Drainage structure for viaduct

By designing a fast disassembly and installed block system and a waterproof spring system that buffers the impact of water flow in the viaduct drainage structure, the existing viaduct drainage structure has solved the problems of low efficiency and short service life, and the effect of efficient disassembly and installation and extended service life is achieved.

CN222715794UActive Publication Date: 2025-04-04NINGBO JUNMAO MUNICIPAL GARDEN CONSTRUCTION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420488647.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-14
Publication Date
2025-04-04
Estimated Expiration
2034-03-14

AI Technical Summary

Technical Problem

The existing viaduct drainage structure is inefficient during disassembly and installation, and the drainage pipe is prone to breaking in heavy rain, affecting its service life.

Method used

A drainage structure for viaducts is designed, and the water pipe grooves, chutes, ring grooves, chutes, chute rods and holes are installed to achieve rapid disassembly and installation of drainage pipes; at the same time, fixed blocks, sliders, sliders, waterproof springs and diverters are used to buffer the impact of water flow during heavy rain and reduce damage to drainage pipes.

Benefits of technology

The rapid disassembly and installation of drainage pipes is achieved, and the work efficiency of workers is improved. At the same time, by buffering the impact of water flow, the service life of drainage pipes is extended and economic losses are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222715794U_ABST
    Figure CN222715794U_ABST
Patent Text Reader

Abstract

The utility model discloses a drainage structure for an elevated bridge, wherein a drainage channel is provided inside the bridge deck, and the drainage channel has a certain slope, a drainage pipe is provided at the bottom of the drainage channel, a water pipe groove is provided inside the bottom of the bridge deck, and the water pipe groove is arranged around the bottom of the drainage channel, and the top of the drainage pipe is movably arranged in the water pipe groove. The utility model pushes the drainage pipe upward to move, so that two clamping blocks move upward and leave the two clamping grooves, so that the two clamping blocks move into the annular groove, and then the drainage pipe is rotated to make the two clamping blocks correspond to the two through grooves, and then the drainage pipe is moved downward for convenience in quickly disassembling it, so that the drainage pipe can be quickly disassembled and installed, thereby reducing the working time of workers, thereby improving the working efficiency of workers.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge parts, in particular to a drainage structure for an elevated bridge. Background Art

[0002] With the rapid increase of urban population, the number of vehicles is also increasing. In order to ensure the smooth flow of traffic and avoid the blockage and congestion of the main routes, the overpass and the elevated road form a multi-layer three-dimensional layout. The emergence of urban viaducts greatly improves the speed and passing capacity, and urban viaducts have become an important symbol of modern cities. In order to ensure that the viaduct can be used normally on rainy days, drainage channels are set on both sides of the bridge deck, and the bottom of the drainage channel is generally directly connected with a drainage pipe by bolts to discharge rainwater. However, this design has great disadvantages. When the drainage pipe is damaged and needs to be replaced, workers need to spend more time to turn the bolts to remove the broken drainage pipe. When installing, it also takes more time to turn the bolts to install the new drainage pipe, so that the drainage pipe cannot be quickly disassembled and installed, which increases the working time of the workers and reduces the work efficiency of the workers. At the same time, when the rainfall is heavy, the rushing water will violently impact the drainage pipe, exerting a lot of pressure on the drainage pipe, which is easy to cause the drainage pipe to rupture. Therefore, it is necessary to provide a drainage structure for viaducts to solve the above problems. Utility Model Content

[0003] The purpose of the utility model is to solve the problem that the drainage pipe cannot be quickly disassembled and installed in the prior art, and thus a drainage structure for an elevated bridge is proposed.

[0004] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a drainage structure for an elevated bridge, including a bridge deck, a drainage channel is opened inside the bridge deck, and the drainage channel has a certain slope, a drainage pipe is arranged at the bottom of the drainage channel, a water pipe groove is opened inside the bottom of the bridge deck, and the water pipe groove is arranged around the bottom of the drainage channel, and the top of the drainage pipe is movably arranged in the water pipe groove.

