An equipment for installing and coating insulation boards for exterior wall insulation

By designing an exterior wall insulation board installation coating equipment containing multiple functional rooms, the problems of uneven surface finishing layer, low processing efficiency and slow drying speed in the prior art are solved, and fast and automated coating and drying treatment are achieved, and the overall performance and use effect of the insulation board are improved.

CN222710023UActive Publication Date: 2025-04-04CHINA THIRD METALLURGICAL GRP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421209816.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-04-04
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

During processing, existing exterior wall insulation boards have problems such as uneven finishing layers, low processing efficiency and slow drying speed, which affects the overall appearance and use effect.

Method used

A coating equipment for insulation panel installation for exterior wall insulation is designed, including a pressing chamber, grinding chamber, cleaning chamber, coating chamber and drying chamber in the processing shell. The mobile processing and coating process is carried out using automated equipment, and components such as infrared sensors, grinding motors, cleaning wipe blocks and infrared heat sources are used to achieve rapid and automated coating and drying treatment.

Benefits of technology

Through automated equipment, rapid and effective coating treatment is achieved, the appearance uniformity and use effect of the insulation board are improved, damage caused by manual handling is reduced and work efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222710023U_ABST
    Figure CN222710023U_ABST
Patent Text Reader

Abstract

The utility model discloses an insulation board installation and coating equipment for exterior wall insulation, comprising a processing shell, wherein a pressing chamber, a grinding chamber, a cleaning chamber, a coating chamber and a drying chamber are sequentially arranged inside the processing shell, wherein a rectangular slot is penetrated through the processing shell along the width direction, and support rollers equidistantly distributed are rotatably arranged inside the processing shell, a loading slot is arranged on an inner wall on one side of the pressing chamber, and a first electric slide rail is fixed parallel to the width direction of the processing shell inside the pressing chamber, and a first electric slider is slidably connected to the inner wall of the first electric slide rail; after the outer wall of the insulation board is effectively coated, in order to improve the drying effect, the utility model uses infrared radiation drying to quickly dry the coating inside the paint film, reduces the problem of coating collapse caused by uneven drying, and also combines with external thermal cycle baking heating to improve the drying of the coating surface, and the combination of the two can quickly dry the coating layer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of municipal drainage, in particular to a thermal insulation board installation and coating device for external wall thermal insulation. Background Art

[0002] External wall insulation board is a kind of insulation material used for building exterior walls, usually composed of polymer mortar, glass fiber mesh cloth, flame-retardant molded polystyrene foam board or extruded board. This material integrates insulation, waterproofing, finishing and other functions, which can improve the insulation level of industrial and civil building exterior walls. It is also the preferred material for energy-saving transformation of existing buildings. The advantages of external wall insulation board include good thermal insulation performance, strong fire resistance, convenient construction, rich decorative effects, etc. It can effectively improve the energy efficiency of buildings, reduce energy consumption, and also help improve living comfort and extend the service life of buildings.

[0003] However, external wall insulation boards also have some disadvantages, such as relatively high costs and the possibility of requiring more maintenance and upkeep in some cases. In addition, different types of external wall insulation boards have different performances. For example, although rock wool insulation boards have good fire resistance, they have high hygroscopicity and poor insulation effect; while extruded polystyrene boards (XPS boards) have better insulation effects, they are relatively expensive and require interface treatment on the board surface during construction. However, there are still some deficiencies in the treatment of existing insulation boards:

[0004] 1. The surface finishing layer is uneven. When the existing insulation board is in use, a surface finishing layer is provided on the outer wall of the insulation layer for decoration, which not only has the same appearance, but also can prevent rainwater from invading. However, when the existing insulation board is processed, the surface coating of the surface finishing layer is uneven, which affects the overall appearance and use after installation.

[0005] 2. Low processing efficiency. Most of the existing thermal insulation boards are processed by manual handling during coating processing. This processing method not only greatly reduces the overall processing efficiency, but also the continuous manual handling can easily cause damage to the thermal insulation boards.

[0006] 3. Slow drying speed. After the insulation board is coated, the paint layer on its surface cannot dry quickly, so when it is moved immediately after spraying, the surface coating layer will be damaged, thus affecting subsequent use. Utility Model Content

[0007] The utility model aims to solve the shortcomings in the prior art and proposes a thermal insulation board installation and coating device for external wall thermal insulation.

