Construction measurement positioning device
By designing a construction measurement and positioning device including a support chamber, a winding wheel, an adjustment screw, a draw rope, a connecting frame and a marking mechanism, the problems of measurement error and ink sticking in the prior art are solved, and high precision and safety of construction are achieved.
Patent Information
- Application Number
- CN202420675784.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2025-03-25
- Estimated Expiration
- 2034-04-03
AI Technical Summary
The existing construction measurement and positioning device is prone to deviation by manually pulling the ink line, resulting in errors in the measurement point, affecting the accuracy of the construction, and at the same time, the ink is easily stuck to the operator's hands.
Design a construction measurement and positioning device including a support compartment, a winding wheel, an adjustment screw, a draw rope, a connecting frame and a marking mechanism. By manually operating the support frame and a rotary frame, the draw rope and a sponge ring are driven to rotate, and accurately mark the line on the wall or the ground to reduce errors and prevent ink from sticking to the hands.
Accurate marking on walls or ground is achieved, measuring errors are reduced, construction accuracy and accuracy are ensured, while preventing ink from sticking to the hands of the operator.
Smart Images

Figure CN222671065U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of construction, in particular to a construction measurement and positioning device. Background Art
[0002] Construction measurement and positioning refers to the use of various measurement tools and techniques to accurately measure and position buildings or engineering projects during the construction process to ensure that the location, size and elevation of the building meet the design requirements. Construction measurement and positioning devices are equipment used for measurement and positioning at the construction site.
[0003] The existing construction measurement and positioning is carried out by using a laser level, and then the ink line or rope in the ink cartridge is dipped in ink, and then the ink line is pulled out manually, and then the ink line is pulled by people so that the ink line contacts the wall or the ground for marking. The ink line is easily offset when pulled by people, resulting in errors in the measurement points, affecting the accuracy of the construction. At the same time, the ink is easy to stick to the hands of the operator.
[0004] Therefore, it is necessary to design a construction measurement and positioning device that can draw lines on the wall or the ground for measurement and positioning, reduce errors, ensure the accuracy and precision of construction, and prevent ink from sticking to the operator's hands. Utility Model Content
[0005] In order to overcome the shortcomings of the existing construction measurement and positioning, in which the ink line is easily offset by people pulling it, resulting in errors in the measurement points, affecting the accuracy of the construction, and the ink is easily stuck to the hands of the operator, the utility model provides a construction measurement and positioning device that can draw lines on the wall or the ground for measurement and positioning, reduce errors, ensure the accuracy and precision of the construction, and prevent the ink from sticking to the hands of the operator.
[0006] The technical solution of the utility model is: a construction measurement and positioning device, including a support bin, a winding wheel, an adjusting screw, a pull rope, a connecting frame and a marking mechanism, the support bin is rotatably connected to the winding wheel, the left side of the upper part of the support bin is connected to the adjusting screw by a thread, the adjusting screw is in contact with the winding wheel, two upper and lower pull ropes are wound around the winding wheel, a connecting frame is connected between the right sides of the pull ropes, and a marking mechanism for marking construction lines is provided on the pull ropes.
[0007] Furthermore, it also includes a crank, which is arranged on the upper middle side of the winding wheel.
[0008] Furthermore, a handle is provided on the right side of the upper portion of the connecting frame.
[0009] Furthermore, the marking mechanism includes a support frame, a support wheel, a lifting frame, a rotating bin, a sponge ring and an ink bag. The support frame is slidably connected to the pull rope, and upper and lower support wheels are rotatably connected to the support frame on both sides. The support wheels are in contact with the pull rope, and the lifting frame is slidably connected to the front and rear sides of the support frame. The rotating bin is rotatably connected between the lower parts of the lifting frame, the rotating bin is connected to the sponge ring, and the top of the lifting frame is connected to the ink bag.
[0010] Furthermore, the lifting frames are all hollow structures.
[0011] Furthermore, it also includes a tensioning mechanism, which includes a support arm, a rotating frame, a contact wheel and a torsion spring. The support arm is connected to the left side of the upper part of the connecting frame, and the support arm is in contact with the pull rope. The supporting arm is rotatably connected to the rotating frame, and the contact wheels are rotatably connected to the upper and lower sides of the rotating frame, and the contact wheels are in contact with the pull rope. Two front and rear torsion springs are connected between the rotating frame and the support arm.
