Alternate maintenance equipment for making bricks from waste residues

By designing alternate maintenance equipment for waste slag bricks and using alternating lifting mechanisms to achieve efficient maintenance of bricks, the problems of time-consuming and labor-intensive maintenance and insufficient maintenance of bricks in traditional methods are solved, and efficient and time-saving maintenance effects are achieved.

CN222807342UActive Publication Date: 2025-04-29HUANGSHI WANGXIN ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421050313.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-15
Publication Date
2025-04-29
Estimated Expiration
2034-05-15

AI Technical Summary

Technical Problem

During the process of making bricks made by solid waste materials, bricks need to be repeatedly watered and maintained during the air drying process. The traditional method is time-consuming and labor-intensive. Moreover, the internal brick blanks are difficult to water thoroughly when the bricks are stacked together, resulting in insufficient maintenance and prone to large-scale cracking.

Method used

An alternate maintenance equipment for waste slag bricks is designed, including a side-by-side maintenance pit and an alternating lifting mechanism. The brick blank hanging basket is driven by an alternating lifting and maintenance of brick blanks.

Benefits of technology

It realizes efficient maintenance of a large number of bricks at one time, solves the problems of time-consuming and labor-intensive and inadequate maintenance of traditional methods, improves maintenance efficiency and saves time and effort.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222807342U_ABST
    Figure CN222807342U_ABST
Patent Text Reader

Abstract

The utility model relates to a waste residue brick making alternate maintenance device which comprises a first maintenance pit and a second maintenance pit which are arranged side by side, and maintenance water is injected into the first maintenance pit and the second maintenance pit. The left side and the right side of the first curing pit and the left side and the right side of the second curing pit are provided with stand column supports, the tops of the stand column supports are jointly provided with a bearing cross beam, a left-right alternating lifting mechanism is arranged in the middle of the bearing cross beam, and a first green brick hanging basket and a second green brick hanging basket are hung at the connecting ends of the left side and the right side of the left-right alternating lifting mechanism respectively. Wherein the first green brick hanging basket corresponds to the first curing pit, and the second green brick hanging basket corresponds to the second curing pit; by designing a new mode of alternately lifting and alternately placing different stacked green bricks into the curing water pit in sequence for curing, the problems that time and labor are wasted and the efficiency is low when the green bricks are cured only through manual watering are well solved, a large number of green bricks can be immersed into water at the same time for curing at a time, and the efficiency is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building material maintenance equipment, in particular to a waste slag brick making alternating maintenance equipment. Background Art

[0002] At present, in the process of making environmentally friendly building brick materials using solid waste materials, after the bricks are made, they will be stacked together for air-drying. During the air-drying process, they need to be cured at intervals every day, that is, they need to be repeatedly watered. The traditional method is to directly use water pipes to maintain the formed bricks, repeatedly. This method is time-consuming and labor-intensive, and one-time watering cannot be thorough, so it needs to be done many times. Otherwise, if the bricks are not properly cured, large-scale cracks will easily occur. Moreover, when a large number of brick bodies and brick blanks are stacked together, the bricks placed inside are often not watered thoroughly, resulting in inadequate maintenance. Summary of the invention

[0003] The utility model aims to provide a waste slag brick-making alternating curing device for the above situation, which can provide a large number of stacked bricks for curing operations at one time, and the alternating curing efficiency is high.

[0004] The specific scheme of the utility model is: a waste slag brick-making alternating curing equipment, comprising a first curing pit and a second curing pit arranged side by side, the first curing pit and the second curing pit are both filled with curing water; the left and right sides of the first curing pit and the second curing pit are both provided with column brackets, the tops of the column brackets are jointly equipped with a load-bearing beam, a left-right alternating lifting mechanism is arranged in the middle part of the load-bearing beam, the left and right alternating lifting mechanism The left and right connecting ends are respectively hoisted with a first brick blank hanging basket and a second brick blank hanging basket, wherein the first brick blank hanging basket corresponds to the first curing pit, and the second brick blank hanging basket corresponds to the second curing pit, and the first brick blank hanging basket and the second brick blank hanging basket alternately lift bricks and sink them into the corresponding curing pits.

