Arch bridge steel tube concrete pumping device in deep-cutting canyon environment
By using a combination of multi-stage slurry pipe and secondary mixing device in a deep canyon environment, the transportation and quality problems of steel pipe concrete construction are solved, and rapid and continuous concrete supply and elimination of separation are achieved, ensuring construction quality.
Patent Information
- Application Number
- CN202422317653.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2025-07-25
- Estimated Expiration
- 2034-09-23
AI Technical Summary
In a deep canyon environment, it is difficult to transport steel pipe concrete directly to the arch foot position through a concrete tanker, resulting in construction difficulties and it is difficult to ensure the continuous supply and quality of concrete.
Multi-stage slurry pipe, slip pipe system and secondary mixing device are used to transport concrete along the slope of the mountain through the slip pipe system, and secondary mixing is carried out at the bottom to ensure the continuous supply and quality of concrete, and secondary mixing is used for secondary stirring and elimination of separation.
It realizes rapid and continuous concrete supply in a deep canyon environment, eliminates the phenomenon of separation, ensures the working performance of concrete, and solves construction problems.
Smart Images

Figure CN223151057U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete conveying. More specifically, the utility model relates to a pumping device for concrete-filled steel tubes of an arch bridge in a deep-cut canyon environment. Background Art
[0002] The concrete-filled steel tube arch bridge has the advantages of strong load-bearing capacity, low project cost, and convenient construction. In mountainous areas in the southwest of China and other places, long-span concrete-filled steel tube arch bridges are mostly used as the main channels for crossing rivers or deep-cut canyons. The main reason for the large load-bearing capacity of the concrete-filled steel tube arch bridge is that when the main arch is under compression, the steel tube and the concrete inside the tube interact to generate a hoop force, which improves the ultimate compressive strength of the concrete and the local buckling resistance of the steel tube. During the construction of the concrete-filled steel tube arch bridge, the steel tube is first erected, and after the steel tube is closed to form an arch, the concrete inside the tube is poured. The construction quality of the concrete inside the tube directly affects the load-bearing capacity of the main arch. Therefore, the construction of the concrete-filled steel tube is one of the most important construction processes of the concrete-filled steel tube arch bridge.
[0003] In plains or mountainous areas with good transportation conditions, when pouring concrete-filled steel tubes, the concrete inside the tube is usually transported to the arch foot by a concrete mixer truck first, and then the concrete inside the tube is constructed by the method of upward pumping. However, in the deep-cut canyon environment with poor geological conditions, it is very difficult to build a construction access road, and it is difficult for the concrete inside the tube to be directly transported to the arch foot position by a concrete mixer truck; moreover, to ensure the construction quality of the concrete inside the tube, the concrete inside a single tube needs to be constructed at one time, the amount of concrete inside the tube is large, and the construction time is long. This results in the fact that in the harsh environmental conditions with inconvenient transportation, it is difficult to construct the concrete-filled steel tube by conventional methods. In view of the above problems, it is urgent to propose a method for transporting concrete-filled steel tubes suitable for the deep-cut canyon environment to ensure the efficient and high-quality construction of the concrete inside the tube in the harsh natural environment. Summary of the Utility Model
[0004] An object of the utility model is to solve at least the above problems and provide at least the advantages described later.
[0005] To achieve these objects and other advantages in accordance with the present utility model, there is provided a pumping device for concrete-filled steel tubes of an arch bridge in a deep-cut canyon environment, including a multi-stage slurry inlet pipe arranged from the arch foot to the arch top of the arch bridge, and a hopper, a chute system, and a secondary mixing device connected in sequence; the hopper is arranged at the top of the mountain, the chute system is arranged along the slope of the mountain and fixed on the mountain, and the secondary mixing device is arranged at the bottom of the mountain; the chute system includes a chute and a discharging open trough and a feeding open trough respectively arranged at both ends of the chute; the chute is spliced by a plurality of thin-walled steel pipe segments, and notch openings are formed on the thin-walled steel pipe segments; the slurry inlet pipe is communicated with the corresponding steel tube of the arch bridge, and the output end of the secondary mixing device is connected with each stage of the slurry inlet pipe in sequence along the direction from the arch foot to the arch top.
[0006] Preferably, the thin-walled steel pipe segment is a conical thin-walled steel pipe with a larger diameter at one end and a smaller diameter at the other end.
[0007] Preferably, the difference between the diameters of the two ends of the thin-walled steel pipe segment is greater than the wall thickness of the thin-walled steel pipe segment.
[0008] Preferably, a cover plate is movably connected to the notch of the thin-walled steel pipe segment.
[0009] Preferably, when the slope of the mountain slope is greater than 60°, a plurality of stoppers are arranged on the inner wall of the thin-walled steel pipe segment, and the plurality of stoppers are arranged staggeredly.
[0010] Preferably, the secondary mixing device is a concrete mixer.
