Device for vertically hoisting reinforcing steel bars
By designing a device for vertical lifting of steel bars, the problem of secondary handling of steel bars in the installation of frame column steel bars in the factory buildings with higher floor heights is solved, and efficient steel bar lifting and installation is achieved, and construction efficiency is improved.
Patent Information
- Application Number
- CN202421103493.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-20
- Publication Date
- 2025-05-23
- Estimated Expiration
- 2034-05-20
AI Technical Summary
During the installation of frame column steel bars in the factory with higher floor heights, the steel bars need to be transported again, resulting in low construction efficiency.
A device for vertical lifting of steel bars is designed, including a bucket, steel bar hoop, connecting assembly and binding assembly. The hanging bucket is fixed by steel bar hoops, the steel bar bundle is tied with the binding component, and finally the connecting component is connected with the lifting hook to achieve vertical lifting of the steel bars.
This device improves the strength of the bucket, can stably accommodate and lift multiple steel bars, avoid secondary handling, and significantly improves the construction efficiency of frame column steel bar installation.
Smart Images

Figure CN222892893U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building structure construction, in particular to a device for vertically lifting steel bars. Background Art
[0002] Rebar is the most commonly used material in the construction of building structures. Normally, rebar is lifted horizontally during transportation and transfer. If it is lifted vertically, due to the heavy deadweight of the rebar, multiple rebars are not tied firmly and are easy to fall off. In special cases, vertical lifting can avoid secondary handling. For example, when installing rebars for frame columns of high-rise factories, the installation is often carried out after the support racks are erected. At this time, if the rebar is lifted horizontally, the operator needs to carry it twice and put it vertically into the frame column. If the rebar is lifted vertically, the secondary handling process can be saved and the installation efficiency can be greatly improved. Therefore, a stable device that can lift multiple rebars vertically is needed. Utility Model Content
[0003] In view of this, the utility model provides a device for vertical lifting of steel bars to solve the problem in the prior art that when installing steel bars for frame columns of factory buildings with high storeys, horizontal lifting of steel bars still requires a second transport, resulting in low construction efficiency.
[0004] The utility model provides a device for vertically lifting steel bars, comprising: a bucket suitable for accommodating a steel bar bundle; a steel bar hoop connected to the outer bottom surface and the outer side surface of the bucket and extending out of the top of the bucket; a connecting component, one end of the connecting component is suitable for being connected to a lifting hook, and the other end of the connecting component is connected to the steel bar hoop; and a tying component suitable for tying to the end of the steel bar bundle away from the bucket.
[0005] Beneficial effect: The bucket is fixed by a steel hoop to improve the strength of the bucket, so that the bucket can accommodate one end of the steel bar bundle, and at the same time, the steel bar bundle is tied with the end away from the accommodating component by the binding assembly, and finally the connecting assembly is used for lifting, so that the steel bar bundle is in a vertical lifting posture under the action of gravity. The overall structure of the device for vertical lifting of steel bars is simple and the safety factor is high, which improves the construction efficiency of the frame column steel bar installation and avoids secondary handling.
[0006] In an optional embodiment, the steel bar hoop includes a first steel bar, a second steel bar and a third steel bar, the first steel bar and the second steel bar are arranged along a vertical interval, the first steel bar and the second steel bar are both connected to the outer side surface of the bucket, the third steel bar simultaneously connects the lower end of the first steel bar and the lower end of the second steel bar to form an accommodating space, the bucket is arranged in the accommodating space, the upper end of the first steel bar and the upper end of the second steel bar both extend out of the top of the bucket and are connected to the connecting assembly.
[0007] In an optional embodiment, two of the first steel bars, the second steel bars and the third steel bars are each provided, the two first steel bars are arranged at intervals, the two second steel bars are arranged at intervals, the two third steel bars are arranged at intervals, one ends of the two third steel bars are respectively connected to the lower ends of the two first steel bars, and the other ends of the two third steel bars are respectively connected to the lower ends of the two second steel bars, the steel bar hoop also includes a first bent steel bar and a second bent steel bar, the first bent steel bar simultaneously connects the upper ends of the two first steel bars, and the second bent steel bar simultaneously connects the upper ends of the two second steel bars.
