upper buffer platform, a piston rod of each buffer cylinder passes through the upper buffer platform, and a universal joint is installed on the rod head of the piston rod;

[0010] A lower buffer platform, a plurality of locking cylinders are installed on the lower buffer platform, and a push rod head of each locking cylinder faces the cable to clamp or release the cable;

[0011] The universal joint is installed on the lower buffer platform.

[0012] The lower buffer platform is a circular plate structure;

[0013] The cable passes through the center hole of the circular ring plate.

[0014] The cable is passed through and sleeved in the limit seat;

[0015] The limit seat is placed in the center hole of the lower buffer platform;

[0016] The limit seat includes:

[0017] External limit cylinder;

[0018] An inner limiting cylinder, wherein the cable passes through the inner limiting cylinder and is closely attached to the inner cylinder wall, and a portion of the outer cylinder wall of the inner limiting cylinder first extends radially and then extends axially to form a hook lock;

[0019] The connecting plate and the push rod head of the locking cylinder are fastened to one side of the connecting plate, and the other side of the connecting plate is inserted into the outer limit cylinder, and the plate wall on the inserted side first extends horizontally and then extends vertically to form a hook tongue to cooperate with the hook lock to lock or release the cable.

[0020] The driving mechanisms include:

[0021] A first bracket, the bottom end of which is fixed to the buffer platform and the top end of which is formed with a vertical fixing claw;

[0022] A fixed hydraulic cylinder, the cylinder body of which is mounted on the buffer platform, and a horizontal fixing claw is mounted on the top of the hydraulic push rod;

[0023] A fixed seat, the guide wheel is installed on the fixed seat, and the fixed seat is installed on the first bracket.

[0024] The utility model also provides a pipeline detection machine and equipment, including:

[0025] Door bracket;

[0026] A lifting buffer locking device, the lifting buffer locking device is suspended on the door-type bracket through a pulling mechanism;

[0027] The robot body and the cable passing through the lifting buffer locking device are connected to the robot body.

[0028] The vertical fixing claws and the horizontal fixing claws are clamped on the crossbar of the door-type bracket.

[0029] The lifting buffer locking device proposed in the utility model adopts a three-claw hook and a door-type bracket for fixing. The cable passes through the lifting buffer locking device and is connected to the pipeline inspection robot after passing through the wire pulley. When the cable end on the pipeline inspection robot side touches the limit position, the buffer cylinder in the lifting buffer locking device can effectively transfer the impact force to the buffer cylinder for buffering, thereby avoiding structural damage to the lifting equipment and the robot, or the cable breaking due to the sudden stop of the robot. After the buffer is reset, the locking cylinder in the lifting buffer locking device can clamp and fix the cable end.

[0030] In order to make the above contents of the present invention more clearly understood, preferred embodiments are given below and described in detail in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a three-dimensional diagram of the lifting buffer locking device.

[0032] Figure 2 It is a side view of the lifting buffer locking device.

[0033] Figure 3 Schematic diagram of the lifting buffer locking device suspended on the portal bracket.

[0034] Figure 4 It is a structural diagram of the limit seat.

[0035] Figure 5 This is a top view of the lower buffer platform.

[0036] Description of reference numerals:

[0037] 10. Door type bracket;

[0038] 20. Driving mechanism; 21. Guide wheel; 22. First bracket; 221. Vertical fixing claw; 23. Fixed hydraulic cylinder; 231. Horizontal fixing claw; 24. Fixed seat;

[0039] 30. Buffer platform; 31. Upper buffer platform; 311. Universal joint; 32. Lower buffer platform; 33. Buffer cylinder; 34. Locking cylinder;

[0040] 40. Cables;

[0041] 50. Limit seat; 51. External limit cylinder; 52. Internal limit cylinder; 53. Connecting plate. DETAILED DESCRIPTION

[0042] The following is an explanation of the implementation of the present invention by means of specific embodiments. Those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification.

[0043] It should be noted that, in the present utility model, the up, down, left and right in the figure are deemed to be the up, down, left and right of the lifting buffer locking device and the pipeline detection machine equipment described in this specification.

