Steel hanging box for bridge construction
By introducing auxiliary support components and stabilizing mechanisms into the steel caisson for bridge construction, the problem of inconvenience in replacing damaged adjusting ropes was solved, ensuring hoisting stability and improving the reliability and safety of the caisson.
Patent Information
- Application Number
- CN202423139226.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-19
- Publication Date
- 2025-12-26
- Estimated Expiration
- 2034-12-19
AI Technical Summary
The existing bridge construction caissons have fixed adjustment ropes between the anti-derailment ring and the fixing block, making it difficult to replace the adjustment ropes when they are damaged, which affects the stability of the hoisting.
A steel caisson for bridge construction was designed, employing auxiliary support components and stabilization mechanisms, including docking structures, plug-in parts, and locking parts. The design of a detachable adjusting rope allows for convenient replacement when the adjusting rope is damaged, ensuring hoisting stability.
This allows for easy replacement of the adjusting rope when it is damaged, maintaining the stability of the hoisting and improving the reliability and safety of the hoisting box.
Smart Images

Figure CN223722542U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to bridge construction device technical field especially relates to a bridge construction steel hoist box. BACKGROUND
[0002] Bridge construction refers to the construction of bridgehead approach and diversion structures. The river beach embankment part of the bridgehead approach should be filled with soil with strong water permeability. When encountering a higher construction site, the construction materials are placed on the hoist box. The existing hoist box is hoisted by the cooperation of the lifting rope hook, resulting in poor stability.
[0003] The prior art (CN216583784U) discloses a hoist box for bridge construction, which comprises a bottom plate, a loading and unloading plate is arranged at both ends of the bottom plate, a plurality of adjusting ropes are fixedly arranged between a plurality of anti-dropping rings and a plurality of fixing blocks, a driving motor is arranged on the outer side of the side plate in the middle, a stabilizing mechanism is arranged above the side plate, a retractable belt is arranged on the outer surface of the middle part of the connecting block, an movable rod is arranged at the other end of the loading and unloading plate, the stabilizing mechanism comprises a lifting block, which reduces the inclination of the hoist box, keeps the hoist box stable, facilitates the loading and unloading of goods, reduces the workload of workers, and increases the functionality of the hoist box.
[0004] However, the above-mentioned method has the following problems: since the adjusting ropes are fixedly arranged between the anti-dropping rings and the fixing blocks, it is inconvenient to replace the adjusting ropes when they are damaged, which affects the stability of subsequent hoisting. UTILITY MODEL CONTENTS
[0005] The utility model aims at providing a bridge construction steel hoist box, which aims to solve the problem of the existing hoist box for bridge construction, since the adjusting ropes are fixedly arranged between the anti-dropping rings and the fixing blocks, it is inconvenient to replace the adjusting ropes when they are damaged, which affects the stability of subsequent hoisting.
[0006] To achieve the above-mentioned purpose, the utility model provides a bridge construction steel hoist box, which comprises a hoist box body, two stabilizing mechanisms, a hoisting piece and a plurality of auxiliary supporting assemblies, the two stabilizing mechanisms are arranged on the two sides of the hoist box body respectively, the hoisting piece is arranged on one side of the two stabilizing mechanisms,
[0007] The plurality of auxiliary supporting assemblies are arranged between the hoist box body and the hoisting piece respectively, the auxiliary supporting assembly comprises two butt joint structures, two plug-in pieces and adjusting ropes,
[0008] Two said butt joint structures are arranged on the side of the box body and the hoisting element respectively; the butt joint structure comprises an assembling cylinder and two locking elements, the assembling cylinder is fixedly connected with the box body and located on the side of the box body; the two locking elements are arranged on the two sides of the assembling cylinder respectively; two inserting elements are located in the assembling cylinder respectively; the adjusting ropes are fixedly connected with the two inserting elements and located between the two inserting elements.
