Water conservancy pump station construction pipeline connecting assembly
By designing a construction pipeline connection component of a water conservancy pump station including connecting pipes, ring plates, sleeve columns, support blocks, vertical rods, pressure plates and springs, the pressure plates are driven to tightly connect the pressure plates to the outer wall of the construction pipeline of the water conservancy pump station by using the reset contraction force of the spring, the problem of easy loosening at the pipe connection in the prior art is solved, and the stability of the connection and the practicality of the device are improved.
Patent Information
- Application Number
- CN202420666575.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-02
- Publication Date
- 2025-04-22
- Estimated Expiration
- 2034-04-02
AI Technical Summary
During the installation process, the pipeline connection components of the existing water conservancy pump station are prone to loosening of the pipeline connection due to external impact, which affects the stability of the connection.
A connecting component including connecting pipe, ring plate, sleeve column, support block, vertical rod, pressure plate and spring is designed. Through the mutual installation and cooperation of support block, vertical rod, pressure plate and spring, the pressure plate is driven to tightly connect the pressure plate with the outer wall of the construction pipeline of the water conservancy pump station by using the return contraction force of the spring to avoid shaking caused by external force interference.
The stability of the pipeline connection assembly of the water conservancy pump station construction pipeline is improved to the pipeline connection installation, and the practicality and stability of the device are enhanced.
Smart Images

Figure CN222783163U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of water conservancy pump station pipeline connection, and in particular relates to a water conservancy pump station construction pipeline connection component. Background Art
[0002] The utility model discloses a water conservancy pump station construction pipeline connection component, which is a device used for connecting and installing the pump station construction pipelines in water conservancy projects.
[0003] At present, there are many water conservancy pump station construction pipeline connection components on the market, but the general water conservancy pump station construction pipeline connection components are installed by the staff directly fitting the sleeves on one end of the two water conservancy pump station construction pipelines, until one end of the two water conservancy pump station construction pipelines are fastened and installed, and then the inner wall of the pipeline connection component is directly connected with the outer wall of the water conservancy pump station construction pipeline. It is very easy for external force to impact the water conservancy pump station construction pipeline, causing the connection between the two water conservancy pump station construction pipelines to become loose, thereby affecting the stability of the pipeline connection assembly for the water conservancy pump station construction pipeline connection installation and reducing the practicability of the device.
[0004] Therefore, a water conservancy pump station construction pipeline connection component is needed to solve the problem in the prior art that the inner wall of the pipeline connection component is directly clamped and installed with the outer wall of the water conservancy pump station construction pipeline, which is very likely to cause external force to impact the water conservancy pump station construction pipeline, causing the connection between the two water conservancy pump station construction pipelines to become loose, thereby affecting the stability of the pipeline connection component in the installation of the water conservancy pump station construction pipeline. Utility Model Content
[0005] The utility model aims to provide a water conservancy pump station construction pipeline connection component to solve the problems raised in the above background technology.
[0006] To achieve the above purpose, the utility model provides the following technical solution: a water conservancy pump station construction pipeline connection assembly, comprising:
[0007] A connecting pipe, wherein both ends of the outer wall of the connecting pipe are fixed with ring plates, and one side of the two ring plates is fixed with a sleeve column;
[0008] The mounting mechanism comprises four support blocks, one side of each of the four support blocks is fixed to one end of a sleeve column, both ends of each of the four support blocks are fixed with vertical poles, one end of each of the two sleeve columns is provided with two pressure plates, one end of each of the four pressure plates has two circular holes, the inner walls of the eight circular holes are sleeved with the outer walls of the vertical poles, both ends of the four support blocks are fixed with springs, the inner walls of the eight springs are sleeved with the outer walls of the vertical poles, and the ends of the eight springs away from the support blocks are fixed to one end of the pressure plates.
[0009] It should be noted in the scheme that sealing gaskets are slidably arranged at both ends of the outer wall of the connecting tube, one end of each of the two sealing gaskets is glued to the other side of the ring plate, a fixing plate is fixed to the outer wall of each of the two sealing gaskets, and one side of each of the four fixing plates is glued to the other side of the ring plate.
