Rapid positioning device for PHC pipe pile
By designing a PHC pipe pile rapid positioning device including reference plate and wire rope system, the problem of inability to finely control the position, elevation and verticality of the pipe pile in the prior art is solved, and high-precision pipe pile installation and improved construction efficiency are achieved.
Patent Information
- Application Number
- CN202422182876.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2025-06-10
- Estimated Expiration
- 2034-09-06
AI Technical Summary
The existing water photovoltaic PHC pipe pile positioning technology cannot finely control the position, elevation and verticality of the pipe pile, resulting in large positioning errors and low construction efficiency.
A rapid positioning device for PHC pipe piles is designed, including a reference plate and a rope system. The removable connection between the reference plate and the PHC pipe pile is achieved through the hoop clamping ring and the adjustment hole, and the position, elevation and verticality of the pipe pile are accurately calibrated through the rope.
It significantly improves the installation accuracy of pipe piles, solves the positioning error problems caused by traditional GPS systems, and improves construction efficiency and project quality.
Smart Images

Figure CN222962069U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of positioning measurement of PHC pipe piles on water, in particular to a rapid positioning device for PHC pipe piles. Background Art
[0002] The positioning of PHC pipe piles for floating solar power generation has always been a difficult problem to solve. Generally, the GPS positioning system on the floating pile driving ship is used to control the positioning of the pipe piles. Using the positioning system on the pile driving ship can only roughly position the pipe piles, and it is impossible to finely control the position, elevation and verticality of the pipe piles. Moreover, the GPS positioning error on the pile driving ship is relatively large, the top elevations of the rows of piles are uneven, the spacing between the pipe piles is also uneven, and the verticality of the pile body exceeds the specification requirements. Repeated debugging is required during the installation process, and the construction efficiency is low. Content of the Utility Model
[0003] The utility model provides a rapid positioning device for PHC pipe piles to alleviate the problems that the existing installation method cannot finely control the position, elevation and verticality of the pipe piles, has large errors and low construction efficiency.
[0004] In order to alleviate the above technical problems, the technical solution provided by the utility model lies in:
[0005] The utility model provides a rapid positioning device for PHC pipe piles, including a reference plate;
[0006] The two reference plates are respectively detachably connected to the PHC pipe piles at the head and tail ends in the length direction of the installation area through hoop clips;
[0007] The two reference plates are detachably connected by a cord.
[0008] Furthermore,
[0009] The reference plate is in an inverted L shape, the short side abuts against the upper part of the PHC pipe pile, and the long side is arranged parallel to the length direction of the PHC pipe pile;
[0010] There is a 90° angle between the short side and the long side.
[0011] Furthermore,
[0012] The long side is provided with a plurality of wire hanging holes.
[0013] Furthermore,
[0014] The long side is provided with installation holes;
[0015] The hoop clip is provided with adjustment holes matching the installation holes.
[0016] Furthermore,
[0017] The hoop clip is provided with a plurality of adjustment holes in the horizontal direction.
[0018] Furthermore,
[0019] One hoop clip is provided at each of the upper and lower ends of the long side.
[0020] The beneficial effects of the PHC pipe pile quick positioning device in the present utility model are analyzed as follows:
[0021] This device includes a reference plate; the two reference plates are respectively detachably connected to the PHC pipe piles at the head and tail ends in the length direction of the installation area through hoop clips; the two reference plates are detachably connected by a wire rope. By connecting the two reference plates with a wire rope, the position indicated by the wire rope is used as the positioning mark for the PHC pipe pile, assisting workers in installing the PHC pipe pile, and significantly improving the installation accuracy of the pipe pile in the floating solar project. This device uses the reference plate and wire rope system to accurately calibrate the position, elevation and verticality of the pipe pile, solving the positioning error problem brought by the traditional GPS system. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the specific embodiments of the present utility model or the technical solutions in the related art, the following will briefly introduce the drawings required for use in the description of the specific embodiments or the related art. Obviously, the drawings in the following description are some embodiments of the present utility model. For those of ordinary skill in the art, without creative efforts, other drawings can also be obtained based on these drawings.
[0023] Figure 1 It is the front view structural schematic diagram of this device;
[0024] Figure 2 It is the top view structural schematic diagram of this device.
[0025] ICON:
[0026] 100 - reference plate; 110 - short side; 120 - long side; 121 - wire hanging hole;
[0027] 200 - hoop clip; 210 - adjustment hole;
[0028] 300 - PHC pipe pile. SPECIFIC EMBODIMENTS
[0029] For the positioning of PHC pipe piles in floating solar power plants, the GPS positioning system on the floating pile driver is used to control the positioning of the pipe piles. However, using the positioning system on the pile driver can only roughly position the pipe piles, and it is impossible to precisely control the position, elevation, and verticality of the pipe piles. Moreover, the GPS positioning error on the pile driver is relatively large, resulting in uneven elevations of the tops of the rows of piles, uneven spacing between the pipe piles, and the verticality of the pile bodies exceeding the specification requirements. Repeated debugging is required during the installation process, leading to low construction efficiency.
