Disassembling and assembling tool for combustion furnace of airflow cut-tobacco drier
By designing the disassembly and assembly tooling of the combustion furnace of the airflow wire dryer, and using the oblique braces and positioning holes to connect with the flange, the problems of safety hazards and operation complexity during the disassembly and assembly of the combustion furnace are solved, and efficient and safe disassembly and assembly operations are achieved.
Patent Information
- Application Number
- CN202421637135.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2025-04-22
- Estimated Expiration
- 2034-07-11
AI Technical Summary
During the disassembly and assembly of the flange of the airflow dryer combustion furnace, there are safety hazards such as shaking and damaging people, falling and hitting people, and screw disassembling and injuring teeth. The operation is complicated and inefficient.
An airflow wire dryer combustion furnace disassembly and assembly tool set is designed, including front columns, rear columns, cross beams, longitudinal beams and oblique braces. They abut with the oblique end surface of the flange through the oblique braces and dock with the bolts on the flange through the positioning holes, providing stable support for easy disassembly and assembly.
It realizes fast and convenient flange disassembly and assembly, improves work efficiency, simplifies operating procedures, ensures operation safety, and avoids safety hazards and operation complexity in traditional methods.
Smart Images

Figure CN222779524U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cigarette production equipment maintenance, and more specifically, to a disassembly and assembly tool for a combustion furnace of an airflow tobacco drying machine. Background Art
[0002] The airflow dryer is a kind of production equipment that dries leaf shreds and stem shreds by conduction convection and has a certain aroma preservation effect. Since the combustion furnace and the large fan of the airflow dryer are connected by a flange, the flange needs to be removed before replacing the combustion furnace. The flange installation position forms a certain angle with the horizontal plane and is heavy. When removing the flange, a hoist needs to be installed on the grille for hoisting. There are risks of shaking and injuring people, falling and hitting people, and damaging teeth when removing screws, making disassembly difficult. It takes time to align the holes during installation, the high-altitude working environment on the grille is harsh, stuffy, and tools fall and injure people. This wastes a lot of manpower, material resources and time, affecting production. Utility Model Content
[0003] In view of the above shortcomings, the purpose of the utility model is to provide a disassembly and assembly tool for the combustion furnace of an airflow wire drying machine.
[0004] To achieve the above-mentioned purpose, the utility model provides a disassembly and assembly tool for the combustion furnace of an airflow wire drying machine, comprising two front columns arranged in parallel and two rear columns arranged in parallel, a first cross beam is provided between the two front columns, a second cross beam is connected between the two rear columns, a longitudinal beam is provided between the bottom of the front columns and the bottom of the rear columns located on the same side, a diagonal bracing beam is provided between the top of the front columns and the top of the rear columns located on the same side, the top surfaces of the two diagonal bracing beams can be abutted against the oblique end surfaces of the combustion furnace connecting flange, and the diagonal bracing beams are provided with positioning holes that can be adapted to the connecting bolts on both sides of the combustion furnace connecting flange.
[0005] Preferably, the positioning hole is a waist-shaped hole structure.
[0006] Preferably, there are two first cross beams, and the two first cross beams are respectively connected to the bottom and the top of the two front pillars.
[0007] Preferably, a stopper that can be raised and lowered is provided in the middle of the first crossbeam located at the top of the two front pillars.
[0008] Preferably, guide rods slidably connected to the first crossbeam are provided on both sides of the stopper, and guide holes matched with the guide rods are provided on the first crossbeam. A lifting screw threadedly connected to the first crossbeam is rotatably provided in the middle of the stopper through a bearing.
[0009] Preferably, there are two second cross beams, and the two second cross beams are respectively connected to the bottom and top of the two rear pillars.
[0010] Preferably, slots are provided on both sides of the second cross beam at the bottom of the two rear columns and on both sides of the first cross beam at the bottom of the two front columns, and the slots can allow a forklift arm of a forklift to pass through.
[0011] Preferably, a clamping screw is provided on the top arm of the slot.
[0012] Preferably, the height of the rear pillar is greater than the height of the front pillar.
[0013] Compared with the existing technology, the utility model has the following beneficial effects:
[0014] The utility model discloses a kind of tool for disassembling and assembling the combustion furnace of the airflow wire drying machine, and can quickly and conveniently connect with the bolts on the combustion furnace connecting flange, so that the two diagonal support beams support the flange, thereby being convenient for maintenance personnel to disassemble and assemble the flange, and having high working efficiency, simple operation and guaranteed working safety, and avoiding the problems in the prior art of installing a hoist on the grille for lifting the flange, such as the flange shaking and injuring people, falling and hitting people, being inconvenient for screw alignment, and the harsh high-altitude working environment on the grille, stuffiness, and tools falling and injuring people. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the technical solution of the embodiment of the utility model, the following will briefly introduce the drawings required for the description of the embodiment. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, each element or part is not necessarily drawn according to the actual scale.
[0016] Figure 1 It is a front structural stereogram of the utility model of the disassembly and assembly tooling of the combustion furnace of the airflow drying machine;
[0017] Figure 2 It is a rear structural stereogram of the disassembly and assembly tooling of the combustion furnace of the airflow tofu drying machine of the utility model.
