Prefabricated air conditioner plate cantilever support
By designing the prefabricated air-conditioning panel cantilever bracket and utilizing the structure of overhangs and clamps, the problems of complex structure and troublesome construction of the existing air-conditioning panel support device are solved, and the construction speed is fast and the construction period is shortened.
Patent Information
- Application Number
- CN202421112023.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-21
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2034-05-21
AI Technical Summary
The existing air-conditioning board support device has a complex structure, troublesome construction, and affects the construction period.
Design a prefabricated air-conditioning panel cantilever bracket, including a cantilever piece and a clamping piece. The cantilever piece cantilevers under the exterior wall eaves, and the clamping piece clamps the upper side of the exterior wall overhanging eaves. The overhanging end of the cantilever piece is provided with The jack is used to support the air conditioning panel.
Through the design of the cantilever bracket, the construction speed is fast, the construction period is shortened, the structure is simple and easy to set up, and the cantilever bracket is stably set on the eaves and fixed firmly.
Smart Images

Figure CN222376115U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cantilever brackets for air conditioner panels, in particular to a prefabricated cantilever bracket for air conditioner panels. Background Art
[0002] The air conditioning panel is a support panel on the exterior wall of a building for the later installation of air conditioners. The air conditioning panel support system needs to be set up separately. Since there are many air conditioning panels in university buildings, the existing structure has the following disadvantages:
[0003] When using traditional socket frames, the elevation of the prefabricated air-conditioning panels is adjusted through the supporting frame. The accuracy is easily affected by the stability of the frame. The contact area of the air-conditioning panels is small, the working surface for erecting the socket frames is small, the frame has no fixed module, and buckle frames need to be used for connection. The reliability of the frame cannot be guaranteed, the construction speed is slow, and the construction period is affected.
[0004] The Chinese invention patent application with the publication date of 2023-02-24 and the publication number of CN115711051A discloses a support device for a prefabricated air-conditioning panel, including a base, a lower bracket is arranged on the base, upper brackets are symmetrically arranged on both sides of the lower bracket, the two sides of the two upper brackets are fixedly connected by a number of reinforcing beams, a top seat is arranged above the upper bracket, and then a number of support frames are symmetrically arranged on both sides of the top seat, and a number of support screw holes are evenly and firmly opened on each support frame, and support screw rods are threadedly connected in appropriate support screw holes. When the prefabricated air-conditioning panel is installed, the support device is placed on the prefabricated air-conditioning panel on the lower floor, and after the upper bracket is adjusted to an appropriate height, the support block on the support frame is adjusted to the elevation by rotating the support screw rod, and then the prefabricated air-conditioning panel can be placed on the support device, and then the air-conditioning prefabricated panel can be cast and fixed. However, the support device has a complex structure, troublesome construction, and affects the construction period. Summary of the invention
[0005] In view of the above-mentioned technical problems, the utility model proposes a prefabricated air-conditioning panel cantilever bracket, which is used to solve the problems of the supporting device for the air-conditioning panel in the prior art, such as complex structure, troublesome construction and influence on the construction period.
[0006] In order to achieve the above object, the technical solution of the utility model is implemented as follows:
[0007] A prefabricated air conditioning panel cantilever bracket comprises a cantilevered member cantilevered on the lower side of the external wall cantilevered eave and a clamping member used to clamp the upper side of the external wall cantilevered eave, the clamping member is connected to the cantilevered member; the cantilevered end of the cantilevered member is provided with a top support for supporting the prefabricated member of the air conditioning panel. The utility model sets a cantilever bracket to support the prefabricated member of the air conditioning panel. After the external wall is installed, the cantilever bracket is cantilevered from the hole position, and no external construction is required, which speeds up the construction speed and shortens the construction period; the cantilever bracket is hung above the cantilevered eave of the external wall by using the clamping member, and the cantilevered member is pressed against the lower side of the cantilevered eave, so that the cantilever bracket is stably set on the cantilevered eave, and the structure is simple and easy to set up.
[0008] Furthermore, a steel pipe seat is provided at the cantilevered end of the cantilever member, and the steel pipe seat is plug-fitted with the top support.
[0009] Furthermore, the jacking support comprises a main rod, to which is connected a support member for limiting support on the upper end of the steel pipe seat.
[0010] Furthermore, the support member is a threaded cap screwed to the main rod.
[0011] Furthermore, a bracket is provided at the upper end of the main rod for supporting a prefabricated component of the air conditioning panel.
[0012] Furthermore, the side projection of the clamp is an inverted L-shaped structure, the horizontal portion of the inverted L-shaped structure is used to clamp the upper side of the external wall eaves, and the lower end of the vertical portion is connected to the cantilever member.
