Auxiliary structure of wall-attached frame

By designing an auxiliary structure for wall frames, the force of the guide rail frame is transmitted to the external and internal beams of the building by using the attached wall arms, the main frames of the walls and the support pipes, the problem of high force at high altitude of the construction elevator is solved and the effective bearing of the structure is achieved.

CN222757715UActive Publication Date: 2025-04-15GUANGZHOU YIAN CONSTR MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421603762.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2025-04-15
Estimated Expiration
2034-07-09

AI Technical Summary

Technical Problem

When the installation height of the construction elevator is high, the forces in the X and Y directions are relatively large, and the existing wall frames are difficult to meet the stress requirements.

Method used

An auxiliary structure of the wall frame is designed. Through the first wall seat, the wall main frame, the first support pipe and the wall arm fixed to the outer beam of the building, the force exerted by the guide rail frame is transmitted to the outer beam of the building through the wall arm, the wall main frame and the first support pipe in turn, and then transmitted to the inner beam of the building through the connecting frame and the second support pipe to meet the stress requirements.

Benefits of technology

Through this auxiliary structure, the force exerted by the guide rail frame can be effectively transmitted to the outer and inner beams of the building, meeting the force requirements of high-altitude construction elevators in the X and Y directions, and improving the bearing capacity of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222757715U_ABST
    Figure CN222757715U_ABST
Patent Text Reader

Abstract

A wall-attached frame auxiliary structure comprises a first wall-attached base fixed to a building outer beam, a wall-attached main frame, a first supporting pipe and a wall-attached arm, one end of the wall-attached arm is connected with a guide rail frame, the other end of the wall-attached arm is connected with one end of the wall-attached main frame, the other end of the wall-attached main frame is connected with one end of the first supporting pipe, and the other end of the first supporting pipe is connected with the other end of the second supporting pipe. The other end of the first supporting pipe is connected with the first wall attaching base. The second wall attaching base is fixed to the building inner beam, the connecting frame is arranged between the building outer beam and the building inner beam, one end of the connecting frame is connected with the first wall attaching base, the other end of the connecting frame is connected with one end of the second supporting pipe, and the other end of the second supporting pipe is connected with the second wall attaching base. According to the principle, force borne by the guide rail frame is transmitted to the building outer beam through the wall-attached arm, the wall-attached main frame and the first supporting pipe in sequence and then transmitted to the building inner beam through the connecting frame and the second supporting pipe, and the stress requirement is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model is a design construction elevator, in particular to a wall-mounted frame auxiliary structure. Background Art

[0002] One end of the construction hoist wall bracket is connected and fixed to the guide frame, and the other end is connected and fixed to the building beam, bearing the forces in the X direction (cage length direction) and Y direction (cage width direction) of the construction hoist, while the force in the Z direction of the construction hoist is borne by the guide frame. When the construction hoist is installed at a high height, the forces in the X and Y directions are large, and the building beam connected to the wall bracket cannot meet the force requirements. Summary of the invention

[0003] The technical problem to be solved by the utility model is to provide a wall-mounted frame auxiliary structure to solve the technical problems existing in the prior art.

[0004] In order to solve the above technical problems, the technical solution of the utility model is: a wall-attached frame auxiliary structure, including a first wall-attached seat fixed on the outer beam of the building, a wall-attached main frame, a first support tube and a wall-attached arm, one end of the wall-attached arm is connected to the guide rail frame, the other end of the wall-attached arm is connected to one end of the wall-attached main frame, the other end of the wall-attached main frame is connected to one end of the first support tube, and the other end of the first support tube is connected to the first wall-attached seat; it also includes a second wall-attached seat fixed to the inner beam of the building and a connecting frame arranged between the outer beam of the building and the inner beam of the building, one end of the connecting frame is connected to the first wall-attached seat, the other end of the connecting frame is connected to one end of the second support tube, and the other end of the second support tube is connected to the second wall-attached seat. Principle of the utility model: the force received by the guide rail frame is sequentially transmitted to the outer beam of the building through the wall-attached arm, the wall-attached main frame and the first support tube, and then transmitted to the inner beam of the building through the connecting frame and the second support tube, so as to meet the force requirements.

[0005] As an improvement, the first wall-mounted bracket includes a first connector arranged on the outside of the building's outer beam, a second connector arranged on the inside of the building's outer beam, and a first screw rod, the first screw rod passes through the building's outer beam and is connected to the first connector and the second connector, the first support tube is hinged to the first connector, and the connecting frame is welded to the second connector.

[0006] As an improvement, the second wall mount includes a third connector and a second screw rod arranged on the inner side of the building inner beam, the second screw rod passes through the building inner beam and is connected to the third connector, and the second support tube is welded to the third connector.

[0007] As an improvement, the wall-mounted main frame is connected to the first supporting pipe via a first pipe clamp, and the connecting frame is connected to the second supporting pipe via a second pipe clamp.

[0008] As an improvement, the first connector, the second connector and the third connector are all angle steels.

