Clamp for bridge reinforcement

By designing a clamp for bridge reinforcement and utilizing a combination structure of clamping frame and reinforcement beam, the problems of high construction difficulty and safety before bridge reinforcement were solved, achieving a fast and safe reinforcement effect.

CN223753221UActive Publication Date: 2026-01-02YANTAI UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520027778.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-07
Publication Date
2026-01-02
Estimated Expiration
2035-01-07

AI Technical Summary

Technical Problem

The lack of rapid clamping devices in existing bridge reinforcement technologies makes construction difficult and leaves bridges in a dangerous state before reinforcement.

Method used

Design a bridge reinforcement clamp, including a beam frame, a first clamping frame and a second clamping frame. Through components such as fixing bolts, fixing nuts and reinforcement beams, the bridge can be quickly clamped and reinforced, forming a triangular structure to improve the load-bearing capacity, and using traction steel wires to provide traction force.

Benefits of technology

This enabled rapid reinforcement of the bridge, improved construction efficiency, shortened the processing cycle, and ensured the safety of the bridge before reinforcement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223753221U_ABST
    Figure CN223753221U_ABST
Patent Text Reader

Abstract

The utility model discloses a bridge reinforcing clamp which comprises a beam frame, a first clamping frame and a second clamping frame, the first clamping frame and the second clamping frame are arranged on the two sides of the beam frame, a second fixing frame is arranged on the first clamping frame, and a first fixing frame is connected to the second clamping frame. Fixing bolts which are uniformly distributed are arranged at the position, close to the first clamping frame, of the second clamping frame, fixing nuts are connected to the fixing bolts, and reinforcing beams which are connected with the fixing bolts in a penetrating mode are arranged on the fixing bolts; and the first mounting plate is located at the position, close to the second clamping frame, of the lower side of the first fixing frame, and first anchoring bins are symmetrically mounted on the first mounting plate. Through the first clamping frame and the second clamping frame which are arranged on the two sides of the beam frame, the beam frame can be clamped through the first clamping frame and the second clamping frame, then installation of an equipment foundation frame can be rapidly achieved, and the efficiency of erecting a fixing clamp on the beam frame is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to bridge reinforcing technical field, concretely is a bridge reinforcing clamp for bridge reinforcing. BACKGROUND

[0002] Bridge reinforcing refers to the technology of reinforcing processing on the bridge that has been completed construction and put into use, and the bridge reinforcing can reinforce and repair the bridge that has problems in use, and improve the safety performance of the bridge, so a bridge reinforcing clamp is provided to reinforce the bridge.

[0003] The existing bridge generally adopts pouring reinforcing when reinforcing, and the reinforcing quality is high but the construction difficulty is big, and the waiting time is long, and there is no clamp that can fix and clamp the bridge before reinforcing the bridge, so that the bridge is in a dangerous state before the bridge reinforcing is poured, therefore, a bridge reinforcing clamp is provided to quickly reinforce the bridge. UTILITY MODEL CONTENTS

[0004] The utility model aims at providing a bridge reinforcing clamp to solve the problems in the background art.

[0005] To achieve the above object, the utility model provides the following technical scheme.

[0006] A bridge reinforcing clamp comprises:

[0007] A beam frame and first and second clamping frames arranged on both sides of the beam frame, the first clamping frame is provided with a second fixing frame, the second clamping frame is connected with a first fixing frame, the second clamping frame is provided with uniformly distributed fixing bolts close to the first clamping frame, the fixing bolts are connected with fixing nuts, and a reinforcing beam is arranged on the fixing bolts in penetrating connection with the fixing bolts;

[0008] A first mounting plate is arranged close to the second clamping frame below the first fixing frame, the first mounting plate is symmetrically provided with a first anchoring bin, the first fixing frame is connected with a second mounting plate away from the first mounting plate, the second mounting plate is provided with a mounting hole, and a second anchoring seat is arranged on the edge of the mounting hole;

[0009] A third mounting plate is arranged close to the first clamping frame below the second fixing frame, the second fixing frame is provided with a fourth mounting plate away from the third mounting plate, the third mounting plate is provided with a first mounting groove, the edge of the first mounting groove is provided with a first anchoring groove in advance, an anchoring rod is arranged in the first anchoring groove, and a first anchoring seat is arranged on the third mounting plate close to the first anchoring bin;

[0010] The first positioning bolt is provided through the third mounting plate and the first mounting plate, and a first positioning nut matched with the first positioning bolt is arranged on the first positioning bolt.