[0008] In an optional embodiment, the connecting assembly includes a first buckle and a lifting wire rope, the lower end of the first buckle is connected to the steel bar hoop, the upper end of the first buckle is connected to the lower end of the lifting wire rope, and the upper end of the lifting wire rope is suitable for connection to the lifting hook.
[0009] Beneficial effects: The strength of the steel wire rope is very high and can withstand large loads. The surface hardness of the steel wire rope is high and the wear resistance is also good. It is not easy to be damaged after long-term use. Therefore, steel wire rope is used for lifting.
[0010] In an optional embodiment, two first buckles are provided, and the lower ends of the two first buckles are respectively connected to the first bent steel bar and the second bent steel bar.
[0011] In an optional embodiment, the lifting wire rope includes a first wire rope and a second wire rope, two second wire ropes are provided, the lower end of the first wire rope is connected to the upper ends of two second wire ropes at the same time, the upper end of the first wire rope is suitable for connecting to the lifting hook, and the lower ends of the two second steel wire ropes are respectively connected to the upper ends of two first buckles.
[0012] Beneficial effect: by setting two second steel wire ropes corresponding to the two first buckle connections, the bucket is evenly stressed, which prevents the bucket from tipping over during the lifting process and the steel bar bundle from falling and causing danger.
[0013] In an optional embodiment, the binding assembly includes a binding steel wire rope and a second buckle, and the second buckle is simultaneously connected to both ends of the binding steel wire rope so that the binding steel wire rope forms a rope loop to bind the steel bar bundle.
[0014] In an optional embodiment, the binding assembly further comprises a wire rope buckle, and the wire rope buckle simultaneously connects the binding wire rope and the first wire rope.
[0015] Beneficial effect: by setting the wire rope buckle to connect the binding wire rope and the first wire rope, the steel bar bundle is further fixed to avoid the danger of the steel bar bundle falling due to shaking due to environmental factors during the lifting process. The use of the wire rope buckle further improves the safety of the construction.
[0016] In an optional embodiment, the steel bar hoop is welded to the bucket.
[0017] Beneficial effect: by arranging the steel bar hoop and welding the outer bottom surface and the outer side surface of the bucket, the strength of the bucket is enhanced, the supporting performance of the bucket is improved, and the service life of the device for vertical lifting of steel bars is enhanced.
[0018] In an optional implementation, both the first buckle and the second buckle are U-shaped buckles.
[0019] Beneficial effects: The U-shaped buckle has a large buckling holding force. At the same time, the U-shaped buckle has a U-shaped groove, so that the buckle can be manually moved during disassembly, which is convenient for disassembly. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0021] Figure 1 This is a schematic structural diagram of a device for vertically lifting steel bars according to an embodiment of the utility model;
[0022] Figure 2 A schematic diagram of the structure of a steel bar hoop of a device for vertically lifting steel bars according to an embodiment of the utility model;
[0023] Figure 3 The present invention is a schematic diagram of the structure of a device for vertically lifting steel bars and a steel bar bundle according to an embodiment of the present invention.
[0024] Description of reference numerals:
[0025] 1. Bucket; 2. Steel bar hoop; 201. First steel bar; 202. Second steel bar; 203. Third steel bar; 204. First bent steel bar; 205. Second bent steel bar; 3. Connection assembly; 301. First buckle; 302. Lifting wire rope; 3021. First steel wire rope; 3022. Second steel wire rope; 4. Binding assembly; 401. Binding steel wire rope; 402. Second buckle; 403. Wire rope buckle; 5. Steel bar bundle; 6. Lifting hook. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the utility model.
[0027] Combine the following Figures 1 to 3 , describing an embodiment of the utility model.
