Construction joint waterproof joint structure for pit division construction

By designing the waterproof node structure of the construction joint for the sub-pit construction, using the welded structure of the embedded T-shaped steel plate and the steel plate set up after construction, combined with the rubber water stop strip and stainless steel water connection box, the problem of waterproofing at the construction joint is solved, and efficient waterproofing effect and construction quality are achieved.

CN223048089UActive Publication Date: 2025-07-01POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421844763.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2025-07-01
Estimated Expiration
2034-08-01

AI Technical Summary

Technical Problem

During the construction of urban rail transit underground stations and municipal engineering sub-pits, waterproofing measures at the construction joints are difficult to effectively prevent water leakage, resulting in a long time of repeated grouting and rectification, and poor results.

Method used

A waterproof node structure for construction joint construction is designed for pit construction, including pre-embedded T-shaped steel plates and steel plates set after construction. The two are welded and a rubber water stop strip and a stainless steel water connection box that expands when exposed to water are set at the weld to lead the leakage water to the drainage ditches.

Benefits of technology

Effective waterproofing at the construction joints is achieved, repeated grouting is avoided in the later stage, construction quality is ensured, and project cost and construction period are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223048089U_ABST
    Figure CN223048089U_ABST
Patent Text Reader

Abstract

The utility model provides a construction joint waterproof node structure for pit division construction, which comprises a main body structure and an accessory structure, a T-shaped steel plate is pre-buried in the main body structure, a steel plate is arranged after the accessory structure is completed, the T-shaped steel plate is welded with the steel plate, and a water-swelling rubber water stop strip is arranged at a welding seam of the T-shaped steel plate and the steel plate. The structure has the advantages that the structure design is reasonable, the waterproof effect is good, repeated grouting in the later period is avoided, the construction quality is guaranteed, the construction cost is reduced, and the construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of rail transit engineering, and particularly relates to a construction joint waterproof node structure for separate pit construction. Background Technique

[0002] For the main body of an urban rail transit underground station and its affiliated entrances and ventilation shafts, they are constructed in phases. An inevitable construction joint is formed at the interface between the two. The usual practice is to pre-bury grouting pipes and set water-swelling waterstop strips at the construction joint during the construction of the affiliated structure. However, the phenomenon of water leakage is still serious. Generally, repeated grouting is often carried out to stop the leakage. The rectification time is long, the effect is not good, and it is easy to recur. This kind of situation also exists in the waterproof treatment at the combined part during the separate pit construction of municipal engineering. Content of the Utility Model

[0003] The purpose of the utility model is to provide a construction joint waterproof node structure for separate pit construction, which has reasonable structural design, good waterproof effect, avoids repeated grouting in the later stage, ensures construction quality, reduces project cost, and reduces the construction period.

[0004] In order to achieve the above purpose, the utility model is realized through the following technical solutions:

[0005] A construction joint waterproof node structure for separate pit construction, including a main structure and an affiliated structure. The main structure pre-buries a T-shaped steel plate, and a steel plate is set after the affiliated structure is completed. The T-shaped steel plate is welded to the steel plate, and a water-swelling rubber waterstop strip is set at the weld.

[0006] Furthermore, a stainless steel water receiving box is set on the lower side of the weld, and the leaked water is led to a drainage ditch.

[0007] Compared with the prior art, the utility model has the following advantages:

[0008] The construction joint waterproof node structure for separate pit construction of the utility model has reasonable structural design, good waterproof effect, avoids repeated grouting in the later stage, ensures construction quality, reduces project cost, and reduces the construction period of separate pit construction. Description of the Drawings

[0009] Figure 1 It is a schematic structural diagram of Embodiment 1 of the utility model.

[0010] Figure 2 It is a schematic structural diagram of Embodiment 2 of the utility model.

[0011] Figure 3 It is a schematic structural diagram of Embodiment 3 of the utility model.

[0012] Figure 4 It is a schematic structural diagram of the utility model.

[0013] Reference signs: 1, main structure; 2, T-shaped steel plate; 3, accessory structure; 4, steel plate; 5, rubber water stop strip; 6, stainless steel water receiving box. Specific embodiments

[0014] The following will further describe the embodiments of the present invention in detail with reference to the accompanying drawings.