[0010] It is further worth explaining that two connecting blocks are fixed to the outer walls of the two sleeves, a orifice plate is fixed to the outer walls of the four pressure plates, a connecting groove is opened on one side of the four connecting blocks, a connecting column is provided on the inner walls of the four connecting grooves, and the outer walls of the four connecting columns slide with the inner wall of the orifice plate.
[0011] It should be further explained that a round block is fixed to one end of the eight uprights away from the supporting block, a groove is opened on the inner wall of the four pressing plates, and a rubber plate is provided on the inner wall of the four grooves.
[0012] As a preferred embodiment, a limiting block is fixed on one side of the four fixing plates, and a limiting groove is provided on the other side of the four ring plates, and the inner walls of the four limiting grooves are matched with the outer wall of the limiting block.
[0013] As a preferred implementation, one side of the four orifice plates is glued to a limit plate, and one side of the four limit plates is fixed to one side of a connecting column.
[0014] Compared with the prior art, the utility model provides a water conservancy pump station construction pipeline connection assembly, which has at least the following beneficial effects:
[0015] (1) Through the mutual installation and coordination of the support block, the vertical rod, the pressure plate and the spring, the pressure plate is driven by the restoring contraction force of the spring to be tightly connected to the outer wall of the external water conservancy pump station construction pipeline, thereby preventing the two external water conservancy pump station construction pipelines from shaking due to external force interference at the connection point of the pipeline connection assembly, thereby improving the stability of the device for connecting the two external water conservancy pump station construction pipelines to each other.
[0016] (2) Through the mutual installation and coordination of the orifice plate, the connecting column and the limit plate, the connecting column is inserted into the interior of the connecting groove through the orifice plate, so that the limit plate is glued to one side of the orifice plate, further improving the stability of the connection between the pressure plate and the sleeve column, thereby effectively improving the device to better connect and install the two external water conservancy pump station construction pipelines stably, thereby improving the practicability of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0018] Figure 2 This is a schematic diagram of the exploded structure of the connection pipe and the ring plate separated from each other in the utility model;
[0019] Figure 3 It is a schematic diagram of the exploded structure of the installation mechanism of the utility model;
[0020] Figure 4 This is a schematic diagram of the exploded structure of the connection block and the connection column separated from each other in the utility model.
[0021] In the figure: 1. connecting pipe; 2. ring plate; 3. sleeve column; 4. installation mechanism; 41. support block; 42. vertical pole; 43. pressure plate; 44. round hole; 45. spring; 46. round block; 47. groove; 48. rubber plate; 5. sealing gasket; 6. fixing plate; 7. connecting block; 8. orifice plate; 9. connecting groove; 10. connecting column; 11. limit block; 12. limit groove; 13. limit plate. DETAILED DESCRIPTION
[0022] The utility model is further described below in conjunction with embodiments.
[0023] See also Figure 1-4 The utility model provides a water conservancy pump station construction pipeline connection assembly, comprising:
[0024] A connecting pipe 1, both ends of the outer wall of the connecting pipe 1 are fixed with ring plates 2, and one side of the two ring plates 2 is fixed with a sleeve column 3;
[0025] The installation mechanism 4 includes four support blocks 41, one side of the four support blocks 41 is fixed to one end of the sleeve column 3, both ends of the four support blocks 41 are fixed with vertical poles 42, one end of the two sleeve columns 3 is provided with two pressure plates 43, one end of the four pressure plates 43 is provided with two circular holes 44, the inner walls of the eight circular holes 44 are sleeved with the outer wall of the vertical pole 42, both ends of the four support blocks 41 are fixed with springs 45, the inner walls of the eight springs 45 are sleeved with the outer wall of the vertical pole 42, and the ends of the eight springs 45 away from the support blocks 41 are fixed to one end of the pressure plate 43, so as to facilitate the limiting installation of the water conservancy pump station construction pipeline inserted into the inner wall of the sleeve column 3 by the reinforcement device.
