Cable extruding and belting integrated series machine
By integrating the insulation extrusion and wrapping process of the cable into one production line and sharing the traction, laying and receiving systems, the problems of slow extrusion speed and complex process of FEP materials in existing cable production equipment are solved, and the effect of improving production efficiency and reducing costs is achieved.
Patent Information
- Application Number
- CN202421922564.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2025-06-17
- Estimated Expiration
- 2034-08-09
AI Technical Summary
In existing cable production equipment, the low viscosity of FEP materials leads to slow extrusion speed, and the cable production process is complex, requiring independent traction, laying and retrieving systems, resulting in low production efficiency and high equipment costs.
A cable extrusion and belt integrated series machine is designed to integrate insulation extrusion and winding into one production line, sharing the traction system, wiring release system and wiring collection system, simplifying the process and saving labor and equipment costs.
By integrating processes and equipment, cable production efficiency is improved, defective products are generated, and production costs are reduced.
Smart Images

Figure CN222995152U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cable manufacturing, in particular to a cable extrusion and taping integrated series machine. Background Technique
[0002] The 224G PICE6.0 supporting cable is widely used in the AI field. When used for internal transmission, its market demand is very large, and thus the production efficiency of the corresponding cable needs to be improved. However, in the existing production equipment, the cable needs to go through FEP-filled double-conductor extrusion during the production process. Since the FEP material has too low viscosity during use, in the tube extrusion process, due to the large glue outlet area, the material can only be produced at a low flow rate, resulting in a relatively low production efficiency; when using the extrusion method for production, due to the small glue outlet area, the material is produced at a high flow rate. In this state, due to the too fast flow rate, problems such as turbulent flow and stratification will occur during rapid extrusion, so the defect of slow FEP extrusion speed cannot be solved at the material level for the time being.
[0003] After the existing cable is extruded and formed, the semi-finished product needs to be placed, and then transferred to an independent wrapping and winding station for further operation. In the actual use process, independent traction systems, pay-off systems, and winding systems need to be set for both the extrusion and forming and the wrapping and winding mechanisms, which makes the cable manufacturing process relatively complex. Therefore, there is an urgent need to develop a cable manufacturing equipment that can reduce the process and equipment costs. Summary of the Invention
[0004] In view of the above problems, the utility model provides a cable extrusion and taping integrated series machine, which integrates insulation extrusion and wrapping on one production line, shares the traction system, pay-off system, and winding system, saves processes, reduces labor costs and equipment costs, and improves the production efficiency of the cable.
[0005] A cable extrusion and taping integrated series machine, characterized in that it includes:
[0006] A pay-off system, which is a double-head power pay-off system;
[0007] An extrusion system;
[0008] A cooling system;
[0009] A traction system;
[0010] A wrapping combination system;
[0011] And a winding system;
[0012] The wire feeding system, extrusion system, cooling system, traction system, wrapping combination system, and wire winding system are arranged in a straight line in sequence. After the wire feeding system outputs two conductors, they enter the head of the extrusion system, and are extruded and coated with FEP material through the head. After being cooled by the cooling system, they are pulled by the traction system to the entrance of the wrapping combination system at the rear. After being wrapped by the wrapping combination system, they flow out, and finally are wound by the wire winding system.
[0013] Its further features are as follows:
[0014] The cooling system is an air-cooling system, which occupies a small volume, has a simple structure compared with water-cooling, and has a high cooling efficiency compared with natural cooling;
[0015] An XY-axis eccentric adjustment platform is arranged behind the air-cooling system. The XY-axis eccentric adjustment platform is used to adjust the eccentric position, that is, the offset of the two conductors in the FEP insulation, to ensure that the appearance eccentricity of the core wire extruded with FEP material led out by the subsequent traction system meets the design standard;
[0016] A detection station for the core wire size and appearance eccentricity is integrated at the core wire outlet position of the traction system. After manually intercepting a section of the core wire at this station for detection, if the detection is qualified, the core wire flowing out of the traction system directly flows to the entrance of the wrapping combination system for subsequent wrapping operations. If the core wire intercepted at this station is detected to be unqualified, the front-end XY-axis eccentric adjustment platform is adjusted until the eccentric position of the conductor meets the design requirements, and then the core wire flows to the entrance of the wrapping combination system;
[0017] The wrapping combination system includes a longitudinal wrapping system, a first wrapping system, a second wrapping system, and a heating system arranged in sequence. The longitudinal wrapping system is used to longitudinally wrap the first metal layer on the outer periphery of the insulating layer. The first wrapping system is used to wrap the second metal layer on the outer periphery of the first metal layer. The second wrapping system is used to wrap the mylar on the outer periphery of the second metal layer. The heating system is used to adhere the inner layer of the mylar to the outer periphery of the second metal layer;
[0018] The wire winding system is an axial row wire winding machine.