[0005] Furthermore, blocks are fixedly provided on both sides of the top of the drainage pipe, and two through grooves are opened inside the bottom of the bridge deck. The two through grooves are connected to the water pipe grooves, and the two through grooves are located at the longitudinal ends of the water pipe grooves, and the two blocks are respectively adapted to the two through grooves.

[0006] Furthermore, a circular groove is provided inside the bridge deck, which is connected with the water pipe groove and two through grooves, and the circular groove is located on the top of the water pipe groove and the two through grooves. Card slots are provided at the bottom of both lateral ends of the circular groove, and card rods are fixed inside the two card slots. Card holes are provided in the centers of the two card blocks, and the two card blocks are respectively located in the two card slots, and the two card rods are respectively inserted into the two card holes.

[0007] Furthermore, the inner side wall of the drain pipe is circular and has four fixed blocks fixed at equal intervals. Sliding rods are fixed on the top of the four fixed blocks. Slide blocks are slidably arranged on the surfaces of the four sliding rods. Waterproof springs are fixed between the four slide blocks and the four fixed blocks, and the four waterproof springs are respectively sleeved on the surfaces of the four sliding rods.

[0008] Furthermore, a diverter is movably arranged inside the drain pipe, four sliders are fixedly arranged at four ends of the diverter, and the diverter is located below the drain channel.

[0009] The beneficial effects of the utility model are:

[0010] 1. By arranging water pipe grooves, clamping blocks, through grooves, annular grooves, clamping grooves, clamping rods and clamping holes, when the drain pipe needs to be disassembled, the drain pipe is pushed upward to move, so that the two clamping blocks move upward and leave the two clamping grooves, so that the two clamping blocks move into the annular groove, and then the drain pipe is rotated to make the two clamping blocks correspond to the two through grooves, and then the drain pipe is moved downward to facilitate its quick disassembly, so that the drain pipe can be quickly disassembled and installed, thereby reducing the working time of workers and improving the working efficiency of workers.

[0011] 2. By setting fixed blocks, sliding rods, sliders, waterproof springs and diverters, when the rainfall is heavy, the rushing water flow will violently impact the diverter downward, causing the diverter to move downward, driving the four sliders to move downward on the four sliding rods. The four sliders compress the four waterproof springs downward on the four sliding rods, thereby facilitating the buffering of the diverter, and then facilitating the buffering of the rushing water flow, and then dispersing the rushing water flow through the diverter, which greatly weakens the impact force of the water flow, weakens the damage of the water flow to the pipeline, increases the service life of the pipeline, reduces economic losses, allows the pipeline to continuously and stably perform its drainage function, and ensures the normal traffic on the elevated bridge road surface. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0013] Figure 2 This is a schematic diagram of the main cross-sectional structure of the utility model;

[0014] Figure 3 For this utility model Figure 2 A schematic diagram of the enlarged structure at A in the middle;

[0015] Figure 4 It is a schematic diagram of a partial side cross-sectional structure of the utility model;

[0016] Figure 5 It is a schematic diagram of a partial top view cross-sectional structure of the utility model;

[0017] Figure 6It is a structural schematic diagram of the drainage pipe in the utility model;

[0018] Figure 7 It is a structural schematic diagram of the flow divider in the utility model.

[0019] In the figure: 1 bridge deck, 2 drainage channel, 3 drainage pipe, 4 water pipe groove, 5 clamping block, 6 through groove, 7 circular groove, 8 clamping groove, 9 clamping rod, 10 clamping hole, 11 fixing block, 12 sliding rod, 13 sliding block, 14 waterproof spring, 15 diverter. DETAILED DESCRIPTION

[0020] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0021] Reference Figures 1 to 7 The present embodiment provides a drainage structure for an elevated bridge, including a bridge deck 1, a drainage channel 2 is provided inside the bridge deck 1, and the drainage channel 2 has a certain slope, a drainage pipe 3 is provided at the bottom of the drainage channel 2, a water pipe groove 4 is provided inside the bottom of the bridge deck 1, and the water pipe groove 4 is provided around the bottom of the drainage channel 2, and the top of the drainage pipe 3 is movably provided in the water pipe groove 4; preferably, the drainage channel 2 is provided to facilitate the collection of rainwater on the bridge deck 1, the drainage pipe 3 is provided to facilitate the discharge of rainwater in the drainage channel 2, and the water pipe groove 4 is provided to facilitate the placement of the drainage pipe 3 at the inner bottom of the bridge deck 1, so that the bottom of the drainage channel 2 is surrounded by the drainage pipe 3, thereby preventing the rainwater in the drainage channel 2 from flowing into the drainage pipe 3.

