Rail rack structure of cutoff wall drilling machine
By designing the track frame structure for the water-cutting wall drilling rig, the problems of rig movement and construction inconvenience were solved, thereby accelerating the construction progress and reducing costs.
Patent Information
- Application Number
- CN202422901416.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-27
- Publication Date
- 2025-11-14
- Estimated Expiration
- 2034-11-27
AI Technical Summary
In existing technologies, the drilling rigs for water cutoff walls are inconvenient to move and construct, resulting in slow construction progress and high costs.
A track frame structure for a water-cutting wall drilling rig was designed, including a steel plate, a bottom pressure-bearing module, a movable pressure-relieving module, and an impact drilling rig. Through the combination of components such as sleepers, light rails, I-beam columns, and bearings, a movable track is formed to fix the impact drilling rig, reducing the number of times the equipment moves and the damage to the track caused by vibration.
It effectively reduces the impact force of the impact drilling rig on the track, reduces multiple transfers and personnel input, shortens the construction period, and reduces construction costs.
Smart Images

Figure CN223549205U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the technical field of drilling rig auxiliary equipment, and relates to the track frame structure of a water-cutting wall drilling rig. Background Technology
[0002] A cutoff wall is constructed aft of the dam, a water-retaining structure. Located behind the dam, the cutoff wall is constructed using trench-grooved concrete. Construction employs a method of "staged trenching and hole drilling with impact drilling + main hole drilling followed by auxiliary holes in each section + skipping holes in each section + mud slurry wall protection." The equipment used for trenching and hole drilling is an impact drill, with a drill bit weight of 6.0t and a drilling rig weight of 10.5t. The impact drill is positioned on laid rails parallel to the cutoff wall axis, with the rails laid upstream along the guide groove. An alternating forward movement method ensures smooth rig movement, and the rails are connected to the sleepers using track spikes. However, the existing impact drill directly drills on the rails, generating excessive impact force that can damage the rails, increase the risk of poor hole quality, and increase the frequency of equipment movement, thus increasing construction time and cost. These adverse factors severely impact the construction progress of the cutoff wall, becoming a major challenge in its construction.
[0003] In summary, existing technologies suffer from the problems of inconvenient movement and construction of water-cutting wall drilling rigs. Utility Model Content
[0004] The purpose of this utility model is to provide a track frame structure for a water-cutting wall drilling rig, which solves the problems of inconvenient movement and construction of water-cutting wall drilling rigs in the prior art.
[0005] The technical solution adopted by this utility model is a water-cutting wall drilling rig track frame structure, including a steel plate set on one side of the water-cutting wall, a bottom pressure-bearing module set on the steel plate, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate, and an impact drilling rig set on the movable pressure relief module away from the bottom pressure-bearing module.
[0006] The features of this utility model also include:
[0007] The bottom pressure-bearing module includes several parallel sleepers, one side of which is attached to a steel plate, and the axis of the sleepers is perpendicular to the extension direction of the cutoff wall. Each sleeper includes two wooden posts, and the ends of the two wooden posts are fixed together with nails.
[0008] Several parallel light rails are attached to the side of the sleeper away from the steel plate, and the extension direction of the light rails is parallel to the extension direction of the cutoff wall. The light rails are respectively set at both ends of the sleeper, and the light rails and sleepers are fixed together by track spikes.
[0009] Several steel bars are installed between the sleepers and the light rail, and the steel bars are perpendicular to the extension direction of the light rail track; several light rails are fixedly connected to the steel bars.
[0010] The bottom pressure-bearing module also includes a fine sand layer. One side of the fine sand layer is flush with the outer wall of the light rail away from the sleepers, and the other side is attached to the steel plate. The sleepers and light rail are set inside the fine sand layer.
[0011] The mobile pressure relief module includes a platform, one side of which is attached to the impact drilling rig, and the other side is provided with several I-beam columns arranged in parallel; several bearings are fixed to the side of the I-beam columns away from the platform.
[0012] The mobile pressure relief module also includes several rail wheels, which are fitted into the light rail; the rail wheels are connected to the I-beam column via bearings.
[0013] Lifting lugs are provided on both sides of the bottom pressure-bearing module, and the lifting lugs are fixedly connected to the steel plate.
[0014] The cutoff wall consists of a concrete wall with guide grooves on both sides; a steel plate is placed on the side of the guide groove away from the concrete wall.