[0011] Preferably, the second mounting plate and the fourth mounting plate are both provided with clamping pieces, and the second mounting plate and the fourth mounting plate have the same structure.

[0012] Preferably, the clamping piece is symmetrically provided with a second mounting groove, a second anchoring groove is pre-provided at the side of the second mounting groove, a second positioning bolt is arranged through the mounting hole of the clamping piece, a second positioning nut matched with the second positioning bolt is connected to the second positioning bolt, and a second anchoring bin is arranged close to the second anchoring seat of the clamping piece.

[0013] Preferably, the second anchoring bin and the second anchoring seat are snap-connected, and the second anchoring seat is in communication with the second anchoring groove.

[0014] Preferably, the first anchoring bin and the first anchoring seat are snap-connected, and the first anchoring seat is in communication with the first anchoring groove.

[0015] Preferably, the positioning seat and the first anchoring groove are snap-connected, and the positioning seat is designed in an integrated manner with the anchoring rod.

[0016] Preferably, the reinforcing beam is provided with a perforation, a pulling steel wire is arranged in the perforation, and a positioning workpiece is arranged close to the reinforcing beam.

[0017] Preferably, the perforations are uniformly arranged on the reinforcing beam, and the positioning workpiece and the pulling steel wire are in a threaded fixed mounting connection structure.

[0018] Compared with the prior art, the beneficial effects of the utility model are:

[0019] 1. The first clamping frame and the second clamping frame arranged on both sides of the beam frame can clamp the beam frame, so that the installation of the equipment foundation frame can be quickly realized, and the efficiency of the beam erecting fixing clamp is improved.

[0020] 2. The first mounting plate and the third mounting plate are butted and mounted, so that the second fixed frame and the first fixed frame can be mounted on the first clamping frame and the second clamping frame, the second fixed frame and the first fixed frame form a triangular structure with the first clamping frame and the second clamping frame, the bearing capacity of the first clamping frame and the second clamping frame is improved, and the first clamping frame and the second clamping frame are convenient for subsequent installation of the reinforcing beam.

[0021] 3. The utility model discloses a reinforcing beam can be connected with the beam frame of bridge two ends and handle, and then can pull the beam frame of both sides and realize the reinforcing treatment of bridge whole, install the pulling steel wire on the reinforcing beam can provide the pulling force for reinforcing beam, and then can realize the efficient reinforcing of reinforcing beam, shorten the processing cycle simultaneously. BRIEF DESCRIPTION OF DRAWINGS

[0022] Figure 1 It is the whole installation structure schematic drawing of the utility model;

[0023] Figure 2 It is the whole structure schematic drawing of the utility model;

[0024] Figure 3 It is the first clamping frame and second clamping frame installation structure schematic drawing of the utility model;

[0025] Figure 4 It is the first fixed frame and second fixed frame structure schematic drawing of the utility model.

[0026] In the drawing: 1, beam frame;2, first clamping frame;3, second clamping frame;4, first fixed frame;401, first mounting plate;402, first anchoring bin;403, second mounting plate;404, mounting hole;405, second anchoring seat;

[0027] 5, second fixed frame;501, third mounting plate;502, first installation slot;503, first anchoring slot;504, first anchoring seat;505, anchoring rod;506, positioning seat;507, first positioning bolt;508, first positioning nut;509, fourth mounting plate;

[0028] 6, fixed bolt;7, fixed nut;8, clamping piece;801, second installation slot;802, second anchoring slot;803, second positioning bolt;804, second anchoring bin;805, second positioning nut;

[0029] 9, reinforcing beam;91, through -hole;92, pulling steel wire;93, positioning workpiece. DETAILED DESCRIPTION

[0030] In order to make the technical means, creation features, purposes and effects of the utility model easy to understand, the utility model is further described below in combination with specific embodiments.