[0044] The exemplary embodiments of the present invention are now introduced with reference to the accompanying drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. These embodiments are provided to disclose the present invention in detail and completely and to fully convey the scope of the present invention to those skilled in the art. The terms in the exemplary embodiments shown in the accompanying drawings are not intended to limit the present invention. In the accompanying drawings, the same units / elements are marked with the same reference numerals.

[0045] Unless otherwise specified, the terms (including technical terms) used herein have the commonly understood meanings to those skilled in the art. In addition, it is understood that the terms defined in commonly used dictionaries should be understood to have the same meanings as those in the context of the relevant fields, and should not be understood as idealized or overly formal meanings.

[0046] This embodiment relates to a lifting buffer locking device, which is suitable for lifting a pipeline inspection robot. Figure 1 The lifting buffer locking device includes a pulling mechanism 20 and a buffer platform 30. The pulling mechanism 20 is installed on the pulling mechanism 20. The specific structure thereof is described in detail below.

[0047] The pulling mechanism 20 at least has a wire pulley 21 suitable for winding and guiding the cable 40. The function of the pulling mechanism 20 is to transport the cable 40, change the direction of the cable 40, guide the cable 40 to walk along a preset direction, and finally the cable 40 passes through the buffer platform 30 downward.

[0048] Specifically, the buffer platform 30 is suitable for installing the pulling mechanism 20, and the cable 40 passes through the center of the buffer platform 30. A plurality of buffer cylinders 33 are arranged around the cable 40 to transfer the impact force exerted on the cable 40, and a plurality of locking cylinders 34 are also arranged to lock or release the cable 40.

[0049] The cable 40 passes through the guide wheel 21 and then passes through the buffer platform 30 to be connected to the pipeline inspection robot. Therefore, when the cable end on the pipeline inspection robot side touches the limit position, the buffer cylinder 33 can effectively transfer the impact force to the buffer cylinder 33 for buffering, thereby avoiding structural damage to the lifting equipment and the robot, or cable breakage due to sudden stop of the robot.

[0050] After the buffer is reset, the locking cylinder 34 can clamp and fix the cable end.

[0051] Reference Figure 2 The buffer platform 30 includes an upper buffer platform 31 and a lower buffer platform 32 which are arranged opposite to each other up and down.

[0052] A plurality of buffer cylinders 33 are mounted on the upper buffer platform 31, and the piston rod of each buffer cylinder 33 passes through the upper buffer platform 31, and a universal joint 311 is mounted on the rod head of the piston rod. That is, the cylinder body of the buffer cylinder 33 is mounted on the upper buffer platform 31, and the axial center line of the buffer cylinder 33 is perpendicular to the upper buffer platform 31.

[0053] In some embodiments, the upper buffer platform 31 presents Figure 1 The disc is in the shape of a disk, and a circular hole for the cable 40 to pass through is opened in the center of the disc.

[0054] In some embodiments, the number of buffer cylinders 33 is 4 and they are evenly spaced apart.

[0055] A plurality of locking cylinders 34 are mounted on the lower buffer platform 32, and the push rod head of each locking cylinder 34 faces the cable 40 to clamp or release the cable 40. That is, when the push rod of the locking cylinder 34 is extended, the cable 40 can be clamped; when the push rod of the locking cylinder 34 is retracted, the cable 40 can be released.

[0056] In some embodiments, the number of locking cylinders 34 is two and they are distributed at 180 degrees.

[0057] The universal joint 311 is installed on the lower buffer platform 32, and the process of the buffer cylinder 33 transferring the impact force is as follows:

[0058] When the cable end on the pipeline inspection robot side touches the limit point, the cable 40 transmits the impact force to the lower buffer platform 32, the lower buffer platform 32 swings around the universal joint 311, and the buffer cylinder 33 connected to the universal joint 311 expands and contracts to transfer the impact force, thereby avoiding the impact force from causing structural damage to the lifting equipment and the robot.

[0059] like Figure 1 and Figure 3 As shown, the lower buffer platform 32 is a circular ring plate structure, the cable 40 passes through the center hole of the circular ring plate, and the cylinder body of the locking cylinder 34 is installed at the circular ring of the circular ring plate.

