Piling equipment for water conservancy construction
By deploying the support legs and fixing them with fixing blocks, the instability problem of pile driving equipment used in water conservancy construction was solved, and the stability and accuracy of construction were achieved.
Patent Information
- Application Number
- CN202520426010.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-12
- Publication Date
- 2026-01-23
- Estimated Expiration
- 2035-03-12
AI Technical Summary
Existing pile driving equipment used in water conservancy construction is prone to tipping over during operation and has a high center of gravity, leading to instability in construction.
The support capacity is enhanced by extending the support legs, and the pipe piles are fixed with fixing blocks to ensure the stability of equipment operation and construction quality.
This enhances the stability of the equipment, prevents the pipe piles from shaking and shifting during construction, and ensures the accuracy and safety of the piling process.
Smart Images

Figure CN223824158U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to water conservancy engineering technical field especially relates to a water conservancy construction is with piling equipment. BACKGROUND
[0002] In the water conservancy engineering construction scene, often need to help piling equipment to the original land and implement piling operation, and piling equipment as the mechanical equipment for pile foundation construction in building engineering, can put into the ground pile body such as concrete pile, steel pile or wood pile, play the role of providing support and bearing capacity.
[0003] Through the search, the announcement number CN212200416U a water conservancy construction is with piling equipment, including ground, the both sides of ground top are all installed with installation base, the top of installation base is fixedly connected with bottom rod, the top of bottom rod is fixedly connected with pneumatic cylinder, the output of pneumatic cylinder is fixedly connected with cross bar, the bottom of cross bar is fixedly connected with piling box.The utility model discloses a cylinder pushes up cross bar and moves upwards, and the movement of cross bar makes piling box move, and moves to the same height with wood pile, and wood pile is inserted into the inside of piling box, and wood pile contacts limit plate at this moment, and limit plate moves to the outside, and the movement of limit plate makes clamping spring deform, until the top of wood pile and the bottom of piling rod contact, reach the good stability advantage, solve the stability effect of the poor of the existing water conservancy construction is with piling equipment when using, often incline in the process of piling, so as to not accurate, inconvenient for people to use the problem of piling.
[0004] Based on the above patent, the installation base is used to fix and support the whole device, but the piling equipment is high in height, and the center of gravity is high, which is supported by the installation base alone. The piling equipment is prone to front and back tilting when working. To solve this technical problem, the present application provides a piling equipment for water conservancy construction. Utility model content
[0005] The utility model aims at solving the shortcoming that the piling equipment is prone to front and back tilting when working, and provides a piling equipment for water conservancy construction. By unfolding the supporting legs, the supporting capacity of the supporting column is enhanced, the stability of the equipment during operation is ensured, and the construction safety and quality are guaranteed. The two fixing blocks on the sides are moved close to each other to fix the pipe pile, so as to prevent the pipe pile from shaking, shifting and other situations during construction.
[0006] To achieve the above object, the utility model provides the following technical scheme: A piling equipment for water conservancy construction, including roof, the roof top fixedly connected with hydraulic cylinder, the hydraulic cylinder drive end fixedly connected with punch hammer, the roof bottom left and right sides all are fixedly connected with support column, the support column inner wall all are fixedly connected with motor, motor drive end all are fixedly connected with first screw rod, the first screw rod is connected with support leg through unfolding subassembly, left and right sides The opposite end of support column all are fixedly connected with connecting plate, the opposite end of connecting plate is fixedly connected with sleeve, the sleeve inner wall is provided with fixed cylinder, the fixed cylinder left and right sides all are provided with fixed component.
[0007] Further, the unfolding subassembly includes a threaded sleeve threadedly connected to an outer wall of the first screw rod, the threaded sleeve outer wall is rotatably connected with a support rod on both sides, and the support rod is rotatably connected to the opposite end of the support leg.
[0008] Further, the support column is fixedly connected with a limiting plate on the front and rear sides, and the support leg is slidably connected to the inner wall of the limiting plate.
[0009] Further, the threaded sleeve outer wall is fixedly connected with a first sliding block on both sides, and the first sliding block outer wall is slidably connected to the inner wall of the support column.
[0010] Further, the fixed component includes a knob arranged on the left and right sides of the outer wall of the fixed cylinder, the opposite end of the knob is fixedly connected with a second screw rod, and the opposite end of the second screw rod is rotatably connected with a fixed block.