[0015] The beneficial effects of this utility model are as follows: This utility model combines the construction method of impact drilling rig with the actual on-site construction conditions, fixes the impact drilling rig on the welded frame, and sets rail wheels at the bottom of the frame. The rail wheels are combined with light rails, which effectively reduces the damage of the impact force of the impact drilling rig to the rail wheels, reduces the hole position deviation caused by vibration, reduces the crane investment and personnel investment required for multiple transfers of the drilling rig, and effectively shortens the construction period and reduces the construction cost. Attached Figure Description
[0016] Figure 1 This is a structural schematic diagram of the track frame structure of the water-cutting wall drilling rig of this utility model;
[0017] Figure 2 This is a schematic diagram of the sleepers and light rails in the track frame structure of the water-cutting wall drilling rig of this utility model.
[0018] In the diagram, 1. Steel plate; 2. Sleeper; 3. Horseshoe nail; 4. Light rail; 5. Reinforcing bar; 6. Rail spike; 7. Fine sand layer; 8. Lifting lug; 9. Rail wheel; 10. Platform; 11. I-beam column; 12. Bearing; 13. Impact drilling rig; 14. Drilling tool; 15. Cutoff wall; 1501. Guide channel; 1502. Concrete wall; Detailed Implementation
[0019] The present invention will now be described in detail with reference to the accompanying drawings and specific embodiments.
[0020] The track frame structure of the water-cutting wall drilling rig, such as Figure 1 and Figure 2As shown, it includes a steel plate 1 set on one side of the water-cutting wall 15, a bottom pressure-bearing module set on the steel plate 1, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate 1, and an impact drill 13 set on the side of the movable pressure relief module away from the bottom pressure-bearing module.
[0021] The bottom pressure-bearing module includes several parallel sleepers 2, one side of which is attached to the steel plate 1, and the axis of the sleeper 2 is perpendicular to the extension direction of the cutoff wall 15; the sleeper 2 includes two wooden columns, and the ends of the two wooden columns are fixed together by horse-head nails 3.
[0022] Several parallel light rails 4 are attached to the side of the sleeper 2 away from the steel plate 1. The extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively set at both ends of the sleeper 2, and the light rails 4 and the sleeper 2 are fixed together by rail spikes 6.
[0023] Several steel bars 5 are installed between the sleeper 2 and the light rail 4, and the steel bars 5 are perpendicular to the extension direction of the light rail 4; the light rail 4 is fixedly connected to the steel bars 5 respectively.
[0024] The bottom pressure-bearing module also includes a fine sand layer 7. One side of the fine sand layer 7 is flush with the outer wall of the light rail 4 away from the sleeper 2, and the other side is attached to the steel plate 1. The sleeper 2 and the light rail 4 are set inside the fine sand layer 7.
[0025] The mobile pressure relief module includes a frame 10, one side of which is attached to the impact drilling rig 13, and the other side is provided with several I-beam columns 11, which are arranged in parallel; several bearings 12 are fixedly connected to the side of the I-beam columns 11 away from the frame 10.
[0026] The mobile pressure relief module also includes several rail wheels 9, which are fitted together with the light rail 4; the rail wheels 9 are connected to the I-beam column 11 through bearings 12.
[0027] Lifting lugs 8 are provided on both sides of the bottom pressure-bearing module, and the lifting lugs 8 are fixedly connected to the steel plate 1.
[0028] The water-cutting wall 15 includes a concrete wall 1502, and guide grooves 1501 are respectively provided on both sides of the concrete wall 1502; the steel plate 1 is provided on the side of the guide groove 1501 away from the concrete wall 1502.
[0029] This invention enables drilling equipment to travel on a movable track, with the impact drill 13 fixed on the platform 10. The drill bit 14 is hoisted on the impact drill 13 for easy construction. The lower part of the platform 10 is equipped with a track wheel 9, which reduces the number of times the impact drill 13 needs to be moved and fixed. This effectively reduces the labor intensity of the operators, shortens the drilling time, improves the construction period, and reduces the construction cost. By setting the water-cutting wall drill on the movable track wheel 9 and the platform 10 and combining it with the light rail 4, the average force is increased to the sleepers 2, and the force is transferred to the foundation surface. It can be widely used in the construction of angled seepage interception bodies in water conservancy, municipal engineering, and rail transit.
[0030] In this invention, sleepers 2 and light rail 4 are fixed onto steel plate 1 according to the design dimensions to form a whole, and are then hoisted into place by a crane; the impact drilling equipment is welded and fixed to the frame 10 to form a whole; the impact drilling equipment, the frame 10 and the light rail 4 are connected and slid by rail wheels 9, and the limiting device on the track is fixed when the fixed groove section is constructed.