[0011] Preferably, the secondary mixing device is a concrete pump truck.
[0012] The utility model has at least the following beneficial effects:
[0013] The arch bridge concrete-filled steel tube pumping device provided by the utility model adopts a chute pipe to transport concrete, with fast transportation speed and short time, and can carry out large-volume concrete transportation; through the secondary mixing device for secondary mixing, it can not only ensure the continuity of concrete supply, but also effectively eliminate concrete segregation, ensure the working performance of concrete, and solve the problem of difficult construction of concrete-filled steel tubes in deep-cut canyon environments with inconvenient transportation.
[0014] Other advantages, objectives and features of the utility model will be partially reflected by the following description, and partially will be understood by those skilled in the art through the research and practice of the utility model. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic structural diagram of the arch bridge concrete-filled steel tube pumping device in the deep-cut canyon environment when the secondary mixing device of the utility model is a concrete mixer;
[0016] Figure 2 It is a schematic diagram of the installation position of the slurry inlet pipe of the utility model;
[0017] Figure 3 It is a schematic structural diagram of the arch bridge concrete-filled steel tube pumping device in the deep-cut canyon environment when the secondary mixing device of the utility model is a concrete pump truck;
[0018] Figure 4 It is a schematic structural diagram of the thin-walled steel pipe segment of the utility model;
[0019] Figure 5 It is a schematic structural diagram of the stopper of the utility model; Detailed implementation manners
[0020] The following further elaborates on the present utility model in conjunction with the accompanying drawings, so that those skilled in the art can implement it with reference to the text of the specification.
[0021] It should be noted that, unless otherwise specified, the experimental methods described in the following implementation schemes are all conventional methods, and the reagents and materials, unless otherwise specified, can all be obtained through commercial channels; in the description of the present utility model, the terms "horizontal", "longitudinal", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. It is only for the convenience of describing the present utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be construed as a limitation to the present utility model.
[0022] As Figures 1 to 5 shown, the present utility model provides a concrete pumping device for concrete-filled steel tubes of an arch bridge in a deep canyon environment, including a multi-stage slurry inlet pipe arranged from the arch feet to the arch crown of the arch bridge, and a hopper 1, a chute system, and a secondary stirring device connected in sequence; the hopper 1 is arranged at the top of the mountain body, the chute system is arranged along the slope of the mountain body and fixed on the mountain body, and the secondary stirring device is arranged at the bottom of the mountain body; the chute system includes a chute 3, and a discharging open trough 2 and a discharging open trough 5 respectively arranged at both ends of the chute; the chute 3 is spliced by a plurality of thin-walled steel pipe segments 31, and a notch 32 is opened on the thin-walled steel pipe segment 31; the slurry inlet pipe is communicated with the corresponding concrete-filled steel pipe of the arch bridge, and the output end of the secondary stirring device is connected to each stage of the slurry inlet pipe in sequence along the direction from the arch feet to the arch crown.
[0023] In this technical solution, the concrete-filled steel tube is transported to a position near the arch seat by a concrete mixer truck, unloaded into the hopper 1, enters the chute 3 through the discharging open trough 2, is transported downward along the slope through the chute 3 to the discharging open trough 5, then enters the secondary stirring device, and then the concrete is pumped into the grading slurry inlet pipe at the arch feet position through the secondary stirring device. As Figure 2In the example shown, there are four levels of slurry inlet pipes. In actual construction, the number of slurry inlet pipes is flexibly set according to the size of the arch bridge steel pipe, and the slurry inlet pipes of each level are connected to the arch bridge steel pipes at the corresponding height position. First, the output end of the secondary mixing device is connected to the primary slurry inlet pipe, and the steel tube concrete is pumped from the position of the primary slurry inlet pipe; when the concrete reaches the position of the secondary slurry inlet pipe, the connection between the secondary mixing device and the primary slurry inlet pipe is closed, and the secondary mixing device is connected to the secondary slurry inlet pipe, and the steel tube concrete is continued to be pumped from the position of the secondary slurry inlet pipe, and this is repeated until the steel tube concrete is pumped. The chute 3 is fixed on the mountain through multiple brackets, and its height from the slope surface is about 40cm; for areas with large local slope changes, the height of the bracket is adjusted to make the linear angle of the pipeline smaller, so as to reduce the impact effect during the concrete chute. The length of the thin-walled steel pipe segment 31 can be set to 2m, and the notch 32 is opened. Preferably, on the vertical section, the central angle α corresponding to the notch 32 can be set to 90°. Through the notch 32, it is possible to quickly clean and dredge the pipe when it is blocked. When the external environment temperature is high, the inner wall of the chute 3 is sprayed to form a moisture-retaining layer, thereby lowering the wall temperature and reducing the evaporation of concrete water.