[0018] Explanation of main figure markings: 1. front column; 2. rear column; 3. first cross beam; 4. second cross beam; 5. longitudinal beam; 6. diagonal support beam; 7. positioning hole; 8. block; 9. guide rod; 10. lifting screw; 11. slot; 12. clamping screw; 13. arc-shaped groove. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. The following is an explanation of the embodiments of the utility model based on its overall structure.
[0020] The specific implementation of the utility model is as follows:
[0021] The utility model:
[0022] like Figure 1-Figure 2 As shown, a disassembly and assembly tool for a combustion furnace of an airflow wire drying machine comprises two front columns 1 arranged in parallel and two rear columns 2 arranged in parallel, wherein the height of the rear columns 2 is greater than that of the front columns 1, a first cross beam 3 is arranged between the two front columns 1, a second cross beam 4 is connected between the two rear columns 2, a longitudinal beam 5 is arranged between the bottom of the front column 1 and the bottom of the rear column 2 on the same side, a diagonal bracing beam 6 is arranged between the top of the front column 1 and the top of the rear column 2 on the same side, the top surfaces of the two diagonal bracing beams 6 can abut against the oblique end surfaces of the combustion furnace connecting flange, and the diagonal bracing beams 6 are provided with positioning holes 7 which can be adapted to the connecting bolts on both sides of the combustion furnace connecting flange.
[0023] In the present disassembly and assembly tool of the combustion furnace of the airflow wire drying machine, two front columns 1, two rear columns 2, a first crossbeam 3, a second crossbeam 4 and two diagonal bracing beams 6 form a frame with a central hole, the frame can be sleeved on the outside of the combustion furnace of the airflow wire drying machine, and the combustion furnace and other structures are accommodated inside the frame, and then the two diagonal bracing beams 6 are abutted against the oblique end faces of the combustion furnace connecting flange, and then the positioning holes 7 on the diagonal bracing beams 6 are matched with the bolts on both sides of the combustion furnace connecting flange, and the combustion furnace connecting flange and the diagonal bracing beams 6 are fixed by nuts, so that the present tool supports the combustion furnace connecting flange, thereby facilitating the connection of the combustion furnace The flange is removed from between the combustion furnace and the large fan, or the combustion furnace is installed on the large fan. The gas flow wire drying machine combustion furnace disassembly and assembly tool can quickly and conveniently connect with the bolts on the combustion furnace connecting flange, so that the two diagonal support beams 6 support the flange, thereby facilitating the maintenance staff to disassemble and assemble the flange, with high work efficiency, simple operation, and guaranteed work safety, avoiding the problems of flange shaking and injuring people, falling and hitting people, inconvenience in screw hole alignment, harsh high-altitude working environment on the grille, stuffiness, and tool falling and injuring people when the flange is hoisted on the grille in the prior art.
[0024] In this embodiment, the positioning hole 7 is a waist-shaped hole structure, and the positioning hole 7 is set as a waist-shaped hole structure to facilitate docking with the bolts on the flange.
[0025] In this embodiment, there are two first cross beams 3, and the two first cross beams 3 are respectively connected to the bottom and the top of the two front pillars 1. The two first cross beams 3 support the two front pillars 1 to ensure the firmness and stability of the entire tooling.
[0026] In this embodiment, a liftable stopper 8 is provided in the middle of the first cross beam 3 located at the top of the two front columns 1, and an arc-shaped groove 13 is provided on the stopper 8. After the positioning holes 7 on the diagonal support beam 6 are connected with the bolts on the flange, the stopper 8 can be lifted so that the stopper 8 abuts against the bottom surface of the flange to provide auxiliary support for the flange, thereby reducing the tangential force on the bolts caused by the gravity of the flange and preventing the bolts from bending.
[0027] In this embodiment, guide rods 9 slidingly connected to the first crossbeam 3 are provided on both sides of the stopper 8, and guide holes matching the guide rods 9 are provided on the first crossbeam 3. A lifting screw 10 threadedly connected to the first crossbeam 3 is provided in the middle of the stopper 8 through a bearing. The lifting screw 10 rotates forward or reversely to drive the stopper 8 to rise or fall, and adjust the height of the stopper 8 so that the arc groove 13 on the stopper 8 can abut against the bottom of the flange to support the bottom of the flange.
[0028] In this embodiment, there are two second cross beams 4, and the two second cross beams 4 are respectively connected to the bottom and the top of the two rear pillars 2. The two second cross beams 4 support the two rear pillars 2 to ensure the firmness and stability of the entire tooling.
[0029] In this embodiment, slots 11 are provided on both sides of the second cross beam 4 at the bottom of the two rear columns 2 and on both sides of the first cross beam 3 at the bottom of the two front columns 1. The slots 11 can allow the forklift arm of a forklift to pass through, and the slots 11 can be slidably connected to the forklift arm. During the process of using a forklift to transport and lift the disassembly and assembly tooling of the airflow silk drying machine combustion furnace, the slots 11 can limit the forklift arm to prevent the forklift arm from separating from the tooling, thereby ensuring the safety of the transport operation.