[0028] According to the embodiments of the present utility model, Figure 1 As shown, a device for vertical lifting of steel bars is provided, comprising: a bucket 1, a steel bar hoop 2, a connection assembly 3 and a tying assembly 4. The bucket 1 is suitable for accommodating a steel bar bundle 5. The steel bar hoop 2 is connected to the outer bottom surface and the outer side surface of the bucket 1 at the same time and extends out of the top of the bucket 1. One end of the connection assembly 3 is suitable for being connected to a lifting hook 6, and the other end of the connection assembly 3 is connected to the steel bar hoop 2. The tying assembly 4 is suitable for tying to the end of the steel bar bundle 5 away from the bucket 1.
[0029] The bucket 1 is fixed by the steel bar hoop 2, thereby improving the strength of the bucket 1, so that the bucket 1 can accommodate one end of the steel bar bundle 5, and at the same time, the steel bar bundle 5 is tied with the end away from the accommodating component by the tying component 4, and finally hoisted by the connecting component 3, so that the steel bar bundle 5 is in a vertical hoisting posture under the action of gravity. The overall structure of the device for vertical lifting of steel bars is simple and the safety factor is high, which improves the construction efficiency of the frame column steel bar installation and avoids secondary transportation.
[0030] In one embodiment, Figure 1 As shown, the steel bar hoop 2 includes a first steel bar 201, a second steel bar 202 and a third steel bar 203. The first steel bar 201 and the second steel bar 202 are arranged along the vertical interval. The first steel bar 201 and the second steel bar 202 are both connected to the outer side of the bucket 1. The third steel bar 203 simultaneously connects the lower end of the first steel bar 201 and the lower end of the second steel bar 202 to form an accommodating space. The bucket 1 is arranged in the accommodating space. The upper end of the first steel bar 201 and the upper end of the second steel bar 202 both extend out of the top of the bucket 1 and are connected to the connecting component 3.
[0031] Specifically, the spacing between the first steel bar 201 and the second steel bar 202 is the same as the maximum outer diameter length of the bucket 1, so that the first steel bar 201 and the second steel bar 202 can more stably clamp the bucket 1, and the force of the connection between the connecting component 3 and the bucket 1 is balanced to prevent the bucket 1 from overturning.
[0032] In one embodiment, Figure 2 As shown, two first steel bars 201, two second steel bars 202 and two third steel bars 203 are provided, the two first steel bars 201 are arranged at intervals, the two second steel bars 202 are arranged at intervals, the two third steel bars 203 are arranged at intervals, one end of the two third steel bars 203 is respectively connected to the lower ends of the two first steel bars 201, and the other ends of the two third steel bars 203 are respectively connected to the lower ends of the two second steel bars 202, the steel bar hoop 2 also includes a first bent steel bar 204 and a second bent steel bar 205, the first bent steel bar 204 is connected to the upper ends of the two first steel bars 201 at the same time, and the second bent steel bar 205 is connected to the upper ends of the two second steel bars 202 at the same time.
[0033] Of course, in other alternative implementations, the first steel bar 201, the second steel bar 202 and the third steel bar 203 can also be provided as one steel bar, as long as the strength requirements are met.
[0034] It should be noted that the first steel bar 201, the second steel bar 202 and the third steel bar 203 are all steel bars that can be found at the construction site, with low cost and high strength. Therefore, the first steel bar 201, the second steel bar 202 and the third steel bar 203 can be set as a plurality of steel bars. By setting a plurality of steel bars, the connection performance between the steel bar hoop 2 and the bucket 1 can be greatly improved without increasing the cost of producing the device for vertical lifting of steel bars.
[0035] It is worth noting that the first steel bar 201, the second steel bar 202, the third steel bar 203, the first bent steel bar 204 and the second bent steel bar 205 can all be steel bar segments, and the steel bar hoop 2 can be formed by welding the steel bar segments end to end. Alternatively, the steel bar hoop 2 can be formed by bending a long steel bar. Figure 2 The steel bar hoop 2 of the shape shown enables different parts of the steel bar to form the first steel bar 201, the second steel bar 202, the third steel bar 203, the first bent steel bar 204 and the second bent steel bar 205 respectively. After the steel bar is bent into shape, the ends are welded and fixed.