[0019] After adopting the above technical solution, when operating this equipment, it is divided into two parts:
[0020] The first part: The wire feeding system releases two conductors. The two conductors are extruded and coated with FEP material through the head to form insulation, and then are cooled by the cooling system. The core wire pulled out by the traction system can detect design requirements such as the core wire size and appearance eccentricity. Up to the traction system as a node, the debugging waste wire can be directly scrapped here and not enter the subsequent equipment. When it is confirmed that the first-piece inspection is qualified, the second part is implemented;
[0021] In the second part, the qualified core wires are passed through each group of systems in the wrapping combination system and then connected to the take-up machine. While the wires are being routed, the wrapping tapes for the spacer layers are gradually assembled.
[0022] The above two parts can be operated independently or combined in a linkage process. It integrates insulation extrusion and wrapping on one production line, sharing the traction system, wire feeding system, and take-up system, saving processes, labor costs, and equipment costs, and improving the production efficiency of cables. Brief Description of the Drawings
[0023] Figure 1 is a schematic structural diagram of the present utility model;
[0024] Figure 2 is a cross-sectional view of the cable structure corresponding to the production of the present utility model;
[0025] The names corresponding to the numbers in the figure are as follows:
[0026] Wire feeding system 1, extrusion system 2, air cooling system 3, XY-axis eccentric adjustment platform 4, traction system 5, longitudinal wrapping system 6, first wrapping system 7, second wrapping system 8, heating system 9, take-up system 10;
[0027] Double-conductor cable 100, conductor 101, insulation 102, first aluminum foil layer 103, second aluminum foil layer 104, Mylar wrapping layer 105. Detailed Embodiment
[0028] A cable extrusion and wrapping integrated tandem machine, as shown in Figure 1 , which includes a wire feeding system 1, an extrusion system 2, a cooling system, a traction system 5, a wrapping combination system, and a take-up system 10;
[0029] Specifically, the wire feeding system 1 is a double-head power wire feeding system;
[0030] The cooling system is an air cooling system 3, which occupies a small volume, has a simple structure compared to water cooling, and has a high cooling efficiency compared to natural cooling. An XY-axis eccentric adjustment platform 4 is arranged behind the outlet of the air cooling system 3. The XY-axis eccentric adjustment platform 4 is used to adjust the eccentric position, that is, the offset of the two conductors 101 in the FEP insulation 102, to ensure that the appearance eccentricity of the extruded core wire with FEP material derived by the subsequent traction system 5 meets the design standard;
[0031] The traction system 6 is equipped with a power adjustment mechanism and a guiding mechanism;
[0032] The wrapping combination system includes a longitudinal wrapping system 6, a first wrapping system 7, a second wrapping system 8, and a heating system 9 arranged in sequence;
[0033] The wire feeding system 1, extrusion system 2, air cooling system 3, XY-axis eccentric adjustment platform 4, traction system 5, longitudinal wrapping system 6, first wrapping system 7, second wrapping system 8, heating system 9, and wire winding system 10 are arranged in sequence in a straight line. The wire feeding system 2 outputs two conductors and then enters the head of the extrusion system 3. After being extruded by the head, an FEP material is coated. After being cooled by the air cooling system 3, it passes through the XY-axis eccentric adjustment platform 4, and then is pulled by the traction system 5. At the core wire outlet position of the traction system 5, there is an integrated inspection station for the size, appearance, and eccentricity of the core wire (not shown in the figure, only a single-operator station needs to be accommodated here). After manually intercepting a section of the core wire at this station for inspection, if the inspection is qualified, the core wire flowing out of the traction system 5 directly flows to the inlet of the wrapping combination system for subsequent wrapping operations. If the core wire intercepted at this station fails the inspection, the XY-axis eccentric adjustment platform 4 at the front end is adjusted until the eccentric position of the conductor meets the design requirements, and then the core wire passes through the longitudinal wrapping system 6, first wrapping system 7, second wrapping system 8, heating system 9 in sequence, and finally is wound by the wire winding system 10.
[0034] After adopting the above technical solution, when operating this equipment, it is divided into two parts:
[0035] The first part: The wire feeding system 1 releases two conductors. The two conductors are extruded by the head and coated with FEP material to form insulation. After that, they are cooled by the air cooling system 3. The core wire pulled out by the traction system 5 can be inspected for design requirements such as the size, appearance, and eccentricity of the core wire. Up to the traction system 5 as a node, the debugging waste wire can be directly scrapped here and not enter the subsequent equipment. When it is confirmed that the first-piece inspection is qualified, the second part is implemented;
[0036] The second part: The qualified core wire is passed through each system in the wrapping combination system and then connected to the wire winding machine 10. While the wire is passing, the spacer tapes are gradually assembled.
[0037] The above two parts can be operated independently or combined in a linkage process. It integrates insulation extrusion and wrapping on one production line, sharing the traction system, wire feeding system, and wire winding system, saving processes, labor costs, and equipment costs, and improving the production efficiency of cables.
[0038] Specifically, the wire feeding system 1 is a double-head wire feeder, and the heating system 9 is specifically an oven system.