[0009] The butt joint structure further comprises two guide frames, the two guide frames are fixedly connected with the assembling cylinder and located in the assembling cylinder respectively; the guide frame is provided with a guide groove located on the side of the guide frame.
[0010] The locking element comprises an operating screw, a knob and a bolt, the operating screw is threadedly connected with the assembling cylinder and located in the assembling cylinder; the knob is fixedly connected with the operating screw and located on the side of the bolt.
[0011] The inserting element comprises a connecting part and an inserting column, the connecting part is fixedly connected with the adjusting rope and located on the side of the adjusting rope; the inserting column is fixedly connected with the connecting part and located on the side of the connecting part.
[0012] The inserting element further comprises two guide blocks and two inclined heads, the two guide blocks are fixedly connected with the inserting column and located on the two sides of the inserting column respectively; the two inclined heads are fixedly connected with the two guide blocks and located on the side of the two guide blocks respectively.
[0013] The bridge construction steel box of the utility model, the hoisting element cooperates with multiple auxiliary support assemblies and two stabilizing mechanisms for stabilizing the box body, and is assembled with hoisting equipment, when one of the adjusting ropes is damaged, the locking elements on the two sides of the assembling cylinder on the box body and the assembling cylinder on the hoisting element are operated respectively, so that the corresponding locking elements loosen the corresponding inserting elements on the adjusting ropes, then the two inserting elements of the functional intact adjusting rope are assembled into the assembling cylinder on the box body and the assembling cylinder on the hoisting element respectively, then the inserting elements are locked and fixed by operating the locking elements on the corresponding assembling cylinders, the replacement of the adjusting ropes can be completed, thereby solving the problem that the existing bridge construction box is inconvenient to replace the adjusting ropes when the adjusting ropes are damaged, thereby affecting the stability of subsequent hoisting. BRIEF DESCRIPTION OF DRAWINGS
[0014] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the drawings needed to be used in the embodiments or prior art description will be briefly introduced.
[0015] Figure 1 is the overall structure schematic diagram of the utility model.
[0016] Figure 2 is the front view of the whole of the utility model.
[0017] Figure 3 is the front view of the butt joint structure of the utility model.
[0018] Figure 4 is the section view of the butt joint structure and the plug-in piece of the utility model.
[0019] 101-hanging box body, 102-stabilizing mechanism, 103-lifting piece, 104-butt joint structure, 105-plug-in piece, 106-adjusting rope, 107-assembly cylinder, 108-locking piece, 109-guiding frame, 110-guiding groove, 111-operating screw rod, 112-knob, 113-latch, 114-connecting part, 115-plug-in column, 116-guiding block, 117-inclined head. DETAILED DESCRIPTION
[0020] The embodiments of the utility model will be described in detail below, the examples of the embodiments are shown in the drawings, the embodiments described below by referring to the drawings are exemplary, and are intended to explain the utility model, and cannot be understood as the limitation of the utility model.
[0021] Please refer to Figures 1-4 , wherein, Figure 1 is the overall structure schematic diagram of the utility model, Figure 2 is the front view of the whole of the utility model, Figure 3 is the front view of the butt joint structure of the utility model, Figure 4 is the section view of the butt joint structure and the plug-in piece of the utility model.
[0022] The utility model discloses a bridge construction steel hangs the box, including the box body 101, two stabilizing mechanisms 102, hoist 103 and a plurality of auxiliary support components, the auxiliary support component includes two docking structure 104, two insert parts 105 and the adjusting rope 106, the docking structure 104 includes the assembly cylinder 107, two locking pieces 108 and two guide frame 109, the guide frame 109 has the guide groove 110, the locking piece 108 includes operating screw rod 111, knob 112 and latch 113, the insert part 105 includes the connecting portion 114 and the insert column 115, the insert part 105 still includes two guide blocks 116 and two oblique head 117, and the preceding scheme has solved the existing bridge construction with the box, because the adjusting rope 106 is fixedly arranged between the anti -drop ring and fixed block, so when the adjusting rope 106 is damaged, it is inconvenient to replace its adjusting rope 106, and then the stability of subsequent hoisting is affected.