[0031] In the description of the utility model, it needs to explain, the term "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and so on indicate the position relation or position relation based on the position relation shown in the drawing, only for the convenience of describing the utility model and simplifying the description, and it is not indicated or implied that the indicated device or element must have a specific orientation, a specific orientation and operation, therefore it cannot be understood as the limitation of the utility model. In addition, the term "first", "second" is only for the purpose of description, and cannot be understood as indicating or implying relative importance.

[0032] In the description of the utility model, it needs to explain, unless otherwise specified and limited, the terms "installation", "setting", "connection" and so on should be understood broadly, for example, "connection", can be fixed connection, can be detachable connection, or integrally connected, can be mechanical connection, can be electrical connection, can be directly connected, can be indirectly connected through intermediate medium, can be the communication inside two elements. For ordinary skilled in the art, the specific meaning of the above terms in the utility model can be understood according to the specific circumstances.

[0033] The technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model, obviously, the described embodiments are only a part of the embodiments of the utility model, not all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary skilled in the art without creative labor belong to the scope of protection of the utility model.

[0034] Please refer to Figures 1-4 The utility model provides an embodiment:

[0035] A kind of clamp for bridge reinforcement, it includes:

[0036] Beam frame 1 and the first clamping frame 2 and second clamping frame 3 of being set at its both sides, second fixed frame 5 is provided on the first clamping frame 2, first fixed frame 4 is connected on the second clamping frame 3, second clamping frame 3 is close to the first clamping frame 2 place and is provided with the fixed bolt 6 of uniform distribution, and fixed nut 7 is connected on the fixed bolt 6, fixed bolt 6 is provided with reinforcing beam 9 connected with it and is penetrated;

[0037] First mounting plate 401, first mounting plate 401 is located at the lower side of first fixed frame 4 close to second clamping frame 3, first mounting plate 401 is symmetrically installed with first anchoring bin 402, the end of first fixed frame 4 away from first mounting plate 401 is connected with second mounting plate 403, second mounting plate 403 is provided with mounting hole 404, second anchoring seat 405 is installed at the edge of mounting hole 404;

[0038] The third mounting plate 501 is located close to the first clamping frame 2 at the lower end of the second fixed frame 5, the end of the second fixed frame 5 away from the third mounting plate 501 is provided with a fourth mounting plate 509, the third mounting plate 501 is provided with a first mounting slot 502, the edge of the first mounting slot 502 is provided with a first anchoring slot 503, the first anchoring slot 503 is provided with an anchoring rod 505, the third mounting plate 501 is provided with a first anchoring seat 504 close to the first anchoring bin 402, the first anchoring bin 402 and the first anchoring seat 504 are snap-fit connected, the first anchoring seat 504 is in communication with the first anchoring slot 503, the first anchoring bin 402 and the first anchoring seat 504 are in butt joint to form a pouring bin, and the butt joint of the first mounting plate 401 and the third mounting plate 501 is improved.

[0039] The first positioning bolt 507 is arranged between the third mounting plate 501 and the first mounting plate 401, and the first positioning bolt 507 is provided with a first positioning nut 508 matched therewith, the side of the anchoring rod 505 is provided with a positioning seat 506 corresponding to the first anchoring slot 503, the positioning seat 506 and the first anchoring slot 503 are snap-fit connected, and the positioning seat 506 and the anchoring rod 505 are designed in an integrated manner, so that the anchoring rod 505 is convenient to install and grouting treatment is carried out.

[0040] In one of the embodiments, the second mounting plate 403 and the fourth mounting plate 509 are provided with clamping pieces 8, the second mounting plate 403 and the fourth mounting plate 509 have the same structure, the clamping pieces 8 mounted on the second mounting plate 403 and the fourth mounting plate 509 can position the top end interval of the first fixed frame 4 and the second fixed frame 5, and cooperate with the second fixed frame 5 and the first fixed frame 4 to form a triangular structure with the first clamping frame 2 and the second clamping frame 3, so that the bearing capacity of the first clamping frame 2 and the second clamping frame 3 is improved.

