Inspection hole grouting device
By designing multi-section pipe assemblies and grouting pipe assemblies for dam inspection holes, the problem of difficult to save chemical slurry and ensure grouting quality in the prior art is solved, and the smoothness of grouting pipes and efficient grouting effect are achieved.
Patent Information
- Application Number
- CN202421415176.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-20
- Publication Date
- 2025-05-23
- Estimated Expiration
- 2034-06-20
AI Technical Summary
In the prior art, it is difficult to effectively save chemical slurry during the grouting process of dam inspection holes, while ensuring the smoothness of the grouting pipeline and grouting quality.
An inspection hole grouting device is designed, including a multi-section tube assembly and a grouting tube assembly. The multi-section pipe assembly is clamped and fixed by the upper plug and stable part to ensure the smoothness of the grouting pipe. The grouting pipe assembly is filled with alternative slurry through the gap between the outer wall of the long-pass pipe and the inner wall of the multi-section pipe assembly, saving costs.
It achieves the smoothness and grouting quality of the grouting pipeline while saving chemical slurry, and improves assembly efficiency.
Smart Images

Figure CN222893638U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of dam inspection holes, in particular to an inspection hole grouting device. Background Art
[0002] The dam concrete inspection hole is a hole drilled during the construction or maintenance of the dam to check the quality of concrete or the integrity of other structural materials inside the dam. The inspection hole can be used for sampling, detecting cracks or other potential structural problems. After the inspection, grouting backfilling is required. Due to the low viscosity and good fluidity of chemical slurry, chemical slurry can effectively prevent leakage and improve the bearing capacity of the structure. However, the cost of chemical slurry is high. In the prior art, some fillers are often used to fill the borehole to save the use of chemical slurry, such as backfilling the borehole core sample (concrete or rock) and backfilling steel bars (also used as anchor bars), but there are certain shortcomings. When backfilling the borehole core sample, due to the short length of the core sample (usually within 50cm), the friction with the hole wall when filling the borehole is easy to get stuck in the middle of the borehole, making it difficult to fill the borehole; at the same time, it may squeeze or damage the pre-buried plastic grouting pipe and exhaust pipe, affecting the chemical grouting effect. When backfilling the steel bars, using leftover steel bars will have similar shortcomings as backfilling the drilled core samples. Using finished steel bars will result in material waste, and the connection and installation of the steel bars will be time-consuming and labor-intensive. Moreover, the steel bars that also serve as anchor bars may not be completely wrapped by the slurry, thus affecting the anchoring force, failing to achieve the expected effect, and making it more difficult to scan the hole again.
[0003] Therefore, a device is needed that can save chemical slurry while ensuring the backfill effect, ensuring the smoothness of the grouting pipeline, and ensuring the grouting quality. Utility Model Content
[0004] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and utility model name of this application to avoid blurring the purpose of this section, specification abstract and utility model name, and such simplifications or omissions cannot be used to limit the scope of the utility model.
[0005] In view of the need for a device in the above-mentioned prior art that can ensure the smoothness of the grouting pipeline while saving costs, the present utility model is proposed.
[0006] The utility model aims to provide a grouting device for an inspection hole.
[0007] In order to solve the above technical problems, the utility model provides the following technical solutions: including a multi-section pipe assembly, including an upper plug-in part and a stabilizing part arranged at the bottom of the upper plug-in part; and a grouting pipe assembly, including a grouting pipe body arranged at the bottom of the multi-section pipe assembly and a long through pipe arranged inside the grouting pipe body.
[0008] As a preferred solution of the inspection hole grouting device of the utility model, the upper plug-in portion comprises a multi-section tube body, the top of the multi-section tube body is provided with a plug-in slope, and the outer wall of the plug-in slope is provided with a clamping arc groove.
[0009] As a preferred solution of the inspection hole grouting device of the utility model, wherein: the stabilizing part includes an intermediate rod arranged inside the multi-section tube body, and a fixed clamping arc plate is arranged on the side of the intermediate rod.
[0010] As a preferred solution of the inspection hole grouting device of the utility model, wherein: a movable clamping plate is arranged on the side of the fixed clamping arc plate, a clamping plate is arranged on the side of the movable clamping plate, and the clamping plate is made of elastic material.
[0011] As a preferred solution of the inspection hole grouting device of the utility model, wherein: a sliding rod is arranged on the side of the movable clamping plate, a sliding frame is arranged on the outer wall of the sliding rod, and the side of the sliding frame is connected to the multi-section pipe body.
[0012] As a preferred solution of the inspection hole grouting device of the utility model, wherein: the number of the multi-section pipe bodies is multiple.