[0011] Further, the opposite end of the fixed block is fixedly connected with two limiting rods, and the limiting rod outer wall is fixedly connected to the inner wall of the fixed cylinder.
[0012] Further, the fixed cylinder outer wall is fixedly connected with a second sliding block on both sides, and the second sliding block outer wall is slidably connected to the inner wall of the sleeve.
[0013] The utility model has the following beneficial effects:
[0014] 1. In the utility model, the first screw rod is driven to rotate by the motor, the threaded sleeve moves to support the support rod outward, the support leg is unfolded, the support ability of the support column is enhanced, the stability during equipment operation is ensured, and the construction safety and construction quality are further ensured.
[0015] 2. In the utility model, the second screw rod is driven to rotate by rotating the knob, the fixed blocks on both sides are close to each other to fix the pipe pile, so as to prevent the pipe pile from shaking, displacement and other conditions during construction, and ensure the stability and accuracy of the pipe pile during piling. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 A perspective view of a piling equipment for water conservancy construction is provided in the utility model;
[0017] Figure 2 A support column sectional view of the piling equipment for water conservancy construction is provided in the utility model;
[0018] Figure 3 A threaded sleeve schematic view of the piling equipment for water conservancy construction is provided in the utility model;
[0019] Figure 4 A fixed cylinder sectional view of the piling equipment for water conservancy construction is provided in the utility model.
[0020] Legend:
[0021] 1, top plate; 2, hydraulic cylinder; 3, punch hammer; 4, support column; 5, motor; 6, first screw rod; 7, threaded sleeve; 8, support rod; 9, support leg; 10, limit plate; 11, first sliding block; 12, connecting plate; 13, sleeve; 14, fixed cylinder; 15, fixed block; 16, second screw rod; 17, knob; 18, limit rod; 19, second sliding block. DETAILED DESCRIPTION
[0022] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the protection scope of the utility model.
[0023] With reference to Figures 1-3 The utility model provides an embodiment: a piling equipment for water conservancy construction, including top plate 1, top plate 1 top fixedly connected with hydraulic cylinder 2, and hydraulic cylinder 2 drive end fixedly connected with punch hammer 3, and top plate 1 bottom both sides are fixedly connected with support column 4, and support column 4 inner wall is fixedly connected with motor 5, and motor 5 drive end is fixedly connected with first screw rod 6, and first screw rod 6 outer wall is connected with threaded sleeve 7 in screw thread, and threaded sleeve 7 outer wall both sides are rotatably connected with support rod 8, and support rod 8 other end is rotatably connected in support leg 9 opposite end respectively, and support column 4 front and back both sides are fixedly connected with limit plate 10, and support leg 9 outer wall is slidably connected in limit plate 10 inner wall, and threaded sleeve 7 outer wall both sides are fixedly connected with first sliding block 11, and first sliding block 11 outer wall is slidably connected in support column 4 inner wall.
[0024] Specifically, when the first screw rod 6 rotates to move the threaded sleeve 7 up and down, the first sliding block 11 on the outer wall of the threaded sleeve 7 moves in the inner wall of the support column 4 to limit the movement of the threaded sleeve 7, so that the threaded sleeve 7 can only move up and down. Meanwhile, when the support rod 8 moves the support leg 9 outward, the support leg 9 slides in the inner wall of the limiting plate 10, and the limiting plate 10 limits the lateral movement of the support leg 9.
[0025] With reference to Figure 1 and Figure 4 , the opposite ends of the left and right support columns 4 are fixedly connected with the connecting plates 12, the opposite ends of the connecting plates 12 are fixedly connected with the sleeves 13, the inner wall of the sleeve 13 is provided with the fixed cylinder 14, the outer wall of the fixed cylinder 14 is provided with the knobs 17 on the left and right sides, the opposite ends of the knobs 17 are fixedly connected with the second screw rods 16, the opposite ends of the second screw rods 16 are rotatably connected with the fixed blocks 15, the opposite ends of the fixed blocks 15 are fixedly connected with the two limiting rods 18, the outer wall of the limiting rod 18 is fixedly connected with the inner wall of the fixed cylinder 14, and the outer wall of the second sliding block 19 is fixedly connected with the inner wall of the sleeve 13.
