Traveling road for crossing underground pipe culvert and drainage ditch pipe
By constructing a driving walkway through stacked support structures and combined high-strength crossing pavement, the problems of high construction cost and long construction period for heavy machinery crossing underground culverts and drainage ditches are solved, the passage and drainage functions of heavy machinery are realized, and the structure is disassembled and reused.
Patent Information
- Application Number
- CN202422902016.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-27
- Publication Date
- 2025-10-17
- Estimated Expiration
- 2034-11-27
AI Technical Summary
At the construction site, when heavy machinery needs to cross underground culverts and drainage ditches, the existing design cannot meet the load demands of heavy machinery and drainage requirements at the same time. In addition, the construction cost of traditional bridge structures is high, the construction cycle is long, and they cannot be reused.
A stacked support structure and a combined high-strength spanning pavement are adopted. The driving walkway is constructed by precast concrete cubes and I-beams. Combined with a buffer protection layer and isolation joints, a detachable spanning structure is formed, which is supported above the underground culvert and drainage ditch.
It significantly reduces construction costs, shortens construction periods, enables the passage of heavy machinery and drainage functions, and the structure can be reused, avoiding damage to the original underground structure.
Smart Images

Figure CN223445918U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to a traffic convenient road, especially a traffic convenient road for crossing underground pipe culvert and drainage ditch pipe belongs to road reconstruction engineering structure design construction technical field. BACKGROUND
[0002] At present, when heavy construction machinery passes through the culvert and underground drainage pipe position of the construction site, the water ditch is usually diverted, and the original water ditch is relocated to other positions, then the original culvert and drainage ditch can be abandoned, so that the heavy construction machinery can directly cross or stop on the existing drainage ditch and culvert. However, if the construction space is very limited, there is no space to relocate the culvert and drainage ditch, and the rainfall in this area is very large, which needs to be drained in time. At this time, the original drainage ditch and culvert need to be continued to be used, and the original designed drainage ditch and culvert cannot bear the load of heavy machinery. What measures should be taken to protect the existing drainage ditch and culvert to ensure smooth drainage and meet the requirements of heavy construction machinery walking and stopping becomes a technical problem that needs to be solved by the technical personnel in the field.
[0003] At present, when large machinery needs to cross the underground structure to be protected, the bridge structure principle is usually used to cross the underground structure to be protected by using a small bridge to ensure that the load of large machinery is not transmitted to the underground drainage structure. When the small bridge crossing structure construction is carried out, the method of on-site binding reinforcement and on-site pouring concrete is usually used. However, the method of cast-in-place reinforced concrete needs a certain time to form the structure strength, and the structure cannot be reused, which is a one-time use structure, and the construction cost is significantly increased. UTILITY MODEL CONTENTS
[0004] The technical problem to be solved by the utility model is to provide a traffic convenient road for crossing underground pipe culvert and drainage ditch pipe, which can significantly reduce the construction cost and significantly shorten the construction period.
[0005] The technical scheme adopted to solve the above technical problem is: a traffic convenient road for crossing underground pipe culvert and drainage ditch pipe, including underground pipe culvert and / or drainage ditch pipe, the traffic convenient road further includes a stacked support structure and a combined high-strength crossing road surface, the combined high-strength crossing road surface is arranged above the underground pipe culvert and / or drainage ditch pipe through the stacked support structure; a buffer protection layer is further filled below the combined high-strength crossing road surface, and a separation joint with a height not less than 100mm is arranged between the buffer protection layer and the combined high-strength crossing road surface.
[0006] Further, the said traffic access road further comprises excavated and compacted foundation pits arranged on both sides of the underground pipe culvert and / or the drainage ditch pipe along the width direction, the stacked support structures are arranged on both sides of the underground pipe culvert and / or the drainage ditch pipe through the respective excavated and compacted foundation pits, and the combined high-strength crossing road surface is arranged above the underground pipe culvert and / or the drainage ditch pipe through the stacked support structures arranged on the respective excavated and compacted foundation pits.