[0008] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0009] An insulation board installation and coating device for exterior wall insulation comprises a processing shell, wherein a pressing chamber, a grinding chamber, a cleaning chamber, a coating chamber and a drying chamber are sequentially arranged inside the processing shell, a rectangular notch is opened through the processing shell along the width direction, and support rollers equidistantly distributed are rotatably arranged inside the processing shell, a loading notch is opened on the inner wall of one side of the pressing chamber, and a first electric slide rail is fixed in parallel inside the pressing chamber along the width direction of the processing shell, a first electric slider is slidably connected to the inner wall of the first electric slide rail, and a top plate is fixed between the two first electric sliders by screws;

[0010] An outer wall of one side of the processing shell is provided with first infrared sensors distributed at equal distances, and an inner wall of one side of the grinding chamber close to the pressing chamber is installed with second infrared sensors distributed at equal distances, inner walls on both sides of the grinding chamber are provided with first telescopic cylinders distributed symmetrically, and a Z-shaped positioning clamp is fixed to the piston rod of the first telescopic cylinder by screws, a second electric slide rail is fixed to the inner wall of the top of the grinding chamber by bolts, and a second electric slider is slidably connected to the inner wall of the second electric slide rail, a connecting plate is provided between the two second electric sliders, and a third electric slide rail is fixed below the connecting plate by screws, the inner wall of the third electric slide rail is slidably connected to the third electric slider, and a second telescopic cylinder is fixed to the bottom of the third electric slider; a mounting seat is welded to the outer wall of the bottom of the second telescopic cylinder, and a grinding motor whose output shaft is connected to a grinding wheel is fixed to the mounting seat by bolts;

[0011] A sealing baffle is provided on the outer wall of the rectangular notch on one side of the cleaning chamber close to the polishing chamber, and a third electric telescopic rod is fixedly connected to the bottom of the sealing baffle, and fourth electric slide rails parallel to each other are provided on the top inner wall of the cleaning chamber along the length direction, and a fourth electric slider is slidably connected to the inner wall of the fourth electric slide rail, a third telescopic cylinder is fixed between the two fourth electric sliders by screws, and a cleaning wiping block is welded to the bottom outer wall of the third telescopic cylinder;

[0012] The inner wall of the coating room is parallelly provided with a symmetrically distributed fifth electric slide rail along the length direction, and the inner wall of the fifth electric slide rail is slidably inserted with a fifth electric slider, a paint spray tube is fixed between the two fifth electric sliders, and the bottom inner wall of the paint spray tube is screwed with equidistantly distributed spray heads, and the middle inner wall of the drying room is installed with equidistantly distributed infrared heat sources.

[0013] As a further solution of the utility model: a toothed pulley is welded to the outer wall of the same side of multiple supporting roller shafts, and a synchronous belt is meshed on the outer wall of the toothed pulley, and a driving motor output shaft is fixed to the axis of one of the toothed pulleys by bolts.

[0014] As a further solution of the utility model: the outer walls at both ends of the bottom of the top plate are fixed with a first electric telescopic rod by bolts, and a fixed suction cup is provided at the piston rod at the bottom of the first electric telescopic rod, and the inner wall of one end of the fixed suction cup is connected to an exhaust pipe.

[0015] As a further solution of the utility model: a positioning rod is arranged on one side of the bottom of the pressing chamber close to the grinding chamber, and a second electric telescopic rod is fixed below the positioning rod.

[0016] As a further solution of the utility model: an inner wall on one side of the bottom of the grinding chamber is connected to an exhaust pipe, and an exhaust fan is arranged inside the exhaust pipe, and a dust filter bag is sleeved on the end of the exhaust pipe.

[0017] As a further solution of the utility model: an inner wall on one side of the top of the grinding chamber is connected with a ventilation duct, and the end of the ventilation duct is rotatably connected with a sealing cover.

[0018] As a further solution of the utility model: a fourth electric telescopic rod is fixed to an inner wall of one side of the cleaning chamber by bolts, and a dust suction shell is fixed at the piston rod of the fourth electric telescopic rod, a dust suction pipe is connected to an inner wall of one side of the dust suction shell, and the size of the groove on the inner wall of the dust suction shell is adapted to the size of the cleaning wiping block.

[0019] As a further solution of the utility model: a connecting pipe is connected to the inner wall of one side of the bottom of the drying chamber, and a circulating fan is fixed at the axis of the connecting pipe, and one end of the connecting pipe away from the drying chamber is connected to a heating box.

[0020] As a further solution of the utility model: a guide tube is connected between the top of the heating box and the drying chamber, and the inner wall of the heating box is installed with electric heating wires distributed at equal distances. The outer wall of one end of the heating box is connected to an air inlet duct, and a valve is provided at the end of the air inlet duct.