[0026] Further Figure 1 and Figure 2 As shown, it is worth explaining in detail that sealing gaskets 5 are slidably arranged at both ends of the outer wall of the connecting pipe 1, one end of the two sealing gaskets 5 is glue-connected to the other side of the ring plate 2, and the outer walls of the two sealing gaskets 5 are fixed with fixing plates 6, one side of the four fixing plates 6 is glue-connected to the other side of the ring plate 2, one side of the four fixing plates 6 is fixed with limiting blocks 11, and the other side of the four ring plates 2 is provided with limiting grooves 12, and the inner walls of the four limiting grooves 12 are matched with the outer walls of the limiting blocks 11, so as to further improve the stability of the connection between the ring plate 2 and the connecting pipe 1 of the device, which is beneficial to the normal use of the device.
[0027] Further Figure 4As shown, it is worth specifically explaining that two connecting blocks 7 are fixed to the outer walls of the two sleeves 3, and a orifice plate 8 is fixed to the outer walls of the four pressure plates 43. A connecting groove 9 is opened on one side of the four connecting blocks 7, and a connecting column 10 is provided on the inner wall of the four connecting grooves 9. The outer walls of the four connecting columns 10 slide with the inner wall of the orifice plate 8, and one side of the four orifice plates 8 is glue-connected with a limiting plate 13, and one side of the four limiting plates 13 is fixed to one side of the connecting column 10, so as to further improve the stability of the connection between the pressure plate 43 and the sleeve 3, thereby effectively improving the device to better connect and install the two external water conservancy pump station construction pipelines.
[0028] This scheme has the following working process: in the process of using the pipeline connection assembly for the construction of the water conservancy pump station, the inner walls of the two ring plates 2 are respectively fixed to the outer wall of the connecting pipe 1, and the inner walls of the two sealing pads 5 are controlled to slide with the outer wall of the connecting pipe 1, until one end of the sealing pad 5 is glued to the other side of the ring plate 2, and at the same time, the limit block 11 fixed on one side of the fixing plate 6 is inserted into the limit groove 12 opened on the other side of the ring plate 2, so that the sealing pad 5 is tightly connected with the ring plate 2, and the inner wall of the circular hole 44 opened at one end of the pressing plate 43 is used to slide with the outer wall of the vertical rod 42, so that the outer wall of the vertical rod 42 is The spring 45 sleeved on the wall stretches and moves until one end of the external water conservancy pump station construction pipeline slides against the inner wall of the sleeve column 3 respectively, so that one end of the pipeline is fitted and installed with one end of the connecting pipe 1, and the pressure plate 43 is loosened. The restoring contraction force of the spring 45 pulls the pressure plate 43 to reset and move until one end of the pressure plate 43 is glued to the outer wall of the external water conservancy pump station construction pipeline, and the outer wall of the connecting column 10 and the inner wall of the orifice plate 8 are penetrated and sleeved until the connecting column 10 is inserted into the connecting groove 9 opened on one side of the connecting block 7, and then the two external water conservancy pump station construction pipelines are connected and installed through the device.
[0029] According to the above working process, it can be known that: through the mutual installation and cooperation of the support block 41, the vertical rod 42, the pressure plate 43 and the spring 45, the pressure plate 43 is driven by the resetting contraction force of the spring 45 to be tightly connected with the outer wall of the external water conservancy pump station construction pipeline, so as to avoid the two external water conservancy pump station construction pipelines being disturbed by external forces at the connection point of the pipeline connection assembly, thereby improving the stability of the device for connecting the two external water conservancy pump station construction pipelines to each other;
[0030] By means of the mutual installation and coordination of the orifice plate 8, the connecting groove 9, the connecting column 10 and the limiting plate 13, the connecting column 10 is inserted through the orifice plate 8 into the interior of the connecting groove 9, so that the limiting plate 13 is glued to one side of the orifice plate 8, thereby further improving the stability of the connection between the pressure plate 43 and the sleeve column 3, thereby effectively improving the device's better stable connection and installation between the two external water conservancy pump station construction pipelines, thereby improving the practicability of the device.