[0007] Preferably, the distance between the adjacent two excavated and compacted foundation pits along the width direction of the underground pipe culvert and / or the drainage ditch pipe is not less than 1.5 times the width of the underground pipe culvert and / or the drainage ditch pipe, and a filling and compacting layer is arranged at the bottom of each excavated and compacted foundation pit, and the thickness of the filling and compacting layer is not less than 50 mm.
[0008] Further, the stacked support structure comprises at least six concrete prefabricated cubic blocks, each of the concrete prefabricated cubic blocks is stacked in a pyramid shape in two groups to form two stacked support piers, one stacked support pier is arranged on each side of the underground pipe culvert and / or the drainage ditch pipe, and the two ends of the combined high-strength crossing road surface are supported on the two stacked support piers respectively.
[0009] Preferably, each of the concrete prefabricated cubic blocks is a cube or a cuboid, each stacked support pier comprises at least two layers of the concrete prefabricated cubic blocks along the height direction, and each stacked support pier comprises at least three concrete prefabricated cubic blocks along the width direction of the traffic access road.
[0010] Further, a rough and flat concrete cast-in-place layer with a thickness of not less than 50 mm is further arranged on the top surface of each stacked support pier, and the two ends of the combined high-strength crossing road surface are arranged on the corresponding stacked support piers through the corresponding rough and flat concrete cast-in-place layers.
[0011] Preferably, the combined high-strength crossing road surface comprises support I-beams and a road surface steel plate, at least three support I-beams are arranged on the bottom surface of the road surface steel plate along the width direction, and the road surface steel plate is crossed and supported on the two stacked support piers on both sides of the underground pipe culvert and / or the drainage ditch pipe through the respective support I-beams.
[0012] Further, the specification of each support I-beam is determined according to the maximum weight of the running equipment to be passed, and the arrangement distance between the adjacent two support I-beams is not more than the height of a single support I-beam.
[0013] Preferably, compacted filling soil bodies are further arranged on the outer sides of the two stacked support piers, a gravel compacted layer is further arranged on the compacted filling soil bodies, a concrete leveling layer is further arranged on the gravel compacted layer, and a concrete road surface layer is further cast on the concrete leveling layer, and the height of the concrete road surface layer is not more than the height of the combined high-strength crossing road surface.
[0014] Further, the thickness of the concrete leveling layer is not less than 50mm, the concrete pavement layer is composed of a C20 / 25 concrete layer with a thickness not less than 150mm, and the thickness of the pavement steel plate is not less than 25mm.
[0015] The technical scheme provided by the application has the advantages that: the driving convenience path of the application is constructed by increasing the stacked support structure and the combined high-strength road surface crossing structure based on the existing underground pipe culvert and / or drainage ditch pipe, and then the combined high-strength road surface crossing structure is arranged above the underground pipe culvert and / or drainage ditch pipe through the stacked support structure; and a buffer protection layer is also filled below the combined high-strength road surface crossing structure, and a separation joint with a height not less than 100mm is left between the buffer protection layer and the combined high-strength road surface crossing structure. The technical scheme solves the technical problem of high construction cost caused by long construction period and non-reusable structure in the prior art, and the driving convenience path of the application can be built at any time according to the site condition when needed, and the stacked support structure and the combined high-strength road surface crossing structure can be recycled after use, which not only significantly reduces the construction cost, but also significantly shortens the construction period. In combination with the production site and the prior art, the stacked support structure of the application can directly use pre-buried concrete cubic blocks as the foundation, and then arrange the pavement of the steel plate structure on the top surface of the concrete cubic blocks, so as to achieve the purpose of reducing cost, facilitating manufacturing and installation during construction. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 FIG. 1 is a planar arrangement structure schematic view of the driving convenience path for crossing the underground pipe culvert and the drainage ditch pipe of the application;
[0017] Figure 2 FIG. 2 is an A-A sectional view of the driving convenience path for crossing the underground pipe culvert and the drainage ditch pipe of the application; Figure 1
[0018] Figure 3 FIG. 3 is a B-B sectional view of the driving convenience path for crossing the underground pipe culvert and the drainage ditch pipe of the application. Figure 1