[0013] As a preferred solution of the inspection hole grouting device of the utility model, wherein: the inner wall of the grouting pipe body is provided with a positioning plate, and the inner wall of the positioning plate is connected to the long through pipe.
[0014] As a preferred solution of the inspection hole grouting device of the utility model, a grouting hole is opened at the bottom of the grouting pipe body, and a ventilation pipe rack is arranged at the bottom of the positioning plate, and the ventilation pipe rack is located above the grouting hole.
[0015] As a preferred solution of the inspection hole grouting device of the utility model, a grouting pipe rack is arranged on the side of the ventilation pipe rack, and the top of the grouting pipe rack is connected to the positioning plate.
[0016] As a preferred solution of the inspection hole grouting device of the utility model, wherein: the bottom of the grouting pipe rack extends to the bottom of the ventilation pipe rack, and the grouting pipe rack is located above the grouting hole.
[0017] The beneficial effects of the inspection hole grouting device of the utility model are as follows: cement slurry or other alternative slurry is poured into the gap entrance between the outer wall of the long through pipe and the inner wall of the multi-section pipe assembly, thereby saving costs; while the multi-section pipe assembly is plugged in, the stabilizing part at the bottom will clamp and fix the long through pipe, thereby ensuring the smooth flow of the grouting pipeline, guaranteeing the grouting quality, and improving the assembly efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0019] Figure 1 It is a schematic diagram of the overall structure of the utility model.
[0020] Figure 2 It is a structural schematic diagram of the multi-section pipe assembly in the utility model.
[0021] Figure 3 It is a structural schematic diagram of the grouting pipe assembly in the utility model.
[0022] Figure 4 It is a schematic diagram of the structure of the utility model device after grouting. DETAILED DESCRIPTION
[0023] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0024] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0025] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.
[0026] Example 1, reference Figure 1-2, is the first embodiment of the utility model, which provides an inspection hole grouting device, including a multi-section pipe assembly 100, including an upper plug-in portion 101 and a stabilizing portion 102 arranged at the bottom of the upper plug-in portion 101, the number of the multi-section pipe assemblies 100 is multiple, and the multiple multi-section pipe assemblies 100 are connected head to tail, and the structure in the stabilizing portion 102 and the components in the upper plug-in portion 101 can be quickly plugged in and connected into a whole to meet the needs of extending into the bottom of the inspection hole for complete grouting; and a grouting pipe assembly 200, including a grouting pipe body 201 arranged at the bottom of the multi-section pipe assembly 100 and a long through pipe 206 arranged inside the grouting pipe body 201, the top of the grouting pipe body 201 is also provided with an upper plug-in portion 101, which can be plugged with the multi-section pipe assembly 100, the grouting pipe body 201 is the bottom of the device, and the multi-section pipe assembly 100 is plugged in section by section from the top, and the multi-section pipe When the component 100 is plugged in, the stabilizing portion 102 at the bottom will clamp and fix the long through tube 206, and fix it at multiple locations on the outer wall of the long through tube 206 to ensure the correct posture of the long through tube 206 when the device is extended into the bottom of the borehole, so as to ensure the smoothness of subsequent grouting and improve the grouting quality. After the entire device is plugged in, the gap between the outer wall of the long through tube 206 and the inner wall of the multi-section pipe component 100 is filled with alternative slurry. After the device is extended into the bottom of the borehole, cement slurry and other alternative slurries are poured from the gap entrance between the outer wall of the upper long through tube 206 and the inner wall of the multi-section pipe component 100, saving costs and ensuring the filling quality. Two long through tubes 206 extend from the bottom of the device to the top, one is an exhaust pipe, and the other is a grouting pipe. Chemical slurry is poured into the grouting pipe, and the grouting pipe body 201 and the long through tube 206 cooperate to pour chemical slurry from the bottom of the inspection hole.
[0027] Usage process: The grouting pipe body 201 is the bottom of the device. The multi-section pipe assembly 100 is inserted section by section from the top. When the multi-section pipe assembly 100 is inserted, the stabilizing part 102 at the bottom will clamp and fix the long through pipe 206. The long through pipe 206 is fixed at multiple locations on the outer wall of the long through pipe 206. After the device is extended into the bottom of the borehole, cement slurry or other alternative slurries are poured in from the gap entrance between the outer wall of the upper long through pipe 206 and the inner wall of the multi-section pipe assembly 100, which saves costs and ensures the filling quality. Two long through pipes 206 extend from the bottom of the device to the top, one is an exhaust pipe, and the other is a grouting pipe. Chemical slurry is poured into the grouting pipe, and the grouting pipe body 201 and the long through pipe 206 cooperate to pour the chemical slurry from the bottom of the inspection hole.