[0022] Furthermore, blocks 5 are fixedly provided on both sides of the top of the drainage pipe 3, and two through grooves 6 are opened inside the bottom of the bridge deck 1. The two through grooves 6 are connected to the water pipe groove 4, and the two through grooves 6 are located at the longitudinal ends of the water pipe groove 4. The two blocks 5 are respectively adapted to the two through grooves 6; preferably, by providing two through grooves 6, it is convenient for the drainage pipe 3 to drive the two blocks 5 to be inserted into the water pipe groove 4, and the drainage pipe 3 is inserted into the water pipe groove 4 through the top, so as to facilitate driving the two blocks 5 to be inserted into the two through grooves 6.

[0023] Furthermore, an annular groove 7 is provided inside the bridge deck 1, which is connected with the water pipe groove 4 and the two through grooves 6, and the annular groove 7 is located at the top of the water pipe groove 4 and the two through grooves 6. A clamping groove 8 is provided at the bottom of the two lateral ends of the annular groove 7, and a clamping rod 9 is fixedly provided inside the two clamping grooves 8. A clamping hole 10 is provided in the center of the two clamping blocks 5, and the two clamping blocks 5 are respectively located in the two clamping grooves 8, and the two clamping rods 9 are respectively inserted into the two clamping holes 10; preferably, by pushing the drain pipe 3 upward to move, it is convenient to drive the two clamping blocks 5 to enter the annular groove 7, and then rotate the drain pipe 3 to rotate in the water pipe groove 4, and the rotation of the drain pipe 3 is convenient to drive the two clamping blocks 5 to rotate in the annular groove 7. When the two clamping blocks 5 correspond to the two clamping grooves 8, pulling the drain pipe 3 downward to move drives the two clamping blocks 5 to be clamped into the two clamping grooves 8, and then the two clamping rods 9 are clamped into the two clamping holes 10, so as to facilitate the fixed installation of the drain pipe 3 at the bottom of the drainage channel 2.

[0024] Furthermore, the inner side wall of the drain pipe 3 is circular and fixed with four fixed blocks 11 at equal intervals, the tops of the four fixed blocks 11 are fixed with sliding bars 12, the surfaces of the four sliding bars 12 are slidably provided with sliders 13, waterproof springs 14 are fixedly provided between the four sliders 13 and the four fixed blocks 11, and the four waterproof springs 14 are respectively sleeved on the surfaces of the four sliding bars 12; preferably, the four fixed blocks 11 are provided to facilitate the four sliding bars 12 to be fixedly installed inside the drain pipe 3, and the four sliding bars 13 are conveniently slid up and down on the four sliding bars 12 by moving the four sliding bars 13 up and down, thereby facilitating the four sliding bars 13 to stretch or contract the four waterproof springs 14 on the four sliding bars 12, thereby facilitating the buffering of the sliding of the four sliding bars 13 on the four sliding bars 12, thereby preventing the four sliding bars 13 from contacting the four fixed blocks 11.

[0025] Furthermore, a diverter 15 is movably provided inside the drain pipe 3, and four sliders 13 are respectively fixed at the four ends of the diverter 15, and the diverter 15 is located below the drain channel 2; preferably, the diverter 15 moves downward in the drain pipe 3, so as to facilitate the four sliders 13 to slide downward on the four slide bars 12, and then facilitate the four sliders 13 to compress the four waterproof springs 14 on the four slide bars 12, so as to facilitate the buffering of the diverter 15. By providing the diverter 15, it is convenient to disperse the rushing water flow.