[0021] Compared with the prior art, the utility model provides an installation and coating device for thermal insulation boards for exterior wall insulation, which has the following beneficial effects:

[0022] 1. The insulation board installation and coating equipment for exterior wall insulation of this design adopts automated equipment for mobile processing and coating treatment as a whole, which can realize complete coating treatment inside a single processing shell, reduce the damage caused by traditional manual handling and improve work efficiency.

[0023] 2. The insulation board coating equipment for exterior wall insulation of this design is installed. When processing the insulation board, it is first positioned and pressed, and then with the help of external grinding components, the surface layer of the insulation board can be quickly ground and polished, thereby improving the overall smoothness and decorative effect of the subsequent coating layer, and effectively improving the overall appearance uniformity of the insulation board.

[0024] 3. The insulation board coating equipment for exterior wall insulation of this design is installed. After the surface is polished and smooth, in order to avoid residual particles and dust affecting the coating effect, the contact cleaning component can quickly clean the outer wall of the insulation board. After cleaning, it can automatically clean and absorb dust, so that the cleaning component can maintain an effective cleaning effect for a long time.

[0025] 4. The insulation board for exterior wall insulation of this design is installed with coating equipment. After the outer wall of the insulation board is effectively coated, in order to improve the drying effect, infrared radiation drying is used to quickly dry the coating inside the paint film, reducing the problem of coating collapse caused by uneven drying. It is also combined with external thermal cycle baking heating to improve the drying of the coating surface. The combination of the two can quickly dry the coating layer.

[0026] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a schematic diagram of the overall structure of an insulation board installation and coating device for exterior wall insulation proposed by the utility model;

[0028] Figure 2 This is a side view of the overall structure of an insulation board installation and coating device for exterior wall insulation proposed by the utility model;

[0029] Figure 3 This is a first-view structural schematic diagram of a thermal insulation board installation and coating device for exterior wall thermal insulation proposed by the utility model;

[0030] Figure 4 This is a schematic diagram of the disassembled structure of an insulation board installation and coating device for exterior wall insulation proposed by the utility model;

[0031] Figure 5 This is a schematic diagram of the internal structure of an insulation board installation and coating device for exterior wall insulation proposed by the utility model;

[0032] Figure 6 This is a second perspective structural schematic diagram of a thermal insulation board installation and coating device for external wall thermal insulation proposed by the utility model;

[0033] Figure 7 The utility model discloses a front view of the temporal structure of a thermal insulation board installation and coating device for exterior wall thermal insulation.

[0034] In the figure: 1. Processing shell; 2. Laminating chamber; 3. Grinding chamber; 4. Cleaning chamber; 5. Coating chamber; 6. Drying chamber; 7. Rectangular notch; 8. Support roller; 9. Toothed pulley; 10. Synchronous belt; 11. Driving motor; 12. Loading notch; 13. First electric slide rail; 14. First electric slider; 15. Top plate; 16. First electric telescopic rod; 17. Fixed suction cup; 18. Exhaust pipe; 19. Positioning fence; 20. Second electric telescopic rod; 21. First infrared sensor; 22. Second infrared sensor; 23. First telescopic cylinder; 24. Z-shaped positioning clamp; 25. Second electric slide rail; 26. Second electric slider; 27. Connecting plate; 28. Third electric slide rail; 29. The third electric slider; 30. The second telescopic cylinder; 31. The mounting seat; 32. The grinding motor; 33. The grinding wheel; 34. The exhaust pipe; 35. The exhaust fan; 36. The dust filter bag; 37. The sealing baffle; 38. The third electric telescopic rod; 39. The fourth electric slide rail; 40. The fourth electric slider; 41. The third telescopic cylinder; 42. The cleaning wiping block; 43. The fourth electric telescopic rod; 44. The dust suction shell; 45. The dust suction pipe; 46. The fifth electric slide rail; 47. The fifth electric slider; 48. The paint spraying pipe; 49. The nozzle; 50. The infrared heat source; 51. The connecting pipe; 52. The circulation fan; 53. The heating box; 54. The guide pipe; 55. The electric heating wire; 56. The air inlet duct. DETAILED DESCRIPTION

[0035] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0036] Embodiment 1:

[0037] An insulation board installation and coating device for exterior wall insulation. This embodiment is based on the existing insulation board surface coating problem, in order to achieve fast and effective coating processing, such as Figure 1-4 As shown, it includes a processing shell 1, characterized in that a pressing chamber 2, a grinding chamber 3, a cleaning chamber 4, a coating chamber 5 and a drying chamber 6 are sequentially arranged inside the processing shell 1, a rectangular notch 7 is opened through the processing shell 1 along the width direction, and a supporting roller 8 equidistantly distributed is rotatably arranged inside the processing shell 1, a loading notch 12 is opened on the inner wall of one side of the pressing chamber 2, and a first electric slide rail 13 is fixed in parallel to the inside of the pressing chamber 2 along the width direction of the processing shell 1, a first electric slider 14 is slidably connected to the inner wall of the first electric slide rail 13, and a top plate 15 is fixed between the two first electric sliders 14 by screws;

