Aluminum plate curtain wall construction device

By designing an aluminum panel curtain wall device, the problem of waste collection and treatment in existing technologies has been solved. This invention provides an aluminum panel curtain wall device and an aluminum panel curtain wall construction device, which solves the problems of environmental pollution and increased cleanup costs caused by improper waste disposal during aluminum panel curtain wall construction. Through the design of the main frame, aluminum panel clamps, waste recycling funnel, and waste recycling tank, efficient collection and treatment of waste are achieved, keeping the construction site clean.

CN223621265UActive Publication Date: 2025-12-02HAINING JIAYE CONSTRUCT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423122365.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-17
Publication Date
2025-12-02
Estimated Expiration
2034-12-17

AI Technical Summary

Technical Problem

Improper waste disposal during aluminum panel curtain wall construction can lead to environmental pollution, increase cleaning costs, and affect the cleanliness of the construction site.

Method used

Design an aluminum panel curtain wall construction device, including a main frame, aluminum panel clamps, a waste recycling funnel and a waste recycling tank, for collecting and processing construction waste. The main frame is formed by four metal rods connected end to end, with supporting feet at the bottom. There is a metal plate groove above the clamps. The waste recycling funnel is connected to the waste tank to enhance stability and convenience.

Benefits of technology

It enables efficient collection and treatment of waste materials, reduces pollution and cleanup costs at the construction site, and maintains the cleanliness of the construction site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223621265U_ABST
    Figure CN223621265U_ABST
Patent Text Reader

Abstract

The utility model provides an aluminum plate curtain wall construction device which comprises a main frame formed by connecting four metal rods end to end, supporting legs are arranged at the bottom of the main frame, an aluminum plate clamp is arranged above the main frame, the aluminum plate clamp is a metal plate stretching across the main frame, a fixing groove is formed in the metal plate, and the aluminum plate is arranged in the fixing groove. A waste recovery funnel is arranged below the aluminum plate clamp, and the bottom of the waste recovery funnel is connected with a waste recovery tank. According to the aluminum plate curtain wall construction device, follow-up treatment of waste materials in the aluminum plate cutting process is facilitated, and a construction site is kept clean and tidy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of curtain wall technology, specifically relating to an aluminum panel curtain wall construction device. Background Technology

[0002] In the construction industry, especially in curtain wall construction, aluminum panel curtain walls are widely used due to their lightweight, high strength, good weather resistance, and decorative properties. During construction, aluminum panel curtain walls require specific sizes, necessitating cutting. Improper handling of waste materials during cutting can not only affect the cleanliness of the construction site but also potentially pollute the environment and increase subsequent cleanup costs. Utility Model Content

[0003] The main purpose of this utility model is to provide an aluminum panel curtain wall construction device that can conveniently collect waste materials and process them uniformly, thereby reducing cleaning costs.

[0004] To achieve the above objectives, this utility model provides an aluminum panel curtain wall construction device. The aluminum panel curtain wall construction device includes a main frame formed by four metal rods connected end to end. The bottom of the main frame is provided with supporting feet. An aluminum plate clamp is provided above the main frame. The aluminum plate clamp is a metal plate that spans the main frame. A fixing groove is provided on the metal plate. A waste recycling funnel is provided below the aluminum plate clamp. A waste recycling tank is connected to the bottom of the waste recycling funnel.

[0005] This utility model provides an aluminum panel curtain wall construction device. The main frame of the device is formed by four metal rods connected end to end, resulting in a simple and stable structure. Support feet are provided at the bottom of the main frame to support the entire device and ensure stability. An aluminum plate clamp is installed above the main frame, with a metal plate design spanning the main frame for fixing and manipulating the aluminum plate, facilitating aluminum plate cutting. A waste recycling funnel is located below the aluminum plate clamp to collect waste generated during construction. A waste recycling tank is connected to the bottom of the waste recycling funnel to store the collected waste, facilitating subsequent waste disposal and maintaining a clean construction site.

[0006] In one possible implementation, the two sides of the waste recycling funnel are mounted on the bottom of both sides of the main frame.

[0007] In one possible implementation, the main frame is provided with a plurality of first reinforcing rods, the direction of which is parallel to the direction of the aluminum plate clamp. The provision of a plurality of first reinforcing rods on the main frame, parallel to the direction of the aluminum plate clamp, enhances the stability and load-bearing capacity of the main frame.

[0008] In one possible implementation, a second reinforcing rod is provided on the support foot, with one end of the second reinforcing rod attached to the support foot and the other end connected to the outer wall of the waste recycling hopper. This design further enhances the stability of the entire device.