[0060] See also Figure 2 The cable 40 is inserted through the limit seat 50, and the limit seat 50 is placed in the center hole of the lower buffer platform 32. The push rod of the locking cylinder 34 clamps the cable 40 by clamping the limit seat 50. Specifically, the limit seat 50 includes:

[0061] The outer limiting cylinder 51 and the inner limiting cylinder 52 are coaxially sleeved.

[0062] See also Figure 4The cable 40 passes through the inner stopper 52 and is close to the inner wall, and part of the outer wall of the inner stopper 52 first extends radially and then extends axially to form a hook lock. In some embodiments, the upper outer wall of the inner stopper 52 forms a hook lock.

[0063] It is worth mentioning that although the inner limiting tube 52 is placed inside the outer limiting tube 51, the length of the inner limiting tube 52 is greater than that of the outer limiting tube 51. Figure 4 As shown, the bottom end of the inner limiting tube 52 extends along the cable 40 to the outside of the outer limiting tube 51 , and its function is to extend the protection of the cable 40 .

[0064] The limit seat 50 also includes a connecting plate 53, the push rod head of the locking cylinder 34 is fastened to one side of the connecting plate 53, and the other side of the connecting plate 53 is inserted into the outer limit tube 51, and the plate wall on the inserted side first extends horizontally and then extends vertically to form a hook tongue to cooperate with the hook lock to lock or release the cable 40.

[0065] It should be noted that, in another embodiment, two ribs are also fixed to the lower buffer platform 32 , and the two ribs are distributed on the lower buffer platform 32 at an angle of 180 degrees, and the ends of the two ribs are connected and clamped to the outer limiting cylinder 51 of the limiting seat 50 .

[0066] The arrangement of the two ribs and the two locking cylinders 34 is shown in Figure 5 .

[0067] About the working process of locking cylinder 34:

[0068] When the cable end on the pipeline inspection robot side touches the limit position, the cable 40 transmits the impact force to the lower buffer platform 32 through the limit seat 50 and the rib plate, and the lower buffer platform 32 swings around the universal joint 311, and the buffer cylinder 33 connected to the universal joint 311 expands and contracts to transfer the impact force. As the impact force is gradually dissipated, the cable 40 is gradually reset. At this time, the push rod of the locking cylinder 34 extends / retracts, and the push rod drives the connecting plate 53. The hook tongue on the connecting plate 53 gradually cooperates with the hook lock in the limit seat 50. The hook tongue and the hook lock can clamp or release the cable 40 after being locked or released.

[0069] Please continue reading Figure 2 , the driving mechanism 20 comprises:

[0070] (1) The first bracket 22 has a bottom end fixed to the buffer platform 30 and a top end formed with a vertical fixing claw 221 .

[0071] In some embodiments, the bottom end of the first bracket 22 is fixed on the upper buffer platform 31, and the top end of the first bracket 22 is formed with two vertical fixing claws 221, which are used to grasp the door-type bracket 10. Figure 3 shown.

[0072] In some embodiments, the first bracket 22 has two vertical arms, a vertical fixing claw 221 is installed at the top of each of the two vertical arms, and the bottom ends of the two vertical arms are fixed on the upper buffer platform 31 .

[0073] (2) Fix the hydraulic cylinder 23.

[0074] The cylinder body of the fixed hydraulic cylinder 23 is installed on the buffer platform 30, specifically on the upper buffer platform 31. A horizontal fixing claw 231 is installed on the top of the hydraulic push rod. The horizontal fixing claw 231 is located between the two vertical fixing claws 221 to form a three-claw hook to ensure that the lifting buffer locking device can be firmly hung on the door-type bracket 10.

[0075] The extension and retraction of the fixing hydraulic cylinder 23 can control the clamping and releasing of the horizontal fixing claws 231 .

[0076] (3) Fixed seat 24.

[0077] The guide wheel 21 is mounted on a fixing seat 24 , and the fixing seat 24 is mounted on the first bracket 22 .

[0078] Specifically, the first bracket 22 also includes a lower horizontal rod, which is located between the two vertical arms and is installed on the upper buffer platform 31, and an upper horizontal rod is also installed between the top ends of the two vertical arms. The fixed seat 24 is installed between the upper horizontal rod and the lower horizontal rod, and the wire wheel 21 is arranged on the fixed seat 24, and the wire wheel 21 can rotate around the fixed seat 24.