[0023] For this specific implementation, the hoisting piece 103 cooperates with multiple auxiliary support assemblies and two stabilizing mechanisms 102 to stabilize the box body 101, and is assembled with a hoisting device to then hoist the box body 101. The specific structure of the stabilizing mechanism 102 and the hoisting piece 103 is referred to the patent document with publication number CN216583784U, which will not be described in detail here.
[0024] Two said docking structures 104 are arranged on one side of the lifting box body 101 and the lifting piece 103 respectively; the docking structure 104 comprises an assembly cylinder 107 and two locking pieces 108, the assembly cylinder 107 is fixedly connected with the lifting box body 101 and located on one side of the lifting box body 101; two said locking pieces 108 are arranged on both sides of the assembly cylinder 107; two said plug-in pieces 105 are located inside the assembly cylinder 107; the adjusting rope 106 is fixedly connected with two said plug-in pieces 105 and located between two said plug-in pieces 105, the lifting piece 103 cooperates with a plurality of said auxiliary support assemblies and two said stabilizing mechanisms 102 to stabilize the lifting box body 101, and is assembled with a lifting device, when one of the adjusting ropes 106 is damaged, the locking pieces 108 on both sides of the assembly cylinder 107 on the lifting box body 101 and the assembly cylinder 107 on the lifting piece 103 are operated respectively, so that the corresponding locking piece 108 loosens the corresponding plug-in piece 105 on the adjusting rope 106, then the two plug-in pieces 105 of the functional adjusting rope 106 are assembled into the assembly cylinder 107 on the lifting box body 101 and the assembly cylinder 107 on the lifting piece 103 respectively, then the plug-in piece 105 is locked and fixed by operating the locking piece 108 on the corresponding assembly cylinder 107, the replacement of the adjusting rope 106 can be completed, thereby solving the problem that the existing bridge construction lifting box is inconvenient to replace the adjusting rope 106 because the adjusting rope 106 is fixedly arranged between the anti-dropping ring and the fixed block, thereby affecting the stability of subsequent lifting.
[0025] Secondly, two said guide frames 109 are fixedly connected with the assembly cylinder 107 and located inside the assembly cylinder 107 respectively; the guide frame 109 has a guide groove 110 located on one side of the guide frame 109, the guide groove 110 provides a guiding effect for the plug-in piece 105, so that the plug-in piece 105 can be better inserted into the assembly cylinder 107 and aligned with two said locking pieces 108.
[0026] Thirdly, the operation screw 111 is threadedly connected with the assembly cylinder 107 and located inside the assembly cylinder 107; the knob 112 is fixedly connected with the operation screw 111 and located on one side of the plug pin 113, when the plug-in piece 105 is located in the assembly cylinder 107, the knob 112 is twisted to make the operation screw 111 rotate, the operation screw 111 drives the plug pin 113 to insert into the plug-in piece 105, and the fixing of the adjusting rope 106 is completed.
[0027] In addition, the connecting part 114 is fixedly connected with the adjusting rope 106 and located on one side of the adjusting rope 106; the inserting column 115 is fixedly connected with the connecting part 114 and located on one side of the connecting part 114, and the connecting part 114 is used for supporting the assembly of the inserting column 115, and the inserting column 115 is used for being inserted into the assembly cylinder 107.
[0028] Furthermore, two guiding blocks 116 are respectively fixedly connected with the inserting columns 115 and respectively located on two sides of the inserting columns 115; two inclined heads 117 are respectively fixedly connected with the two guiding blocks 116 and respectively located on one side of the two guiding blocks 116, and the guiding blocks 116 are arranged on the inserting columns 115 and used for providing guiding action in cooperation with the guiding grooves 110 on the guiding frames 109 when the inserting columns 115 are inserted into the assembly cylinder 107, so that the inserting columns 115 can be better aligned with the locking pieces 108.