[0036] In one embodiment, Figure 1 As shown, the connection assembly 3 includes a first buckle 301 and a hoisting wire rope 302. The lower end of the first buckle 301 is connected to the steel hoop 2, and the upper end of the first buckle 301 is connected to the lower end of the hoisting wire rope 302. The upper end of the hoisting wire rope 302 is suitable for connecting to the lifting hook 6. The strength of the wire rope is very high and can withstand a large load. The surface hardness of the wire rope is high, the wear resistance is also good, and it is not easy to be damaged after long-term use. Therefore, the wire rope is used for hoisting.
[0037] In one embodiment, Figure 1As shown, two first buckles 301 are provided, and the lower ends of the two first buckles 301 are connected to the first bent steel bar 204 and the second bent steel bar 205 respectively.
[0038] Preferably, the first clips 301 can be set to several numbers, the first steel bar 201 can be set to several first clips 301 correspondingly, and the second steel bar 202 can be set to several first clips 301 correspondingly, to prevent any one of the first clips 301 from being damaged, causing the bucket 1 to lose balance and overturn.
[0039] In one embodiment, Figure 1 As shown, the hoisting wire rope 302 includes a first wire rope 3021 and a second wire rope 3022. Two second wire ropes 3022 are provided. The lower end of the first wire rope 3021 is connected to the upper ends of the two second wire ropes 3022 at the same time. The upper end of the first wire rope 3021 is suitable for connecting to the lifting hook 6, and the lower ends of the two second wire ropes 3022 are respectively connected to the upper ends of the two first buckles 301. By providing two second wire ropes 3022 corresponding to the two first buckles 301, the bucket 1 is evenly stressed, preventing the bucket 1 from tipping over during the hoisting process, causing the steel bar bundle 5 to fall easily and cause danger.
[0040] Preferably, a plurality of second steel wire ropes 3022 may be provided, and the plurality of second steel wire ropes 3022 are provided corresponding to the first buckle 301 to prevent any second steel wire rope 3022 from breaking and causing the bucket 1 to lose balance and overturn.
[0041] In one embodiment, Figure 1 As shown, the binding assembly 4 includes a binding steel wire rope 401 and a second buckle 402 , and the second buckle 402 is connected to both ends of the binding steel wire rope 401 at the same time so that the binding steel wire rope 401 forms a rope loop to bind the steel bar bundle 5 .
[0042] Specifically, a plurality of tying steel wire ropes 401 may be provided, and the plurality of tying steel wire ropes 401 are arranged at intervals along the extension direction of the steel bar bundle 5 to enhance the fixation of the steel bar bundle 5 and prevent the steel bars from falling and causing danger.
[0043] In one embodiment, Figure 1 As shown, the tying assembly 4 also includes a wire rope buckle 403, which simultaneously connects the tying wire rope 401 and the first wire rope 3021. The tying wire rope 401 and the first wire rope 3021 are connected by the wire rope buckle 403, so as to further fix the steel bar bundle 5, thereby preventing the steel bar bundle 5 from shaking and falling due to environmental factors during the hoisting process, and thus further improving the safety of the construction by using the wire rope buckle 403.
[0044] In one embodiment, the steel bar hoop 2 is welded to the bucket 1. By arranging the steel bar hoop 2 to be welded to the outer bottom surface and the outer side surface of the bucket 1, the strength of the bucket 1 is enhanced, the supporting performance of the bucket 1 is improved, and the service life of the device for vertical lifting of steel bars is enhanced.
[0045] In one embodiment, the first buckle 301 and the second buckle 402 are both U-shaped buckles. The U-shaped buckle has a large buckle retention force, and at the same time, the U-shaped buckle has a U-shaped groove, so that the buckle can be manually moved during disassembly, which is convenient for disassembly.
[0046] In an alternative embodiment, the U-shaped buckle may be replaced by other components that play a connecting role.
[0047] When using the device for vertical lifting of steel bars of this embodiment, Figure 3 As shown, first, put the steel bar bundle 5 into the bucket 1; then, use the second buckle 402 to tie the tying wire rope 401 to the end of the steel bar bundle 5 away from the bucket 1; then, fix the tying wire rope 401 and the first steel wire rope 3021 by the wire rope buckle 403; finally, use the lifting hook 6 to hook the second end of the first steel wire rope 3021, and lift the steel bar bundle 5 vertically to the construction site.