[0079] In some embodiments, the wire wheel 21 is mounted on the fixing seat 24 via a clamping plate, and the clamping plate is detachable, thereby facilitating the replacement of the wire wheel 21, thereby adapting to cables of various specifications.

[0080] This embodiment also provides a pipeline inspection machine device, including a door-type bracket 10, a lifting buffer locking device, and a robot body, see Figure 3 The lifting buffer locking device is suspended on the door-type bracket 10 through the pulling mechanism 20, and the cable 40 passing through the lifting buffer locking device is connected to the robot body (not shown in the figure).

[0081] The vertical fixing claws 221 and the horizontal fixing claws 231 are both clamped on the crossbar of the door-shaped bracket 10 .

[0082] Those skilled in the art will appreciate that the above-mentioned embodiments are specific examples for implementing the present invention, and in actual applications, various changes may be made thereto in form and detail without departing from the spirit and scope of the present invention.

Claims

1. The lifting buffer locking device is characterized by: Suitable for lifting pipeline inspection robots, including: A pulling mechanism (20) having at least a wire pulley (21) suitable for winding and guiding the cable (40); A buffer platform (30) is suitable for installing the pulling mechanism (20), the cable (40) passes through the center of the buffer platform (30), surrounds the cable (40), and a plurality of buffer cylinders (33) are arranged on the buffer platform (30) to transfer the impact force applied to the cable (40), and a plurality of locking cylinders (34) are also arranged to lock or release the cable (40).

2. The lifting buffer locking device according to claim 1, characterized in that: The buffer platform (30) comprises: An upper buffer platform (31), a plurality of buffer cylinders (33) being mounted on the upper buffer platform (31), a piston rod of each buffer cylinder (33) passing through the upper buffer platform (31), and a universal joint (311) being mounted on the rod head of the piston rod; A lower buffer platform (32), a plurality of locking cylinders (34) being mounted on the lower buffer platform (32), a push rod head of each locking cylinder (34) facing the cable (40) to clamp or release the cable (40); The universal joint (311) is mounted on the lower buffer platform (32).

3. The lifting buffer locking device according to claim 2 is characterized in that: The lower buffer platform (32) is a circular ring plate structure; The cable (40) passes through the central hole of the circular ring plate.

4. The lifting buffer locking device according to claim 3 is characterized in that: The cable (40) penetrates and is sleeved in the limiting seat (50); The limiting seat (50) is placed in the central hole of the lower buffer platform (32); The limiting seat (50) comprises: External limiting cylinder (51); An inner limiting cylinder (52), the cable (40) passing through the inner limiting cylinder (52) and closely attached to the inner cylinder wall, a portion of the outer cylinder wall of the inner limiting cylinder (52) first extending radially and then extending axially to form a hook lock; A connecting plate (53), a push rod head of the locking cylinder (34) is fastened to one side of the connecting plate (53), and the other side of the connecting plate (53) is inserted into the outer limit tube (51), and the plate wall on the inserted side first extends horizontally and then extends vertically to form a hook tongue to cooperate with the hook lock to lock or release the cable (40).

5. The lifting buffer locking device according to claim 1 or 4, characterized in that: The pulling mechanism (20) comprises: A first bracket (22), the bottom end of which is fixed to the buffer platform (30) and the top end of which is formed with a vertical fixing claw (221); A fixed hydraulic cylinder (23), the cylinder body of which is mounted on the buffer platform (30), and a horizontal fixing claw (231) is mounted on the top of the hydraulic push rod; A fixing seat (24), the guide wheel (21) is mounted on the fixing seat (24), and the fixing seat (24) is mounted on the first bracket (22).

6. Pipeline inspection machine equipment, characterized in that: include: Door bracket (10); The lifting buffer locking device according to claim 5, wherein the lifting buffer locking device is suspended on the door-shaped bracket (10) through the pulling mechanism (20); The robot body, the cable (40) passing through the lifting buffer locking device is connected to the robot body.

7. The pipeline detection machine equipment according to claim 6, characterized in that: The vertical fixing claw (221) and the horizontal fixing claw (231) are both clamped on the crossbar of the door-shaped bracket (10).