[0029] In use of the utility model, the hoisting piece 103 cooperates with the plurality of auxiliary support assemblies and the two stabilizing mechanisms 102 to be used for stabilizing the hoist box body 101 and assembled with hoisting equipment, when one of the adjusting ropes 106 is damaged, the locking pieces 108 on two sides of the assembly cylinder 107 on the hoist box body 101 and the hoisting piece 103 are respectively operated, the knob 112 is twisted to make the operating screw rod 111 drive the bolt 113 to loosen the corresponding inserting columns 115 on the adjusting rope 106, and then the adjusting rope 106 is taken down, then the two inserting columns 115 of the functional intact adjusting rope 106 are inserted into the assembly cylinder 107 through the inclined heads 117 on the guiding blocks 116, and then the two inserting columns 115 are respectively assembled into the assembly cylinder 107 on the hoist box body 101 and the hoisting piece 103 in cooperation with the guiding grooves 110 on the guiding frames 109 on two sides of the assembly cylinder 107, then the locking pieces 108 on the corresponding assembly cylinder 107 are operated, the knob 112 is twisted to make the operating screw rod 111 drive the bolt 113 to be inserted into the inserting column 115, and the replacement of the adjusting rope 106 can be completed, so that the problem that the existing hoist box for bridge construction is inconvenient to replace the adjusting rope 106 when the adjusting rope 106 is damaged and the stability of subsequent hoisting is affected is solved.
[0030] The above disclosure only shows one or more preferred embodiments of the present application, and cannot limit the scope of the present application. Those skilled in the art can understand that the implementation of all or part of the above processes, and the equivalent changes made according to the claims of the present application, still belong to the scope covered by the present application.
Claims
1. A bridge construction steel hanging box, comprising a hanging box body, two stabilizing mechanisms and a lifting piece, the two stabilizing mechanisms are respectively arranged on both sides of the hanging box body; the lifting piece is arranged on one side of the two stabilizing mechanisms; characterized in that, it further comprises a plurality of auxiliary support assemblies, a plurality of the auxiliary support assemblies are respectively arranged between the hanging box body and the lifting piece; the auxiliary support assembly comprises two butt joint structures, two plug-in pieces and an adjusting rope; two butt joint structures are respectively arranged on one side of the hanging box body and the lifting piece; the butt joint structure comprises an assembly cylinder and two locking pieces, the assembly cylinder is fixedly connected with the hanging box body and located on one side of the hanging box body; two locking pieces are respectively arranged on both sides of the assembly cylinder; two plug-in pieces are respectively located inside the assembly cylinder; the adjusting rope is fixedly connected with two plug-in pieces and located between two plug-in pieces.
2. The bridge construction steel hanging box of claim 1, characterized in that, the butt joint structure further comprises two guide frames, two guide frames are respectively fixedly connected with the assembly cylinder and respectively located inside the assembly cylinder; the guide frame has a guide groove, the guide groove is located on one side of the guide frame.
3. The bridge construction steel hanging box of claim 2, characterized in that, the locking piece comprises an operating screw, a knob and a bolt, the operating screw is threadedly connected with the assembly cylinder and located inside the assembly cylinder; the knob is fixedly connected with the operating screw and located on one side of the bolt.
4. The bridge construction steel hanging box of claim 3, characterized in that, the plug-in piece comprises a connecting part and a plug-in column, the connecting part is fixedly connected with the adjusting rope and located on one side of the adjusting rope; the plug-in column is fixedly connected with the connecting part and located on one side of the connecting part.
5. The bridge construction steel hanging box of claim 4, characterized in that, the plug-in piece further comprises two guide blocks and two inclined heads, two guide blocks are respectively fixedly connected with the plug-in column and respectively located on both sides of the plug-in column; two inclined heads are respectively fixedly connected with two guide blocks and respectively located on one side of two guide blocks.