[0031] Example 1
[0032] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2 As shown, it includes a steel plate 1 set on one side of the water-cutting wall 15, a bottom pressure-bearing module set on the steel plate 1, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate 1, and an impact drill 13 set on the side of the movable pressure relief module away from the bottom pressure-bearing module.
[0033] Example 2
[0034] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2 As shown, the structure includes a steel plate 1 mounted on one side of the cutoff wall 15. A bottom pressure-bearing module is mounted on the steel plate 1. A movable pressure relief module is slidably connected to the bottom pressure-bearing module on the side away from the steel plate 1. An impact drill rig 13 is mounted on the side of the movable pressure relief module away from the bottom pressure-bearing module. The bottom pressure-bearing module includes several parallel sleepers 2. One side of each sleeper 2 is attached to the steel plate 1, and the axis of the sleeper 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by nails 3.
[0035] Example 3
[0036] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2As shown, the structure includes a steel plate 1 mounted on one side of the cutoff wall 15. A bottom pressure-bearing module is mounted on the steel plate 1. A movable pressure relief module is slidably connected to the bottom pressure-bearing module on the side away from the steel plate 1. An impact drill rig 13 is mounted on the side of the movable pressure relief module away from the bottom pressure-bearing module. The bottom pressure-bearing module includes several parallel sleepers 2. One side of each sleeper 2 is attached to the steel plate 1, and the axis of the sleeper 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by bolts 3. Four parallel light rails 4 are attached to the side of the sleepers 2 away from the steel plate 1. The extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively mounted at both ends of the sleepers 2, and the light rails 4 and the sleepers 2 are fixed together by rail spikes 6.
[0037] Example 4
[0038] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2 As shown, it includes a steel plate 1 set on one side of the water-cutting wall 15, a bottom pressure-bearing module set on the steel plate 1, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate 1, and an impact drill 13 set on the side of the movable pressure relief module away from the bottom pressure-bearing module.
[0039] The bottom pressure-bearing module includes several parallel sleepers 2, one side of which is attached to the steel plate 1. The axis of the sleeper 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by bolts 3. Four parallel light rails 4 are attached to the side of the sleeper 2 away from the steel plate 1. The extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively located at both ends of the sleepers 2 and are fixed to the sleepers 2 by rail spikes 6. Three steel bars 5 are installed between the sleepers 2 and the light rails 4. The steel bars 5 are perpendicular to the extension direction of the light rails 4. The four light rails 4 are fixed to the steel bars 5 respectively.
[0040] Example 5
[0041] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2 As shown, it includes a steel plate 1 set on one side of the water-cutting wall 15, a bottom pressure-bearing module set on the steel plate 1, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate 1, and an impact drill 13 set on the side of the movable pressure relief module away from the bottom pressure-bearing module.
[0042] The bottom pressure-bearing module includes several parallel sleepers 2, one side of which is attached to the steel plate 1, and the axis of the sleepers 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by bolts 3. Four parallel light rails 4 are attached to the side of the sleepers away from the steel plate 1, and the extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively located at both ends of the sleepers 2, and the light rails 4 and the sleepers 2 are fixed together by rail spikes 6. Three steel bars 5 are set between the sleepers 2 and the light rails 4, and the steel bars 5 are perpendicular to the extension direction of the light rails 4. The four light rails 4 are fixed together with the steel bars 5. The bottom pressure-bearing module also includes a fine sand layer 7, one side of which is flush with the outer wall of the light rails 4 away from the sleepers 2, and the other side is attached to the steel plate 1. The sleepers 2 and the light rails 4 are set within the fine sand layer 7.
[0043] Example 6
[0044] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2 As shown, it includes a steel plate 1 set on one side of the water-cutting wall 15, a bottom pressure-bearing module set on the steel plate 1, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate 1, and an impact drill 13 set on the side of the movable pressure relief module away from the bottom pressure-bearing module.
[0045] The bottom pressure-bearing module includes several parallel sleepers 2, one side of which is attached to the steel plate 1, and the axis of the sleepers 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by bolts 3. Four parallel light rails 4 are attached to the side of the sleepers away from the steel plate 1, and the extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively located at both ends of the sleepers 2, and the light rails 4 and the sleepers 2 are fixed together by rail spikes 6. Three steel bars 5 are set between the sleepers 2 and the light rails 4, and the steel bars 5 are perpendicular to the extension direction of the light rails 4. The four light rails 4 are fixed together with the steel bars 5. The bottom pressure-bearing module also includes a fine sand layer 7, one side of which is flush with the outer wall of the light rails 4 away from the sleepers 2, and the other side is attached to the steel plate 1. The sleepers 2 and the light rails 4 are set within the fine sand layer 7.