[0030] In this embodiment, a clamping screw 12 is provided on the top arm of the slot 11, and the slot 11 is a channel steel structure. The slot 11 is fixed to the first beam 3 and the second beam 4 by welding. The clamping screw 12 is threadedly connected to the first beam 3 and the second beam 4, and passes through the top arm of the slot 11. After the forklift arm of the forklift is inserted into the slot 11, the forklift arm can be clamped by tightening the clamping screw 12 to prevent relative sliding between the forklift arm and the slot 11 when transporting the tooling.
[0031] Working principle:
[0032] When disassembling, use the forklift arm of a forklift to insert into the slot 11 at the bottom of the tooling, and then fix it by tightening the screw 12;
[0033] Next, the forklift arm of the forklift lifts the tooling, so that the combustion furnace is inserted into the cavity between the two diagonal bracing beams 6. The two diagonal bracing beams 6 are adapted to the rear end surface of the flange of the combustion furnace. The position of the tooling is adjusted so that the bolts on both sides of the flange are plugged into the positioning holes 7 on the diagonal bracing beams 6. Then, the flange and the diagonal bracing beams 6 are fixed by nuts. At the same time, the position of the stopper 8 is adjusted by the lifting screw 10 so that the stopper 8 supports the bottom of the flange.
[0034] Then, with the support of the burner flange by this tooling, the staff can remove the burner flange from the large fan flange, and then operate a forklift to move the burner and the burner flange to the designated location.
[0035] The foregoing descriptions of specific exemplary embodiments of the present invention are for the purpose of explanation and illustration. These descriptions are not intended to limit the present invention to the precise form disclosed, and it is obvious that many changes and variations can be made based on the above teachings. Although an embodiment of the present invention has been shown and described, this specific embodiment is only an explanation of the present invention and is not a limitation of the present invention. The specific features, structures, materials or characteristics described can be combined in a suitable manner in any one or more embodiments or examples. The purpose of selecting and describing the exemplary embodiments is to explain the specific principles of the present invention and its practical application, so that those skilled in the art can make modifications, substitutions, variations and various selections and changes to the embodiments without creative contribution as needed after reading this specification without departing from the principles and purpose of the present invention, but they are protected by patent law as long as they are within the scope of the claims of the present invention.
Claims
1. A disassembly and assembly tool for a combustion furnace of an airflow drying machine, characterized in that: The invention comprises two parallel front columns (1) and two parallel rear columns (2), a first cross beam (3) is arranged between the two front columns (1), a second cross beam (4) is connected between the two rear columns (2), a longitudinal beam (5) is arranged between the bottom of the front columns (1) and the bottom of the rear columns (2) on the same side, and a diagonal bracing beam (6) is arranged between the top of the front columns (1) and the top of the rear columns (2) on the same side, the top surfaces of the two diagonal bracing beams (6) can abut against the oblique end surfaces of the combustion furnace connection flange, and the diagonal bracing beams (6) are provided with positioning holes (7) that can be matched with the connecting bolts on both sides of the combustion furnace connection flange.
2. The assembly and disassembly tool for the combustion furnace of the airflow torrefaction drying machine according to claim 1, characterized in that: The positioning hole (7) is a waist-shaped hole structure.
3. The assembly and disassembly tool of the combustion furnace of the airflow drying machine according to claim 1, characterized in that: There are two first cross beams (3), and the two first cross beams (3) are respectively connected to the bottom and top of the two front upright posts (1).
4. The disassembly and assembly tool for the combustion furnace of the airflow torrefaction drying machine according to claim 3 is characterized in that: A stopper (8) capable of being raised and lowered is provided in the middle of the first crossbeam (3) located at the top of the two front upright posts (1).
5. The assembly and disassembly tool of the combustion furnace of the airflow tofu drying machine according to claim 4, characterized in that: Guide rods (9) slidably connected to the first cross beam (3) are provided on both sides of the stopper (8); guide holes matched with the guide rods (9) are provided on the first cross beam (3); and a lifting screw rod (10) threadably connected to the first cross beam (3) is provided in the middle of the stopper (8) via a bearing.
6. A disassembly and assembly tool for the combustion furnace of an airflow tofu drying machine according to any one of claims 1 to 5, characterized in that: There are two second cross beams (4), and the two second cross beams (4) are respectively connected to the bottom and top of the two rear upright posts (2).
7. The assembly and disassembly tool for the combustion furnace of the airflow tofu drying machine according to claim 6, characterized in that: Slots (11) are provided on both sides of the second cross beam (4) at the bottom of the two rear columns (2) and on both sides of the first cross beam (3) at the bottom of the two front columns (1), and the slots (11) can allow forklift arms of forklifts to pass through.
8. The assembly and disassembly tool for the combustion furnace of the airflow tofu drying machine according to claim 7, characterized in that: A clamping screw (12) is provided on the top arm of the slot (11).
9. The assembly and disassembly tool for the combustion furnace of the airflow tofu drying machine according to claim 6, characterized in that: The height of the rear pillar (2) is greater than the height of the front pillar (1).