Bottom sealing compartment structure of hanging box cofferdam

Design support separate components in the foundation partition structure of the crane coffin, including strengthening the ribs, trailers, first partitions, and second partitions, which solves the large amount of materials in the existing technology, economical and infiltrated infiltration. The problem of leakage realizes the overall formation of concrete and the stability of the installation installation.

CN222413087UActive Publication Date: 2025-01-28CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421137524.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-23
Publication Date
2025-01-28
Estimated Expiration
2034-05-23

AI Technical Summary

Technical Problem

The existing hanging box cofferdam bottom seal partition structure has problems such as high material usage, inefficiency and inconvenience during construction, and water leakage may occur due to concrete shrinkage and creep.

Method used

Design a supporting partition component that includes enhanced vertical ribs, trailers, first partitions, and second partitions. Through the settings of these components, pour the foundation concrete blocks in the block, and pass the load to the extension cross frame and Strengthen vertical ribs to prevent cracks.

Benefits of technology

The overall formation of concrete is achieved to prevent the occurrence of leakage phenomenon. At the same time, it improves the stability of the installation installation, and reduces the amount of material and the construction cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222413087U_ABST
    Figure CN222413087U_ABST
Patent Text Reader

Abstract

The utility model discloses a bottom sealing partition bin structure of a hanging box cofferdam, and particularly relates to the technical field of cofferdam bottom sealing partition bins, the bottom sealing partition bin structure of the hanging box cofferdam comprises a base plate used for supporting, a supporting partition assembly is arranged on the base plate, and the supporting partition assembly comprises a plurality of reinforcing vertical rib frames used for supporting. The supporting and separating assembly is arranged, the overall design is simple, the structure is reasonable, all the structures are correspondingly used in a matched mode, through the arrangement of the first separating plate and the second separating plate, the supporting effect is good, and the supporting effect is good. Large-area bottom sealing concrete is poured in blocks and areas, side pressure of the bottom sealing concrete and horizontal load generated in the construction process are transmitted to the extension cross and the reinforcing vertical rib frame, the concrete can form a whole easily, and the phenomenon that the partition plate generates cracks due to shrinkage and creep of the concrete, and then water leakage occurs is prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cofferdam bottom sealing compartments, and more specifically, to a bottom sealing compartment structure of a hanging box cofferdam. Background Art

[0002] The truss keel of the hanging box cofferdam also serves as the bottom partition, which is a common method in construction to construct a closed space. It is usually used to provide a safe and dry working environment when constructing deep foundation pits or deep-water high pile caps of cross-sea bridges at the construction site.

[0003] Installation of the box cofferdam: First, build a series of steel box cofferdams in the water to enclose the construction area and prevent water from entering the construction area. Inside the box cofferdam, steel pipes or concrete piles are driven into the bottom of the water and fixed to the bottom of the water through special construction techniques to form a deep-water high-pile foundation. Inside the box cofferdam, according to construction needs, the construction area is divided into different rooms or areas by building partitions, truss keels and other structures to form bottom-sealed compartments. This takes a long time to construct, is inconvenient, requires a lot of materials, is not economical, and is not convenient enough to use. Utility Model Content

[0004] In order to overcome the above-mentioned defects of the prior art, the utility model provides a bottom sealing compartment structure of a hanging box cofferdam, aiming to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a bottom-sealing compartment structure of a hanging box cofferdam, comprising a base plate for support, wherein a support partition assembly is arranged on the base plate;

[0006] The supporting partition assembly includes a plurality of reinforcing vertical ribs for supporting, and each of the reinforcing vertical ribs is respectively arranged on both sides of the top of the base plate, and a truss bar for supporting is arranged on the top of the plurality of reinforcing vertical ribs, and each of the truss bars is provided with a plurality of drag rods for supporting, and a first partition for partitioning is arranged on the reinforcing vertical ribs;

[0007] An extended cross is provided at both ends of the base plate and between two adjacent reinforced vertical ribs, a second partition is provided at the bottom of the extended cross, and a central groove is provided on the surface of the base plate and between each reinforced vertical rib;

[0008] It can be seen that in the above technical scheme, by strengthening the setting of vertical ribs and drag rods, their function is to bear the vertical load and horizontal load generated by the bottom concrete and the construction process. Through the setting of the first partition plate and the second partition plate, the large area of ​​bottom concrete can be poured in blocks and regions, and the side pressure of the bottom concrete and the horizontal load generated by the construction process are transmitted to the extended cross and the strengthened vertical ribs, which makes it easy for the concrete to form a whole and prevents cracks in the partition plate due to concrete shrinkage and creep, thereby preventing water leakage.