[0048] Although the embodiments of the present invention are described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A device for vertically lifting steel bars, characterized in that: include: A bucket (1) adapted to receive a steel bar tendon (5); A steel bar hoop (2) is connected to the outer bottom surface and the outer side surface of the bucket (1) and extends out of the top end of the bucket (1); A connecting assembly (3), one end of the connecting assembly (3) is suitable for connecting to a lifting hook (6), and the other end of the connecting assembly (3) is connected to the steel bar hoop (2); A tying assembly (4) adapted to be tied to an end of the steel bar bundle (5) away from the bucket (1); The steel bar hoop (2) comprises a first steel bar (201), a second steel bar (202) and a third steel bar (203); the first steel bar (201) and the second steel bar (202) are arranged at intervals along a vertical direction; the first steel bar (201) and the second steel bar (202) are both connected to the outer side surface of the bucket (1); the third steel bar (203) simultaneously connects the lower end of the first steel bar (201) and the lower end of the second steel bar (202) to form a receiving space; the bucket (1) is arranged in the receiving space; the upper end of the first steel bar (201) and the upper end of the second steel bar (202) both extend out of the top of the bucket (1) and are connected to the connecting component (3).
2. The device for vertically lifting steel bars according to claim 1, characterized in that: Two of the first steel bars (201), the second steel bars (202) and the third steel bars (203) are provided, the two first steel bars (201) are arranged at intervals, the two second steel bars (202) are arranged at intervals, and the two third steel bars (203) are arranged at intervals, one end of the two third steel bars (203) is respectively connected to the lower ends of the two first steel bars (201), and the other end of the two third steel bars (203) is respectively connected to the lower ends of the two second steel bars (202), and the steel bar hoop (2) further comprises a first bent steel bar (204) and a second bent steel bar (205), the first bent steel bar (204) is connected to the upper ends of the two first steel bars (201) at the same time, and the second bent steel bar (205) is connected to the upper ends of the two second steel bars (202) at the same time.
3. The device for vertically lifting steel bars according to claim 2, characterized in that: The connecting assembly (3) comprises a first buckle (301) and a lifting wire rope (302), wherein the lower end of the first buckle (301) is connected to the steel bar hoop (2), the upper end of the first buckle (301) is connected to the lower end of the lifting wire rope (302), and the upper end of the lifting wire rope (302) is suitable for being connected to the lifting hook (6).
4. The device for vertically lifting steel bars according to claim 3, characterized in that: Two first buckles (301) are provided, and the lower ends of the two first buckles (301) are respectively connected to the first bent steel bar (204) and the second bent steel bar (205).
5. The device for vertically lifting steel bars according to claim 3 or 4, characterized in that: The lifting wire rope (302) includes a first wire rope (3021) and a second wire rope (3022), two second wire ropes (3022) are provided, the lower end of the first wire rope (3021) is connected to the upper ends of the two second wire ropes (3022) at the same time, the upper end of the first wire rope (3021) is suitable for connecting to the lifting hook (6), and the lower ends of the two second steel wire ropes (3022) are respectively connected to the upper ends of the two first buckles (301).
6. The device for vertically lifting steel bars according to claim 5, characterized in that: The binding assembly (4) comprises a binding steel wire rope (401) and a second buckle (402), wherein the second buckle (402) is simultaneously connected to both ends of the binding steel wire rope (401) so that the binding steel wire rope (401) forms a rope loop to bind the steel bar bundle (5).
7. The device for vertically lifting steel bars according to claim 6, characterized in that: The tying assembly (4) further comprises a wire rope buckle (403), wherein the wire rope buckle (403) simultaneously connects the tying wire rope (401) and the first wire rope (3021).
8. The device for vertically lifting steel bars according to any one of claims 1 to 2, characterized in that: The steel bar hoop (2) is connected to the bucket (1) by welding.
9. The device for vertically lifting steel bars according to claim 6, characterized in that: The first buckle (301) and the second buckle (402) are both U-shaped buckles.