[0009] Compared with the prior art, the utility model has the following beneficial effects:

[0010] The force applied to the guide rail frame is successively transmitted to the outer beam of the building through the wall-mounted arm, the wall-mounted main frame and the first supporting tube, and then transmitted to the inner beam of the building through the connecting frame and the second supporting tube, thus meeting the force requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a side view of the utility model.

[0012] Figure 2 It is a top view of the utility model. DETAILED DESCRIPTION

[0013] The utility model will be further described below in conjunction with the accompanying drawings.

[0014] like Figure 1 , 2As shown, a wall-mounted frame auxiliary structure includes a first wall-mounted frame 6 fixed to an outer beam 7 of a building, a second wall-mounted frame 12 fixed to an inner beam 11 of a building, a main wall-mounted frame 3, a first support tube 5, a wall-mounted arm 2, a second support tube 10, and a connecting frame 8 provided between the outer beam 7 of the building and the inner beam 11 of the building. One end of the wall-mounted arm 2 is fixedly connected to the guide rail frame 1, the other end of the wall-mounted arm 2 is hinged to one end of the main wall-mounted frame 3 through a pin, the other end of the main wall-mounted frame 3 is fixedly connected to one end of the first support tube 5 through a first pipe clamp 4, and the other end of the first support tube 5 is hinged to the first wall-mounted frame 6; one end of the connecting frame 8 is fixedly connected to the first wall-mounted frame 6, the other end of the connecting frame 8 is fixedly connected to one end of the second support tube 10 through a second pipe clamp 9, and the other end of the second support tube 10 is fixedly connected to the second wall-mounted frame 12. The first wall-attached seat 6 includes a first connector 61 disposed on the outside of the building outer beam 7, a second connector 62 disposed on the inside of the building outer beam 7, and a first screw 63, the first screw 63 passes through the building outer beam 7 and is connected to the first connector 61 and the second connector 62, the first support tube 5 is hinged to the first connector 61, and the connecting frame 8 is welded to the second connector 62. The second wall-attached seat 12 includes a third connector 121 and a second screw 122 disposed on the inside of the building inner beam 11, the second screw 122 passes through the building inner beam 11 and is connected to the third connector 121, and the second support tube 10 is welded to the third connector 121. The first connector 61, the second connector 62 and the third connector 121 are all angle steels, and one side of the connector can be close to the building beam. The wall-attached arm 2 includes two arm tubes arranged in parallel, the wall-attached main frame 3 includes two main tubes arranged in parallel, the two main tubes correspond to the two first support tubes 5, and the connecting frame 8 includes two connecting tubes arranged in parallel, the two connecting tubes correspond to the two second support tubes 10. The position of the first tube clamp can be adjusted according to the wall-attached distance to make the wall-attached frame tight; the position of the second tube clamp can be adjusted according to the distance between the building outer beam 7 and the building inner beam 11 to make the auxiliary structure tight.

[0015] Principle of the utility model: the force applied to the guide rail frame 1 is sequentially transmitted to the outer beam 7 of the building through the wall-mounted arm 2, the wall-mounted main frame 3 and the first support tube 5, and then transmitted to the inner beam 11 of the building through the connecting frame 8 and the second support tube 10, so as to meet the force requirements.

Claims

1. A wall-mounted frame auxiliary structure, comprising a first wall-mounted frame fixed to an outer beam of a building, a wall-mounted frame, a first support tube and a wall-mounted arm, wherein one end of the wall-mounted arm is connected to a guide rail frame, the other end of the wall-mounted arm is connected to one end of the wall-mounted frame, the other end of the wall-mounted frame is connected to one end of the first support tube, and the other end of the first support tube is connected to the first wall-mounted frame; characterized in that: It also includes a second wall-attached seat fixed to the inner beam of the building and a connecting frame arranged between the outer beam of the building and the inner beam of the building, one end of the connecting frame is connected to the first wall-attached seat, the other end of the connecting frame is connected to one end of the second support tube, and the other end of the second support tube is connected to the second wall-attached seat.

2. The wall-mounted frame auxiliary structure according to claim 1, characterized in that: The first wall-mounted bracket includes a first connector arranged on the outside of the building's outer beam, a second connector arranged on the inside of the building's outer beam, and a first screw rod. The first screw rod passes through the building's outer beam and is connected to the first connector and the second connector. The first support tube is hinged to the first connector, and the connecting frame is welded to the second connector.

3. The wall-mounted frame auxiliary structure according to claim 1, characterized in that: The second wall-mounted base includes a third connector and a second screw rod disposed on the inner side of the building inner beam, the second screw rod passes through the building inner beam and is connected to the third connector, and the second support tube is welded to the third connector.

4. The wall-mounted frame auxiliary structure according to claim 1, characterized in that: The wall-mounted main frame is connected to the first supporting pipe through a first pipe clamp, and the connecting frame is connected to the second supporting pipe through a second pipe clamp.

5. The wall-mounted frame auxiliary structure according to claim 2, characterized in that: The first connector, the second connector and the third connector are all angle steels.