[0009] Optionally, in a possible implementation, the cross-sectional shape of the extended cross is set to a cross shape, an upper supporting cross bar for support is arranged on the top of the extended cross, a plurality of the reinforced vertical ribs are detachably connected to the base plate, and an installation cavity is formed between each two adjacent reinforced vertical ribs, a center plate for support is arranged in the installation cavity, a docking plate for partition is arranged on one side of the center plate, a reinforced cross bar for support is arranged on the top of the center plate, a plurality of connecting blocks for support are arranged on the reinforced cross bar, a counterweight block is arranged on the center plate and on one side of the docking plate, and the counterweight block is detachably connected to the center plate;

[0010] It can be seen that in the above technical solution, the cross-sectional shape of the extended cross is set to a cross shape, which is easy to limit the reinforced vertical ribs and the extended cross when the concrete between the reinforced vertical ribs forms a whole. The function is to transfer the side pressure of the bottom concrete and the horizontal load generated during the construction process to the reinforced vertical ribs through the extended cross, and then transfer the reinforced vertical ribs to the truss keel, thereby improving the stability of the device installation.

[0011] Technical effects and advantages of the utility model:

[0012] By setting the supporting partition components, the overall design is simple and the structure is reasonable. Through the corresponding coordinated use of various structures and the setting of the first partition and the second partition, the large-area bottom concrete can be poured in blocks and regions, and the side pressure of the bottom concrete and the horizontal load generated during the construction process are transmitted to the extended cross and the reinforced vertical rib frame, which makes it easy for the concrete to form a whole and prevents cracks in the partition plate due to concrete shrinkage and creep, thereby preventing water leakage;

[0013] In addition, the cross-sectional shape of the extended cross is set to a cross shape, which is easy to limit the reinforced vertical ribs and the extended cross when the concrete between the reinforced vertical ribs forms a whole. Its function is to transfer the side pressure of the bottom concrete and the horizontal load generated during the construction process to the reinforced vertical ribs through the extended cross, and then transfer the reinforced vertical ribs to the truss keel, thereby improving the stability of the device installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the technical solutions in the present disclosure, the following briefly introduces the drawings required to be used in some embodiments of the present disclosure. Obviously, the drawings described below are only drawings of some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can also be obtained based on these drawings. In addition, the drawings described below can be regarded as schematic diagrams, and are not limitations on the actual size of the product involved in the embodiments of the present disclosure, the actual process of the method, the actual timing of the signal, etc.

[0015] Figure 1 It is the front view of the overall structure of the utility model.

[0016] Figure 2 It is a top view of the overall structure of the utility model.

[0017] Figure 3 It is a side view of the overall structure of the utility model.

[0018] Figure 4 It is the front view of each structure on the center plate of the utility model.

[0019] Figure 5 The front view of the base plate, the extended cross, the reinforced vertical ribs and the towing rod of this utility model

[0020] The accompanying drawings are marked as follows: 1. base plate; 2. reinforced vertical ribs; 3. truss rails; 4. tow rods; 5. first partition; 6. extended cross; 7. upper cross rails; 8. second partition; 9. center plate; 10. docking plate; 11. reinforced cross bar; 12. connecting block; 13. counterweight block; 14. center groove. DETAILED DESCRIPTION

[0021] In order to enable those skilled in the art to better understand the technical solution of the utility model, the utility model is further described in detail below in conjunction with the accompanying drawings and the best embodiment. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the utility model.

[0022] In the description of the utility model, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction or be constructed in a specific direction.

[0023] Example 1

[0024] In the embodiment, as shown in the attached Figure 1-5The bottom partition structure of a hanging box cofferdam shown in the figure, through the support partition assembly arranged on the base plate 1, through the arrangement of the first partition plate 5 and the second partition plate 8, realizes the pouring of a large area of ​​bottom concrete in blocks and regions, and transmits the side pressure of the bottom concrete and the horizontal load generated during the construction process to the extension cross 6 and the reinforced vertical rib frame 2, which is easy for the concrete to form a whole and prevents the partition plate from cracking due to concrete shrinkage and creep and then water leakage. The cross-sectional shape of the extension cross 6 is set to a cross shape, which is easy to limit the reinforced vertical rib frame 2 and the extension cross 6 when the concrete between each reinforced vertical rib frame 2 forms a whole. The function is to transmit the side pressure of the bottom concrete and the horizontal load generated during the construction process to the reinforced vertical rib frame 2 through the extension cross 6, and then the reinforced vertical rib frame 2 is transmitted to the truss keel, thereby improving the stability of the device installation, and the specific structural arrangement of the assembly is as follows;

[0025] The supporting partition assembly includes a plurality of reinforcing vertical ribs 2 for supporting, and each of the reinforcing vertical ribs 2 is respectively arranged on both sides of the top of the base plate 1, and a truss fence 3 for supporting is arranged on the top of each of the plurality of reinforcing vertical ribs 2, and a plurality of drag rods 4 for supporting are arranged on each of the truss fences 3, and a first partition 5 for partitioning is arranged on the reinforcing vertical ribs 2;

[0026] An extension cross 6 is provided at both ends of the base plate 1 and between two adjacent reinforcing vertical ribs 2, a second partition 8 is provided at the bottom of the extension cross 6, and a central groove 14 is provided on the surface of the base plate 1 and between each reinforcing vertical rib 2.