[0012] The utility model has the following advantages: 1. The utility model pulls the support frame left and right by hand to make the support wheel rotate, thereby driving the lifting frame to move, making the rotating bin rotate, and then driving the sponge ring to rotate, so as to draw lines on the wall or the ground for measurement and positioning, and can accurately draw straight lines or mark points, reduce errors, ensure the accuracy and precision of construction, and prevent ink from sticking to the hands of operators.
[0013] 2. The utility model twists the rotating frame on the support arm to the left by hand, causing the torsion spring to deform, and then releases the hand, causing the torsion spring to rotate and reset, thereby driving the rotating frame to reset, causing the contact wheel to rotate and move, thereby straightening the pull rope for measurement and positioning, ensuring the accuracy of measurement and positioning, and preventing inaccurate measurement and positioning due to loose pull rope. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a three-dimensional structural schematic diagram of the utility model.
[0015] Figure 2 It is a cross-sectional view of the utility model.
[0016] Figure 3 It is a schematic diagram of the three-dimensional structure of the marking mechanism of the utility model.
[0017] Figure 4 It is a cross-sectional view of the scribing mechanism of the present utility model.
[0018] Figure 5 It is a schematic diagram of the three-dimensional structure of the tensioning mechanism of the utility model.
[0019] In the accompanying drawings: 1_support bin, 2_winding wheel, 3_crank, 4_adjusting screw, 5_pull rope, 6_connecting frame, 7_marking mechanism, 71_support frame, 72_support wheel, 73_lifting frame, 74_rotating bin, 75_sponge ring, 76_ink sac, 8_tensioning mechanism, 81_support arm, 82_rotating frame, 83_contact wheel, 84_torsion spring. DETAILED DESCRIPTION
[0020] The preferred technical solution of the present utility model is described in detail below in conjunction with the accompanying drawings.
[0021] A construction measurement and positioning device, such as Figure 1-Figure 4 As shown, it includes a support bin 1, a winding wheel 2, an adjusting screw 4, a pull rope 5, a connecting frame 6 and a marking mechanism 7. The winding wheel 2 is rotatably connected to the support bin 1, and also includes a crank 3. The crank 3 is provided on the upper side of the middle of the winding wheel 2. The adjusting screw 4 is threadedly connected to the left side of the upper part of the support bin 1. The adjusting screw 4 is in contact with the winding wheel 2. Two upper and lower pull ropes 5 are wound around the winding wheel 2. A connecting frame 6 is connected between the right sides of the pull ropes 5. A handle is provided on the upper right side of the connecting frame 6. A marking mechanism 7 for marking lines during construction is provided on the pull rope 5.
[0022] like Figure 1 , Figure 3 and Figure 4 As shown, the marking mechanism 7 includes a support frame 71, a support wheel 72, a lifting frame 73, a rotating bin 74, a sponge ring 75 and an ink bag 76. The support frame 71 is slidably connected to the pull rope 5. The upper and lower sides of the support frame 71 are rotatably connected to the upper and lower support wheels 72. The support wheels 72 are in contact with the pull rope 5. The front and rear sides of the support frame 71 are slidably connected to the lifting frames 73. The lifting frames 73 are all hollow structures. The rotating bin 74 is rotatably connected between the lower parts of the lifting frames 73. The rotating bin 74 is connected to the sponge ring 75, and the top of the lifting frames 73 is connected to the ink bag 76.
[0023] When measurement and positioning are required for construction, the device can be used and brought to the construction site. The support bin 1 is fixed on the wall or the ground, and then the winding wheel 2 is driven to rotate by turning the crank 3 to release the pull rope 5. After the release is completed, the winding wheel 2 is contacted by twisting the adjusting screw 4 to fix the winding wheel 2 and stop it from rotating. Then, the connecting frame 6 is pulled by the handle to move, and then the connecting frame 6 is fixed on the wall or the ground to straighten the pull rope 5. Then, the height of the lifting frame 73 is adjusted to make the sponge ring 75 contact the wall or the ground, and the ink in the ink bag 76 flows from the lifting frame 73 into the rotating bin 74 and then flows on the rotating bin 74. The lifting frames 73 are all hollow structures, which are convenient for the ink to flow out of the rotating bin 74. The support frame 71 moves left and right, causing the support wheel 72 to rotate, thereby driving the lifting frame 73 to move, causing the rotating bin 74 to rotate, and then driving the sponge ring 75 to rotate. During the movement of the lifting frame 73, the lifting frame 73 will move up and down to adapt to the undulations of the ground, thereby drawing lines on the wall or on the ground for measurement and positioning, and can accurately draw straight lines or mark points, reduce errors, ensure the accuracy and precision of construction, and prevent ink from sticking to the hands of operators. After the measurement is completed, pull the lifting frame 73 to reset, so that the sponge ring 75 is separated from the wall or the ground, the support bin 1 and the connecting frame 6 are removed, and then the support frame 71 is moved and reset, and then the adjusting screw 4 is twisted in the reverse direction to disengage the winding wheel 2, and the winding wheel 2 is driven to rotate by rotating the crank 3 in the reverse direction, and the pull rope 5 can be reeled in.
