Rapid positioning and mounting device for steel keel
By designing a steel keel rapid positioning and installation device including columns, mounting seats, beams and fine-tuning mechanisms, the problem of low positioning efficiency of steel keel installation in irregular spaces is solved, and fast, accurate positioning and efficient installation are achieved.
Patent Information
- Application Number
- CN202421330685.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2025-04-15
- Estimated Expiration
- 2034-06-12
AI Technical Summary
In irregular spaces, the installation and positioning of the steel keel is inefficient and requires multiple measurements and manual lifting, which is time-consuming and labor-intensive.
A steel keel rapid positioning and installation device is designed, including a first column, mounting seat, beam, fine-tuning mechanism, etc., and the first position is performed through the beam support, and then fine-tuning is performed through the fine-tuning mechanism to achieve accurate positioning.
It improves the installation efficiency of steel keels, can quickly locate in irregular spaces, and reduces labor costs.
Smart Images

Figure CN222759420U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction auxiliary equipment, and in particular to a device for quickly positioning and installing a steel keel. Background Art
[0002] Steel keels are commonly used supporting frames in construction and need to be positioned during installation.
[0003] However, when performing precise positioning in irregular spaces, the use of a total station requires multiple measurements, which is not only inefficient but also requires manual lifting during installation, which is time-consuming and labor-intensive. Utility Model Content
[0004] The embodiments of the present specification provide a device for quickly positioning and installing a steel keel, which is used to solve the problem of low installation efficiency in the prior art.
[0005] The technical solutions provided by the embodiments of this specification are:
[0006] The present application provides a steel keel quick positioning and installation device, comprising:
[0007] First pillar;
[0008] The first mounting seat and the second mounting seat are both connected to the first column and can adjust the mounting position along the vertical direction of the first column, and the second mounting seat is arranged above the first mounting seat;
[0009] A crossbeam, one end of which is fixedly connected to the first mounting seat;
[0010] A third mounting seat is arranged on the crossbeam;
[0011] A second column, fixedly connected to the other end of the crossbeam, forming a U-shaped structure with the first column and the crossbeam;
[0012] a fourth mounting seat, connected to the second column, capable of adjusting the mounting position along the vertical direction of the second column;
[0013] The second mounting seat, the third mounting seat and the fourth mounting seat are respectively provided with fine-tuning structures, which can fine-tune the steel keel placed in the U-shaped structure.
[0014] Furthermore, the first column, the cross beam and the second column are in a square column structure.
[0015] Furthermore, the first mounting seat is in a cylindrical structure and is sleeved on the first column. A bolt through hole is opened on the first mounting seat. A fastening bolt is arranged in the bolt through hole. The first mounting seat is fixedly mounted on the first column by the fastening bolt.
[0016] Furthermore, the cross beam is integrally connected to the second column.
[0017] Furthermore, the fine-tuning mechanism includes:
[0018] Mounting nut;
[0019] The adjusting screw rod is matched with the thread of the mounting nut, and the end of the adjusting screw rod can be pressed against the steel keel.
[0020] Furthermore, a mounting base plate is connected to the bottom of the column.
[0021] At least one of the above technical solutions adopted in the embodiments of the present application can achieve the following beneficial effects: initial positioning is performed by lifting with a crossbeam, and then fine-tuning is performed by a fine-tuning mechanism for precise positioning, thereby improving the installation efficiency of the steel keel. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0023] Figure 1 This is a schematic diagram of the overall structure provided in the embodiments of this specification. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical solution and advantages of the present application clearer, the technical solution of the present application will be clearly and completely described below in combination with the specific embodiments of the present application and the corresponding drawings. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.
[0025] The technical solutions provided by various embodiments of the present application are described in detail below in conjunction with the accompanying drawings.
[0026] This specification provides a steel keel quick positioning and installation device. Figure 1 As shown, it includes a first column 1, a first mounting seat 2, a second mounting seat 3, a crossbeam 4, a third mounting seat 5, a second column 6, a fourth mounting seat 7 and a fine-tuning mechanism.