[0019] Marked in the figure: underground pipe culvert and / or drainage ditch pipe 1, buffer protection layer 2, separation joint 3, filling and compaction layer 4, concrete prefabricated cubic block 5, rough and flat concrete cast-in-place layer 6, support I-beam 7, pavement steel plate 8, compacted filling soil body 9, crushed stone compaction layer 10, concrete leveling layer 11, concrete pavement layer 12. DETAILED DESCRIPTION
[0020] As Figure 1 , Figure 2 and Figure 3 The utility model provides a kind of traffic lane for crossing underground pipe culvert and drainage ditch pipe, which can significantly reduce construction cost and shorten construction period obviously.The traffic lane includes underground pipe culvert and / or drainage ditch pipe 1, and further includes stacked support structure and combined high-strength crossing pavement.The combined high-strength crossing pavement is detachably arranged above the underground pipe culvert and / or drainage ditch pipe 1 by the stacked support structure.A buffer protection layer 2 is filled below the combined high-strength crossing pavement, and a separation joint 3 with a height not less than 100mm is arranged between the buffer protection layer 2 and the combined high-strength crossing pavement.The technical solution provided in the present application is based on the existing underground pipe culvert and / or drainage ditch pipe, and the stacked support structure and combined high-strength crossing pavement are added to construct the traffic lane of the present application.The combined high-strength crossing pavement is detachably arranged above the underground pipe culvert and / or drainage ditch pipe by the stacked support structure.A buffer protection layer is filled below the combined high-strength crossing pavement, and a separation joint with a height not less than 100mm is left between the buffer protection layer and the combined high-strength crossing pavement.The technical problem of high construction cost caused by long construction period and non-reusable structure in the prior art is solved.The traffic lane of the present application can be built at any time according to the site condition when needed, and the stacked support structure and combined high-strength crossing pavement can be recycled after use, which can not only significantly reduce construction cost, but also significantly shorten construction period.
[0021] Correspondingly, in order to facilitate the rapid construction of the driving road of the application, and to avoid excessive deformation or damage of the driving road during the construction period and to avoid deep repair and maintenance, the driving road of the application further comprises an excavated and compacted foundation pit arranged on both sides of the underground pipe culvert and / or drainage ditch pipe 1 along the width direction, the stacked support structure is arranged on both sides of the underground pipe culvert and / or drainage ditch pipe 1 through each excavated and compacted foundation pit, and the combined high-strength crossing road surface is supported above the underground pipe culvert and / or drainage ditch pipe 1 through the stacked support structure arranged on each excavated and compacted foundation pit. In combination with the influence line of the friction angle and soil force of the soil near the pipe culvert or drainage ditch pipe, when arranging the stacked support structure, the distance between the adjacent two excavated and compacted foundation pits along the width direction of the underground pipe culvert and / or drainage ditch pipe is not less than 1.5 times the width of the underground pipe culvert and / or drainage ditch pipe, and a filled and compacted layer 4 is further arranged at the bottom of each excavated and compacted foundation pit, and the thickness of the filled and compacted layer 4 is not less than 50 mm. As described above, in order to avoid excessive deformation or damage of the driving road during the construction period and to avoid deep repair and maintenance, the stacked support structure of the application comprises at least six concrete prefabricated cubic blocks 5, each concrete prefabricated cubic block 5 is stacked into two stacked support piers in the form of a pyramid in two groups, one stacked support pier is arranged on each side of the underground pipe culvert and / or drainage ditch pipe 1, and the two ends of the combined high-strength crossing road surface are supported on the two stacked support piers, respectively. The combined high-strength crossing road surface of the application comprises a support I-beam 7 and a road surface steel plate 8, at least three support I-beams 7 are arranged on the bottom surface of the road surface steel plate 8 along the width direction, and the road surface steel plate 8 is crossed and supported on the two stacked support piers on both sides of the underground pipe culvert and / or drainage ditch pipe 1 through each support I-beam 7. Preferably, each concrete prefabricated cubic block 5 is a cube or a cuboid, each stacked support pier comprises at least two layers of concrete prefabricated cubic blocks 5 along the height direction, and each stacked support pier comprises at least three concrete prefabricated cubic blocks 5 along the width direction of the driving road. The specification of each support I-beam 7 is determined according to the maximum weight of the running equipment that needs to pass, and the arrangement distance between the adjacent two support I-beams 7 is not more than the height of a single support I-beam 7.