[0046] The mobile pressure relief module includes a frame 10, one side of which is attached to the impact drill 13, and the other side is provided with four I-beam columns 11, which are arranged in parallel; six bearings 12 are fixedly connected to the side of the I-beam columns 11 away from the frame 10.
[0047] Example 7
[0048] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2As shown, the structure includes a steel plate 1 mounted on one side of the cutoff wall 15. A bottom pressure-bearing module is mounted on the steel plate 1. A movable pressure relief module is slidably connected to the bottom pressure-bearing module on the side away from the steel plate 1. An impact drill rig 13 is mounted on the side of the movable pressure relief module away from the bottom pressure-bearing module. The bottom pressure-bearing module includes several parallel sleepers 2, one side of which is attached to the steel plate 1. The axis of the sleepers 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by bolts 3. Four parallel light rails 4 are attached to the side of the sleepers 2 away from the steel plate 1. The extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively mounted at both ends of the sleepers 2 and are fixed to the sleepers 2 by rail spikes 6. Three steel bars 5 are installed between the sleepers 2 and the light rails 4, perpendicular to the extension direction of the light rails 4. The four light rails 4 are fixed to the steel bars 5 respectively. The bottom pressure-bearing module also includes a fine sand layer 7. One side of the fine sand layer 7 is flush with the outer wall of the light rail 4 away from the sleeper 2, and the other side is attached to the steel plate 1. The sleeper 2 and the light rail 4 are set inside the fine sand layer 7.
[0049] The mobile pressure relief module includes a platform 10, one side of which is fitted to the impact drilling rig 13, and the other side is equipped with four I-beam columns 11 arranged in parallel. Six bearings 12 are fixed to the side of the I-beam columns 11 away from the platform 10. The mobile pressure relief module also includes four rail wheels 9, which are fitted to the light rail 4. The rail wheels 9 are connected to the I-beam columns 11 through the bearings 12.
[0050] Lifting lugs 8 are provided on both sides of the bottom pressure-bearing module, and the lifting lugs 8 are fixedly connected to the steel plate 1.
[0051] Example 8
[0052] This embodiment proposes a track frame structure for a water-cutting wall drilling rig, such as... Figure 1 and Figure 2 As shown, it includes a steel plate 1 set on one side of the water-cutting wall 15, a bottom pressure-bearing module set on the steel plate 1, a movable pressure relief module slidably connected to the bottom pressure-bearing module away from the steel plate 1, and an impact drill 13 set on the side of the movable pressure relief module away from the bottom pressure-bearing module.
[0053] The bottom pressure-bearing module includes several parallel sleepers 2, one side of which is attached to the steel plate 1, and the axis of the sleepers 2 is perpendicular to the extension direction of the cutoff wall 15. Each sleeper 2 includes two wooden posts, the ends of which are fixed together by bolts 3. Four parallel light rails 4 are attached to the side of the sleepers away from the steel plate 1, and the extension direction of the light rails 4 is parallel to the extension direction of the cutoff wall 15. The light rails 4 are respectively located at both ends of the sleepers 2, and the light rails 4 and the sleepers 2 are fixed together by rail spikes 6. Three steel bars 5 are set between the sleepers 2 and the light rails 4, and the steel bars 5 are perpendicular to the extension direction of the light rails 4. The four light rails 4 are fixed together with the steel bars 5. The bottom pressure-bearing module also includes a fine sand layer 7, one side of which is flush with the outer wall of the light rails 4 away from the sleepers 2, and the other side is attached to the steel plate 1. The sleepers 2 and the light rails 4 are set within the fine sand layer 7.
[0054] The mobile pressure relief module includes a platform 10, one side of which is fitted to the impact drilling rig 13, and the other side is equipped with four I-beam columns 11 arranged in parallel. Six bearings 12 are fixed to the side of the I-beam columns 11 away from the platform 10. The mobile pressure relief module also includes four rail wheels 9, which are fitted to the light rail 4. The rail wheels 9 are connected to the I-beam columns 11 through the bearings 12.
[0055] The water-cutting wall 15 includes a concrete wall 1502, and guide grooves 1501 are respectively provided on both sides of the concrete wall 1502; the steel plate 1 is provided on the side of the guide groove 1501 away from the concrete wall 1502.