[0038] The outer walls of the same side of the plurality of support roller shafts 8 are all welded with toothed pulleys 9, and the outer wall of the toothed pulleys 9 is meshed with a synchronous belt 10, and the output shaft of a driving motor 11 is fixed to the axis of one of the toothed pulleys 9 by bolts;

[0039] The outer walls at both ends of the bottom of the top plate 15 are fixed with first electric telescopic rods 16 by bolts, and a fixed suction cup 17 is provided at the piston rod at the bottom of the first electric telescopic rod 16, and an inner wall at one end of the fixed suction cup 17 is connected to an exhaust pipe 18, and a positioning rod 19 is provided on the bottom side of the pressing chamber 2 close to the grinding chamber 3, and a second electric telescopic rod 20 is fixed below the positioning rod 19;

[0040] An outer wall of one side of the processing housing 1 is provided with first infrared sensors 21 distributed at equal distances, and an inner wall of one side of the grinding chamber 3 close to the pressing chamber 2 is installed with second infrared sensors 22 distributed at equal distances, and the inner walls of both sides of the grinding chamber 3 are provided with symmetrically distributed first telescopic cylinders 23, and a Z-shaped positioning clamp 24 is fixed at the piston rod of the first telescopic cylinder 23 by screws, and a second electric slide rail 25 is fixed to the inner wall of the top of the grinding chamber 3 by bolts, and a second electric slider 26 is slidably connected to the inner wall of the second electric slide rail 25;

[0041] The inner wall of the bottom side of the polishing chamber 3 is connected to an exhaust pipe 34, and an exhaust fan 35 is arranged inside the exhaust pipe 34. A dust filter bag 36 is sleeved at the end of the exhaust pipe 34. The inner wall of the top side of the polishing chamber 3 is connected to a ventilation pipe, and a sealing cover is rotatably connected to the end of the ventilation pipe.

[0042] The whole adopts automated equipment for mobile processing and coating, which can realize complete coating processing inside a single processing shell 1, reduce the damage caused by traditional manual handling and improve work efficiency;

[0043] A connecting plate 27 is provided between the two second electric sliders 26, and a third electric slide rail 28 is fixed to the bottom of the connecting plate 27 by screws, a third electric slide rail 29 is slidably connected to the inner wall of the third electric slide rail 28, and a second telescopic cylinder 30 is fixed to the bottom of the third electric slide rail 29; a mounting seat 31 is welded to the outer wall of the bottom of the second telescopic cylinder 30, and a grinding motor 32 whose output shaft is connected to a grinding wheel 33 is fixed to the mounting seat 31 by bolts;

[0044] A sealing baffle 37 is provided on the outer wall of the rectangular notch 7 on one side of the cleaning chamber 4 close to the polishing chamber 3, and a third electric telescopic rod 38 is fixedly connected to the bottom of the sealing baffle 37, and fourth electric slide rails 39 parallel to each other are provided on the top inner wall of the cleaning chamber 4 along the length direction, and a fourth electric slider 40 is slidably connected to the inner wall of the fourth electric slide rail 39, a third telescopic cylinder 41 is fixed between the two fourth electric sliders 40 by screws, and a cleaning wiping block 42 is welded to the bottom outer wall of the third telescopic cylinder 41;

[0045] When processing the insulation board, it is first positioned and pressed, and then the surface finishing layer of the insulation board can be quickly polished with the help of the external polishing component, thereby improving the overall smoothness and decorative effect of the subsequent coating layer, and effectively improving the overall appearance uniformity of the insulation board;

[0046] A fourth electric telescopic rod 43 is fixed to the inner wall of one side of the cleaning chamber 4 by bolts, and a dust suction shell 44 is fixed to the piston rod of the fourth electric telescopic rod 43. A dust suction pipe 45 is connected to the inner wall of one side of the dust suction shell 44, and the size of the groove on the inner wall of the dust suction shell 44 is adapted to the size of the cleaning wiping block 42.