[0022] Further, in order to improve the overall stability of the lane, a layer of rough plain concrete cast-in-place layer 6 with a thickness of not less than 50 mm is arranged on the top surface of each stacked support pier, and the two ends of the combined high-strength crossing road surface are arranged on the corresponding stacked support piers through the corresponding rough plain concrete cast-in-place layer 6. Compacted filling soil bodies 9 are arranged on the outer sides of the two stacked support piers, gravel compacted layers 10 are arranged on the compacted filling soil bodies 9, concrete leveling layers 11 are arranged on the gravel compacted layers 10, and concrete road surface layers 12 are poured on the concrete leveling layers 11, and the height of the concrete road surface layer 12 does not exceed the height of the combined high-strength crossing road surface. The specific thickness is that the thickness of the concrete leveling layer 11 is not less than 50 mm, the concrete road surface layer 12 is composed of a C20 / 25 concrete layer with a thickness of not less than 150 mm, and the thickness of the road steel plate 8 is not less than 25 mm.
[0023] In summary, the driving access with the above structure of the application has the following advantages,
[0024] 1. The precast concrete block is reusable;
[0025] 2. The structure of the application uses I-beam welded to the structure of the iron plate, and the load is transmitted to the concrete block by the I-beam;
[0026] 3. Compared with the traditional crossing structure, the foundation and the I-beam panel can be reused, which improves the construction speed and reduces the construction cost;
[0027] 4. The driving access of the application is different from the traditional crossing structure, both the foundation and the panel structure use precast structure, which is simple and convenient to construct, and because it can be reused, both the precast concrete block and the I-beam can be rented, which greatly reduces the construction cost. The completed access can ensure that the original drainage structure is not damaged, and heavy construction machinery can pass through or park above the culvert for construction work.
[0028] 5. The stacked support structure of the application directly uses pre-embedded concrete blocks as the foundation, and then arranges the steel plate structure road surface on the top surface of the concrete block, which achieves the purpose of reducing cost, facilitating manufacturing and installation during construction.
[0029] The technical solutions of the application will be further described through specific embodiments:
[0030] Embodiment one
[0031] 1. First, determine the specific location and depth of the underground iron pipe or culvert through pipe exploration work;
[0032] 2, determine the friction angle of the soil near the iron pipe, determine the influence line of the soil force, and further determine the maximum depth of the buried concrete block; the stacking method of the concrete cube is to stack the pyramid;
[0033] 3, after determining the buried depth of the concrete block, start excavating to the bottom elevation of the bottom layer of concrete block, and compact the original ground;
[0034] 4, after stacking the concrete cube according to the pyramid using the hoisting machine, pouring 50mm thick rough flat concrete on the topmost concrete block, waiting for the strength of the rough flat concrete to form;
[0035] 5, according to the calculation book, calculate the maximum load that the structure needs to bear, determine the spacing of the I-beam that needs to transfer the load, and then weld the I-beam on the 25mm thick steel plate according to the required spacing of the calculation result, forming a whole steel structure;
[0036] 6, in order to increase the overall stiffness of the steel structure, weld steel plates on both sides of the flange of the I-beam at the outermost edge of the steel structure to increase the overall strength of the steel structure;
[0037] 7, according to the site conditions, lay the corresponding thickness of the gravel structure on both sides of the steel structure, and fully compact;
[0038] 8, pour 50mm thick leveling concrete on the compacted gravel structure on both sides;
[0039] 9, after the strength of the rough flat concrete is formed, pour 150mm thick C20 / 25 concrete on both ends of the rough flat concrete, and once the strength of the concrete is formed, the structure can bear the weight of the large construction machinery on the construction site, or the large construction machinery can be parked in the position, without damaging the underground water pipe or culvert.