[0041] In one of the embodiments, the clamping piece 8 is provided with a second mounting slot 801 symmetrically arranged thereon, the side of the second mounting slot 801 is provided with a second anchoring slot 802, the clamping piece 8 is provided with a second positioning bolt 803 also penetrating the mounting hole 404, the second positioning bolt 803 is connected with a second positioning nut 805 matched therewith, the clamping piece 8 is provided with a second anchoring bin 804 close to the second anchoring seat 405, the second anchoring bin 804 and the second anchoring seat 405 are snap-fit connected, the second anchoring seat 405 is in communication with the second anchoring slot 802, the second anchoring bin 804 and the second anchoring seat 405 are in butt joint to form a pouring bin, the fixed slurry can be injected into the pouring bin through the second anchoring slot 802, and the fixed connection of the clamping piece 8 with the second mounting plate 403 and the fourth mounting plate 509 is realized.

[0042] In one of the embodiments, the reinforcing beam 9 is provided with a through hole 91, and a pulling steel wire 92 is arranged in the through hole 91, and the pulling steel wire 92 is provided with a positioning workpiece 93 close to the reinforcing beam 9, the through holes 91 are uniformly arranged on the reinforcing beam 9, and the positioning workpiece 93 and the pulling steel wire 92 are in a threaded fixed mounting connection structure, the beam frame 1 at both ends of the bridge can be connected and processed by mounting the reinforcing beam 9, so that the beam frame 1 at both sides can be pulled to realize the reinforcement of the whole bridge, and the reinforcing beam 9 can provide pulling force for the reinforcing beam 9, so that efficient reinforcement of the reinforcing beam 9 can be realized, and the processing cycle is shortened.

[0043] The working principle of the utility model is as follows: firstly, the first clamping frame 2 and the second clamping frame 3 need to be installed, the first clamping frame 2 and the second clamping frame 3 are butted and attached on the both sides of the beam frame 1, then the first mounting plate 401 and the third mounting plate 501 are butted, the first anchoring bin 402 and the first anchoring seat 504 are butted during butting, the first positioning bolt 507 is taken out and penetrates the first mounting plate 401 and the third mounting plate 501 and the first positioning nut 508 is tightened to be installed, at this time, the first fixed frame 4 and the second fixed frame 5 can be installed on the first clamping frame 2 and the second clamping frame 3, stronger supporting force is provided for the first clamping frame 2 and the second clamping frame 3, and the installation and positioning of the first clamping frame 2 and the second clamping frame 3 and the beam frame 1 are completed, then the clamping piece 8 is taken out and placed on the fourth mounting plate 509 and the second mounting plate 403, the second positioning bolt 803 is taken out and penetrated into the clamping piece 8, the fourth mounting plate 509 and the second mounting plate 403 are butted, the second positioning nut 805 is tightened to complete the positioning installation of the clamping piece 8, finally, the reinforcing beam 9 is taken out and inserted and installed on the fixed bolt 6, the installation of the reinforcing beam 9 is positioned by the fixed nut 7, then the pulling steel wire 92 is taken out and penetrated into the through hole 91 and butted with the reinforcing beam 9 on the opposite beam frame 1, then the pulling steel wire 92 is tensioned and positioned by the positioning workpiece 93, and the reinforcing beam 9 clamps and reinforces the top of the first clamping frame 2 and the second clamping frame 3, the fastening installation of the first clamping frame 2 and the second clamping frame 3 is realized, and the pulling force is provided by the pulling steel wire 92 during use, and the bridge is quickly reinforced.