[0047] The inner wall of the coating chamber 5 is parallelly provided with symmetrically distributed fifth electric slide rails 46 along the length direction, and the inner wall of the fifth electric slide rail 46 is slidably plugged with a fifth electric slider 47, a paint spraying tube 48 is fixed between the two fifth electric sliders 47, and the inner wall at the bottom of the paint spraying tube 48 is screwed with spray heads 49 distributed at equal distances, and the middle inner wall of the drying chamber 6 is installed with infrared heat sources 50 distributed at equal distances;

[0048] The inner wall of one side of the bottom of the drying chamber 6 is connected to a connecting pipe 51, and a circulating fan 52 is fixed at the axis of the connecting pipe 51, the end of the connecting pipe 51 away from the drying chamber 6 is connected to a heating box 53, a guide pipe 54 is connected between the top of the heating box 53 and the drying chamber 6, and the inner wall of the heating box 53 is installed with electric heating wires 55 distributed at equal distances, the outer wall of one end of the heating box 53 is connected to an air inlet duct 56, and a valve is provided at the end of the air inlet duct 56.

[0049] When the present embodiment is used, the coating equipment is first connected to an external power supply for a test run. After the test run is completed, the side drive motor 11 is started, and the drive motor 11 is used to drive the support roller 8 to rotate, and then the insulation board to be coated is slowly pushed from the rectangular notch 7 into the interior of the pressing chamber 2. When the first infrared sensor 21 detects that the insulation board has entered, the second electric telescopic rod 20 drives the positioning rod 19 to rise, so that the insulation board is positioned against the positioning rod 19 to complete the positioning. After the positioning is completed, the first electric slider 14 is used to drive the top plate 15 to move outward, and the metal facing plate with glue on the bottom outer wall is adsorbed and fixed in cooperation with the adsorption treatment of the fixed suction cup 17 at the bottom. After moving to the interior of the pressing chamber 2, when it is located directly above the insulation board, the first electric telescopic rod 16 is used to press down to complete the overall pressing of the insulation board. After the pressing is completed, the second electric telescopic rod 20 is retracted to remove the positioning rod 19, and the insulation board is moved to the interior of the polishing chamber 3 with the help of the rotating support roller 8.

[0050] When the insulation board enters the grinding chamber 3, the second infrared sensor 22 first detects the insulation board, and then the third electric telescopic rod 38 on its side drives the sealing baffle 37 to move up to seal the grinding chamber 3, and starts the exhaust fan 35 on the side, opens the cover of the top ventilation duct, and realizes air circulation. First, the first telescopic cylinders 23 on both sides drive the Z-shaped positioning clamps 24 to complete the clamping and fixing of the insulation board. After the fixing is completed, the second electric slide rail 25 and the third electric slide rail 28 cooperate with each other to complete the position adjustment of the grinding motor 32, and then the second telescopic cylinder 30 drives the grinding wheel 33 to descend. When the grinding wheel 33 fits the surface veneer, it will grind the impurities, oil stains and particles on the surface, and the dust in the grinding process will be quickly discharged. The polished insulation board will be transported to the inside of the cleaning chamber 4;

[0051] When the insulation board enters the cleaning chamber 4, its cleaning wiping block 42 is first adjusted to the rectangular slot 7 close to the insulation board, and is lowered with the help of the third telescopic cylinder 41 on the top, so that the cleaning wiping block 42 can be used to wipe the top surface layer of the insulation board to wipe off dust and other particulate matter. After wiping, the insulation board will enter the drying chamber 6, thereby starting the infrared heat source 50. Infrared heating can be used to quickly dry the coating inside the paint film, reducing the problem of coating collapse caused by uneven drying.

[0052] Embodiment 2:

[0053] An insulation board installation and coating device for exterior wall insulation, such as Figure 1-4As shown, this embodiment makes the following supplements on the basis of embodiment 1: it includes a processing shell 1, characterized in that a pressing chamber 2, a grinding chamber 3, a cleaning chamber 4, a coating chamber 5 and a drying chamber 6 are sequentially arranged inside the processing shell 1, a rectangular notch 7 is opened through the processing shell 1 along the width direction, and support rollers 8 equidistantly distributed are rotatably arranged inside the processing shell 1, a loading notch 12 is opened on the inner wall of one side of the pressing chamber 2, and a first electric slide rail 13 is fixed in parallel to the inside of the pressing chamber 2 along the width direction of the processing shell 1, a first electric slider 14 is slidably connected to the inner wall of the first electric slide rail 13, and a top plate 15 is fixed between the two first electric sliders 14 by screws;

[0054] The outer walls of the same side of the plurality of support roller shafts 8 are all welded with toothed pulleys 9, and the outer wall of the toothed pulleys 9 is meshed with a synchronous belt 10, and the output shaft of a driving motor 11 is fixed to the axis of one of the toothed pulleys 9 by bolts;

