Electromechanical installation pipeline equipment

By designing electromechanical and mechanical installation pipeline equipment with liftable bearing rods and clamping blocks, the problem of low installation efficiency in the existing technology is solved, flexible fixing and reasonable layout of the pipeline is realized, and the installation efficiency and scope of application are improved.

CN223152981UActive Publication Date: 2025-07-25许军
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422424631.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2025-07-25
Estimated Expiration
2034-10-09

AI Technical Summary

Technical Problem

The existing mechanical and electrical mounting frame is fixed, resulting in low pipeline installation efficiency. Bolts need to be inserted on both sides of the pipeline for limiting, which is troublesome.

Method used

An electromechanical installation pipeline equipment including a hoisting rod, a vertical rod and a load bearing rod is designed. The vertical rod is a hollow structure. The hoisting rod can slide above the vertical rod. A clamping groove and an adjustable clamping block are provided on the load bearing rod. By cooperating the adjustment rod and the clamping block, the flexible fixing of the pipeline is achieved.

Benefits of technology

It realizes adaptive adjustment according to the height requirements of pipeline layout, avoids collision between pipelines and other pipelines, improves the rationality of pipeline layout and installation efficiency, and has high flexibility in adjusting clamping blocks, which is suitable for pipeline fixation of different diameters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223152981U_ABST
    Figure CN223152981U_ABST
Patent Text Reader

Abstract

The utility model discloses electromechanical pipeline installation equipment, belongs to the technical field of electromechanical engineering, and aims at solving the problems that in the prior art, an installation frame is fixed in structure, pipeline installation efficiency is low, bolts need to be screwed into the two sides of a pipeline for limiting, and operation is troublesome. Comprising a hoisting rod, vertical rods, a bearing rod and a fixing mechanism, the bearing rod is horizontally arranged, the vertical rods are vertically arranged on the two sides of the upper surface of the bearing rod, the interiors of the vertical rods are of hollow structures, and the hoisting rod vertically slides in along the upper portions of the vertical rods; the fixing structure is mounted between the two vertical rods; a plurality of clamping grooves are horizontally formed in the upper surface of the bearing rod and distributed at intervals, and two sets of clamping blocks moving relatively are arranged in each clamping groove. According to the electromechanical pipeline installation equipment, adaptive adjustment can be carried out according to the height requirement of pipeline arrangement, when pipelines are hoisted and arranged on a roof, collision with other pipelines can be avoided, and the pipeline arrangement reasonability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of mechatronic engineering, and particularly relates to a mechatronic installation pipeline device. Background Technique

[0002] Mechatronic pipelines are an indispensable part of mechatronic installation projects. They involve multiple professional fields, such as electricity, water supply and drainage, heating, ventilation and air conditioning, etc. These pipelines are intricate and intertwined inside buildings, jointly maintaining the normal operation of buildings. Mechatronic pipelines are a crucial part of mechatronic installation projects. Through reasonable layout, advanced construction techniques, and regular maintenance and upkeep, the normal operation of mechatronic pipelines can be ensured and their service life can be extended, thus providing strong guarantee for the normal operation of buildings. During the installation process of mechatronic pipelines, they need to be arranged along the wall. During hoisting, the pipelines need to be attached to the ceiling of the wall and an installation rack is used to support the pipelines. The installation rack is fixed to the ceiling of the wall, and then the pipelines are connected to the installation rack. However, the current structure of the installation rack is fixed, resulting in low installation efficiency for pipelines. Bolts need to be driven on both sides of the pipelines for limiting, which is troublesome to operate. Therefore, the inventor proposes a mechatronic installation pipeline device. Content of the Utility Model

[0003] (1) Technical Problems to be Solved

[0004] Aiming at the deficiencies of the prior art, the purpose of the utility model is to provide a mechatronic installation pipeline device, aiming to solve the problems that the structure of the existing installation rack is fixed, the installation efficiency of pipelines is low, bolts need to be driven on both sides of the pipelines for limiting, and the operation is troublesome.

[0005] (2) Technical Solutions

[0006] To solve the above technical problems, the utility model provides such a mechatronic installation pipeline device, which includes a hoisting rod, a vertical rod, a bearing rod, and a fixing mechanism. The bearing rod is horizontally arranged, and the vertical rods are vertically arranged on both sides of the upper surface of the bearing rod. The inside of the vertical rod is a hollow structure, and the hoisting rod slides vertically into the upper part of the vertical rod; the fixing structure is installed between the two vertical rods; a plurality of clamping grooves are horizontally opened on the upper surface of the bearing rod, and the plurality of clamping grooves are spaced apart. Two sets of relatively moving clamping blocks are respectively arranged in each clamping groove, and an adjusting rod is rotatably penetrated through the side wall of the bearing rod, and the end of the adjusting rod extends into the clamping groove. Thanks to the setting of the liftable bearing rod, it can be adaptively adjusted according to the height requirements of pipeline layout. When hoisting and arranging pipelines on the roof, collision with other pipelines can be avoided, and the rationality of pipeline layout can be improved.

