Bathroom caisson structure based on light brick backfilling
By adopting a combined structure of lightweight bricks and foamed concrete layers in the bathroom caisson, the problems of water seepage and odor are solved, costs are reduced, and structural stability and drainage efficiency are improved, adapting to modern construction needs and providing a comfortable and safe living environment.
Patent Information
- Application Number
- CN202422953730.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-02
- Publication Date
- 2025-10-10
- Estimated Expiration
- 2034-12-02
AI Technical Summary
The existing bathroom caisson structure is prone to water seepage during use, increasing the load and causing odor. In addition, the traditional foamed concrete filling cost is high, making it difficult to reduce construction costs while ensuring quality.
The structural design adopts lightweight brick backfill combined with foamed concrete layer, including a waterproof layer, lightweight brick layer, foamed concrete layer, installation cavity, water guide groove and waterproof layer. Lightweight materials are used to reduce the structural weight and the water guide groove and waterproof layer are used to prevent water penetration. The inner casing is combined to prevent backflow, thereby enhancing structural stability and drainage efficiency.
It reduces construction costs while improving structural stability and drainage efficiency, preventing water seepage and odor, extending service life and enhancing safety.
Smart Images

Figure CN223423560U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction, in particular to a bathroom caisson structure based on light brick backfill. Background Art
[0002] The main design and construction of existing floor bathrooms generally adopt a caisson-type bathroom design structure. The caisson is generally backfilled with construction waste. After the bathroom caisson is backfilled, a cavity needs to be opened above the backfill layer to place the squat toilet. The current cavity is generally opened directly by manually digging the backfill layer. The cavity of this structure is prone to water seepage problems, increasing the load on the bathroom, and easily causing odor after long-term use.
[0003] For fine-decorated houses with higher quality requirements, lightweight foamed cement is generally used in batches to backfill the bottom of the bathroom box in an integrated foamed manner. However, using foamed concrete for all fillings will increase costs. Therefore, how to further reduce construction costs while ensuring the same construction quality is a challenge that needs to be faced. Utility Model Content
[0004] In response to the above problems, the utility model provides a bathroom caisson structure based on lightweight brick backfill, which is used to solve the problems of the existing bathroom caisson structure being prone to water seepage after long-term use, increasing the bathroom load, and easily returning odor. It can increase drainage efficiency, avoid blockage or leakage of drainage pipes, and further reduce construction costs while ensuring construction quality.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] The bathroom caisson structure based on lightweight brick backfill includes a waterproof layer arranged on the inner wall of the caisson, a lightweight brick layer arranged on the waterproof layer at the bottom of the caisson, and a foamed concrete layer arranged on the lightweight brick layer; an installation cavity cooperating with a squat toilet is arranged on the foamed concrete layer; a sewer pipe is arranged in the installation cavity; a water guide groove is distributed on the foamed concrete layer, one end of the water guide groove is connected to the installation cavity; a waterproof layer is arranged on the surface of the foamed concrete layer, the water guide groove and the installation cavity; sand and gravel are filled in the water guide groove; a mortar layer is arranged on the waterproof layer of the foamed concrete layer, and a decorative brick layer is arranged on the mortar layer; a water hole is opened on the side wall of the sewer pipe.
[0007] As a further improvement of the above solution, a groove is provided on the lightweight brick layer; the groove is filled with a foamed concrete layer; and the installation cavity is located above the groove.
[0008] The technical effect of this improvement is that it enhances the overall stability of the structure while reducing its weight. Because both lightweight bricks and foamed concrete are lightweight materials, the groove design further reduces the amount of foamed concrete required and allows the foamed concrete layer to be tightly bonded to the lightweight brick layer, improving the structure's load-bearing capacity.
[0009] As a further improvement of the above solution, the waterproof layer forms a closed cavity; the lightweight brick layer and the foamed concrete layer are both located in the cavity.
[0010] The technical effect of the above improvement is: by forming a closed waterproof cavity, it can effectively prevent moisture from penetrating, protect the structure from moisture erosion, reduce the load on the bathroom, and extend the service life.
[0011] As a further improvement of the above solution, mortar or foamed concrete is filled between the installation cavity and the squat toilet.
[0012] The technical effect of the above improvement is that this filling method can ensure the installation stability of the squat toilet.
