Formwork device for well wall concrete pouring

By designing multiple sets of support formwork units and detachable and connected support structures, the problem of inconvenient disassembly and assembly of the well wall concrete pouring formwork is solved, and convenient and efficient well wall construction is achieved.

CN223074790UActive Publication Date: 2025-07-08ANHUI ROAD & BRIDGE GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422082457.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2025-07-08
Estimated Expiration
2034-08-26

AI Technical Summary

Technical Problem

The existing well wall concrete pouring formwork device is inconvenient to disassemble and assemble, resulting in low construction efficiency and difficult to meet the convenience and efficiency requirements of construction.

Method used

A formwork device composed of multiple sets of support formwork units is designed, including the formwork body and the support mechanism, and is connected by vertical and transverse support members and detachable fasteners to form a stable support structure, suitable for pouring of well wall concrete.

Benefits of technology

It realizes the convenient disassembly and assembly and reuse of formwork devices, improves construction efficiency, ensures the quality of concrete pouring on the well wall, shortens the construction cycle, and is suitable for well wall construction such as inverted wells.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223074790U_ABST
    Figure CN223074790U_ABST
Patent Text Reader

Abstract

The utility model discloses a template device for well wall concrete pouring, which is composed of a plurality of groups of supporting template units, each supporting template unit comprises a template body and a supporting mechanism, and each supporting mechanism comprises a vertical supporting piece, a fastener and a transverse supporting piece fixed on the template body; in the installation state, the multiple sets of supporting formwork units are sequentially arranged at the well bottom in the circumferential direction of the well wall, formwork bodies of the multiple sets of supporting formwork units are enclosed and spliced to form a circle of annular formwork, the vertical supporting pieces are connected to the ground of the well bottom in an inserted mode, and the transverse supporting pieces are detachably connected to the vertical supporting pieces through the fasteners. The template device disclosed by the utility model can be repeatedly disassembled and assembled, can be recycled, is very convenient to disassemble and assemble, greatly improves the operation simplicity of workers, shortens the time for disassembling and assembling the template support, provides help for realizing the safety, convenience, high efficiency and high quality of construction, and is suitable for well wall construction of upside down wells and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of construction, in particular to a formwork device for well wall concrete pouring. Background Art

[0002] In the municipal drainage pipe network project, in residential areas, where the road section is prosperous and there are many underground pipelines, pipe jacking construction is generally adopted to minimize the impact on the surrounding environment as much as possible. In the pipe jacking project, the inverted well is the most common structure. When constructing, the well wall is used as a retaining wall, and the construction is carried out by the top-down reverse construction method, and the well wall pouring needs to be carried out in layers.

[0003] The formwork for well wall pouring needs to be continuously rotated, that is, it needs to be continuously demolished and installed. The prior art generally uses square pipes or wooden bars to support and install the formwork, which is not convenient for disassembly and assembly, resulting in a reduction in construction efficiency. Summary of the Utility Model

[0004] The main purpose of the utility model is to provide a formwork device for well wall concrete pouring, which is convenient for disassembly and assembly, is convenient for recycling, and shortens the construction period.

[0005] To achieve the above purpose, the utility model provides a formwork device for well wall concrete pouring, which is composed of multiple groups of supporting formwork units. The supporting formwork unit includes a formwork body and a supporting mechanism. The supporting mechanism includes a vertical support member, a fastener, and a horizontal support member fixed on the formwork body.

[0006] In the installation state, multiple groups of the supporting formwork units are sequentially arranged along the circumferential direction of the well wall at the bottom of the well. The formwork bodies of multiple groups of the supporting formwork units are enclosed and spliced into a circular formwork. The vertical support member is inserted into the ground at the bottom of the well, and the horizontal support member is detachably connected to the vertical support member through the fastener.

[0007] Further, the vertical support member includes a vertical strut and a soil nail fixed at the lower end of the vertical strut.

[0008] Further, in the installation state, the formwork body is arranged in an inclined manner with the top inward. The horizontal support member includes a first horizontal strut and a second horizontal strut. The second horizontal strut is located below the first horizontal strut and the length of the second horizontal strut is greater than the length of the first horizontal strut.

[0009] Further, the fastener is composed of a first hoop and a second hoop connected together.

[0010] Further, the first hoop and the second hoop are rotatably connected.

[0011] Further, the first hoop and the second hoop have the same structure, both including a first hoop body, a second hoop body, an internal thread sleeve and a locking bolt. One end of the first hoop body is rotatably connected to one end of the second hoop body. The internal thread sleeve is connected to the other end of the first hoop body. A notch for accommodating the locking bolt is formed at the other end of the second hoop body. In the installed state, the locking bolt passes through the notch and is threadedly connected to the internal thread sleeve.