[0005] Furthermore, the left and right alternating lifting mechanism in the utility model includes a driving motor, a power sprocket, a first redirecting sprocket, a second redirecting sprocket, a first lifting sprocket, a second lifting sprocket and an alternating lifting chain, the alternating lifting chain is wound around the power sprocket, one end of the alternating lifting chain is sequentially wound around the first redirecting sprocket and the first lifting sprocket and hoisted and fixed on the load-bearing beam, the other end of the alternating lifting chain is sequentially wound around the second redirecting sprocket and the second lifting sprocket and hoisted and fixed on the load-bearing beam; the first lifting sprocket and the second lifting sprocket are respectively mounted on the corresponding first brick blank hanging basket and the second brick blank hanging basket through sprocket mounting seats; the driving motor is placed on the load-bearing beam and is transmission-connected to the power sprocket.

[0006] Furthermore, in the present invention, the first redirecting sprocket and the second redirecting sprocket are symmetrically arranged on the left and right sides of the power sprocket.

[0007] Furthermore, an installation window is provided on the left and right sides of the load-bearing crossbeam in the utility model, and the first redirecting sprocket and the second redirecting sprocket are installed in the two installation windows respectively.

[0008] Furthermore, the first brick blank hanging basket and the second brick blank hanging basket in the utility model have the same structure and both have a lifting beam, and a vertical hanging rod is provided downward at both ends of the bottom surface of the lifting beam, and the lower ends of the two vertical hanging rods are commonly connected to a bearing platform plate for carrying stacked brick blanks.

[0009] Furthermore, the load-bearing platform plate in the utility model is a grid structure formed by assembling and welding transverse steel strips and longitudinal steel strips.

[0010] Furthermore, a limiting slide rail is arranged from top to bottom on the inner wall of the column bracket in the utility model, and the first brick blank hanging basket and the second brick blank hanging basket are respectively provided with a limiting slide groove along the limiting slide rail on the corresponding side, and the limiting slide groove and the limiting slide rail are used in combination.

[0011] The utility model designs a new method of alternately lifting and lowering, and alternately placing different stacked bricks into a curing water pit for curing in sequence, thereby effectively solving the problem of time-consuming, labor-intensive and inefficient curing of bricks by manual watering alone. A large number of bricks can be immersed in water for curing at one time, which greatly improves efficiency, saves time, labor and is highly efficient, and has good practical use and promotion value. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a schematic diagram of the main viewing direction structure of the utility model;

[0013] Figure 2 It is a schematic diagram of the structure of the utility model in a top view;

[0014] Figure 3 yes Figure 1 Schematic diagram of the structure in the AA direction;

[0015] Figure 4 yes Figure 3 Enlarged schematic diagram of the structure at K in the middle.

[0016] In the figure: 1-column bracket, 2-first lifting sprocket, 3-first redirecting sprocket, 4-power sprocket, 5-driving motor, 6-alternating lifting chain, 7-second redirecting sprocket, 8-second lifting sprocket, 9-lifting beam, 10-load-bearing beam, 11-limiting slide rail, 12-vertical hanging rod, 13-bearing platform plate, 14-first maintenance pit, 15-installation window, 16-second maintenance pit, 17-limiting slide groove. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings of the utility model to clearly and completely describe the technical solution of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work belong to the protection scope of the utility model.

[0018] In the description of the present utility model, it should be noted that the terms "upper", "lower", "inside", "outside" and the like indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, or are the directions or positional relationships in which the utility model product is usually placed when in use. They are only for the convenience of describing the present utility model or simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed or operated in a specific direction. Therefore, they cannot be understood as limitations on the present utility model.