[0007] Preferably, one end of the adjusting rod penetrating into the clamping groove is fixedly connected with a driving bevel gear, and the driving bevel gear is concentric with the adjusting rod.

[0008] Preferably, a driven bevel gear is provided beside the driving bevel gear, and the driven bevel gear is vertically distributed in engagement with the driving bevel gear.

[0009] Preferably, a driving screw rod is fixedly passed through the middle of the driven bevel gear. Both ends of the driving screw rod are respectively rotatably connected to the inner wall of the clamping groove. The driving screw rod is threadedly connected to the bottom of the clamping block. The clamping block has a T-shaped structure and its bottom penetrates into the clamping groove.

[0010] Preferably, the fixing mechanism includes a fixing rod and an inserting rod. The fixing rod is fixedly connected to the inner side wall of the vertical rod. An inserting rod is movably installed on the surface of the fixing rod facing the vertical rod. A jack adapted to the inserting rod is provided on the side wall of the hoisting rod, and the inserting rod passes through the vertical rod and is inserted into the jack in an adapted manner.

[0011] Preferably, a moving groove is horizontally opened on the upper surface of the bearing rod. A fixing block is fixedly installed in the middle of the moving groove. Springs are respectively connected to both sides of the fixing block. One end of the spring away from the fixing block is fixedly connected to an operating block.

[0012] Preferably, the operating block slides along the moving groove, and the surface of the operating block away from the spring is fixedly connected to the inserting rod.

[0013] (3) Beneficial effects

[0014] Compared with the prior art, the beneficial effects of the present utility model are as follows:

[0015] Benefiting from the setting of the liftable bearing rod, it can be adaptively adjusted according to the height requirements of pipeline layout. When hoisting and arranging pipelines on the roof, it can avoid collision with other pipelines, improve the rationality of pipeline layout, and the height adjustment operation of the bearing rod is convenient. Benefiting from the setting of the clamping block, when the pipeline is installed on the bearing rod, rotate the adjusting rod, and the two clamping blocks move relatively closer to clamp both sides of the pipeline, playing a role of limiting and fixing, which is applicable to fixing pipelines with different diameters. The adjustment of the clamping block is highly flexible and has a wide application range, and can be widely promoted. Description of the drawings

[0016] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the following will briefly introduce the drawings required for use in the description of the embodiments or the prior art. Obviously, the following drawings are only some embodiments of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative efforts.

[0017] Figure 1 is a structural schematic diagram of the present utility model;

[0018] Figure 2 is a structural schematic diagram of the fixing mechanism;

[0019] Figure 3 is Figure 2 The enlarged structural schematic diagram at position A in

[0020] Figure 4 the structural schematic diagram of the clamping block.

[0021] The reference signs in the drawings are: 1, lifting rod; 2, bearing rod; 3, vertical rod; 4, jack; 5, fixing mechanism; 6, clamping groove; 7, clamping block; 8, adjusting rod; 9, operating block; 10, inserting rod; 11, moving groove; 12, fixing block; 13, fixing rod; 14, spring; 15, driving bevel gear; 16, driving screw; 17, driven bevel gear. Specific embodiments

[0022] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0023] This specific embodiment is a mechanical and electrical installation pipeline device, and its structural schematic diagram is as Figure 1 shown, including a lifting rod 1, a vertical rod 3, a bearing rod 2 and a fixing mechanism 5. It is characterized in that the bearing rod 2 is horizontally arranged, the vertical rod 3 is vertically arranged on both sides of the upper surface of the bearing rod 2, the inside of the vertical rod 3 is a hollow structure, and the lifting rod 1 vertically slides into the upper part of the vertical rod 3; the fixing structure is installed between the two vertical rods 3; a plurality of clamping grooves 6 are horizontally opened on the upper surface of the bearing rod 2, the plurality of clamping grooves 6 are spaced apart, and two sets of relatively moving clamping blocks 7 are respectively arranged in each clamping groove 6, and an adjusting rod 8 is rotatably inserted into the side wall of the bearing rod 2, and the end of the adjusting rod 8 extends into the clamping groove 6.

[0024] Referring to Figure 3 , the fixing mechanism 5 includes a fixing rod 13 and an inserting rod 10. The fixing rod 13 is fixedly connected to the inner side wall of the vertical rod 3, an inserting rod 10 is movably installed on the surface of the fixing rod 13 facing the vertical rod 3, a jack 4 adapted to the inserting rod 10 is opened on the side wall of the lifting rod 1, and the inserting rod 10 passes through the vertical rod 3 and is adaptively inserted into the jack 4. A moving groove 11 is horizontally opened on the upper surface of the bearing rod 2, a fixing block 12 is fixedly installed in the middle of the moving groove 11, two springs 14 are respectively connected to both sides of the fixing block 12, and one end of the spring 14 away from the fixing block 12 is fixedly connected to an operating block 9. The operating block 9 slides along the moving groove 11, and the surface of the operating block 9 away from the spring 14 is fixedly connected to the inserting rod 10.

