Climbing frame type unloading platform for building construction
The design of the climbing frame unloading platform solves the problems of cumbersome construction and inconvenient hoisting of existing unloading platforms, and realizes convenient installation and safe hoisting, which is suitable for construction needs at different heights.
Patent Information
- Application Number
- CN202520061019.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-10
- Publication Date
- 2025-12-26
- Estimated Expiration
- 2035-01-10
AI Technical Summary
Existing construction unloading platforms are generally built from the ground floor, which is a complicated process, inconvenient for hoisting, and poses safety risks, and is time-consuming and labor-intensive.
The climbing frame unloading platform is constructed by attaching it to the climbing frame and building. The combination of movable outriggers and main beams enables convenient installation and lifting of the platform, avoiding repeated construction.
It enables convenient installation and hoisting of the unloading platform, improves safety and efficiency, has a wide range of applications, and meets the needs of different heights.
Smart Images

Figure CN223724194U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of work platform, concretely relates to a climbing frame type unloading platform for building construction. BACKGROUND
[0002] The building work platform plays different roles in building construction according to different specific types, and has the following roles: 1) providing working space, in the building construction process, the construction platform provides a temporary working space for the construction personnel, so that they can conveniently carry out high-altitude operation, such as installation, welding, plastering, etc.; 2) ensuring construction safety, the construction platform is usually built with scaffolding, steel pipes and other materials, has sufficient stability and carrying capacity, can effectively prevent falling accidents of construction personnel during high-altitude operation, and ensures their life safety; 3) improving work efficiency: the construction of the construction platform enables the construction personnel to more conveniently carry out high-altitude operation, reduces unnecessary movement and waiting time, and thus improves work efficiency; 4) saving construction cost, compared with the traditional high-altitude operation mode, the use of the construction platform can reduce the labor cost and time cost of construction, and also can alleviate the pressure of engineering appropriation, effectively saves the construction cost.
[0003] However, the existing construction unloading platform generally starts to be installed directly from the bottom layer, the hoisting process is complicated, inconvenient to use, the unloading platform is very inconvenient to hoist, and there is a certain safety risk during hoisting, which is time-consuming and laborious, and the above problems are solved by the unloading platform built by the climbing frame combined with the building, which is convenient to build and easy to use. SUMMARY
[0004] The utility model discloses to the present construction unloading platform generally starts to be built directly from the bottom layer, occupies many materials, the building process is complicated, inconvenient to use, the unloading platform is very inconvenient to hoist, and there is a certain safety risk during hoisting, which is time-consuming and laborious, and the above problems are solved by the unloading platform built by the climbing frame combined with the building, which is convenient to build and easy to use.
[0005] In order to achieve the above object, the utility model adopts the technical scheme, a kind of building construction is unloaded with climbing frame type platform, including two movable legs being fixed in parallel on building main body and two main beams being installed on climbing frame, two movable legs are movably connected with two main beams respectively, at least one vice beam is fixed between two main beams, and step is installed between the frame formed by vice beam and main beam, the end of two main beams away from movable leg is fixed with stand column, and pull rod is arranged between two stand columns and two main beams, when using, first, two main beams are fixed on climbing frame by bolt, then two movable legs are installed on building main body, vice beam is installed between two main beams, then step is installed, the installation of steel structure part of work platform is completed, it is not necessary to build from bottom layer as traditional unloading platform, it can be directly installed and used at the height required, when the height of unloading platform needs to be changed, after two movable legs are disassembled, unloading platform is lifted by the lifting of climbing frame, so that unloading platform is raised and lowered along with climbing frame, it need not be repeatedly built, different height use demand can be met, and it is more convenient to use, the platform is easy to install, convenient to use, and good in use effect.
[0006] Further, pull ear is also fixed on main beam, and steel wire rope is arranged between pull ear and building, to further improve the stability of work platform.
[0007] Further, pull rod is telescopic pull rod, which is convenient to install on different specifications of protective platform.
[0008] Further, the top of main beam is also provided with guardrail, which can improve the safety of work platform.
[0009] Further, the step is made of 2-4mm thick steel plate.
[0010] Further, rotation connection is adopted between main beam and movable leg, and the angle of work platform can be adjusted by rotation connection of main beam and movable leg, so that the application range is wider.