[0028] Example 2, reference Figure 1-2, which is the second embodiment of the utility model. Different from the previous embodiment, the upper plug-in part 101 includes a multi-section tube body 101a, and the number of the multi-section tube body 101a is multiple. The top of the multi-section tube body 101a is provided with a plug-in slope 101b, and the outer wall of the plug-in slope 101b is provided with a clamping arc groove 101c. The multi-section tube body 101a is the supporting body of the multi-section tube assembly 100.
[0029] Furthermore, the stabilizing portion 102 includes an intermediate rod 102a arranged inside the multi-section tube body 101a, and a fixed arc plate 102b is arranged on the side of the intermediate rod 102a. The fixed arc plate 102b is fixed on the intermediate rod 102a, and when fixing the long through tube 206, it will be close to the long through tube 206 to help positioning, and a movable clamping plate 102c is arranged on the side of the fixed arc plate 102b, and a clamping plate 102d is arranged on the side of the movable clamping plate 102c. The clamping plate 102d is made of elastic material. When the multi-section tube body 101a is plugged in, the clamping plate 102d is inserted into the plug-in arc surface of the upper plug-in portion 101, and the clamping plate 102d will undergo a slight deformation until the bottom of the clamping plate 102d is plugged into the plug-in arc groove 101c, completing quick plug-in, saving assembly time, and improving work efficiency.
[0030] Furthermore, a slide bar 102e is provided on the side of the movable clamping plate 102c, and a slide rack 102f is provided on the outer wall of the slide bar 102e. The side of the slide rack 102f is connected to the multi-section tube body 101a. During the plug-in process of the multi-section tube body 101a, the clamping plate 102d is deformed to exert a force toward the movable clamping plate 102c, pushing the movable clamping plate 102c toward the fixed clamping plate until the movable clamping plate 102c contacts the long through tube 206, clamping the long through tube 206, fixing the long through tube 206 while plugging, stabilizing the correct posture of the long through tube 206 during deep drilling and grouting, preventing blockage caused by twisting of the long through tube 206, and ensuring the quality of grouting.
[0031] Usage process: When plugging in the multi-section tube body 101a, the clamping plate 102d is inserted into the plugging arc surface of the upper plug-in part 101, and the clamping plate 102d will deform slightly until the bottom of the clamping plate 102d is stuck in the plugging arc groove 101c to complete the quick plug-in. During the plug-in process of the multi-section tube body 101a, the deformation of the clamping plate 102d will exert a force on the movable clamping plate 102c toward the movable clamping plate 102c, pushing the movable clamping plate 102c toward the fixed clamping plate until the movable clamping plate 102c contacts the long through tube 206, clamping the long through tube 206, fixing the long through tube 206 while plugging, and stabilizing the correct posture of the long through tube 206 during deep drilling and grouting.
[0032] Example 3, reference Figure 1 to Figure 4, which is the third embodiment of the utility model. Different from the previous embodiment, the inner wall of the grouting pipe body 201 is provided with a positioning plate 202, and the inner wall of the positioning plate 202 is connected to the long through pipe 206. Cement slurry is poured into the gap entrance between the outer wall of the long through pipe 206 and the inner wall of the multi-section pipe assembly 100 from the top of the device. The cement slurry reaches the positioning plate 202 at the deepest. This part is filled and replaced by cement slurry to save the more expensive chemical slurry and save costs.
[0033] Furthermore, a grouting hole 205 is provided at the bottom of the grouting pipe body 201, a ventilation pipe rack 204 is provided at the bottom of the positioning plate 202, a long through pipe 206 is provided on the top of the ventilation pipe rack 204, and the ventilation pipe rack 204 is located above the grouting hole 205. A grouting pipe rack 203 is provided on the side of the ventilation pipe rack 204, and a long through pipe 206 is provided on the top of the grouting pipe rack 203, which is a grouting pipe. The top of 3 is connected with the positioning plate 202, the bottom of the grouting pipe rack 203 extends to the bottom of the ventilation pipe rack 204, and the grouting pipe rack 203 is located above the grouting hole 205. When the device is assembled, the chemical slurry is poured into the grouting pipe, and the chemical slurry is poured into the bottom of the grouting pipe body 201 from the grouting pipe, and discharged into the drilled hole from the grouting hole 205 at the bottom of the grouting pipe. The air inside the grouting pipe escapes from the exhaust pipe to ensure the grouting quality.