[0012] Further, an installation groove is formed at the other end of the first hoop body, and one end of the internal thread sleeve is rotatably installed in the installation groove through a connecting shaft.

[0013] Further, a groove for cooperating with a gasket is formed on the outer side surface of the other end of the second hoop body.

[0014] Further, the device is made of steel.

[0015] The beneficial effects of the present utility model are embodied in:

[0016] The formwork device of the present utility model has stable support installation, is not prone to formwork running problems during concrete pouring, can ensure the quality of well wall concrete pouring, and can be disassembled and assembled repeatedly for cyclic use. The disassembly and assembly are also very convenient, greatly improving the simplicity of worker operation, reducing the time for removing and installing formwork supports, and providing help for realizing the safety, convenience, high efficiency and high quality of construction. It is applicable to well wall construction such as inverted wells. Description of the Drawings

[0017] Figure 1 is a schematic structural diagram (top view) of an embodiment of the present utility model;

[0018] Figure 2 is a schematic structural diagram (side view) of an embodiment of the present utility model;

[0019] Figure 3 is a schematic structural diagram of a fastener in an embodiment of the present utility model.

[0020] Description of the Reference Numerals:

[0021] 100, support formwork unit; 110, formwork body; 120, support mechanism;

[0022] 10, vertical support member; 101, vertical support rod; 102, soil nail;

[0023] 20, horizontal support member; 201, first cross support rod; 202, second cross support rod;

[0024] 30. Fastener; 301. First hoop body; 302. Second hoop body; 303. Internal thread sleeve; 304. Locking bolt; 305. Notch; 306. Installation groove; 307. Connecting shaft; 308. Groove. Specific embodiments

[0025] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. It should be noted that if there are directional indications (such as up, down, left, right, front, back...) in the embodiments of the present invention, the directional indications are only used to explain the relative positional relationship and movement conditions between components in a specific posture (as shown in the drawings). If the specific posture changes, the directional indications will also change accordingly.

[0026] In addition, if there are descriptions such as "first" and "second" in the embodiments of the present invention, the descriptions of "first", "second", etc. are only for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the quantity of the indicated technical features. Thus, the features defined with "first" and "second" may explicitly or implicitly include at least one such feature. In addition, "a plurality" means two or more. In addition, the technical solutions between various embodiments can be combined with each other.

[0027] See Figures 1 to 3 .

[0028] The formwork device of the present invention for the concrete pouring of the well wall is composed of multiple groups of support formwork units 100. The support formwork unit includes a formwork body 110 and a support mechanism 120. The support mechanism 120 includes a vertical support member 10, a fastener 30, and a horizontal support member 20 fixed on the formwork body 110.

[0029] In the installation state, multiple groups of the support formwork units 100 are sequentially arranged along the circumferential direction of the well wall at the bottom of the well. The formwork bodies 110 of multiple groups of the support formwork units 100 are enclosed and spliced into a circular formwork. The vertical support member 10 is inserted into the ground at the bottom of the well, and the horizontal support member 20 is detachably connected to the vertical support member 10 through the fastener 30.

[0030] The structure of the present invention is simple. Through the support mechanism, the formwork body can be stably supported and installed. After the pouring is completed, as long as the fastener is removed and the vertical support member is pulled out of the ground at the bottom of the well, the disassembly of the support formwork unit can be realized. When it needs to be used again, as long as the vertical support member is re-driven into the soil, the formwork body is set up again, and the corresponding components are connected with the fastener.

[0031] The formwork device of the present utility model is stably supported and installed, and it is not easy to have the problem of formwork displacement during concrete pouring, which can ensure the quality of the well wall concrete pouring. Moreover, it can be disassembled and assembled repeatedly and used cyclically, and the disassembly and assembly are very convenient, greatly improving the simplicity of the workers' operation and reducing the time for removing and installing the formwork support, providing help for realizing the safety, convenience, high efficiency and high quality of construction, and being applicable to the construction of well walls such as inverted wells.

[0032] In one embodiment, the vertical support member 10 includes a vertical strut 101 and a soil nail 102 fixed to the lower end of the vertical strut 101. With such a design, the structure is simple and it is convenient for the vertical support member to be inserted into the bottom ground of the well.

[0033] In one embodiment, in the installed state, the formwork body 110 is arranged in an inclined manner with the top inward. The transverse support member 20 includes a first cross strut 201 and a second cross strut 202. The second cross strut 202 is located below the first cross strut 201 and the length of the second cross strut 202 is greater than the length of the first cross strut 201. With such a design, the first cross strut, the second cross strut, the vertical strut and the formwork body form a trapezoidal structure, and the support is more stable.