[0044] The above only is the embodiment of the present application, and the well-known specific structure and characteristics and other common knowledge are not described in detail herein. For those skilled in the art, it is obvious that the present application is not limited to the details of the above exemplary embodiments, and the present application can be implemented in other specific forms without departing from the spirit or basic characteristics of the present application. Therefore, from any point of view, the embodiments should be regarded as exemplary and non-limiting, and the scope of the present application is defined by the appended claims rather than the above description, and therefore all changes falling within the meaning and scope of the equivalent elements of the claims are intended to be included in the present application. Any reference signs in the claims should not be regarded as limiting the claims involved.

Claims

1. A bridge reinforcing clamp characterized by comprising: It includes: Beam frame (1) and first clamping frame (2) and second clamping frame (3) arranged at both sides thereof, second fixed frame (5) is arranged on the first clamping frame (2), first fixed frame (4) is connected on the second clamping frame (3), the second clamping frame (3) is close to the first clamping frame (2) and is provided with uniformly distributed fixed bolt (6), and fixed nut (7) is connected on the fixed bolt (6), reinforcing beam (9) is provided on the fixed bolt (6) and is connected with the fixed bolt (6) through penetration; First mounting plate (401), the first mounting plate (401) is located at the lower side of the first fixed frame (4) and is close to the second clamping frame (3), the first mounting plate (401) is symmetrically provided with first anchor bin (402), the second end of the first fixed frame (4) away from the first mounting plate (401) is connected with second mounting plate (403), the second mounting plate (403) is provided with mounting hole (404), and the edge of the mounting hole (404) is provided with second anchor base (405); Third mounting plate (501), the third mounting plate (501) is located at the lower end of the second fixed frame (5) and is close to the first clamping frame (2), the fourth mounting plate (509) is arranged at the end of the second fixed frame (5) away from the third mounting plate (501), the first mounting groove (502) is formed in the third mounting plate (501), the first anchor groove (503) is preformed at the edge of the first mounting groove (502), the anchor rod (505) is arranged in the first anchor groove (503), and the first anchor base (504) is arranged on the third mounting plate (501) close to the first anchor bin (402); The first positioning bolt (507) is arranged between the third mounting plate (501) and the first mounting plate (401) through penetration, and the first positioning nut (508) matched with the first positioning bolt (507) is arranged on the first positioning bolt (507), and the side of the anchor rod (505) is provided with the positioning base (506) corresponding to the first anchor groove (503).

2. A bridge reinforcement clamp according to claim 1, characterized in that: The second mounting plate (403) and the fourth mounting plate (509) are provided with clamping pieces (8), and the second mounting plate (403) and the fourth mounting plate (509) have the same structure.

3. A bridge reinforcement clamp according to claim 2, wherein: The second mounting groove (801) is symmetrically formed in the clamping piece (8), the second anchor groove (802) is preformed at the side of the second mounting groove (801), the second positioning bolt (803) is arranged on the clamping piece (8) and penetrates the mounting hole (404), the second positioning nut (805) matched with the second positioning bolt (803) is connected on the second positioning bolt (803), and the second anchor bin (804) is arranged on the clamping piece (8) close to the second anchor base (405).

4. A bridge reinforcement clamp according to claim 3, wherein: The second anchor bin (804) and the second anchor base (405) are connected in a clamping mode, and the second anchor base (405) is communicated with the second anchor groove (802).

5. The bridge reinforcement clamp of claim 1, wherein: The first anchor bin (402) and the first anchor base (504) are connected in a clamping mode, and the first anchor base (504) is communicated with the first anchor groove (503).

6. The bridge reinforcement clamp of claim 1, wherein: The positioning seat (506) is in clasp connection with the first anchoring groove (503), and the positioning seat (506) is in integral design with the anchoring rod (505).

7. The bridge reinforcement clamp of claim 1, wherein: The reinforcing beam (9) is provided with a through hole (91), and the through hole (91) is provided with a pulling steel wire (92); the pulling steel wire (92) is provided with a positioning workpiece (93) close to the reinforcing beam (9).

8. A bridge reinforcement clamp according to claim 7, wherein: The through holes (91) are uniformly arranged on the reinforcing beam (9), and the positioning workpiece (93) and the pulling steel wire (92) are in a threaded fixed mounting connection structure.