[0013] As a further improvement of the above solution, a mortar layer is provided above the waterproof layer above the foamed concrete layer, and a decorative brick layer is provided above the mortar layer.
[0014] The technical effects of the above improvements are: increasing the aesthetics of the structure, while the mortar layer and the decorative brick layer provide additional protection to prevent the upper structure from causing damage to the waterproof layer.
[0015] As a further improvement of the above solution, an inner sleeve is sleeved inside the upper end of the sewer pipe; the diameter of the inner sleeve is smaller than the inner diameter of the sewer pipe, so that a gap is formed between the inner sleeve and the sewer pipe; the water hole is located higher than the lower end of the inner sleeve.
[0016] The technical effect of the above improvement is: this design can prevent the water in the squat toilet from returning to the installation cavity through the water hole, eliminating the odor problem, and at the same time allows the water entering the water hole from the installation cavity to flush the sewer pipe, preventing the excrement in the sewer pipe from clumping and causing blockage.
[0017] As a further improvement of the above solution, a groove is left in the lightweight brick layer for the installation of the horizontal section of the sewer pipe; and the lightweight bricks located above the horizontal section are placed on both sides of the lightweight bricks on both sides of the sewer pipe, so that the horizontal section of the sewer pipe will not be squeezed by the upper layer of lightweight bricks.
[0018] The technical effect of the above improvements is that it can protect the sewer pipes from being compressed by the superstructure, reduce the risk of pipe deformation and damage, and ensure the smoothness and safety of the drainage system.
[0019] Compared with the prior art, the utility model has the following technical effects:
[0020] The utility model discloses through above-mentioned improvement, realized light, waterproof effect, reduced construction cost simultaneously, improved construction efficiency and quality, prolonged the service life of building, and strengthened the stability and security of structure. These improvements jointly act, make the bathroom caisson structure more adapt to the demand of modern building, provide more comfortable, safe and economic living environment for the user. BRIEF DESCRIPTION OF DRAWINGS
[0021] Figure 1 It is the sectional view structural schematic drawing of the utility model.
[0022] Figure 2 It is the overhead structure schematic drawing of foamed concrete layer.
[0023] Figure 3 It is the sectional view structural schematic drawing of the inner sleeve pipe in sewer pipe.
[0024] Figure 4 It is the sectional structure schematic drawing of water guide groove.
[0025] Figure 5 It is the installation structure schematic drawing of the horizontal section of sewer pipe or floor drain pipe in light brick layer.
[0026] In the drawing: 1, sewage pipe, 2, foamed concrete layer, 3, floor drain pipe, 4, mortar layer, 5, waterproof layer, 6, installation cavity, 7, squatting closet, 8, decorative brick layer, 9, sewer pipe, 10, light brick layer, 11, water guide groove, 12, sandstone, 91, water hole, 92, inner sleeve pipe. DETAILED DESCRIPTION
[0027] In order to make the person skilled in the art better understand the technical scheme, the utility model is described in detail below in conjunction with examples, and the description of this part is only exemplary and explanatory, and should not have any limit to the protection scope of the utility model.
[0028] As Figures 1-5As shown, the specific scheme of this embodiment is: a bathroom caisson structure based on lightweight brick backfill, including a waterproof layer 5 arranged on the inner wall of the caisson, a lightweight brick layer 10, that is, lightweight foam bricks, is arranged on the waterproof layer 5 at the bottom of the caisson, and a foamed concrete layer 2 is arranged on the lightweight brick layer 10; an installation cavity 6 cooperating with the squat toilet 7 is arranged on the foamed concrete layer 2; a sewer pipe 9 is arranged in the installation cavity 6; a water guide groove 11 is distributed on the foamed concrete layer 2, and one end of the water guide groove 11 is connected to the installation cavity 6; a waterproof layer 5 is arranged on the surface of the foamed concrete layer 2, the water guide groove 11 and the installation cavity 6; sand and gravel 12 are filled in the water guide groove 11; a mortar layer 4 is arranged on the waterproof layer 5 of the foamed concrete layer 2, and a decorative brick layer 8 is arranged on the mortar layer 4; a water hole 91 is opened on the side wall of the sewer pipe 9 near the bottom of the installation cavity 6.
