Transfer device for tire curing bladder production

By designing a tire vulcanized capsule transport device that can adjust the transport space, the problems of unstable and low efficiency of capsule transport in the prior art are solved, and efficient and stable transport under different capsule quantity is achieved.

CN222629354UActive Publication Date: 2025-03-18NO 5 ENGINEERING COMPANY LTD OF CCCC FIRST HARBOR ENGINEERING COMPANY LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421486182.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2025-03-18
Estimated Expiration
2034-06-26

AI Technical Summary

Technical Problem

In the prior art, when the tire vulcanized capsules are transported, multiple transfers are required when there are many capsules, and when there are few capsules, the transportation space is too large, resulting in poor stability.

Method used

A transport device for the production of tire vulcanized capsules is designed. By installing the first support frame and the second support frame, and adjusting the distance with an electric push rod, the size of the transport space is dynamically adjusted to ensure the stability and efficiency of the capsule during transport.

Benefits of technology

It is realized that under different numbers of capsules, the transportation space is dynamically adjusted, the number of transports is reduced, and the stability and transportation efficiency of the capsule are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222629354U_ABST
    Figure CN222629354U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of curing bladder production, and discloses a transfer device for tire curing bladder production, which comprises a main body mechanism, the main body mechanism comprises a first moving base, and a second moving base is movably arranged on the right side of the first moving base. Locking universal wheels are movably arranged below the first movable base and the second movable base, and a first supporting frame is movably arranged above the first movable base. According to the transfer device for tire curing bladder production, the distance between the first moving base and the second moving base is adjusted through the electric push rod, so that the distance between the first supporting frame and the second supporting frame is enlarged, the transportation space of the device is enlarged, more tire curing bladders can be transferred at a time, and when the number of the tire curing bladders is small, the device is convenient to use. And the distance between the first supporting frame and the second supporting frame is reduced, so that the movement range of the tire curing bladder can be better limited by the internal space, and the tire curing bladder is more stable during transportation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of vulcanization bladder production, in particular to a transfer device for tire vulcanization bladder production. Background Art

[0002] Tire vulcanization bladders are consumables used in the tire vulcanization process. They are made of butyl rubber and are equivalent to the inner mold of the tire mold. They are installed on the central mechanism of the tire vulcanizer and play a role in shaping and transferring heat during the tire vulcanization process. Shaping is to squeeze the bladder along the inner center of the tire blank to both sides to remove the gas remaining on the inner wall of the tire, so that the surface of the bladder is completely attached to the inner wall of the tire blank, which is beneficial to the heat conduction during the vulcanization of the tire blank.

[0003] Prior art CN217532957U proposes a transfer device for tire vulcanization bladder production, in which a transfer frame is provided with an upper loading space and a lower loading space, and a plurality of formed vulcanization bladders can be transferred at a time, and a plurality of devices can be connected to each other, which further increases the transfer volume of vulcanization bladders and improves production efficiency; by providing a lifting device, it is convenient to take and place the vulcanization bladders, and has a wide range of applications; a power component is provided, and when the transfer volume of the vulcanization bladders is large or the transportation ground is uphill, the device can save labor.

[0004] When the prior art is used, a transfer cart is usually used for transfer, but the transport space of each transfer cart is fixed. When there are many tire curing capsules, multiple transfers are required. When there are few tire curing capsules, the transport space is too large, resulting in a large movable range of the tire curing capsules and poor stability. Utility Model Content

[0005] 1. Technical issues to be resolved

[0006] The utility model aims to provide a transfer device for the production of tire curing bladders, so as to solve the problem proposed in the above background technology that when there are many tire curing bladders, they need to be transferred multiple times, and when there are fewer tire curing bladders, the transportation space is too large, resulting in a large movable range and poor stability of the tire curing bladders.

[0007] (II) Technical solution

[0008] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a transfer device for producing tire vulcanization bladders, comprising a main body mechanism, the main body mechanism comprising a first movable base, a second movable base is movably provided on the right side of the first movable base, locking universal wheels are movably provided below the first movable base and the second movable base, a first support frame is movably provided above the first movable base, a mounting plate is fixedly installed at the lower right end of the first support frame, a fixing bolt is movably provided above the mounting plate, and the first support frame is mounted on the first movable base by the fixing bolt and the mounting plate.

[0009] Preferably, a second support frame is movably provided above the second movable base, and the second support frame is also installed on the second movable base through fixing bolts and mounting plates, and a first upper docking rod is fixedly installed on the upper right end of the first support frame.

[0010] Preferably, a second upper docking rod is fixedly mounted on the upper left end of the second support frame, and an upper limit rod is movably provided on the other ends of the first upper docking rod and the second upper docking rod, and the first upper docking rod and the second upper docking rod are connected together via the upper limit rod.