[0019] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0020] See also Figures 1 to 4 The utility model is an alternating curing device for making waste slag bricks, comprising a first curing pit 14 and a second curing pit 16 arranged side by side, both of which are filled with curing water; column brackets 1 are arranged on the left and right sides of the first curing pit and the second curing pit, and a load-bearing beam 10 is commonly installed on the top of the column brackets, and a left-right alternating lifting mechanism is arranged in the middle part of the load-bearing beam, and the left and right connecting ends of the left-right alternating lifting mechanism are respectively hoisted with a first brick blank hanging basket and a second brick blank hanging basket, wherein the first brick blank hanging basket corresponds to the first curing pit, and the second brick blank hanging basket corresponds to the second curing pit, and the first brick blank hanging basket and the second brick blank hanging basket alternately hoist brick blanks and sink them into the corresponding curing pits.

[0021] Furthermore, the left and right alternating lifting mechanism in this embodiment includes a driving motor 5, a power sprocket 4, a first redirecting sprocket 3, a second redirecting sprocket 7, a first lifting sprocket 2, a second lifting sprocket 8 and an alternating lifting chain 6, the alternating lifting chain is wound around the power sprocket, one end of the alternating lifting chain is sequentially wound around the first redirecting sprocket and the first lifting sprocket and hoisted and fixed on the load-bearing beam, the other end of the alternating lifting chain is sequentially wound around the second redirecting sprocket and the second lifting sprocket and hoisted and fixed on the load-bearing beam; the first lifting sprocket and the second lifting sprocket are respectively mounted on the corresponding first brick blank hanging basket and the second brick blank hanging basket through sprocket mounting seats; the driving motor is placed on the load-bearing beam and is transmission-connected to the power sprocket.

[0022] Furthermore, in this embodiment, the first redirecting sprocket and the second redirecting sprocket are symmetrically arranged on the left and right sides of the power sprocket.

[0023] Furthermore, in the present embodiment, an installation window 15 is respectively provided on the left and right sides of the load-bearing crossbeam, and the first redirecting sprocket and the second redirecting sprocket are respectively installed in the two installation windows.

[0024] Furthermore, in this embodiment, the first brick blank hanging basket and the second brick blank hanging basket have the same structure and both have a lifting beam 9, and a vertical hanging rod 12 is provided downward at both ends of the bottom surface of the lifting beam, and the lower ends of the two vertical hanging rods are connected together with a bearing platform plate 13 for carrying stacked brick blanks.

[0025] Furthermore, the load-bearing platform plate in this embodiment is a grid structure formed by assembling and welding transverse steel strips and longitudinal steel strips.

[0026] Furthermore, a limiting slide rail 11 is provided from top to bottom on the inner wall of the column bracket in this embodiment, and the first brick blank hanging basket and the second brick blank hanging basket are each provided with a limiting slide groove 17 along the limiting slide rail on the corresponding side, and the limiting slide groove and the limiting slide rail are used in combination.

[0027] When the utility model is in use, a large number of brick blanks need to be stacked together in the shape of a rectangular parallelepiped, and a forklift carrying plate is placed underneath to facilitate forklift transportation. Each time, a stacked cube is used as a maintenance unit. First, maintenance water is injected into the first maintenance pit 14 and the second maintenance pit 16, and the water volume reaches the top surface of the maintenance pit, or slightly lower. Then, the forklift forks the entire stack of brick blanks and transports them to one of the groups of carrying platform plates to put the brick blanks down, and the driving motor is started. The carrying platform plate on which the brick blanks are placed is driven down by the alternating lifting chain until the entire stack of brick blanks is completely sunk into the maintenance water. At this time, the carrying platform plate at the other end just rises up and exposes the water surface. The brick blanks can be immersed in the water for 3-5 minutes. When the cured brick blanks need to be raised from underwater, the forklift places another stack of brick blanks on the empty carrying platform plate and sinks them up and down. In this way, the two carrying platform plates alternately rise and fall, and the brick blanks can be alternately sent into the water to be immersed, and the other stack of cured brick blanks is raised and transported away by the forklift, and the process is performed alternately in sequence, which is fast and efficient.