[0029] Specifically, a waterproof layer 5 is first applied to the bottom and side walls of the caisson. After the waterproof layer 5 is dry, lightweight bricks are filled in the caisson. Lightweight bricks are generally honeycomb bricks. When filling lightweight bricks, be careful to avoid the positions of the floor drain pipe 3, the sewage pipe 1, and the sewer pipe 9. A foamed concrete layer 2 is filled above the lightweight brick layer 10. The thickness of the foamed concrete layer 2 is generally greater than the height of the squat toilet 7. An installation cavity 6 is opened above the foamed concrete layer 2 for installing the squat toilet 7. At the same time, a water guide groove 11 is opened on the foamed concrete layer 2. The water guide groove 11 is radially centered around the installation cavity 6. Distribution; the water guide groove 11 is used to guide the moisture that has penetrated into the foamed concrete layer 2 into the installation cavity 6 for drainage; a waterproof layer 5 is arranged above the foamed concrete layer 2, and the waterproof layer 5 is also located on the surface of the water guide groove 11 and the installation cavity 6, which can prevent moisture from penetrating into the foamed concrete layer 2, and finally a mortar layer 4 is filled above the foamed concrete layer 2, and then the decorative brick layer 8 is installed. The decorative brick layer 8 is generally a ceramic tile. The cross-section of the water guide groove 11 generally adopts a V-shaped structure, which is filled with sand and gravel 12, and the diameter of the sand and gravel 12 at the bottom is larger than the diameter of the sand and gravel 12 in the upper layer.
[0030] like Figure 1 As shown, as a preferred embodiment of the above embodiment, a groove is provided on the lightweight brick layer 10; the groove is filled with a foamed concrete layer 2; and the mounting cavity 6 is located above the groove. To increase the use of lightweight bricks, reduce the use of foamed concrete, reduce costs, and further improve structural stability, a rectangular groove can be provided on the lightweight brick layer 10, filled with foamed concrete, and finally, the mounting cavity 6 is located above the groove.
[0031] like Figure 1As shown, as a preferred embodiment of the above embodiment, the waterproof layer 5 forms a closed cavity; the lightweight brick layer 10 and the foamed concrete layer 2 are both located within the cavity. Specifically, the waterproof layer 5 above the foamed concrete layer 2 and the waterproof layers 5 on the side walls and bottom of the caisson together form a closed cavity, preventing moisture from penetrating into the foamed concrete layer 2 and the lightweight brick layer 10. This allows moisture in the bathroom to penetrate only below the mortar layer 4. This moisture can then enter the installation cavity 6 through the water guide groove 11 and finally drain through the water hole 91 into the sewer pipe 9.
[0032] As a preferred embodiment of the above embodiment, mortar or foamed concrete is filled between the mounting cavity 6 and the squat toilet 7. To improve the structural stability of the squat toilet 7, the mounting cavity 6 is filled with mortar or foamed concrete, the squat toilet 7 is installed in the mounting cavity 6, and the excess mortar or foamed concrete that is squeezed out is removed.
[0033] like Figure 1 As shown, as a preferred embodiment of the above embodiment, a mortar layer 4 is provided above the waterproof layer 5 above the foamed concrete layer 2, and a decorative brick layer 8 is provided above the mortar layer 4. This is for installing the decorative brick layer 8, which is generally ceramic tiles.
[0034] like Figure 3 As shown, as a preferred embodiment of the above embodiment, an inner sleeve 92 is sleeved inside the upper end of the downpipe 9; the diameter of the inner sleeve 92 is smaller than the inner diameter of the downpipe 9, so that a gap is formed between the inner sleeve 92 and the downpipe 9; and the water hole 91 is positioned higher than the lower end of the inner sleeve 92. The drain outlet of the squat toilet 7 is connected to the upper end of the inner sleeve 92, so that flushing water from the squat toilet 7 is discharged from the inner sleeve into the downpipe 9; the inner sleeve 92 is used to isolate the sewage from the squat toilet 7 from the water hole 91, preventing water from flowing back into the installation cavity 6; and the water immersed in the installation cavity 6 is discharged from the water hole 91 into the downpipe 9, thereby draining the water in the installation cavity 6 and allowing the water in the installation cavity 6 to flush the inner wall of the downpipe 9.