[0026] Specifically, when the pipe pile is placed in the fixed cylinder 14, the rotation of the knobs 17 on the left and right sides drives the second screw rod 16 to rotate, so that the fixed block 15 moves inward, and the limiting rod 18 on the outer side of the fixed block 15 slides in the inner wall of the fixed cylinder 14 to limit the fixed block 15, so that the fixed block 15 moves linearly. After the pipe pile is fixed in the fixed cylinder 14, the fixed cylinder 14 is located at a higher position in the sleeve 13, and when the punch hammer 3 presses downward on the fixed cylinder 14, the fixed cylinder 14 moves in the inner wall of the sleeve 13 through the second sliding block 19 to keep the pipe pile stable.
[0027] Working principle: in use, first, fix the support column 4 at the bottom end of the top plate 1, then start the motor 5 to drive the first screw rod 6 to rotate, and the first screw rod 6 drives the threaded sleeve 7 to move upward, so that the threaded sleeve 7 expands the support rods 8 on the left and right sides outward, and the support rods 8 move the support legs 9 outward to expand the support legs 9 and enhance the support capacity of the support column 4. Then, place the pipe pile in the middle of the fixed cylinder 14, and then rotate the knobs 17 on the left and right sides of the fixed cylinder 14 to drive the second screw rod 16 to rotate, and the second screw rod 16 fixes the fixed block 15 on the outer wall of the pipe pile to fix the pipe pile. At this time, the pipe pile is limited by the sleeve 13 and the connecting plate 12, so that it is perpendicular to the punch hammer 3 at the top. Start the hydraulic cylinder 2 to drive the punch hammer 3 to press downward on the top end of the fixed cylinder 14, and the fixed cylinder 14 slides in the inner wall of the sleeve 13 to ensure the perpendicularity of the pipe pile when it is driven into the ground.
[0028] Finally, it should be noted that: the above only for the preferred embodiments of the present application, and is not intended to limit the present application, although the foregoing embodiments of the present application has been described in detail, for the skilled in the art, it still can be modified, or for part of the technical features of the equivalent replacement, the spirit and principles of the present application, made any modification, equivalent replacement, improvement, etc., should be included within the scope of the present application.
Claims
1. A pile driving device for hydraulic construction, characterized in that, The system includes a top plate (1), a hydraulic cylinder (2) fixedly connected to the top of the top plate (1), a punch hammer (3) fixedly connected to the driving end of the hydraulic cylinder (2), support columns (4) fixedly connected to the left and right sides of the bottom of the top plate (1), motors (5) fixedly connected to the inner walls of the support columns (4), and first lead screws (6) fixedly connected to the driving ends of the motors (5). The first lead screws (6) are connected to the support legs (9) through the unfolding assembly. Connecting plates (12) are fixedly connected to the opposite ends of the support columns (4) on both the left and right sides. Sleeves (13) are fixedly connected to the opposite ends of the connecting plates (12). A fixing cylinder (14) is provided on the inner wall of the sleeve (13). Fixing components are provided on the left and right sides of the fixing cylinder (14).
2. The piling equipment for water conservancy construction according to claim 1, characterized in that: The unfolding assembly includes a threaded sleeve (7) threaded to the outer wall of the first lead screw (6), and support rods (8) are rotatably connected to both sides of the outer wall of the threaded sleeve (7). The other end of the support rods (8) is rotatably connected to the opposite end of the support leg (9).
3. The piling equipment for water conservancy construction according to claim 2, characterized in that: The support column (4) is fixedly connected to the limit plate (10) on both the front and rear sides, and the outer wall of the support leg (9) is slidably connected to the inner wall of the limit plate (10).
4. The piling equipment for water conservancy construction according to claim 2, characterized in that: The threaded sleeve (7) has a first slider (11) fixedly connected to both sides of its outer wall, and the outer wall of the first slider (11) is slidably connected to the inner wall of the support column (4).
5. A piling device for water conservancy construction according to claim 1, characterized in that: The fixing assembly includes knobs (17) disposed on the left and right sides of the outer wall of the fixing cylinder (14). Each knob (17) is fixedly connected to a second lead screw (16) at one end, and each second lead screw (16) is rotatably connected to a fixing block (15) at one end.
6. A piling device for water conservancy construction according to claim 5, characterized in that: Two limiting rods (18) are fixedly connected to the opposite ends of the fixed block (15), and the outer walls of the limiting rods (18) are fixedly connected to the inner wall of the fixed cylinder (14).
7. A piling device for water conservancy construction according to claim 1, characterized in that: The outer walls of the fixed cylinder (14) are fixedly connected to the second sliders (19) on both sides, and the outer walls of the second sliders (19) are slidably connected to the inner walls of the sleeve (13).