[0056] In this embodiment of the utility model, the steel plate 1 can be 10mm×5.0m×5.5m in size. The sleepers 2 and light rails 4 are fixed together to form a whole, and are moved by a crane. The sleepers 2 can be 20cm×20cm×2.5m in size, and the spacing between the sleepers 2 can be 70cm. The sleepers 2 are located above the steel plate 1 and below the light rails 4. The nails 3 are 20cm long, and two three-sided fixings are used to connect the two sleepers 2 in an "X" shape. The four light rails 4 are welded into a whole by steel bars 5. A "T" shape is welded on the outside of the joint between the light rails 4 and the steel bars 5. The horizontal spacing of each steel bar 5 can be 2.1m. The light rails 4 are located on the laid sleepers 2, and the light rails 4 are parallel to the axis of the water-cutting wall 15. The light rails 4 can be located at a distance of 10mm×5.0m×5.5m. The guide channel 1501 of the intercepting wall is laid 60cm upstream. The light rail 4 is spaced 65cm apart, with a total of four rails laid, two in a group, and the spacing between groups is 3m. The rail spikes 6 are 8cm long and are used to fix the joint between the light rail 4 and the sleeper 2. Two rail spikes are set on each side of the light rail 4 for fixing. The fine sand layer 7 is backfilled and compacted with fine granular material, located between the sleepers 2. The top surface of the backfill is flush with the top of the sleeper 2 and is manually compacted. The lifting lugs 8 are ten-ton "U"-shaped buckles, with a total of 4 located at the four corners of the steel plate 1. The platform 10 is made of I-beams welded into a 5.7m×2.0m platform. The bottom of the platform 10 is equipped with rail wheels 9, two in a group, three on each side, for a total of six groups. The rail wheels 9 are welded to the bearings 12 between each group.
Claims
1. A track frame structure for a water-cutting wall drilling rig, characterized in that, It includes a steel plate (1) set on one side of the water-cutting wall (15), a bottom pressure-bearing module is set on the steel plate (1), a movable pressure relief module is slidably connected to the side of the bottom pressure-bearing module away from the steel plate (1), and an impact drill (13) is set on the side of the movable pressure relief module away from the bottom pressure-bearing module. The bottom pressure-bearing module includes several parallel sleepers (2), one side of which is attached to the steel plate (1), and the axial direction of the sleepers (2) is perpendicular to the extension direction of the cutoff wall (15); the sleepers (2) include two wooden columns, and the ends of the two wooden columns are fixed together by rivets (3). The sleeper (2) is fitted with several parallel light rails (4) on the side away from the steel plate (1). The extension direction of the light rails (4) is parallel to the extension direction of the cutoff wall (15). The light rails (4) are respectively set at both ends of the sleeper (2). The light rails (4) and the sleeper (2) are fixed together by rail spikes (6). The bottom pressure-bearing module also includes a fine sand layer (7), one side of which is flush with the outer wall of the light rail (4) away from the sleeper (2), and the other side is attached to the steel plate (1); the sleeper (2) and the light rail (4) are set inside the fine sand layer (7); The mobile pressure relief module includes a platform (10), one side of which is attached to the impact drill (13), and the other side is provided with a number of I-beam columns (11), which are arranged in parallel; a number of bearings (12) are fixedly connected to the side of the I-beam column (11) away from the platform (10). The mobile pressure relief module also includes several rail wheels (9), which are fitted together with the light rail (4); the rail wheels (9) are connected to the I-beam column (11) through bearings (12).
2. The track frame structure for the water-cutting wall drilling rig according to claim 1, characterized in that, A number of steel bars (5) are provided between the sleeper (2) and the light rail (4), and the steel bars (5) are perpendicular to the track extension direction of the light rail (4); the light rail (4) is fixedly connected to the steel bars (5) respectively.
3. The track frame structure for the water-cutting wall drilling rig according to any one of claims 1-2, characterized in that, The bottom pressure-bearing module is provided with lifting lugs (8) on both sides, and the lifting lugs (8) are fixedly connected to the steel plate (1).
4. The track frame structure for the water-cutting wall drilling rig according to any one of claims 1-2, characterized in that, The water-cutting wall (15) includes a concrete wall (1502), and guide grooves (1501) are respectively provided on both sides of the concrete wall (1502); the steel plate (1) is provided on the side of the guide groove (1501) away from the concrete wall (1502).