[0055] The outer walls at both ends of the bottom of the top plate 15 are fixed with first electric telescopic rods 16 by bolts, and a fixed suction cup 17 is provided at the piston rod at the bottom of the first electric telescopic rod 16, and an inner wall at one end of the fixed suction cup 17 is connected to an exhaust pipe 18, and a positioning rod 19 is provided on the bottom side of the pressing chamber 2 close to the grinding chamber 3, and a second electric telescopic rod 20 is fixed below the positioning rod 19;

[0056] After the surface is polished and smoothed, in order to avoid residual particles and dust affecting the coating effect, the contact cleaning component can quickly clean the outer wall of the insulation board, and after cleaning, it can automatically clean and absorb dust, so that the cleaning component can maintain an effective cleaning effect for a long time;

[0057] An outer wall of one side of the processing housing 1 is provided with first infrared sensors 21 distributed at equal distances, and an inner wall of one side of the grinding chamber 3 close to the pressing chamber 2 is installed with second infrared sensors 22 distributed at equal distances, and the inner walls of both sides of the grinding chamber 3 are provided with symmetrically distributed first telescopic cylinders 23, and a Z-shaped positioning clamp 24 is fixed at the piston rod of the first telescopic cylinder 23 by screws, and a second electric slide rail 25 is fixed to the inner wall of the top of the grinding chamber 3 by bolts, and a second electric slider 26 is slidably connected to the inner wall of the second electric slide rail 25;

[0058] The inner wall of the bottom side of the polishing chamber 3 is connected to an exhaust pipe 34, and an exhaust fan 35 is arranged inside the exhaust pipe 34. A dust filter bag 36 is sleeved at the end of the exhaust pipe 34. The inner wall of the top side of the polishing chamber 3 is connected to a ventilation pipe, and a sealing cover is rotatably connected to the end of the ventilation pipe.

[0059] After the outer wall of the insulation board is effectively coated, in order to improve the drying effect, infrared radiation drying can be used to quickly dry the coating inside the paint film, reducing the problem of coating collapse caused by uneven drying. In addition, combined with external thermal cycle baking heating, the drying of the coating surface can be improved. The combination of the two can quickly dry the coating layer;

[0060] A connecting plate 27 is provided between the two second electric sliders 26, and a third electric slide rail 28 is fixed to the bottom of the connecting plate 27 by screws, a third electric slide rail 29 is slidably connected to the inner wall of the third electric slide rail 28, and a second telescopic cylinder 30 is fixed to the bottom of the third electric slide rail 29; a mounting seat 31 is welded to the outer wall of the bottom of the second telescopic cylinder 30, and a grinding motor 32 whose output shaft is connected to a grinding wheel 33 is fixed to the mounting seat 31 by bolts;

[0061] A sealing baffle 37 is provided on the outer wall of the rectangular notch 7 on one side of the cleaning chamber 4 close to the polishing chamber 3, and a third electric telescopic rod 38 is fixedly connected to the bottom of the sealing baffle 37, and fourth electric slide rails 39 parallel to each other are provided on the top inner wall of the cleaning chamber 4 along the length direction, and a fourth electric slider 40 is slidably connected to the inner wall of the fourth electric slide rail 39, a third telescopic cylinder 41 is fixed between the two fourth electric sliders 40 by screws, and a cleaning wiping block 42 is welded to the bottom outer wall of the third telescopic cylinder 41;

[0062] A fourth electric telescopic rod 43 is fixed to the inner wall of one side of the cleaning chamber 4 by bolts, and a dust suction shell 44 is fixed to the piston rod of the fourth electric telescopic rod 43. A dust suction pipe 45 is connected to the inner wall of one side of the dust suction shell 44, and the size of the groove on the inner wall of the dust suction shell 44 is adapted to the size of the cleaning wiping block 42.

[0063] The inner wall of the coating chamber 5 is parallelly provided with symmetrically distributed fifth electric slide rails 46 along the length direction, and the inner wall of the fifth electric slide rail 46 is slidably plugged with a fifth electric slider 47, a paint spraying tube 48 is fixed between the two fifth electric sliders 47, and the inner wall at the bottom of the paint spraying tube 48 is screwed with spray heads 49 distributed at equal distances, and the middle inner wall of the drying chamber 6 is installed with infrared heat sources 50 distributed at equal distances;

[0064] The inner wall of one side of the bottom of the drying chamber 6 is connected to a connecting pipe 51, and a circulating fan 52 is fixed at the axis of the connecting pipe 51, the end of the connecting pipe 51 away from the drying chamber 6 is connected to a heating box 53, a guide pipe 54 is connected between the top of the heating box 53 and the drying chamber 6, and the inner wall of the heating box 53 is installed with electric heating wires 55 distributed at equal distances, the outer wall of one end of the heating box 53 is connected to an air inlet duct 56, and a valve is provided at the end of the air inlet duct 56.