[0024] In another technical solution, Figure 4 As shown, the thin-walled steel pipe segment 31 is a tapered thin-walled steel pipe with a larger diameter at one end than at the other end. Furthermore, the difference in diameter between the two ends of the thin-walled steel pipe segment 31 is larger than the wall thickness of the thin-walled steel pipe segment 31. This facilitates the splicing of the thin-walled steel pipe segments 31. Preferably, an internal thread can be provided on the inner wall of the large-diameter pipe opening of the thin-walled steel pipe segment 31, and a matching external thread can be provided on the outer wall of the small-diameter pipe opening.
[0025] In another technical solution, a cover plate is movably connected to the notch 32 of the thin-walled steel pipe segment 31. The cover plate can prevent the concrete water from evaporating too quickly and prevent rainwater from entering the chute 3.
[0026] In another technical solution, Figure 5 As shown, when the slope of the mountain is greater than 60°, a plurality of blocks 33 are arranged on the inner wall of the thin-walled steel pipe segment 31, and the plurality of blocks 33 are arranged in a staggered manner. The blocks 33 are helpful in slowing down the transportation speed of the concrete chute in the pipe, avoiding serious segregation of the steel pipe concrete and causing pipe blockage. Figure 4 As shown, the included angle between the stopper 33 and the inner wall of the thin-walled steel pipe segment 31 can be set to 30°~45°.
[0027] In another technical solution, Figure 1As shown, the secondary mixing device is a concrete mixer 6. The concrete filled steel tube enters the concrete mixer 6 through the discharge open trough 5 at the end of the chute 3. The concrete mixer 6 performs secondary mixing on the concrete transported by the chute to eliminate possible segregation phenomena. Using a concrete mixer for secondary mixing enables the concrete to enter from one end and be output from the other end after mixing, ensuring the continuous supply of concrete. The mixed concrete filled steel tube is pumped in stages from the arch foot position by a concrete pump truck 7.
[0028] In another technical solution, as Figure 3 shown, the secondary mixing device is a concrete pump truck 7. The concrete pump truck 7 is directly used for secondary mixing. The concrete filled steel tube enters the hopper of the concrete pump truck through the discharge open trough 5 at the end of the chute 3, and the concrete pump truck 7 performs secondary mixing on the concrete transported by the chute. During use, the hopper of the concrete pump truck 7 can be heightened to increase the stock of concrete in the concrete pump truck and ensure the continuity of the supply of the concrete filled steel tube.
[0029] Although the embodiments of the present utility model have been disclosed as above, it is not limited to only the applications listed in the description and the embodiments. It can be fully applied to various fields suitable for the present utility model. For those familiar with the field, additional modifications can be easily made. Therefore, without departing from the general concept defined by the claims and the equivalent scope, the present utility model is not limited to the specific details and the illustrated and described examples here.
Claims
1. An arch bridge concrete-filled steel tube pumping device in a deep-cut canyon environment, characterized in that, It includes multiple stages of slurry inlet pipes arranged from the arch feet to the arch crown of the arch bridge, as well as a hopper, a chute system, and a secondary stirring device connected in sequence; the hopper is arranged at the top of the mountain body, the chute system is arranged along the slope of the mountain body and fixed on the mountain body, and the secondary stirring device is arranged at the bottom of the mountain body; the chute system includes a chute and a discharging open trough and a feeding open trough respectively arranged at both ends of the chute; the chute is spliced by multiple thin-walled steel pipe segments, and notches are opened on the thin-walled steel pipe segments; the slurry inlet pipe is communicated with the corresponding arch bridge steel pipe, and the output end of the secondary stirring device is connected to each stage of the slurry inlet pipe in sequence along the direction from the arch feet to the arch crown.
2. The concrete pumping device for the concrete-filled steel tubular arch bridge in the deep canyon environment according to claim 1, wherein The thin-walled steel pipe segment is a conical thin-walled steel pipe with the diameter of one end pipe orifice larger than that of the other end pipe orifice.
3. The concrete pumping device for arch bridges in deep canyon environments as described in claim 2, wherein The difference between the diameters of the two end pipe orifices of the thin-walled steel pipe segment is greater than the wall thickness of the thin-walled steel pipe segment.
4. The concrete pumping device for arch bridge filled with concrete in steel tube under deep and narrow canyon environment as claimed in claim 1, wherein, A cover plate is movably connected to the notch of the thin-walled steel pipe segment.
5. The concrete pumping device for the concrete-filled steel tubular arch bridge in the deep canyon environment as claimed in claim 1, wherein, When the slope of the slope of the mountain body is greater than 60°, multiple blocking blocks are arranged on the inner wall of the thin-walled steel pipe segment, and the multiple blocking blocks are arranged staggeredly.
6. The concrete pumping device for concrete-filled steel tubular arch bridges in deep canyon environments according to claim 1, characterized in that The secondary stirring device is a concrete mixer.
7. The concrete pumping device for the concrete-filled steel tubular arch bridge in the deep canyon environment according to claim 1, wherein The secondary stirring device is a concrete pump truck.