[0034] Usage process: A long through pipe 206 is set on the top of the ventilation pipe rack 204, which is a exhaust pipe. A long through pipe 206 is set on the top of the grouting pipe rack 203, which is a grouting pipe. When the device is assembled, chemical slurry is poured into the grouting pipe, and the chemical slurry is poured into the bottom of the grouting pipe body 201 from the grouting pipe, and discharged into the drilled hole from the grouting hole 205 at the bottom of the grouting pipe. The air inside the grouting pipe escapes from the exhaust pipe to ensure the grouting quality.
[0035] Importantly, it should be noted that the construction and arrangement of the present application shown in a plurality of different exemplary embodiments are only exemplary. Although only a few embodiments are described in detail in this disclosure, it should be readily understood by those who refer to this disclosure that many modifications are possible (e.g., the size, scale, structure, shape and ratio of various elements, and parameter values (e.g., temperature, pressure, etc.), installation arrangements, use of materials, color, directional changes, etc.) without substantially departing from the novel teachings and advantages of the subject matter described in the application. For example, the element shown as integrally formed can be composed of multiple parts or elements, the position of the element can be inverted or otherwise changed, and the nature or number or position of the discrete element can be changed or changed. Therefore, all such modifications are intended to be included in the scope of the present utility model. The order or sequence of any process or method steps can be changed or reordered according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure of performing the function described herein, and is not only structurally equivalent but also equivalent structure. Without departing from the scope of the present invention, other substitutions, modifications, changes and omissions may be made in the design, operating conditions and arrangement of the exemplary embodiments. Therefore, the present invention is not limited to a specific embodiment, but extends to various modifications that still fall within the scope of the appended claims.
[0036] Additionally, in order to provide a concise description of example embodiments, all features of an actual embodiment (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those that are not relevant to implementing the invention) may not be described.
[0037] It will be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but will be a routine task of design, fabrication, and production for those of ordinary skill having the benefit of this disclosure without undue experimentation.
[0038] It should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.
Claims
1. An inspection hole grouting device, characterized in that: include, A multi-section pipe assembly (100) comprises an upper plug-in portion (101) and a stabilizing portion (102) disposed at the bottom of the upper plug-in portion (101); and, The grouting pipe assembly (200) comprises a grouting pipe body (201) arranged at the bottom of the multi-section pipe assembly (100) and a long through pipe (206) arranged inside the grouting pipe body (201).
2. The inspection hole grouting device according to claim 1, characterized in that: The upper plug-in portion (101) comprises a multi-section tube body (101a), the top of which is provided with a plug-in inclined surface (101b), and the outer wall of the plug-in inclined surface (101b) is provided with a clamping arc groove (101c).
3. The inspection hole grouting device according to claim 2, characterized in that: The stabilizing portion (102) comprises an intermediate rod (102a) arranged inside the multi-section tube body (101a), and a fixed arc-clamping plate (102b) is arranged on the side of the intermediate rod (102a).
4. The inspection hole grouting device according to claim 3, characterized in that: A movable clamping plate (102c) is arranged on the side of the fixed clamping arc plate (102b), and a clamping plate (102d) is arranged on the side of the movable clamping plate (102c), and the clamping plate (102d) is made of elastic material.
5. The inspection hole grouting device according to claim 4, characterized in that: A sliding rod (102e) is arranged on the side of the movable clamping plate (102c), a sliding rack (102f) is arranged on the outer wall of the sliding rod (102e), and a side of the sliding rack (102f) is connected to the multi-section tube body (101a).
6. The inspection hole grouting device according to claim 5, characterized in that: The number of the multi-section tube bodies (101a) is plural.
7. The inspection hole grouting device according to claim 6, characterized in that: The inner wall of the grouting pipe body (201) is provided with a positioning plate (202), and the inner wall of the positioning plate (202) is connected to the long through pipe (206).
8. The inspection hole grouting device according to claim 7, characterized in that: A grouting hole (205) is provided at the bottom of the grouting pipe body (201), and a ventilation pipe rack (204) is provided at the bottom of the positioning plate (202), wherein the ventilation pipe rack (204) is located above the grouting hole (205).
9. The inspection hole grouting device according to claim 8, characterized in that: A grouting pipe rack (203) is provided on the side of the ventilation pipe rack (204), and the top of the grouting pipe rack (203) is connected to the positioning plate (202).
10. The inspection hole grouting device according to claim 9, characterized in that: The bottom of the grouting pipe rack (203) extends to below the ventilation pipe rack (204), and the grouting pipe rack (203) is located above the grouting hole (205).