[0065] When the present embodiment is used, the coating equipment is first connected to an external power supply for a test run. After the test run is completed, the side drive motor 11 is started, and the drive motor 11 is used to drive the support roller 8 to rotate, and then the insulation board to be coated is slowly pushed from the rectangular notch 7 into the interior of the pressing chamber 2. When the first infrared sensor 21 detects that the insulation board has entered, the second electric telescopic rod 20 drives the positioning rod 19 to rise, so that the insulation board is positioned against the positioning rod 19 to complete the positioning. After the positioning is completed, the first electric slider 14 is used to drive the top plate 15 to move outward, and the metal facing plate with glue on the bottom outer wall is adsorbed and fixed in cooperation with the adsorption treatment of the fixed suction cup 17 at the bottom. After moving to the interior of the pressing chamber 2, when it is located directly above the insulation board, the first electric telescopic rod 16 is used to press down to complete the overall pressing of the insulation board. After the pressing is completed, the second electric telescopic rod 20 is retracted to remove the positioning rod 19, and the insulation board is moved to the interior of the polishing chamber 3 with the help of the rotating support roller 8.

[0066] When the insulation board enters the grinding chamber 3, the second infrared sensor 22 first detects the insulation board, and then the third electric telescopic rod 38 on its side drives the sealing baffle 37 to move up to seal the grinding chamber 3, and starts the exhaust fan 35 on the side, opens the cover of the top ventilation duct, and realizes air circulation. First, the first telescopic cylinders 23 on both sides drive the Z-shaped positioning clamps 24 to complete the clamping and fixing of the insulation board. After the fixing is completed, the second electric slide rail 25 and the third electric slide rail 28 cooperate with each other to complete the position adjustment of the grinding motor 32, and then the second telescopic cylinder 30 drives the grinding wheel 33 to descend. When the grinding wheel 33 fits the surface veneer, it will grind the impurities, oil stains and particles on the surface, and the dust in the grinding process will be quickly discharged. The polished insulation board will be transported to the inside of the cleaning chamber 4;

[0067] When the insulation board enters the interior of the cleaning chamber 4, its cleaning wiping block 42 is first adjusted to the rectangular slot 7 close to the insulation board, and is lowered with the help of the third telescopic cylinder 41 on the top, so that the cleaning wiping block 42 is used to wipe the top surface of the insulation board to clean the dust and other particulate matter. After wiping, the insulation board will enter the drying chamber 6. When a large amount of dust is adhered to the surface of the cleaning wiping block 42, in order to effectively maintain the subsequent cleaning efficiency, the cleaning wiping block 42 is moved to the inside of the dust suction shell 44. After the connection is completed, the outside of the dust suction pipe 45 is connected to the vacuum pump. Continuous suction will quickly suck away the dust adhered to the outer wall of the cleaning wiping block 42, and In order to improve the overall cleaning effect, the fourth electric telescopic rod 43 is continuously telescopically moved, so that the dust particles under the cleaning wiping block 42 can be quickly cleaned, thereby starting the infrared heat source 50. Infrared heating can quickly dry the coating inside the paint film, reducing the problem of coating collapse caused by uneven drying. When the efficiency of single infrared drying is not high, the electric heating wire 55 inside the heating box 53 is started, and the circulating fan 52 is continuously blown to quickly and evenly blow the heated hot air into the drying chamber 6, thereby combining with the external thermal circulation baking heating to improve the drying of the coating surface. The combination of the two can quickly dry the coating layer.