[0034] In one embodiment, the fastener 30 is composed of a first hoop and a second hoop connected together. The first hoop and the second hoop are respectively used to hoop around the vertical strut and the first cross strut or the second cross strut. In this way, the transverse support member can be detachably connected to the vertical support member.

[0035] In one embodiment, the first hoop and the second hoop are rotatably connected. With such a design, the angle between the first and second hoops is adjustable and can be adaptively adjusted according to the angle between the vertical strut and the first cross strut or the second cross strut. Specifically, the hoop body 301 of the first hoop and the hoop body 301 of the second hoop can be rotatably connected through a rotating shaft 309.

[0036] In one embodiment, the first hoop and the second hoop have the same structure, and both include a hoop body 301, a hoop body 302, an internal thread sleeve 303 and a locking bolt 304. One end of the hoop body 301 is rotatably connected to one end of the hoop body 302. The internal thread sleeve 303 is connected to the other end of the hoop body 301. A notch 305 for accommodating the locking bolt 304 is formed at the other end of the hoop body 302. In the installed state, the locking bolt 304 passes through the notch 305 and is threadedly connected to the internal thread sleeve 303. This kind of hoop has a simple structure, is easy to manufacture, and is convenient for disassembly and assembly, and the rod member is clamped between the hoop body 301 and the hoop body 302.

[0037] In one embodiment, an installation groove 306 is formed at the other end of the hoop body 301, and one end of the internal-threaded sleeve 303 is rotatably installed in the installation groove 306 through a connecting shaft 307. With this design, the angle of the internal-threaded sleeve can also be adjusted, making it easier to cooperate and connect with the locking bolt.

[0038] In one embodiment, a groove 308 for cooperating with a gasket is formed on the outer side surface of the other end of the hoop body 302. With this design, during installation, a gasket can be sleeved on the locking bolt between the nut and the hoop body 302 to increase the locking firmness. The gasket is snapped into this groove for greater stability.

[0039] In one embodiment, the device is made of steel.

[0040] In specific implementation, the lateral support member is connected to the template body by welding to form an integral whole; the vertical strut and the soil nail are connected by welding to form an integral whole; the adjacent template bodies can also be connected by screws to further enhance the structural stability.

[0041] The above are only the preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. A formwork device for wellbore concrete pouring, characterized in that, It is composed of multiple groups of supporting formwork units. Each supporting formwork unit includes a formwork body and a supporting mechanism. The supporting mechanism includes a vertical support member, a fastener, and a horizontal support member fixed on the formwork body. In the installed state, multiple groups of the supporting formwork units are sequentially arranged at the bottom of the well along the circumferential direction of the well wall. The formwork bodies of multiple groups of the supporting formwork units are enclosed and spliced into a circular formwork. The vertical support member is inserted into the ground at the bottom of the well, and the horizontal support member is detachably connected to the vertical support member through the fastener.

2. The formwork device for wellbore concrete pouring according to claim 1, characterized in that, The vertical support member includes a vertical support rod and a soil nail fixed at the lower end of the vertical support rod.

3. The formwork device for wellbore concrete pouring according to claim 1, characterized in that, In the installed state, the formwork body is arranged in an inclined manner with the top inward. The horizontal support member includes a first cross support rod and a second cross support rod. The second cross support rod is located below the first cross support rod and the length of the second cross support rod is greater than that of the first cross support rod.

4. The formwork device for wellbore concrete pouring according to claim 1, characterized in that, The fastener is composed of a first hoop and a second hoop connected together.

5. The formwork device for wellbore concrete pouring according to claim 4, characterized in that, The first hoop and the second hoop are rotatably connected.

6. The formwork device for wellbore concrete pouring according to claim 4 or 5, characterized in that, The first hoop and the second hoop have the same structure and both include a first hoop body, a second hoop body, an internal thread sleeve, and a locking bolt. One end of the first hoop body is rotatably connected to one end of the second hoop body. The internal thread sleeve is connected to the other end of the first hoop body. A notch for allowing the locking bolt to pass through is formed at the other end of the second hoop body. In the installed state, the locking bolt passes through the notch and is threadedly connected to the internal thread sleeve.

7. The formwork device for wellbore concrete pouring according to claim 6, characterized in that, An installation groove is formed at the other end of the first hoop body, and one end of the internal thread sleeve is rotatably installed in the installation groove through a connecting shaft.

8. The formwork device for wellbore concrete placement according to claim 6, wherein, A groove for cooperating with a gasket is formed on the outer side surface of the other end of the second hoop body.

9. The formwork device for wellbore concrete pouring according to claim 1, wherein, The device is made of steel.