[0039] Specific embodiments are used for processing such as Figure 2The high-speed line 224G product shown, namely the twin-conductor cable 100, has two conductors 101 arranged at intervals in the center of the twin-conductor cable 100. The two conductors 101 are extrusion-coated with FEP material to form insulation 102. A first aluminum foil layer 103, a second aluminum foil layer 104, and a mylar wrapping layer 105 are sequentially wrapped around the outer periphery of the insulation 102. The two processing parts are respectively: 1. Insulation extrusion, Figure 2 In this step, the middle conductor 101 and the insulation 102 part are completed; 2. Tape winding (two layers of aluminum foil + one layer of mylar are completed in this process). Using a cable extrusion and taping integrated series machine to combine the two steps, the generation of defective products is reduced, and the possibility of semi-finished product stagnation is eliminated. The specific process of processing through the integrated series machine is as follows:
[0040] S1. The double-head pay-off machine releases two independent conductors 101;
[0041] S2. The extrusion system 2 extrudes and coats with FEP material to form insulation 102;
[0042] S3. The air-cooling system 3 completes the cooling of the insulation 102;
[0043] S4. The XY-axis eccentric adjustment platform 4 is used to adjust the offset of the conductor 101 in the insulation 102;
[0044] S5. The traction system 5 provides power, and employees can cut the wire and detect and adjust the size of the insulation structure and the offset of the conductor 101 in the insulation 102;
[0045] S5. The longitudinal wrapping system completes the longitudinal wrapping of the first aluminum foil layer 103, so that the first aluminum foil layer 103 is longitudinally wrapped around the outer periphery of the insulation;
[0046] S6. The first wrapping system wraps to form the second aluminum foil layer 103;
[0047] S7. The second wrapping system wraps to form the mylar wrapping layer 104;
[0048] S8. The oven system 9 melts the inner hot melt adhesive on the mylar wrapping layer 105, so that the mylar wrapping layer 105 is reliably attached to the outer periphery of the second aluminum foil layer 104;
[0049] S9. Take up the wire through the take-up system 10.
[0050] The advantages of the present utility model are that the production process can be reduced from two processes to one, reducing labor costs, and reducing the extrusion risk of semi-finished product inventory during transfer or storage, and reducing the generation of defective products; two sets of equipment share one set of pay-off, take-up and traction systems, thereby reducing the overall production cost.
[0051] For those skilled in the art, it is obvious that the present utility model is not limited to the details of the above-mentioned exemplary embodiments, and the present utility model can be implemented in other specific forms without departing from the spirit or basic characteristics of the present utility model. Therefore, from any point of view, the embodiments should be regarded as exemplary and non-limiting. The scope of the present utility model is defined by the appended claims rather than the above description. Therefore, all changes falling within the meaning and scope of the equivalent elements of the claims are intended to be embraced within the present utility model. Any reference signs in the claims should not be construed as limiting the claims involved.
[0052] In addition, it should be understood that although this specification is described according to embodiments, not every embodiment only contains an independent technical solution. This narrative way of the specification is only for clarity. Those skilled in the art should regard the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.
Claims
1. A cable extrusion and taping integrated tandem machine, characterized in that: It includes: Pay-off system, which is a double-head powered pay-off system; Extrusion system; Cooling system; Traction system; Wrapping combination system; and the take-up system; The pay-off system, extrusion system, cooling system, traction system, winding assembly system and take-up system are arranged in a straight line in sequence. The pay-off system outputs two conductors and then enters the head of the extrusion system, where they are extruded and coated with FEP material. After being cooled by the cooling system, they are pulled to the entrance of the winding assembly system at the rear by the traction system, are wrapped by the winding assembly system, flow out, and are finally wound up by the take-up system.
2. The cable extrusion and taping integrated tandem machine according to claim 1, characterized in that: The cooling system is an air cooling system.
3. The cable extrusion and taping integrated tandem machine according to claim 2, characterized in that: An XY-axis eccentricity adjustment platform is arranged at the rear of the air cooling system, and the XY-axis eccentricity adjustment platform is used to adjust the eccentric position, that is, the offset of the two conductors in the FEP insulation.
4. The cable extrusion and taping integrated tandem machine according to claim 1, characterized in that: The core wire outlet position of the traction system is integrated with a station for detecting the eccentricity of the core wire size and appearance. A section of the core wire is manually cut off at this station for inspection. After passing the inspection, the core wire flowing out of the traction system directly flows to the entrance of the winding combination system for subsequent winding operations. If the core wire cut off at this station fails the inspection, the front end XY axis eccentricity adjustment platform is adjusted until the eccentric position of the conductor meets the design requirements, so that the core wire flows to the entrance of the winding combination system.
5. The cable extrusion and taping integrated tandem machine according to claim 1, characterized in that: The wrapping combination system includes a longitudinal wrapping system, a first wrapping system, a second wrapping system, and a heating system arranged in sequence. The longitudinal wrapping system is used to longitudinally wrap the first metal layer around the outer periphery of the insulating layer, the first wrapping system is used to wrap the second metal layer around the outer periphery of the first metal layer, the second wrapping system is used to wrap Mylar around the outer periphery of the second metal layer, and the heating system is used to adhere the inner layer of Mylar to the outer periphery of the second metal layer.
6. The cable extrusion and taping integrated tandem machine according to claim 1, characterized in that: The wire taking-up system is a shaft-arranged wire taking-up machine.