[0068] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. An insulation board installation and coating device for exterior wall insulation, comprising a processing shell (1), characterized in that: The processing shell (1) is provided with a pressing chamber (2), a grinding chamber (3), a cleaning chamber (4), a coating chamber (5) and a drying chamber (6) in sequence. The processing shell (1) is provided with a rectangular slot (7) running through it in the width direction, and support rollers (8) are rotatably provided in the processing shell (1) at equal intervals. A loading slot (12) is provided on the inner wall of one side of the pressing chamber (2), and a first electric slide rail (13) is fixed in parallel to the inside of the pressing chamber (2) along the width direction of the processing shell (1). The inner wall of the first electric slide rail (13) is slidably connected to a first electric slider (14), and a top plate (15) is fixed between the two first electric sliders (14) by screws. The outer wall of one side of the processing housing (1) is provided with first infrared sensors (21) distributed at equal distances, and the inner wall of one side of the grinding chamber (3) close to the pressing chamber (2) is installed with second infrared sensors (22) distributed at equal distances, the inner walls of both sides of the grinding chamber (3) are provided with first telescopic cylinders (23) distributed symmetrically, and the piston rod of the first telescopic cylinder (23) is fixed with a Z-shaped positioning clamp (24) by screws, the inner wall of the top of the grinding chamber (3) is fixed with a second electric slide rail (25) by bolts, and the inner wall of the second electric slide rail (25) is slidably connected with A second electric slider (26), a connecting plate (27) is provided between the two second electric sliders (26), and a third electric slide rail (28) is fixed below the connecting plate (27) by screws, a third electric slider (29) is slidably connected to the inner wall of the third electric slide rail (28), and a second telescopic cylinder (30) is fixed at the bottom of the third electric slider (29); a mounting seat (31) is welded to the outer wall of the bottom of the second telescopic cylinder (30), and a grinding motor (32) whose output shaft is connected to a grinding wheel (33) is fixed on the mounting seat (31) by bolts; A sealing baffle (37) is provided on the outer wall of the rectangular notch (7) on one side of the cleaning chamber (4) close to the polishing chamber (3), and a third electric telescopic rod (38) is fixedly connected to the bottom of the sealing baffle (37); fourth electric slide rails (39) parallel to each other are provided on the top inner wall of the cleaning chamber (4) along the length direction, and a fourth electric slider (40) is slidably connected to the inner wall of the fourth electric slide rail (39); a third telescopic cylinder (41) is fixed between the two fourth electric sliders (40) by screws, and a cleaning wiping block (42) is welded to the outer wall of the bottom of the third telescopic cylinder (41); The inner wall of the coating chamber (5) is parallelly provided with a fifth electric slide rail (46) which is symmetrically distributed along the length direction, and the inner wall of the fifth electric slide rail (46) is slidably plugged with a fifth electric slider (47), a paint spraying tube (48) is fixed between the two fifth electric sliders (47), and the inner wall at the bottom of the paint spraying tube (48) is screwed with spray heads (49) which are equidistantly distributed, and the middle inner wall of the drying chamber (6) is installed with infrared heat sources (50) which are equidistantly distributed.

2. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 1 is characterized in that: A toothed pulley (9) is welded to the outer wall of the same side of the plurality of support roller shafts (8), and a synchronous belt (10) is meshed on the outer wall of the toothed pulley (9), wherein the output shaft of a driving motor (11) is fixed to the axis of one of the toothed pulleys (9) by bolts.

3. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 1, characterized in that: The outer walls at both ends of the bottom of the top plate (15) are fixed with a first electric telescopic rod (16) by bolts, and a fixed suction cup (17) is provided at the piston rod at the bottom of the first electric telescopic rod (16), and the inner wall at one end of the fixed suction cup (17) is connected to an exhaust pipe (18).

4. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 1, characterized in that: A positioning rod (19) is provided on one side of the bottom of the pressing chamber (2) close to the grinding chamber (3), and a second electric telescopic rod (20) is fixed below the positioning rod (19).

5. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 1, characterized in that: An inner wall at one side of the bottom of the polishing chamber (3) is connected to an exhaust pipe (34), an exhaust fan (35) is arranged inside the exhaust pipe (34), and a dust filter bag (36) is sleeved at the end of the exhaust pipe (34).

6. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 5, characterized in that: The inner wall on one side of the top of the grinding chamber (3) is connected to a ventilation duct, and the end of the ventilation duct is rotatably connected to a sealing cover.

7. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 1, characterized in that: A fourth electric telescopic rod (43) is fixed to an inner wall of one side of the cleaning chamber (4) by means of bolts, and a dust collection shell (44) is fixed to the piston rod of the fourth electric telescopic rod (43); a dust collection pipe (45) is connected to an inner wall of one side of the dust collection shell (44), and the size of the groove on the inner wall of the dust collection shell (44) is adapted to the size of the cleaning wiping block (42).

8. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 1, characterized in that: A connecting pipe (51) is connected to the inner wall of one side of the bottom of the drying chamber (6), and a circulating fan (52) is fixed at the axis of the connecting pipe (51). The end of the connecting pipe (51) away from the drying chamber (6) is connected to a heating box (53).

9. The thermal insulation board installation and coating equipment for exterior wall thermal insulation according to claim 8, characterized in that: A flow guide tube (54) is connected between the top of the heating box (53) and the drying chamber (6), and electric heating wires (55) are installed on the inner wall of the heating box (53) at equal distances. The outer wall of one end of the heating box (53) is connected to an air inlet duct (56), and a valve is provided at the end of the air inlet duct (56).

Citation Information

Cited By

  • Preparation process and preparation device of silicone rubber composite film

    CN120133102A