Combined prefabricated shear wall mounting structure

By using a modular precast shear wall structure and connecting staggered closed stirrups with reinforced channel steel and high-strength bolts, the problem of interference of closed stirrups during the hoisting of precast shear walls was solved, improving construction efficiency and overall integrity, and ensuring the performance of the reinforcing steel.

CN223723952UActive Publication Date: 2025-12-26CHANGZHOU ARCHITECTUAL RES INST GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520095139.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-15
Publication Date
2025-12-26
Estimated Expiration
2035-01-15

AI Technical Summary

Technical Problem

In the existing precast shear wall hoisting process, the reserved closed stirrups are prone to interference, which leads to slow construction progress and affects the mechanical and durability properties of the steel bars.

Method used

The composite precast shear wall structure is adopted. By staggering the reserved closed stirrups in two adjacent precast shear wall panels and connecting them with reinforced channel steel and high-strength bolts, an integral structure is formed for hoisting.

Benefits of technology

This avoids interference from the closed stirrups when hoisting precast shear walls individually, improves construction efficiency, enhances overall integrity, and ensures the mechanical and durability properties of the reinforcing steel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223723952U_ABST
    Figure CN223723952U_ABST
Patent Text Reader

Abstract

The utility model discloses a combined type prefabricated shear wall installation structure which comprises at least two prefabricated shear wall plates which are sequentially spliced and assembled in the lateral direction, reserved closed stirrups are arranged on the left side and the right side of each prefabricated shear wall plate, and the reserved closed stirrups at the butt joint position of every two adjacent prefabricated shear wall plates are arranged in a staggered mode. Every two adjacent prefabricated shear wall plates are connected through a reinforcing steel channel set. When the prefabricated shear wall is integrally hoisted, the problem that lateral closed stirrups interfere with one another when the prefabricated shear wall is independently hoisted is avoided, the method of forcibly bending, pulling and pulling the closed stirrups in construction operation is avoided, meanwhile, the integrity of adjacent prefabricated shear wall bodies is enhanced, and the construction efficiency of fabricated vertical operation hoisting is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to prefabricated shear wall installation technical field especially a combined prefabricated shear wall installation structure. BACKGROUND

[0002] With the vigorous popularization and promotion of the national fabricated building, local and enterprises actively respond and implement, prefabricated building occupies a proportion more and more in industry and civil building. At the same time, many problems also appear in the hoisting process of the fabricated shear wall. The general fabricated shear wall structure is connected by post-poured concrete structure between the prefabricated wall, so the prefabricated wall will reserve the steel bar laterally, and the reserved closed steel bar will appear the phenomenon of "fighting" when hoisting the adjacent shear wall, which affects the construction progress and greatly reduces the efficiency of prefabricated hoisting operation.

[0003] Because of the vertical steel bar or grouting sleeve at the installation plug-in place of the prefabricated shear wall and the bottom plate, when completing the installation of single prefabricated shear wall plate, the reserved closed stirrup of the adjacent shear wall plate will interfere with the reserved closed stirrup of the last shear wall plate, and the phenomenon of "fighting" appears. In the field hoisting, the reserved lateral closed stirrup is often bent and pulled and pulled, which realizes the requirement of field hoisting and speeds up the engineering construction progress, but also affects the mechanical properties and durability of the steel bar. UTILITY MODEL CONTENTS

[0004] The technical problem to be solved by the utility model is that in order to overcome the deficiencies in the prior art, a combined prefabricated shear wall installation structure is provided.

[0005] The technical scheme adopted by the utility model to solve the technical problem is that a combined prefabricated shear wall installation structure comprises at least two prefabricated shear wall plates which are sequentially assembled laterally, and the left and right sides of the prefabricated shear wall plate are provided with reserved closed stirrups, and the reserved closed stirrups of the two adjacent prefabricated shear wall plates at the butt joint are arranged in a staggered manner.

[0006] The two adjacent prefabricated shear wall plates are connected through a reinforcing channel steel group.

[0007] Further, the reinforcing channel steel group comprises upper and lower reinforcing channel steel groups arranged on the front and / or back of the prefabricated shear wall plate.

[0008] Further, the prefabricated shear wall plate and the reinforcing channel steel are provided with corresponding reserved holes and are connected through bolts.

[0009] The precast shear wall plate is usually 200mm thick, and the punching position of the high-strength bolt must avoid the embedded steel mesh, and the selection of the reinforcing channel steel and the high-strength bolt is determined according to the size of the wall plate and through calculation. Meanwhile, according to the requirements of the project, a 10mm gap is left between the closed stirrup and the adjacent shear wall at the staggered contact position.

[0010] Further, the upper end of the shear wall plate is provided with vertical steel bars.