[0024] like Figure 1 and Figure 5 As shown, it also includes a tensioning mechanism 8, which includes a support arm 81, a rotating frame 82, a contact wheel 83 and a torsion spring 84. The support arm 81 is connected to the left side of the upper part of the connecting frame 6, and the support arm 81 is in contact with the pull rope 5. The support arm 81 is rotatably connected to the rotating frame 82, and the contact wheels 83 are rotatably connected to the upper and lower sides of the rotating frame 82. The contact wheels 83 are in contact with the pull rope 5, and two front and rear torsion springs 84 are connected between the rotating frame 82 and the support arm 81.
[0025] Before pulling the support frame 71 to move left and right to draw a line, you can twist the rotating frame 82 on the support arm 81 to the left by hand, so that the torsion spring 84 is deformed, and then let go, the torsion spring 84 rotates and resets, thereby driving the rotating frame 82 to reset, so that the contact wheel 83 rotates and moves, thereby straightening the pull rope 5 for measurement and positioning, ensuring the accuracy of measurement and positioning, and preventing the pull rope 5 from loosening and causing inaccurate measurement and positioning.
[0026] The above embodiments are provided for persons familiar with the art to implement or use the present invention. Personnel familiar with the art can make various modifications or changes to the above embodiments without departing from the utility model concept of the present invention. Therefore, the protection scope of the present invention is not limited to the above embodiments, but should be the maximum scope of the innovative features mentioned in the claims.
Claims
1. A construction measurement and positioning device, characterized in that: The invention comprises a support bin (1), a winding wheel (2), an adjusting screw (4), a pull rope (5), a connecting frame (6) and a marking mechanism (7); the winding wheel (2) is rotatably connected to the support bin (1); the adjusting screw (4) is threadedly connected to the left side of the upper part of the support bin (1); the adjusting screw (4) is in contact with the winding wheel (2); two upper and lower pull ropes (5) are wound around the winding wheel (2); the connecting frame (6) is connected between the right sides of the pull ropes (5); and the drawing mechanism (7) for marking lines during construction is provided on the pull ropes (5).
2. A construction measurement and positioning device according to claim 1, characterized in that: It also includes a crank (3), which is arranged on the upper middle side of the winding wheel (2).
3. A construction measurement and positioning device according to claim 2, characterized in that: A handle is provided on the right side of the upper part of the connecting frame (6).
4. A construction measurement and positioning device according to claim 3, characterized in that: The marking mechanism (7) comprises a support frame (71), a support wheel (72), a lifting frame (73), a rotating bin (74), a sponge ring (75) and an ink bag (76); the pull rope (5) is slidably connected to the support frame (71); upper and lower sides of the support frame (71) are rotatably connected to two support wheels (72); the support wheels (72) are in contact with the pull rope (5); the front and rear sides of the support frame (71) are slidably connected to the lifting frame (73); the lower part of the lifting frame (73) is rotatably connected to the rotating bin (74); the rotating bin (74) is connected to the sponge ring (75); and the top of the lifting frame (73) is connected to the ink bag (76).
5. A construction measurement and positioning device according to claim 4, characterized in that: The lifting frames (73) are all hollow structures.
6. A construction measurement and positioning device according to claim 5, characterized in that: The invention also comprises a tensioning mechanism (8), the tensioning mechanism (8) comprising a support arm (81), a rotating frame (82), a contact wheel (83) and a torsion spring (84), the upper left side of the connecting frame (6) is connected to the support arm (81), the support arm (81) is in contact with the pull rope (5), the support arm (81) is rotatably connected to the rotating frame (82), and the rotating frame (82) The upper and lower sides are both rotatably connected with contact wheels (83), and the contact wheels (83) are in contact with the pull rope (5). Two front and rear torsion springs (84) are connected between the rotating frame (82) and the supporting arm (81).