[0011] The utility model has the advantages of:
[0012] Two main beams are fixed on climbing frame by bolt, then two movable legs are installed on building main body, vice beam is installed between two main beams, then step is installed, the installation of steel structure part of work platform is completed, it is not necessary to build from bottom layer as traditional unloading platform, it can be directly installed and used at the height required, when the height of unloading platform needs to be changed, after two movable legs are disassembled, unloading platform is lifted by the lifting of climbing frame, so that unloading platform is raised and lowered along with climbing frame, it need not be repeatedly built, different height use demand can be met, and it is more convenient to use. BRIEF DESCRIPTION OF DRAWINGS
[0013] In order to more clearly illustrate the technical scheme of the present application, the drawings required to be used in the description will be briefly introduced as follows. Obviously, the drawings in the following description are only some embodiments of the present application, and all other embodiments obtained by those skilled in the art without creative labor based on the drawings also belong to the protection scope of the present application.
[0014] Fig. 1 It is the installation state structural schematic diagram of the present application.
[0015] Fig. 2 It is the three-dimensional structural schematic diagram of the present application.
[0016] Fig. 3 It is the front view structural schematic diagram of the present application.
[0017] In the figure: 1, movable supporting leg; 2, main beam; 3, vice beam; 4, pedal; 5, stand column; 6, pull rod. DETAILED DESCRIPTION
[0018] In order to make the purpose, features and advantages of the present application more obvious and easy to understand, the technical scheme of the present application will be described clearly and completely in the following combined with the drawings in the specific embodiments. Obviously, the following described embodiments are only some embodiments of the present application, but not all the embodiments. Based on the embodiments in the present patent, all other embodiments obtained by those skilled in the art without creative labor also belong to the protection scope of the present patent.
[0019] As Figs. 1-3As shown in the embodiment, the utility model provides a building construction is with climbing frame formula unloading platform, including two movable legs 1 and two main beams 2 of installing on the climbing frame of being fixed in parallel on the building main body, two movable legs 1 respectively with two main beams 2 swing joint, the rotation connection between main beam 2 and movable leg 1, through the main beam 2 and movable leg 1 of rotation connection, the angle of work platform can be adjusted, the scope of application is more extensive, main beam 2 still has the pull ear 7 of fixing, and the pull ear 7 with building between setting up wire rope, through wire rope further improves the stability of work platform, between two main beams 2 fixed at least one vice beam 3, and the frame between vice beam 3 and main beam 2 installs the footboard 4, the footboard 4 adopts 2-4mm thick steel sheet, two main beams 2 away from movable leg 1 one end is all fixed with the stand 5, and two stand 5 with two main beams 2 between all are provided with pull rod 6, and pull rod 6 adopts telescopic pull rod, through telescopic pull rod to facilitate installation on different specifications protection platform, the top of main beam 2 still is provided with guardrail, through guardrail can improve the security of work platform, when using, first two main beams 2 are fixed on the climbing frame through bolt, then two movable legs 1 are installed on the building main body, and then install vice beam 3 between two main beams 2, then install footboard 4, complete the installation of work platform steel structure part, need not with traditional unloading platform same from bottom layer starts to build, can directly install and use at the height that needs to use, when needing to change the height of unloading platform, through the unloading platform of two movable legs 1 after dismounting, through the lifting of climbing frame drives, make the unloading platform follow climbing frame and increase and reduce, need not repeat to build, can satisfy the use demand of different height, use more convenient, the platform is convenient to install, convenient to use, and the use effect is good.
[0020] The above description of disclosed embodiments enables those skilled in the art to carry out or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the generic principles defined herein can be applied to other embodiments without departing from the spirit or scope of the present application. Thus, the present application is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A climbing frame type unloading platform for building construction, comprising two movable legs (1) fixed in parallel on a building main body and two main beams (2) installed on the climbing frame, characterized in that, Two movable legs (1) are movably connected with two main beams (2), at least one sub-beam (3) is fixed between the two main beams (2), a pedal (4) is installed between the frame formed by the sub-beam (3) and the main beam (2), a stand (5) is fixed at the end of the two main beams (2) away from the movable leg (1), and a pull rod (6) is arranged between the two stands (5) and the two main beams (2).
2. The climbing scaffold debris platform for construction in accordance with claim 1, wherein, A pull ear (7) is also fixed on the main beam (2), and a steel wire rope is arranged between the pull ear (7) and the building.
3. The climbing scaffold debris platform for construction in accordance with claim 1, wherein, The pull rod (6) is a telescopic pull rod.
4. The climbing scaffold debris platform for construction in accordance with claim 1, wherein, A guardrail is arranged on the top of the main beam (2).
5. The climbing scaffold debris platform for construction, according to claim 1, wherein, The pedal (4) is made of a 2-4mm thick steel plate.
6. The climbing scaffold debris platform for construction, according to claim 1, wherein, The main beam (2) and the movable leg (1) are rotatably connected.