[0031] Further Figure 3As shown, it is worth explaining in detail that a round block 46 is fixed on one end of the eight vertical poles 42 away from the support block 41, grooves 47 are opened on the inner walls of the four pressure plates 43, and rubber plates 48 are provided on the inner walls of the four grooves 47, so as to strengthen the stability of the limit installation between the pressure plate 43 and the outer wall of the external water conservancy pump station construction pipeline and improve the use effect of the device.
[0032] In summary: through the mutual installation and cooperation of the support block 41, the vertical rod 42, the pressure plate 43 and the spring 45, the pressure plate 43 is driven by the resetting contraction force of the spring 45 to be tightly connected with the outer wall of the external water conservancy pump station construction pipeline, so as to avoid the two external water conservancy pump station construction pipelines being disturbed by external forces at the connection point of the pipeline connection assembly, thereby improving the stability of the device for connecting the two external water conservancy pump station construction pipelines to each other;
[0033] By means of the mutual installation and coordination of the orifice plate 8, the connecting groove 9, the connecting column 10 and the limiting plate 13, the connecting column 10 is inserted through the orifice plate 8 into the interior of the connecting groove 9, so that the limiting plate 13 is glued to one side of the orifice plate 8, thereby further improving the stability of the connection between the pressure plate 43 and the sleeve column 3, thereby effectively improving the device's better stable connection and installation between the two external water conservancy pump station construction pipelines, thereby improving the practicability of the device.
Claims
1. A pipe connection assembly for a water conservancy pump station construction, characterized in that: include: A connecting pipe (1), wherein both ends of the outer wall of the connecting pipe (1) are fixed with ring plates (2), and one side of the two ring plates (2) is fixed with a sleeve column (3); The mounting mechanism (4) comprises four support blocks (41), one side of each of the four support blocks (41) is fixed to one end of the sleeve column (3), both ends of each of the four support blocks (41) are fixed with a vertical rod (42), one end of each of the two sleeve columns (3) is provided with two pressing plates (43), one end of each of the four pressing plates (43) is provided with two circular holes (44), the inner walls of the eight circular holes (44) are sleeved with the outer wall of the vertical rod (42), both ends of the four support blocks (41) are fixed with springs (45), the inner walls of the eight springs (45) are sleeved with the outer wall of the vertical rod (42), and the ends of the eight springs (45) away from the support blocks (41) are fixed to one end of the pressing plate (43).
2. A water conservancy pump station construction pipeline connection assembly according to claim 1, characterized in that: Sealing pads (5) are slidably mounted at both ends of the outer wall of the connecting pipe (1), one end of each of the two sealing pads (5) is glue-connected to the other side of the ring plate (2), and a fixing plate (6) is fixed to the outer wall of each of the two sealing pads (5), one side of each of the four fixing plates (6) is glue-connected to the other side of the ring plate (2).
3. A water conservancy pump station construction pipeline connection assembly according to claim 1, characterized in that: Two connecting blocks (7) are fixed to the outer walls of the two sleeve columns (3), a perforated plate (8) is fixed to the outer walls of the four pressure plates (43), a connecting groove (9) is opened on one side of the four connecting blocks (7), a connecting column (10) is provided on the inner walls of the four connecting grooves (9), and the outer walls of the four connecting columns (10) slide with the inner wall of the perforated plate (8).
4. A water conservancy pump station construction pipeline connection assembly according to claim 1, characterized in that: A round block (46) is fixed to one end of the eight vertical rods (42) away from the support block (41), a groove (47) is formed on the inner wall of the four pressure plates (43), and a rubber plate (48) is formed on the inner wall of the four grooves (47).
5. A water conservancy pump station construction pipeline connection assembly according to claim 2, characterized in that: A limiting block (11) is fixed on one side of the four fixing plates (6), and a limiting groove (12) is provided on the other side of the four ring plates (2), and the inner walls of the four limiting grooves (12) are matched with the outer wall of the limiting block (11).
6. A water conservancy pump station construction pipeline connection assembly according to claim 3, characterized in that: One side of the four orifice plates (8) is glue-connected to a limiting plate (13), and one side of the four limiting plates (13) is fixed to one side of a connecting column (10).