[0026] In the utility model, when it is necessary to disassemble the drain pipe 3, the drain pipe 3 is pushed upward to move, so that the two clamping blocks 5 move upward and leave the two clamping grooves 8, and then the two clamping rods 9 leave the two clamping holes 10, so that the two clamping blocks 5 move upward into the annular groove 7, and then the drain pipe 3 is rotated to make the two clamping blocks 5 correspond to the two through grooves 6, and then the drain pipe 3 is moved downward to facilitate its quick disassembly; when it is necessary to install the drain pipe 3, the top of the drain pipe 3 is inserted into the annular groove 7 through the water pipe groove 4, so that the two clamping blocks 5 pass through the two through grooves 6 and enter the annular groove 7, and then the drain pipe 3 is rotated to make the two clamping blocks 5 correspond to the two clamping grooves 8, and then the drain pipe 3 is moved downward to make the two clamping blocks 5 insert into the two clamping grooves. The two clamping rods 9 are inserted into the two clamping holes 10, so that the drain pipe 3 can be quickly installed on the bottom of the drain channel 2, so that the drain pipe 3 can be quickly disassembled and installed; at the same time, when the rainfall is heavy, the rushing water flow will violently impact the diverter 15 downward, so that the diverter 15 moves downward and drives the four sliders 13 to move downward on the four slide bars 12. The four sliders 13 compress the four waterproof springs 14 downward on the four slide bars 12, so as to facilitate the buffering of the diverter 15, and then facilitate the buffering of the rushing water flow, and then disperse the rushing water flow through the diverter 15, which greatly weakens the impact force of the water flow, reduces the damage of the water flow to the pipeline, and increases the service life of the pipeline.

[0027] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A drainage structure for an elevated bridge, comprising a bridge deck (1), characterized in that: A drainage channel (2) is provided inside the bridge deck (1), and the drainage channel (2) has a slope. A drainage pipe (3) is provided at the bottom of the drainage channel (2). A water pipe groove (4) is provided inside the bottom of the bridge deck (1), and the water pipe groove (4) is provided around the bottom of the drainage channel (2). The top of the drainage pipe (3) is movably provided in the water pipe groove (4).

2. The drainage structure for an elevated bridge according to claim 1, characterized in that: Blocks (5) are fixedly provided on both sides of the top of the drainage pipe (3); two through grooves (6) are provided inside the bottom of the bridge deck (1); the two through grooves (6) are connected to the water pipe groove (4); the two through grooves (6) are located at both ends of the water pipe groove (4) in the longitudinal direction; and the two blocks (5) are respectively matched with the two through grooves (6).

3. The drainage structure for an elevated bridge according to claim 2, characterized in that: The bridge deck (1) is provided with an annular groove (7) inside, the annular groove (7) is connected with the water pipe groove (4) and the two through grooves (6), and the annular groove (7) is located at the top of the water pipe groove (4) and the two through grooves (6), and the bottoms of both lateral ends of the annular groove (7) are provided with clamping grooves (8), and clamping rods (9) are fixedly arranged inside the two clamping grooves (8), and clamping holes (10) are provided at the centers of the two clamping blocks (5), and the two clamping blocks (5) are respectively located in the two clamping grooves (8), and the two clamping rods (9) are respectively inserted into the two clamping holes (10).

4. The drainage structure for an elevated bridge according to claim 3, characterized in that: The inner side wall of the drainage pipe (3) is circular and has four fixed blocks (11) fixedly arranged at equal intervals. A sliding rod (12) is fixedly arranged on the top of each of the four fixed blocks (11). Slide blocks (13) are slidably arranged on the surfaces of each of the four slide bars (12). A waterproof spring (14) is fixedly arranged between each of the four slide blocks (13) and the four fixed blocks (11). The four waterproof springs (14) are respectively sleeved on the surfaces of the four slide bars (12).

5. The drainage structure for an elevated bridge according to claim 4, characterized in that: A flow diverter (15) is movably arranged inside the drainage pipe (3), and four sliders (13) are fixedly arranged at four ends of the flow diverter (15), respectively, and the flow diverter (15) is located below the drainage channel (2).