[0027] Among them, in a possible implementation, the first column 1, the crossbeam 4 and the second column 6 are in a square column structure; when in use, the bottom of the first column is welded to the main structure of the building. The first mounting seat 2 and the second mounting seat 3 are both connected to the first column 1, and the first mounting seat 2 and the second mounting seat 3 can adjust the installation position along the vertical direction of the first column 1, and the second mounting seat 3 is arranged above the first mounting seat 2. In a possible implementation, the first mounting seat 2 is in a cylindrical structure, specifically a square cylindrical structure, which matches the first column. Prevent circumferential rotation when in use. The first mounting seat 2 is sleeved on the first column 1, and a bolt through hole is opened on the first mounting seat 1, and a fastening bolt 8 is arranged in the bolt through hole, and the first mounting seat 2 is fixedly installed on the first column 1 by the fastening bolt 8. When in use, after loosening the fastening bolt 8, the first mounting seat is adjusted to a suitable position, and then the fastening bolt 8 is tightened. Further explanation, the second mounting seat, the third mounting seat and the fourth mounting seat are connected in the same manner, and the description is not repeated here. One end of the crossbeam 4 is fixedly connected to the first mounting seat 2; the third mounting seat 5 is arranged on the crossbeam; the second column 6 is fixedly connected to the other end of the crossbeam 4, and the crossbeam 4 and the second column 6 are integrally connected. The crossbeam 4, the second column 6 and the first column 1 form a U-shaped structure; the steel keel is supported by the U-shaped structure. When in use, the height of the support can be adjusted by adjusting the height of the crossbeam 4. The fourth mounting seat 7 is connected to the second column 6, and the installation position can be adjusted along the vertical direction of the second column 6;
[0028] The second mounting seat, the third mounting seat and the fourth mounting seat are respectively equipped with fine-tuning structures, which can fine-tune the steel keel placed in the U-shaped structure. In a possible implementation, the fine-tuning mechanisms are all arranged on the same side of the second mounting seat, the third mounting seat and the fourth mounting seat, and the fine-tuning mechanisms include a mounting nut 9 and an adjusting screw 10 that matches the thread of the mounting nut, and the end of the adjusting screw 10 can be against the steel keel. Further explanation, the mounting nut 9 is installed on the mounting seat. The adjusting screws on the second mounting seat and the fourth mounting seat are arranged horizontally, and the adjusting screw on the third mounting seat is arranged vertically. Thereby achieving the purpose of three-point positioning.
[0029] When in use, the first step is to use a total station to roughly position the device (one device at each end of the keel to be installed), and weld the bottom of the device to the main structure.
[0030] The second step is to hoist the keel onto the positioning device, but the lifting equipment does not release the hook.
[0031] The third step is to roughly position the keel by adjusting the first mounting seat, the second mounting seat, the third mounting seat and the fourth mounting seat; and then adjust the three adjusting screws to accurately position the steel keel.
[0032] After the keel coordinates are adjusted, the keel connection device is installed according to the design drawings, and the keel is welded and fixed. Finally, the device is removed.
[0033] This embodiment achieves the purpose of quickly positioning the steel keel in an irregular space, thereby improving construction efficiency and reducing labor costs.
[0034] Further preferably, the bottom of the column is connected to a mounting base plate, and when in use, the column can be installed with expansion bolts for easy removal. This is not limited here and is selected according to the usage.
[0035] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0036] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.
Claims
1. A steel keel quick positioning and installation device, characterized in that: include: First pillar; The first mounting seat and the second mounting seat are both connected to the first column and can adjust the mounting position along the vertical direction of the first column, and the second mounting seat is arranged above the first mounting seat; A crossbeam, one end of which is fixedly connected to the first mounting seat; A third mounting seat is arranged on the crossbeam; A second column, fixedly connected to the other end of the crossbeam, forming a U-shaped structure with the first column and the crossbeam; a fourth mounting seat, connected to the second column, capable of adjusting the mounting position along the vertical direction of the second column; The second mounting seat, the third mounting seat and the fourth mounting seat are respectively provided with fine-tuning structures, which can fine-tune the steel keel placed in the U-shaped structure.
2. A steel keel quick positioning and installation device according to claim 1, characterized in that: The first column, the cross beam and the second column are in a square column structure.
3. A steel keel quick positioning and installation device according to claim 1, characterized in that: The first mounting seat is in a cylindrical structure and is sleeved on the first column. A bolt through hole is opened on the first mounting seat. A fastening bolt is arranged in the bolt through hole. The first mounting seat is fixedly mounted on the first column by the fastening bolt.
4. A steel keel quick positioning and installation device according to claim 1, characterized in that: The cross beam is integrally connected to the second column.
5. The steel keel quick positioning and installation device according to claim 1, characterized in that: The fine-tuning mechanism comprises: Mounting nut; The adjusting screw rod is matched with the thread of the mounting nut, and the end of the adjusting screw rod can be pressed against the steel keel.
6. The steel keel quick positioning and installation device according to claim 1, characterized in that: The bottom of the column is connected with a mounting base plate.