[0025] Referring to Figure 4, one end of the adjusting rod 8 passing through the inside of the clamping groove 6 is fixedly connected with a driving bevel gear 15, and the driving bevel gear 15 is concentrically distributed with the adjusting rod 8. A driven bevel gear 17 is arranged beside the driving bevel gear 15, and the driven bevel gear 17 is meshed with the driving bevel gear 15 and vertically distributed. A driving screw rod 16 is fixedly passed through the middle part of the driven bevel gear 17. Both ends of the driving screw rod 16 are respectively rotatably connected to the inner wall of the clamping groove 6. The driving screw rod 16 is threadedly connected to the bottom of the clamping block 7. The clamping block 7 is of a T-shaped structure, and the bottom penetrates into the clamping groove 6.

[0026] Working principle: When in use, first fixedly install the hoisting rod 1 on the inner wall of the top of the wall. Subsequently, according to the installation height of the pipeline, adjust the height of the vertical rod 3. Slide the vertical rod 3 along the outside of the hoisting rod 1. Before sliding the vertical rod 3, first pull the two operating blocks 9 in the opposite direction of the fixed block 12. The spring 14 is compressed under force. The operating block 9 drives the insertion rod 10 to retract into the inside of the fixed rod 13. After the insertion rod 10 leaves the inside of the jack 4, the vertical rod 3 can be moved. After adjusting to the required height, release the pulling of the operating block 9. The spring 14 elastically returns. The operating block 9 pushes the insertion rod 10 into the jack 4 at the corresponding position, completing the height adjustment of the bearing rod 2. Subsequently, install the mechanical and electrical pipeline on the bearing rod 2. Clamping blocks 7 are symmetrically distributed on both sides of the pipeline. Rotate the adjusting rod 8. The adjusting rod 8 drives the driving bevel gear 15 to rotate. The driven bevel gear 17 rotates under force. Further, the driving screw rod 16 rotates accordingly. Threadedly cooperating with the clamping block 7, the clamping block 7 moves closer as the driving screw rod 16 rotates. The threads on the outer wall of the driving screw rod 16 are arranged in the opposite direction. Therefore, the two clamping blocks 7 move closer relatively, clamping both sides of the pipeline, playing a role of limiting and fixing.

[0027] Finally, it should be noted that the above are only the preferred embodiments of the present invention and are not used to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, they can still modify the technical solutions recorded in the foregoing embodiments, or perform equivalent replacements for some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An electromechanical installation pipeline device, comprising a hoisting rod (1), a vertical rod (3), a bearing rod (2) and a fixing mechanism (5), characterized in that, The bearing rod (2) is horizontally arranged, the vertical rod (3) is vertically arranged on both sides of the upper surface of the bearing rod (2), the inside of the vertical rod (3) is a hollow structure, and the hoisting rod (1) vertically slides into the vertical rod (3) from above; The fixing mechanism is installed between the two vertical rods (3); A plurality of clamping grooves (6) are horizontally formed on the upper surface of the bearing rod (2), the plurality of clamping grooves (6) are spaced apart from each other, and two groups of relatively moving clamping blocks (7) are respectively arranged in each clamping groove (6). An adjusting rod (8) is rotatably inserted into the side wall of the bearing rod (2), and the end of the adjusting rod (8) extends into the clamping groove (6).

2. An electromechanical installation pipeline device according to claim 1, characterized in that, One end of the adjusting rod (8) penetrating into the inside of the clamping groove (6) is fixedly connected with a driving bevel gear (15), and the driving bevel gear (15) is concentric with the adjusting rod (8).

3. An electromechanical installation pipeline device according to claim 2, characterized in that, A driven bevel gear (17) is arranged beside the driving bevel gear (15), and the driven bevel gear (17) is meshed with the driving bevel gear (15) and vertically distributed.

4. An electromechanical installation pipeline device according to claim 3, characterized in that, A driving screw rod (16) is fixedly penetrated through the middle part of the driven bevel gear (17). The two ends of the driving screw rod (16) are respectively rotatably connected to the inner wall of the clamping groove (6). The driving screw rod (16) is threadedly connected to the bottom of the clamping block (7). The clamping block (7) has a T-shaped structure, and the bottom penetrates into the clamping groove (6).

5. An electromechanical installation pipeline device according to claim 1, characterized in that, The fixing mechanism (5) includes a fixing rod (13) and an inserting rod (10). The fixing rod (13) is fixedly connected to the inner side wall of the vertical rod (3). An inserting rod (10) is movably installed on the surface of the fixing rod (13) facing the vertical rod (3). A jack (4) adapted to the inserting rod (10) is formed on the side wall of the hoisting rod (1), and the inserting rod (10) passes through the vertical rod (3) and is inserted into the jack (4) in an adapted manner.

6. An electromechanical installation pipeline device according to claim 5, characterized in that, A moving groove (11) is horizontally formed on the upper surface of the bearing rod (2). A fixing block (12) is fixedly installed in the middle of the moving groove (11). Springs (14) are respectively connected to both sides of the fixing block (12). One end of the spring (14) far from the fixing block (12) is fixedly connected to an operating block (9).

7. An electromechanical installation pipeline device according to claim 6, characterized in that, The operating block (9) slides along the moving groove (11), and one side of the operating block (9) far from the spring (14) is fixedly connected to the inserting rod (10).