[0011] The utility model discloses utilize the bending tensile capacity of reinforcing channel steel and the shearing capacity of high-strength bolt, realize the integral hoisting of precast shear wall.

[0012] The utility model has the advantages that: the utility model realizes that a plurality of precast shear wall plates are assembled into a whole in advance through structure improvement, avoids the mutual interference of lateral closed stirrups when hoisting the precast shear wall alone, avoids the forced bending and pulling of the closed stirrup in construction operation, enhances the integrity of adjacent precast shear wall bodies, and greatly improves the construction efficiency of assembly type vertical operation hoisting. DRAWINGS

[0013] In order to more clearly illustrate the technical scheme in the embodiments of the utility model or the prior art, the following will briefly introduce the drawings needed to be used in the embodiment or the prior art description, and obviously, the drawings in the following description are only some embodiments in the application, and for those skilled in the art, other drawings can also be obtained according to these drawings without creative labor.

[0014] Fig. 1 It is the structural schematic diagram of the utility model;

[0015] Fig. 2 It is the assembly three-dimensional structure schematic diagram of the precast shear wall plate in the utility model;

[0016] Fig. 3 It is the partial side view of the precast shear wall plate in the utility model.

[0017] The reference numerals in the drawing are: 1, precast shear wall plate, 2, reserved closed stirrup, 3, reinforcing channel steel, 4, bolt, 5, vertical steel bar. CONCRETE EMBODIMENT

[0018] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described in the following with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor belong to the protection scope of the utility model.

[0019] As Figs. 1-3 The utility model discloses a combined prefabricated shear wall mounting structure, which comprises at least two prefabricated shear wall plates 1 which are sequentially spliced and assembled laterally, and reserved closed stirrups 2 are arranged on the left and right sides of the prefabricated shear wall plates 1.

[0020] The two prefabricated shear wall plates 1 are connected through a reinforcing channel steel group.

[0021] The reinforcing channel steel group comprises two sets of reinforcing channel steels 3 arranged on the front and / or back of the prefabricated shear wall plates 1. Corresponding reserved holes are arranged on the prefabricated shear wall plates 1 and the reinforcing channel steels 3, and are connected through bolts 4. Vertical steel bars 5 are arranged at the upper ends of the prefabricated shear wall plates 1.

[0022] Working principle:

[0023] According to the actual working condition, a plurality of prefabricated shear wall plates of a preset number are assembled into a whole in advance.

[0024] Without changing the form of the lateral reserved steel bars of the shear wall, the hoisting sequence on site is improved.

[0025] 1. The reserved closed stirrups of the prefabricated shear wall are arranged in a staggered manner.

[0026] 2. The reinforcing channel steels and high-strength bolts are used to fix and splice into an integral whole.

[0027] 3. The prefabricated shear wall is hoisted integrally from above to below above the reserved inserted steel bars, and the pouring at the final vertical joint is completed.

[0028] When the prefabricated shear wall is hoisted integrally, the problem of mutual interference of the lateral closed stirrups during the hoisting of the prefabricated shear wall alone is avoided, the method of forcibly bending and pulling the closed stirrups during construction operation is avoided, the integrity of the adjacent prefabricated shear wall bodies is enhanced, and the construction efficiency of the assembly type vertical operation hoisting is greatly improved. The prefabricated shear wall is hoisted from above to below above the reserved inserted steel bars, and the reinforcing channel steels and high-strength bolts can be removed after hoisting in place.

[0029] The above merely describes a preferred embodiment of the present application, and the protection scope of the present application is not limited thereto, and any skilled person in the art, according to the technical scheme and the inventive concept of the present application, makes equivalent replacement or change within the technical range disclosed by the present application, which should be covered within the protection scope of the present application.

Claims

1. A combined precast shear wall installation structure, characterized by: The application relates to a prefabricated shear wall panel (1) which comprises at least two prefabricated shear wall panels (1) which are assembled in sequence from left to right, and the left and right sides of the prefabricated shear wall panel (1) are provided with reserved closed stirrups (2), and the reserved closed stirrups (2) of the two adjacent prefabricated shear wall panels (1) are arranged in a staggered mode. The two adjacent prefabricated shear wall panels (1) are connected through a reinforcing channel steel group.

2. The modular precast shear wall installation structure of claim 1, wherein: The reinforcing channel steel group comprises upper and lower reinforcing channel steel groups (3) arranged on the front and / or back of the prefabricated shear wall panel (1).

3. The modular precast shear wall installation structure of claim 1, wherein: The prefabricated shear wall panel (1) and the reinforcing channel steel (3) are provided with corresponding reserved holes, and are connected through bolts (4).

4. The modular precast shear wall installation structure of claim 1, wherein: The upper end of the prefabricated shear wall panel (1) is provided with vertical steel bars (5).