[0035] like Figure 5 As shown, as a preferred embodiment of the above embodiment, a groove is left in the lightweight brick layer 10 for the installation of the horizontal section of the sewer pipe 9; and the lightweight bricks located above the horizontal section are placed on both sides of the lightweight bricks on both sides of the sewer pipe 9, so that the horizontal section of the sewer pipe 9 will not be squeezed by the upper lightweight bricks.
[0036] The specific working principle of this utility model:
[0037] Lightweight bricks are used to fill the toilet caisson, reducing the amount of foamed concrete used and lowering costs. Lightweight bricks are used to shape the overall structure, improving the installation stability of the squat toilet 7 while also reducing pressure on the water pipes and the load on the toilet. An inner sleeve 92 is used to isolate the flushing water of the squat toilet 7 from the installation cavity 6, preventing the flushing water of the squat toilet 7 from entering the installation cavity 6 while also removing moisture from the installation cavity 6.
[0038] It should be noted that, in this article, the terms include, contain or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. Specific examples are used herein to illustrate the principles and implementation methods of the technical solution of the present utility model. The above examples are only used to help understand the method of the present utility model and its core idea. The above is only a preferred embodiment of the present utility model. It should be pointed out that due to the limitations of textual expression and the objective existence of infinite specific structures, ordinary technicians in this technical field can make several improvements, modifications or changes without departing from the principles of the present utility model, and can also combine the above technical features in an appropriate manner; these improvements, modifications, changes or combinations, or the direct application of the concept and technical solution of the utility model to other occasions without improvement, should all be regarded as the scope of protection of the present utility model.
Claims
1. A bathroom caisson structure based on lightweight brick backfill, comprising a waterproof layer (5) arranged on the inner wall of the caisson, characterized in that: A lightweight brick layer (10) is arranged on the waterproof layer (5) at the bottom of the caisson, and a foamed concrete layer (2) is arranged on the lightweight brick layer (10); a mounting cavity (6) matched with a squat toilet (7) is arranged on the foamed concrete layer (2); a downpipe (9) is arranged in the mounting cavity (6); a water guide groove (11) is distributed on the foamed concrete layer (2), and one end of the water guide groove (11) is connected to the mounting cavity (6); a waterproof layer (5) is arranged on the surface of the foamed concrete layer (2), the water guide groove (11) and the mounting cavity (6); a mortar layer (4) is arranged on the waterproof layer (5) of the foamed concrete layer (2), and a decorative brick layer (8) is arranged on the mortar layer (4); a water hole (91) is opened on the side wall of the downpipe (9).
2. The bathroom caisson structure based on lightweight brick backfill according to claim 1 is characterized in that: A groove is provided on the lightweight brick layer (10); the groove is filled with a foamed concrete layer (2); and the installation cavity (6) is located above the groove.
3. The bathroom caisson structure based on lightweight brick backfill according to claim 1 is characterized in that: The waterproof layer (5) forms a closed cavity; the lightweight brick layer (10) and the foamed concrete layer (2) are both located in the cavity.
4. The bathroom caisson structure based on lightweight brick backfill according to claim 1 is characterized in that: The space between the installation cavity (6) and the squat toilet (7) is filled with mortar or foamed concrete.
5. The bathroom caisson structure based on lightweight brick backfill according to claim 1 is characterized in that: A mortar layer (4) is provided above the waterproof layer (5) above the foamed concrete layer (2), and a decorative brick layer (8) is provided above the mortar layer (4).
6. The bathroom caisson structure based on lightweight brick backfill according to claim 1 is characterized in that: An inner sleeve (92) is sleeved inside the upper end of the downpipe (9); the diameter of the inner sleeve (92) is smaller than the inner diameter of the downpipe (9), so that a gap is formed between the inner sleeve (92) and the downpipe (9); and the water hole (91) is positioned higher than the lower end of the inner sleeve (92).
7. The bathroom caisson structure based on lightweight brick backfill according to claim 1 is characterized in that: A groove is left in the lightweight brick layer (10) for installing the horizontal section of the sewer pipe (9); and the lightweight bricks located above the horizontal section are placed on both sides of the lightweight bricks on both sides of the sewer pipe (9), so that the horizontal section of the sewer pipe (9) will not be squeezed by the upper layer of lightweight bricks.