[0027] According to the above structure, when the device is installed, the vertical ribs 2 and the drag rods 4 are strengthened, so that the vertical and horizontal loads generated by the bottom concrete and the construction process can be borne. Through the first partition 5 and the second partition 8, the bottom concrete of a large area can be poured in blocks and regions, and the side pressure of the bottom concrete and the horizontal load generated by the construction process can be transmitted to the extended cross 6 and the strengthened vertical ribs 2, which makes it easy for the concrete to form a whole and prevents cracks in the partition plate due to concrete shrinkage and creep, thereby preventing water leakage.

[0028] Example 2

[0029] As attached Figure 1-5As shown, the cross-sectional shape of the extended cross 6 is set to a cross shape, and an upper supporting cross bar 7 is arranged on the top of the extended cross 6 for support, and a plurality of reinforcing vertical ribs 2 are detachably connected to the base plate 1, and an installation cavity is formed between each adjacent two reinforcing vertical ribs 2, and a center plate 9 for support is arranged in the installation cavity, and a docking plate 10 for partition is arranged on one side of the center plate 9, and a reinforcing cross bar 11 for support is arranged on the top of the center plate 9, and a plurality of connecting blocks 12 for support are arranged on the reinforcing cross bar 11, and a counterweight block 13 is arranged on the center plate 9 and on one side of the docking plate 10, and the counterweight block 13 is detachably connected to the center plate 9.

[0030] According to the above structure, when in use, the cross-sectional shape of the extended cross 6 is set to a cross shape, which is easy to limit the reinforced vertical ribs 2 and the extended cross 6 when the concrete between the reinforced vertical ribs 2 forms a whole. The function is to transfer the side pressure of the bottom concrete and the horizontal load generated during the construction process to the reinforced vertical ribs 2 through the extended cross 6, and then the reinforced vertical ribs 2 are transferred to the truss keel, thereby improving the stability of the device installation.

[0031] Different from the prior art, the present application discloses a bottom partition structure of a hanging box cofferdam. Through the arrangement of the first partition 5 and the second partition 8, the bottom concrete of a large area can be poured in blocks and regions, and the side pressure of the bottom concrete and the horizontal load generated during the construction process are transmitted to the extended cross 6 and the reinforced vertical ribs 2, which is easy for the concrete to form a whole and prevent cracks in the partition plate due to concrete shrinkage and creep, thereby preventing water leakage. The cross-sectional shape of the extended cross 6 is set to a cross shape, which is easy to limit the reinforced vertical ribs 2 and the extended cross 6 when the concrete between each reinforced vertical rib 2 forms a whole. The function is to transfer the side pressure of the bottom concrete and the horizontal load generated during the construction process to the reinforced vertical ribs 2 through the extended cross 6, and then the reinforced vertical ribs 2 are transmitted to the truss keel, thereby improving the stability of the device installation.

[0032] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A bottom compartment structure of a hanging box cofferdam, comprising a base plate (1) for support, characterized in that: A supporting partition assembly is provided on the base plate (1); The supporting partition assembly comprises a plurality of reinforcing vertical ribs (2) for supporting, and each of the reinforcing vertical ribs (2) is respectively arranged on both sides of the top of the base plate (1), a truss fence (3) for supporting is arranged on the top of each of the plurality of reinforcing vertical ribs (2), and each of the truss fences (3) is provided with a plurality of drag rods (4) for supporting, and a first partition (5) for partitioning is arranged on the reinforcing vertical ribs (2); An extended cross (6) is provided at both ends of the base plate (1) and between two adjacent reinforced vertical ribs (2), a second partition plate (8) is provided at the bottom of the extended cross (6), and a central groove (14) is provided on the surface of the base plate (1) and between each reinforced vertical rib (2).

2. The bottom sealing compartment structure of a hanging box cofferdam according to claim 1 is characterized in that: The cross-sectional shape of the extension cross (6) is set to be a cross shape, and the top of the extension cross (6) is provided with an upper supporting cross bar (7) for support.

3. The bottom sealing compartment structure of a hanging box cofferdam according to claim 1 is characterized in that: The plurality of reinforced vertical rib frames (2) are detachably connected to the base plate (1), and an installation cavity is formed between each two adjacent reinforced vertical rib frames (2).

4. The bottom sealing compartment structure of the hanging box cofferdam according to claim 3 is characterized in that: A central plate (9) for support is arranged in the installation cavity, and a docking plate (10) for partition is arranged on one side of the central plate (9).

5. The bottom sealing compartment structure of the hanging box cofferdam according to claim 4 is characterized in that: A reinforcing cross bar (11) for support is arranged on the top of the central plate (9), and a plurality of connecting blocks (12) for support are arranged on the reinforcing cross bar (11).

6. The bottom sealing compartment structure of the hanging box cofferdam according to claim 5 is characterized in that: A counterweight block (13) is provided on the center plate (9) and located on one side of the docking plate (10); the counterweight block (13) is detachably connected to the center plate (9).