[0030] In view of this, as Figure 1 and Figure 2 shown, this solution provides a rapid positioning device for PHC pipe piles to alleviate the above problems. This device includes a reference plate 100;
[0031] Two reference plates 100 are respectively detachably connected to the PHC pipe piles 300 at the head and tail ends in the length direction of the installation area through hoop clamps 200;
[0032] The two reference plates 100 are detachably connected by a string.
[0033] Before using this device for positioning, first position and sink two PHC pipe piles 300 at the head and tail ends in the length direction of the installation area respectively, and then measure and debug the elevation and verticality of the positioning piles. When the two positioning piles pass the re-inspection, then install the two reference plates on the positioning piles on both sides respectively, and then connect the two reference plates by a string, so as to use the position indicated by the string as the positioning mark for the PHC pipe piles 300 to assist workers in installing the PHC pipe piles 300.
[0034] As Figure 1 shown, regarding the shape and structure of the reference plate 100, as well as the installation method, specifically:
[0035] The reference plate 100 is in an inverted L shape, with the short side 110 abutting against the upper part of the PHC pipe pile 300, and the long side 120 is arranged parallel to the length direction of the PHC pipe pile 300;
[0036] There is a 90° angle between the short side 110 and the long side 120;
[0037] The long side 120 is provided with installation holes;
[0038] The hoop clamp 200 is provided with adjustment holes 210 that cooperate with the installation holes.
[0039] The hoop clamp 200 is provided with a plurality of adjustment holes 210 in the horizontal direction.
[0040] Specifically, after the positioning piles are installed, the short side 110 is closely attached to the upper end surface of the positioning piles, the long side 120 is arranged downward and parallel to the length direction of the PHC pipe pile 300, and is clamped on both sides of the long side 120 through the hoop clamp 200. The bolts pass through the adjustment holes 210 and the installation holes and are fixed and connected with nuts. At the same time, the size of the adjustment holes 210 is slightly larger than that of the installation holes to facilitate fine-tuning of the long side 120, making the positioning more accurate.
[0041] In this solution, a plurality of wire-hanging holes 121 are provided on the long side 120. After the positioning and installation of the reference plate 100 are completed, the hanging ropes are passed through the same wire-hanging holes 121 of the two reference plates 100, and are fixed after being straightened, so as to use the indicated position of the wire-hanging holes 121 as the construction reference.
[0042] In order to improve the positioning accuracy of the reference plate 100 and avoid affecting the overall stability of the device due to abnormal factors such as strong winds on the water, hoop clamps 200 are respectively provided at the upper and lower ends of the long side 120.
[0043] This solution has at least the following beneficial effects:
[0044] This device includes a reference plate 100; the two reference plates 100 are respectively detachably connected to the PHC pipe piles 300 at the head and tail ends in the length direction of the installation area through hoop clamps 200; the two reference plates 100 are detachably connected by a wire rope. The two reference plates are connected by the wire rope, so as to use the position indicated by the wire rope as the positioning mark of the PHC pipe pile 300, assisting workers in installing the PHC pipe pile 300, and significantly improving the pipe pile installation accuracy in the floating PV project. This device uses the reference plate and wire rope system to accurately calibrate the position, elevation and verticality of the pipe pile, solving the positioning error problem brought by the traditional GPS system. By finely adjusting the positioning piles before installation and using the calibrated reference plate for auxiliary positioning, the problems of uneven pile top elevation, inconsistent spacing and excessive verticality can be effectively avoided, thus improving the construction operation efficiency and engineering quality.
[0045] Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: they can still modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements on some or all of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A PHC pile rapid positioning device, characterized by: comprising a reference plate (100); The two reference plates (100) are detachably connected to the PHC pipe piles (300) at the first and last ends of the length direction of the installation area through the clamping rings (200); The two reference plates (100) are detachably connected via a rope.
2. The PHC pile rapid positioning device according to claim 1 is characterized in that: The reference plate (100) is in an inverted L-shape, with a short side (110) abutting against the upper part of the PHC pile (300), and a long side (120) arranged parallel to the length direction of the PHC pile (300); The short side (110) and the long side (120) have an included angle of 90°.
3. The PHC pile rapid positioning device according to claim 2 is characterized in that: The long side (120) is provided with a plurality of wire hanging holes (121).
4. The PHC pile rapid positioning device according to claim 3 is characterized in that: The long side (120) is provided with a mounting hole; The clamping ring (200) is provided with an adjustment hole (210) that matches the mounting hole.
5. The PHC pile rapid positioning device according to claim 4 is characterized in that: The clamping ring (200) is provided with a plurality of adjustment holes (210) along the horizontal direction.
6. The PHC pile rapid positioning device according to claim 5, characterized in that: A clamp ring (200) is provided at the upper and lower ends of the long side (120) respectively.