[0011] Preferably, a first lower docking rod is fixedly installed on the lower right end of the first support frame, and a second lower docking rod is fixedly installed on the lower left end of the second support frame. The other ends of the first lower docking rod and the second lower docking rod are movably provided with lower limit rods, and the first lower docking rod and the second support frame are connected together through the lower limit rod.

[0012] Preferably, two fixed rods are fixedly installed on the upper right end of the second movable base, and a movable armrest is fixedly installed inside the upper part of the two fixed rods. An electric push rod is fixedly installed on the left side of the second movable base, and a transmission rod is movably provided on the transmission end of the electric push rod, and the left end of the transmission rod is fixedly connected to the right surface of the first movable base.

[0013] Preferably, the other ends of the first upper docking rod, the second upper docking rod, the first lower docking rod and the second lower docking rod are fixedly mounted with limit plates, and the upper and lower limit rods are fixedly provided with positioning plates inside.

[0014] Compared with the prior art, the beneficial effects of the utility model are:

[0015] 1. The tire curing bladder production transfer device is provided with a first support frame and a second support frame. When in use, the electric push rod is used to adjust the distance between the first mobile base and the second mobile base, so that the distance between the first support frame and the second support frame becomes larger, thereby increasing the transportation space of the device, and more tire curing bladders can be transferred at a time. When there are fewer tire curing bladders, the distance between the first support frame and the second support frame is reduced, so that the internal space can better limit the range of movement of the tire curing bladder, making it more stable during transportation;

[0016] 2. The tire curing bladder production transfer device is equipped with a movable handrail and a locking universal wheel, so that when the device is in use, it can be pushed by holding the outer end of the movable handrail. The locking universal wheel at the bottom has a good ability to adapt to the terrain, so that it can be better moved when transported on different roads;

[0017] 3. The transfer device for producing tire vulcanizing bladders is provided with a plurality of first upper docking rods, second upper docking rods, upper limit rods, first lower docking rods, second lower docking rods and lower limit rods to connect the first support frame and the second support frame, so that the device is more stable when in use. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 The three-dimensional structure of the utility model is shown in FIG. Figure 1 ;

[0019] Figure 2 This is a schematic diagram of the cross-sectional structure of the utility model;

[0020] Figure 3 The three-dimensional structure of the utility model is shown in FIG. Figure 2 ;

[0021] Figure 4 It is a schematic diagram of the cross-sectional structure of the limit rod of the utility model.

[0022] In the figure: 1, main body mechanism; 101, first movable base; 102, second movable base; 103, locking universal wheel; 104, first support frame; 105, mounting plate; 106, fixing bolt; 107, second support frame; 108, first upper docking rod; 109, second upper docking rod; 110, upper limit rod; 111, first lower docking rod; 112, second lower docking rod; 113, lower limit rod; 114, fixing rod; 115, movable armrest; 116, electric push rod; 117, transmission rod; 118, limit plate; 119, positioning plate. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] See also Figure 1 - Figure 4 The utility model provides a technical solution: a transfer device for tire vulcanization bladder production, comprising a main body mechanism 1, the main body mechanism 1 comprising a first mobile base 101, a second mobile base 102 is movably provided on the right side of the first mobile base 101, locking universal wheels 103 are movably provided below the first mobile base 101 and the second mobile base 102, a first support frame 104 is movably provided above the first mobile base 101, a mounting plate 105 is fixedly installed at the lower right end of the first support frame 104, a fixing bolt 106 is movably provided above the mounting plate 105, and the first support frame 104 is installed on the first mobile base 101 through the fixing bolt 106 and the mounting plate 105;

[0025] A second support frame 107 is movably provided above the second mobile base 102. The second support frame 107 is also mounted on the second mobile base 102 through fixing bolts 106 and mounting plates 105. A first upper docking rod 108 is fixedly mounted on the upper right end of the first support frame 104.

[0026] A second upper docking rod 109 is fixedly mounted on the upper left end of the second support frame 107, and an upper limit rod 110 is movably mounted on the other ends of the first upper docking rod 108 and the second upper docking rod 109, and the first upper docking rod 108 and the second upper docking rod 109 are connected together through the upper limit rod 110;

[0027] A first lower docking rod 111 is fixedly installed at the lower right end of the first support frame 104, and a second lower docking rod 112 is fixedly installed at the lower left end of the second support frame 107. A lower limiting rod 113 is movably provided at the other ends of the first lower docking rod 111 and the second lower docking rod 112, and the first lower docking rod 111 and the second support frame 107 are connected together through the lower limiting rod 113;

[0028] Two fixed rods 114 are fixedly installed on the upper right end of the second mobile base 102, and a movable handrail 115 is fixedly installed inside the upper part of the two fixed rods 114. An electric push rod 116 is fixedly installed on the left side of the second mobile base 102, and a transmission rod 117 is movably provided at the transmission end of the electric push rod 116. The left end of the transmission rod 117 is fixedly connected to the right surface of the first mobile base 101;

[0029] The other ends of the first upper docking rod 108 , the second upper docking rod 109 , the first lower docking rod 111 and the second lower docking rod 112 are fixedly mounted with a limiting piece 118 , and the interiors of the upper limiting rod 110 and the lower limiting rod 113 are fixedly provided with a positioning plate 119 .