Claims
1. A vehicle access road for crossing an underground culvert and a drainage ditch pipe, comprising an underground culvert and / or a drainage ditch pipe (1), characterized in that: The driving sidewalk also includes a stacked support structure and a combined high-strength spanning pavement. The combined high-strength spanning pavement is detachably arranged above the underground culvert and / or drainage ditch pipe (1) through the stacked support structure. A buffer protection layer (2) is also filled below the combined high-strength spanning pavement, and an isolation joint (3) with a height of not less than 100 mm is provided between the buffer protection layer (2) and the combined high-strength spanning pavement.
2. The vehicle access road for crossing underground culverts and drainage pipes according to claim 1, characterized in that: The driving walkway further comprises excavated and compacted foundation pits arranged on both sides of the underground culvert and / or drainage ditch pipe (1) along the width direction, the stacked support structures are arranged on both sides of the underground culvert and / or drainage ditch pipe (1) through each excavated and compacted foundation pit, and the combined high-strength spanning road surface is supported above the underground culvert and / or drainage ditch pipe (1) through the stacked support structures arranged on each excavated and compacted foundation pit.
3. The vehicle access road for crossing underground culverts and drainage pipes according to claim 2, characterized in that: Along the width direction of the underground culvert and / or drainage ditch pipe, the distance between two adjacent excavated and compacted foundation pits is not less than 1.5 times the width of the underground culvert and / or drainage ditch pipe. A filling and compacting layer (4) is also provided at the bottom of each excavated and compacted foundation pit, and the thickness of the filling and compacting layer (4) is not less than 50 mm.
4. The vehicle access road for crossing underground culverts and drainage pipes according to claim 1, 2 or 3, characterized in that: The stacked support structure comprises at least six prefabricated concrete cubic blocks (5), each of which is divided into two groups and stacked in a pyramid shape to form two stacked support piers. A stacked support pier is arranged on both sides of the underground culvert and / or drainage ditch pipe (1), and both ends of the combined high-strength spanning road surface are supported on the two stacked support piers.
5. The vehicle access road for crossing underground culverts and drainage pipes according to claim 4, characterized in that: Each prefabricated concrete cubic block (5) is in the shape of a cube or a cuboid. Each stacked support pier includes at least two layers of prefabricated concrete cubic blocks (5) along the height direction, and each stacked support pier includes at least three or more prefabricated concrete cubic blocks (5) along the width direction of the driving sidewalk.
6. The vehicle access road for crossing underground culverts and drainage pipes according to claim 5, characterized in that: A layer of rough-flat concrete cast-in-place layer (6) with a thickness of not less than 50 mm is also laid on the top surface of each stacked support pier, and both ends of the combined high-strength spanning road surface are respectively arranged on the corresponding stacked support piers through corresponding rough-flat concrete cast-in-place layers (6).
7. The vehicle access road for crossing underground culverts and drainage pipes according to claim 6, characterized in that: The combined high-strength spanning pavement comprises supporting I-steels (7) and pavement steel plates (8), wherein at least three supporting I-steels (7) are arranged on the bottom surface of the pavement steel plates (8) along the width direction, and the pavement steel plates (8) are respectively supported on two stacked supporting piers on both sides of an underground culvert and / or a drainage ditch pipe (1) via each supporting I-steel (7).
8. The vehicle access road for crossing underground culverts and drainage pipes according to claim 7, characterized in that: The specification of each supporting I-beam (7) is determined according to the maximum weight of the running equipment that needs to pass through, and the arrangement distance between two adjacent supporting I-beams (7) does not exceed the height of a single supporting I-beam (7).
9. The vehicular access road for crossing underground culverts and drainage pipes according to claim 8, characterized in that: Compacted filling soil (9) is arranged on the outer sides of the two stacked support piers, a crushed stone compaction layer (10) is laid on the compacted filling soil (9), a concrete leveling layer (11) is arranged on the crushed stone compaction layer (10), and a concrete pavement layer (12) is poured on the concrete leveling layer (11), and the height of the concrete pavement layer (12) does not exceed the height of the combined high-strength spanning pavement.
10. The vehicular access road for crossing underground culverts and drainage pipes according to claim 9, characterized in that: The thickness of the concrete leveling layer (11) is not less than 50mm, the concrete pavement layer (12) is composed of a C20 / 25 concrete layer with a thickness of not less than 150mm, and the thickness of the pavement steel plate (8) is not less than 25mm.