[0028] The total length of the alternating lifting chain in this embodiment is certain and is designed in advance, so that it can ensure that one side rises and the other side falls, just alternating. At the same time, the first lifting sprocket 2 and the second lifting sprocket 8 are hoisted on both sides of the alternating lifting chain respectively, but they are bypassed from above the first redirecting sprocket 3 and the second redirecting sprocket 7 to achieve the purpose of redirecting lifting.

[0029] The utility model designs a new method of alternately lifting and lowering, and alternately placing different stacked bricks into a curing water pit for curing in sequence, thereby effectively solving the problem of time-consuming, labor-intensive and inefficient curing of bricks by manual watering alone. A large number of bricks can be immersed in water for curing at one time, which greatly improves efficiency, saves time, labor and is highly efficient, and has good practical use and promotion value.

Claims

1. A waste slag brick-making alternating curing device, characterized in that: It comprises a first curing pit and a second curing pit which are arranged side by side, and curing water is filled in the first curing pit and the second curing pit; column brackets are arranged on the left and right sides of the first curing pit and the second curing pit, and a load-bearing beam is arranged on the top of the column brackets; a left-right alternating lifting mechanism is arranged in the middle part of the load-bearing beam, and a first brick blank hanging basket and a second brick blank hanging basket are hoisted on the left and right connecting ends of the left-right alternating lifting mechanism respectively, wherein the first brick blank hanging basket corresponds to the first curing pit, and the second brick blank hanging basket corresponds to the second curing pit, and the first brick blank hanging basket and the second brick blank hanging basket alternately hoist brick blanks and sink them into the corresponding curing pits.

2. The waste slag brick-making alternating curing equipment according to claim 1 is characterized by: The left and right alternating lifting mechanism includes a driving motor, a power sprocket, a first redirecting sprocket, a second redirecting sprocket, a first lifting sprocket, a second lifting sprocket and an alternating lifting chain. The alternating lifting chain is wound around the power sprocket, one end of the alternating lifting chain is sequentially wound around the first redirecting sprocket and the first lifting sprocket and is hoisted and fixed on the load-bearing beam, and the other end of the alternating lifting chain is sequentially wound around the second redirecting sprocket and the second lifting sprocket and is hoisted and fixed on the load-bearing beam; the first lifting sprocket and the second lifting sprocket are respectively mounted on the corresponding first brick blank hanging basket and the second brick blank hanging basket through sprocket mounting seats; the driving motor is placed on the load-bearing beam and is drivingly connected to the power sprocket.

3. The waste slag brick-making alternating curing equipment according to claim 2 is characterized in that: The first redirecting sprocket and the second redirecting sprocket are symmetrically arranged on the left and right sides of the power sprocket.

4. The waste slag brick-making alternating curing equipment according to claim 2 is characterized by: An installation window is respectively provided on the left and right sides of the load-bearing crossbeam, and a first redirecting sprocket and a second redirecting sprocket are respectively installed in the two installation windows.

5. The waste slag brick-making alternating curing equipment according to claim 1 is characterized by: The first brick blank hanging basket and the second brick blank hanging basket have the same structure and both have a lifting beam. A vertical hanging rod is provided downward at both ends of the bottom surface of the lifting beam. The lower ends of the two vertical hanging rods are connected together with a bearing platform plate for carrying stacked brick blanks.

6. The waste slag brick-making alternating curing equipment according to claim 5 is characterized by: The load-bearing platform plate is a grid-like structure formed by assembling and welding transverse steel strip plates and longitudinal steel strip plates.

7. The waste slag brick-making alternating curing equipment according to claim 1 is characterized by: A limiting slide rail is arranged on the inner side wall of the column bracket from top to bottom, and the first brick blank hanging basket and the second brick blank hanging basket are respectively provided with a limiting slide groove along the limiting slide rail on the corresponding side, and the limiting slide groove and the limiting slide rail are used in combination.