[0030] Working principle: The tire curing bladder production transfer device is installed with a first support frame 104 and a second support frame 107. When in use, the electric push rod 116 is used to adjust the distance between the first mobile base 101 and the second mobile base 102, so that the distance between the first support frame 104 and the second support frame 107 becomes larger, thereby increasing the transportation space of the device, and more tire curing bladders can be transferred at a time. When there are fewer tire curing bladders, the distance between the first support frame 104 and the second support frame 107 is reduced, so that the internal space can better limit the range of movement of the tire curing bladder, so that it can be transported. The transport is more stable; by installing a movable handrail 115 and a locking universal wheel 103, the device can be pushed by holding the outer end of the movable handrail 115 when in use; the bottom locking universal wheel 103 has a better ability to adapt to terrain, so that it can be better moved when transported on different roads; by setting a plurality of first upper docking rods 108, second upper docking rods 109, upper limit rods 110, first lower docking rods 111, second lower docking rods 112 and lower limit rods 113 to connect the first support frame 104 and the second support frame 107, the device is more stable when in use.

[0031] Finally, it should be noted that the above content is only used to illustrate the technical solution of the utility model, rather than to limit the protection scope of the utility model. Simple modifications or equivalent substitutions of the technical solution of the utility model by ordinary technicians in this field do not deviate from the essence and scope of the technical solution of the utility model.

Claims

1. A transfer device for tire curing bladder production, comprising a main body (1), characterized in that: The main body mechanism (1) comprises a first movable base (101), a second movable base (102) is movably arranged on the right side of the first movable base (101), locking universal wheels (103) are movably arranged below the first movable base (101) and the second movable base (102), a first support frame (104) is movably arranged above the first movable base (101), a mounting plate (105) is fixedly installed at the lower right end of the first support frame (104), a fixing bolt (106) is movably arranged above the mounting plate (105), and the first support frame (104) is mounted on the first movable base (101) via the fixing bolt (106) and the mounting plate (105).

2. A transfer device for tire curing bladder production according to claim 1, characterized in that: A second support frame (107) is movably arranged above the second movable base (102), and the second support frame (107) is also installed on the second movable base (102) through fixing bolts (106) and mounting plates (105). A first upper docking rod (108) is fixedly installed at the upper right end of the first support frame (104).

3. A transfer device for tire curing bladder production according to claim 2, characterized in that: A second upper docking rod (109) is fixedly mounted on the upper left end of the second support frame (107); an upper limit rod (110) is movably arranged on the other ends of the first upper docking rod (108) and the second upper docking rod (109); the first upper docking rod (108) and the second upper docking rod (109) are connected together via the upper limit rod (110).

4. A transfer device for tire curing bladder production according to claim 3, characterized in that: A first lower docking rod (111) is fixedly mounted on the lower right end of the first support frame (104), a second lower docking rod (112) is fixedly mounted on the lower left end of the second support frame (107), a lower limit rod (113) is movably mounted on the other ends of the first lower docking rod (111) and the second lower docking rod (112), and the first lower docking rod (111) and the second support frame (107) are connected together via the lower limit rod (113).

5. A transfer device for tire curing bladder production according to claim 4, characterized in that: Two fixed rods (114) are fixedly installed on the upper right end of the second movable base (102), and a movable handrail (115) is fixedly installed inside the upper part of the two fixed rods (114). An electric push rod (116) is fixedly installed on the left side of the second movable base (102), and a transmission rod (117) is movably provided at the transmission end of the electric push rod (116), and the left end of the transmission rod (117) is fixedly connected to the right surface of the first movable base (101).

6. A transfer device for producing tire curing bladders according to claim 5, characterized in that: The other ends of the first upper docking rod (108), the second upper docking rod (109), the first lower docking rod (111) and the second lower docking rod (112) are fixedly mounted with a limiting plate (118), and the interiors of the upper limit rod (110) and the lower limit rod (113) are fixedly provided with a positioning plate (119).

Citation Information

Patent Citations

  • Transfer device for tire curing bladder production

    CN217532957U