[0013] Furthermore, the cantilevered member is provided with two clamping members, and the two clamping members are symmetrically arranged on both sides of the cantilevered member.
[0014] Furthermore, the two clamps are formed by bending a tension rod.
[0015] Furthermore, an embedded nut is provided on the lower side of the exterior wall overhang, and the cantilevered member is connected to the exterior wall overhang by screwing bolts into the embedded nut.
[0016] Furthermore, a wooden wedge is wedged tightly between the clamp and the external wall eaves.
[0017] Beneficial effects of the utility model;
[0018] 1. The utility model provides a cantilever bracket to support the prefabricated components of the air conditioning panel. After the exterior wall is installed, the cantilever bracket is cantilevered from the opening position, and no external construction is required, so the construction speed is fast and the construction period is shortened;
[0019] 2. The utility model provides a clamp made of bent reinforcing bars, and uses the clamp to hang the cantilever bracket above the cantilevered eaves of the exterior wall, and at the same time, the cantilevered member is pressed against the bottom of the cantilevered eaves, so that the cantilever bracket is stably arranged on the cantilevered eaves, and the structure is simple and convenient to arrange;
[0020] 3. The utility model reserves embedded nuts in advance on the lower side of the prefabricated exterior wall eaves, so that the cantilever bracket is fixed to the exterior wall through bolts, so that the cantilever bracket is firmly fixed. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0022] Figure 1 It is a structural schematic diagram of the utility model.
[0023] In the figure: 1. external wall cantilever, 2. bolts, 3. cantilever parts, 4. wooden wedges, 5. tie rods, 6. top supports, 61. screw caps, 7. steel pipe seats. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] like Figure 1 As shown, the cantilever bracket of a prefabricated air conditioning panel described in Example 1 of the utility model comprises a cantilever member 3 cantilevered at the lower side of the outer wall cantilever 1 and a clamping member for clamping the upper side of the outer wall cantilever 1, the upper part of the clamping member clamps the outer wall cantilever 1, and the lower end of the clamping member is connected to the cantilever member 3; the cantilever end of the cantilever member 3 is provided with a top support 6 for supporting the prefabricated component of the air conditioning panel, so as to facilitate the installation of the air conditioning panel. In this embodiment, the cantilever member 3 of the cantilever bracket adopts a channel steel with a length of 1 to 1.8m, and in another embodiment, a steel plate can also be adopted.
[0026] Furthermore, a steel pipe seat 7 is provided at the cantilevered end of the cantilever member 3, and the steel pipe seat 7 is plugged into and matched with the top support 6. This connection method facilitates the assembly, disassembly, storage and turnover of the cantilever bracket.
[0027] Specifically, Figure 1 As shown, the jacking support 6 includes a main rod, to which a support is connected. The support supports the upper end of the steel pipe seat 7 and is used to limit and support the jacking support 6 so that the jacking support 6 can be stably installed in the steel pipe seat 7 after being inserted into the steel pipe seat 7 to avoid up and down movement.
[0028] In this embodiment, the support member is a screw cap 61 screwed to the main rod. The screw cap 61 is screwed to the main rod, which facilitates the adjustment of the position of the screw cap 61 on the main rod, thereby adjusting the height of the jacking 6 to control the elevation accuracy.
[0029] Furthermore, a bracket is provided at the upper end of the main rod for supporting the prefabricated components of the air conditioning panel. Figure 1 As shown, the bracket is a plate, and upward protrusions are provided on both sides of the plate for limiting and supporting long strips, and the long strips support the prefabricated components of the air conditioning panel.
[0030] In addition, for one air conditioning panel, at least two groups of cantilever brackets are used, and at least two top brackets 6 thereon better support the prefabricated components of the air conditioning panel.
[0031] Embodiment 2 is different from Embodiment 1 in that Figure 1 As shown, the side projection of the clamp is an inverted L-shaped structure, the horizontal portion of the inverted L-shaped structure is used to clamp the upper side of the external wall eaves 1, and the lower end of the vertical portion is connected to the cantilever member 3.
[0032] Furthermore, the cantilever member 3 is provided with two clamping members, and the two clamping members are symmetrically arranged on both sides of the cantilever member 3 .
[0033] Furthermore, if Figure 1 As shown, the two clamps are formed by bending a tie rod 5. That is, the two ends of a tie rod 5 are bent into symmetrical inverted L-shaped structures, and the middle part of the tie rod 5 connects the two inverted L-shaped structures. In this embodiment, the middle part of the tie rod 5 penetrates the lower side of the cantilever 3, so that the two inverted L-shaped structures face the upper side of the cantilever 3, and then the middle part of the tie rod 5 is firmly welded to the lower side of the cantilever 3.