[0009] In one possible implementation, a handle is provided on the side wall of the waste recycling tank. The handle facilitates the movement and handling of the waste recycling tank by operators, improving the ease of construction. Attached Figure Description

[0010] Figure 1 This is a schematic diagram of the structure of an aluminum panel curtain wall construction device provided by this utility model;

[0011] Figure 2 This is a bottom schematic diagram of an aluminum panel curtain wall construction device provided by this utility model. Detailed Implementation

[0012] The following description is intended to disclose the present invention so that those skilled in the art can implement it. The preferred embodiments described below are merely examples, and other obvious variations will occur to those skilled in the art. The basic principles of the present invention defined in the following description can be applied to other embodiments, modifications, improvements, equivalents, and other technical solutions that do not depart from the spirit and scope of the present invention.

[0013] In the description of this application, it should be understood that the terms "upper" and "lower" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.

[0014] In the description of this application, the terms "first," "second," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated.

[0015] See attached diagram. Figure 1 This utility model provides an aluminum panel curtain wall construction device, which includes a main frame 1 formed by four metal rods connected end to end. The bottom of the main frame 1 is provided with support feet 2. An aluminum plate clamp 3 is provided above the main frame 1. The aluminum plate clamp 3 is a metal plate that spans the main frame 1. A fixing groove is provided on the metal plate. A waste recycling funnel 4 is provided below the aluminum plate clamp 3. A waste recycling tank 5 is connected to the bottom of the waste recycling funnel 4.

[0016] This utility model provides an aluminum panel curtain wall construction device. The main frame 1 of the device is formed by four metal rods connected end to end, which is simple and stable. Support feet 2 are provided at the bottom of the main frame 1 to support the entire device and ensure stability. An aluminum plate clamp 3 is provided above the main frame 1, with a metal plate design spanning the main frame 1 for fixing and manipulating the aluminum plate, facilitating aluminum plate cutting. A waste recycling funnel 4 is provided below the aluminum plate clamp 3 to collect waste generated during construction. A waste recycling tank 5 is connected to the bottom of the waste recycling funnel 4 to store the collected waste, facilitating subsequent waste disposal and maintaining the cleanliness of the construction site.

[0017] In one possible implementation, the two sides of the waste recycling hopper 4 are mounted on the bottom of both sides of the main frame 1.

[0018] In one possible implementation, the main frame 1 is provided with a plurality of first reinforcing rods 61, the direction of which is parallel to the direction of the aluminum plate clamp 3. The provision of a plurality of first reinforcing rods 61 on the main frame 1, parallel to the direction of the aluminum plate clamp 3, enhances the stability and load-bearing capacity of the main frame 1.

[0019] In one possible implementation, a second reinforcing rod 62 is provided on the support leg 2, with one end of the second reinforcing rod 62 attached to the support leg 2 and the other end connected to the outer wall of the waste recycling hopper 4. This design further enhances the stability of the entire device.

[0020] In one possible implementation, a handle 7 is provided on the side wall of the waste recycling tank 5. The handle 7 facilitates the movement and handling of the waste recycling tank 5 by operators, improving the convenience of construction.

[0021] It is worth mentioning that those skilled in the art can still modify the technical solutions described in the foregoing embodiments, or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.

Claims

1. An aluminum panel curtain wall construction device, characterized in that, The device includes a main frame formed by four metal rods connected end to end. The bottom of the main frame is provided with supporting feet. An aluminum plate clamp is provided above the main frame. The aluminum plate clamp is a metal plate that spans across the main frame. A fixing groove is provided on the metal plate. A waste recycling funnel is provided below the aluminum plate clamp. A waste recycling tank is connected to the bottom of the waste recycling funnel.

2. The aluminum panel curtain wall construction device according to claim 1, characterized in that, The two sides of the waste recycling funnel are installed at the bottom of both sides of the main frame.

3. The aluminum panel curtain wall construction device according to claim 2, characterized in that, The main frame is provided with a number of first reinforcing rods, and the direction of the reinforcing rods is parallel to the direction of the aluminum plate clamp.

4. The aluminum panel curtain wall construction device according to claim 3, characterized in that, A second reinforcing rod is provided on the support foot, one end of the second reinforcing rod is provided on the support foot, and the other end of the second reinforcing rod is connected to the outer wall of the waste recycling funnel.

5. The aluminum panel curtain wall construction device according to claim 4, characterized in that, A handle is provided on the side wall of the waste recycling tank.