[0015] As Figure 4 shown, the waterproof structure of the present invention includes the T-shaped steel plate 2 embedded in the main structure 1 and the steel plate 4 after the construction of the accessory structure 3, and the T-shaped steel plate 2 is welded to the steel plate 4. The main structure 1 of the present invention includes the top plate, bottom plate and side wall of the station main body. Correspondingly, the accessory structure 3 includes the top plate, bottom plate and side wall of the accessory facilities.

[0016] Embodiment 1

[0017] As Figure 1 shown, the side wall top of the station main structure 1 is welded to the channel top plate of the accessory structure 3. The T-shaped steel plate 2 is embedded at the side wall top. The T-shaped steel plate 2 includes a vertical steel plate one and a steel plate two. The steel plate one extends into the top plate, and the surface of the steel plate two is exposed on the top plate. After the construction of the channel top plate, a steel plate 4 is provided to be welded to the steel plate two of the T-shaped steel plate 2; a water-swelling rubber water stop strip 5 is provided at the weld, and a stainless steel water receiving box 6 is provided below the weld, and the seepage water is led to the drainage ditch at the bottom plate.

[0018] Preferably, the thickness of the T-shaped steel plate 2 or the steel plate 4 is 4 mm; the steel plate one of the T-shaped steel plate 2 or the tail of the steel plate 4 is bent, which enhances the supporting force and stress of penetrating into the wall of the main structure or the accessory structure. The length of the bent part is 50 mm, and the length of the unbent part is 150 mm; the two ends of the steel plate two of the T-shaped steel plate 2 are bent inward, which enhances the welding firmness between the T-shaped steel plate 2 and the steel plate 4. The length of the bent part is 50 mm, and the length of the unbent part is 300 mm.

[0019] Embodiment 2

[0020] As Figure 2 shown, the side wall of the station main structure 1 is welded to the channel side wall of the accessory structure 3. The T-shaped steel plate 2 is embedded in the station side wall. The T-shaped steel plate 2 includes a vertical steel plate one and a steel plate two. The steel plate one extends into the side wall, and the surface of the steel plate two is exposed on the side wall. After the construction of the channel side wall, a steel plate 4 is provided to be welded to the steel plate two of the T-shaped steel plate 2; a water-swelling rubber water stop strip 5 is provided at the weld, and a stainless steel water receiving box 6 is provided below the weld, and the seepage water is led to the drainage ditch at the bottom plate.

[0021] The shapes and dimensions of the T-shaped steel plate 2 and the steel plate 4 are the same as those in Embodiment 1.

[0022] Embodiment 3

[0023] As Figure 3 shown, the bottom plate of the main structure 1 of the station is welded to the bottom plate of the passage of the auxiliary structure 3. A T-shaped steel plate 2 is embedded in the bottom plate of the side wall of the station. The T-shaped steel plate 2 includes a vertical steel plate 1 and a steel plate 2. The steel plate 1 extends into the bottom plate, and the surface of the steel plate 2 is exposed on the bottom plate. After the construction of the bottom plate of the passage, a steel plate 4 is provided to be welded to the steel plate 2 of the T-shaped steel plate 2; a water-swellable rubber water stop strip 5 is provided at the weld, and a stainless steel water collecting box 6 is provided on the lower side of the weld to lead the seepage water to the drainage ditch of the bottom plate.

[0024] The shapes and sizes of the T-shaped steel plate 2 and the steel plate 4 are the same as those in Embodiment 1.

[0025] The above are only the preferred embodiments of the present invention. It should be noted that for those of ordinary skill in the art of the present technology, without departing from the concept of the present invention, several improvements and refinements can still be made, and these improvements and refinements should also be regarded as within the protection scope of the present invention.

Claims

1. A construction joint waterproof node structure for pit construction, comprising a main structure and an auxiliary structure, characterized in that: The main structure is pre-buried with a T-shaped steel plate, and the steel plate is arranged after the auxiliary structure is completed. The T-shaped steel plate is welded to the steel plate and a rubber water stop strip that expands when exposed to water is arranged at the weld.

2. A construction joint waterproof node structure for pit construction according to claim 1, characterized in that: A stainless steel water receiving box is arranged at the lower side of the weld to guide the leaking water to the drainage ditch.