[0034] Embodiment 3 is different from Embodiment 2 in that Figure 1 As shown, an embedded nut is provided on the lower side of the external wall eaves 1, and a through hole is provided on the cantilever member 3. The bolt 2 passes through the through hole of the cantilever member 3 and is then screwed into the embedded nut, thereby connecting the cantilever member 3 to the external wall eaves 1.
[0035] Embodiment 4 is different from Embodiment 3 in that Figure 1 As shown, a wooden wedge 4 is wedged tightly between the clamp and the external wall eaves 1.
[0036] The use process of the cantilever bracket:
[0037] There are cantilever eaves above and below the exterior wall windows, and nuts are embedded in the window top position during the prefabrication process of the exterior wall cantilever eaves. Two sets of cantilever brackets are used for one air conditioning panel. While the clamp is hung on the exterior wall cantilever eave 1, the channel steel is inserted into the lower side of the exterior wall cantilever eave 1, and the cantilever 3 is fixed to the lower side of the cantilever eave by screwing the embedded nut into the bolt 2. The wooden wedge 4 is inserted into the gap between the tie bar 5 and the cantilever eave, so that the cantilever bracket clamps the upper and lower sides of the exterior wall cantilever eave 1. The top support 6 is inserted into the steel pipe seat 7, so that the lower side of the screw cap 61 is pressed against the steel pipe seat 7 to stably set the top support 6. During the process, the position of the screw cap 61 on the top support 6 can be adjusted to adjust the height of the bracket used to support the air conditioning panel at the upper end of the top support 6 to control the elevation accuracy, so as to facilitate the accurate installation of the prefabricated air conditioning panel on site. After that, the long slats and the prefabricated components of the air conditioning panel are set on the bracket to install the air conditioning panel. Check the elevation after installation.
[0038] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A prefabricated air conditioning panel cantilever bracket, characterized in that: It comprises a cantilevered member (3) cantilevered on the lower side of an external wall cantilever (1) and a clamping member used to clamp the upper side of the external wall cantilever (1), the clamping member being connected to the cantilevered member (3); a top support (6) is provided at the cantilevered end of the cantilevered member (3) for supporting a prefabricated component of an air conditioning panel.
2. The cantilever bracket of the prefabricated air conditioning panel according to claim 1 is characterized in that: The cantilevered end of the cantilever member (3) is provided with a steel pipe seat (7), and the steel pipe seat (7) is plug-fitted with the top support (6).
3. The cantilever bracket of the prefabricated air conditioning panel according to claim 2 is characterized in that: The jacking support (6) comprises a main rod, to which is connected a support member for limiting support on the upper end of the steel pipe seat (7).
4. The cantilever bracket of the prefabricated air conditioning panel according to claim 3 is characterized in that: The support member is a threaded cap (61) threadedly connected to the main rod.
5. The cantilever bracket of the prefabricated air conditioning panel according to claim 3 or 4, characterized in that: A bracket is provided at the upper end of the main rod for supporting the prefabricated component of the air conditioning panel.
6. The cantilever bracket of the prefabricated air conditioning panel according to any one of claims 1 to 4, characterized in that: The side projection of the clamp is an inverted L-shaped structure, the horizontal portion of the inverted L-shaped structure is used to clamp the upper side of the external wall overhang (1), and the lower end of the vertical portion is connected to the cantilever member (3).
7. The cantilever bracket of the prefabricated air conditioning panel according to claim 6, characterized in that: The cantilevered piece (3) is provided with two clamping pieces, and the two clamping pieces are symmetrically arranged on both sides of the cantilevered piece (3).
8. The cantilever bracket of the prefabricated air conditioning panel according to claim 7, characterized in that: The two clamping parts are formed by bending a tension rod (5).
9. The cantilever bracket of the prefabricated air conditioning panel according to any one of claims 1 to 4 or 7 or 8, characterized in that: The lower side of the external wall overhang (1) is provided with an embedded nut, and the cantilever member (3) is connected to the external wall overhang (1) by screwing a bolt (2) into the embedded nut.
10. The cantilever bracket of the prefabricated air conditioning panel according to any one of claims 1 to 4 or 7 or 8, characterized in that: A wooden wedge (4) is wedged tightly between the clamp and the external wall overhang (1).
Citation Information
Patent Citations
Supporting device for prefabricated air conditioner plate
CN115711051A