Metal pipe cleaning and purging mechanism
By designing a sliding frame and an adjustable component-driven metal pipe cleaning and purging mechanism, the problem of the purging head being unable to move in the existing device was solved, enabling comprehensive purging of the metal pipe and the inside of the basket, thus improving purging efficiency.
Patent Information
- Application Number
- CN202520391120.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-07
- Publication Date
- 2026-02-13
- Estimated Expiration
- 2035-03-07
AI Technical Summary
The existing metal pipe purging device cannot effectively move the purging head, resulting in low purging efficiency, especially in the inability to penetrate deep into the basket for thorough purging.
A metal pipe cleaning and purging mechanism was designed, including a sliding frame, a main purging pipe and a branch purging pipe. By adjusting the sliding frame to move in the height and width directions of the base frame, and in combination with the adjustment component driving the toothed plate to mesh and drive the purging head to rotate, the direction adjustment and coverage of multiple purging heads can be realized.
It improves purging efficiency, fully covers the surface of metal pipes and the inside of the basket, and ensures the comprehensiveness and efficiency of the purging effect.
Smart Images

Figure CN223902540U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to metal pipe processing technical field especially relates to a metal pipe cleaning and blowing mechanism. BACKGROUND
[0002] Metal pipe usually uses multiple metal materials, such as stainless steel, aluminum, copper, carbon steel, etc. The surface of metal pipe will be attached with oil stains, cutting fluid and metal chips and other impurities during processing, so it needs to be flushed and blown after metal pipe processing to ensure that the pipe material is clean.
[0003] The utility model with publication number CN213079377U proposes a metal pipe deburring and blowing machine, relating to the technical field of metal pipe processing, which comprises an operation table, an installation frame is arranged on the operation table, a feeding plate and a conveying track connected with the feeding plate are arranged on the installation frame, a moving assembly is arranged on the installation frame corresponding to the position of the conveying track, a pushing rod for pushing the materials in the conveying track is arranged on the moving assembly, an opening is arranged on the conveying track, a blowing pipe for blowing the materials is arranged at the opening, a driving part for driving the blowing pipe to move is arranged on the installation frame, and a blower is communicated with one end of the blowing pipe away from the conveying track. However, the above-mentioned metal pipe blowing device is not convenient to adjust the movement of the blowing head when blowing the metal pipe, which further causes the blowing head to be unable to fully cover the metal pipe for blowing, and the blowing head cannot be deeply blown in the basket for full blowing, causing the problem of low blowing efficiency, so the present scheme proposes a metal pipe cleaning and blowing mechanism to solve the above-mentioned problems. UTILITY MODEL CONTENTS
[0004] Therefore, the utility model provides a metal pipe cleaning and blowing mechanism to solve the technical problem that the blowing head cannot move, which further causes low blowing efficiency.
[0005] The technical scheme of the utility model is realized as follows: the utility model provides a metal pipe cleaning and blowing mechanism, which comprises a base frame, a sliding connection frame, a blowing main pipe and blowing branch pipes, wherein,
[0006] The sliding connection frame is slidingly arranged on the base frame and slides in the height direction of the base frame.
[0007] The blowing main pipe is slidingly arranged on the sliding connection frame and slides in the width direction of the base frame, and the blowing main pipe extends in the length direction of the base frame, the blowing main pipe is communicated with multiple blowing branch pipes, and the multiple blowing branch pipes are equidistantly distributed in the extension direction of the blowing main pipe.
[0008] On the basis of the above technical scheme, preferably, the sliding connection frame comprises two longitudinal frames and a transverse frame, wherein,
[0009] Two longitudinal frames are fixedly connected to two ends of the horizontal frame and are connected to the horizontal frame perpendicularly.
[0010] On the basis of the above technical scheme, preferably, it further comprises a connecting plate, wherein,
[0011] The connecting plate is slidingly connected to the base frame, and the two longitudinal frames are fixedly connected to the connecting plate, and the two longitudinal frames are symmetrically distributed relative to the middle part of the connecting plate.
[0012] On the basis of the above technical scheme, preferably, it further comprises a blowing head, wherein,
[0013] The blowing head is connected to the end of the blowing branch pipe, and the blowing branch pipe is a blowing hose.
[0014] On the basis of the above technical scheme, preferably, it further comprises an outer connecting block, a first position adjusting gear roller, a gear plate and an adjusting component, wherein,
[0015] The outer connecting block is fixedly connected to the blowing head, and the first position adjusting gear roller is arranged on the outer connecting block;
[0016] Two gear plates are slidingly arranged in the length direction of the base frame and are located on the two sides of the first position adjusting gear roller, and tooth grooves meshing with the first position adjusting gear roller are formed in the two gear plates;
[0017] The adjusting component is used for adjusting the movement of the two gear plates in opposite directions.
[0018] On the basis of the above technical scheme, preferably, the adjusting component comprises a mounting plate and a second position adjusting gear roller, wherein,
[0019] A sliding block is slidingly connected to the horizontal frame, and the sliding block is fixedly connected to the blowing main pipe;
[0020] The mounting plate is fixedly connected to the sliding block, and the second position adjusting gear roller is rotatably arranged on one side of the mounting plate, and the second position adjusting gear roller meshes with the two gear plates.
[0021] On the basis of the above technical scheme, preferably, the adjusting component further comprises a screw rod and a locking nut, wherein,
[0022] A threaded hole is formed in the mounting plate, the screw rod is threadedly connected to the threaded hole and is fixedly connected to the second position adjusting gear roller;
[0023] Two locking nuts are threadedly connected to the screw rod and are located on the two sides of the mounting plate.
[0024] On the basis of the above technical scheme, preferably, a handle is fixedly connected to the screw rod.
[0025] Preferably, the blowing head is a conical head.
[0026] Preferably, the bottom of the sliding block is provided with a chuck, and the chuck is clamped and connected with the blowing main pipe.
[0027] The metal pipe cleaning and blowing mechanism has the following beneficial effects compared with the prior art:
[0028] (1) By adjusting the height direction of the sliding bracket on the base frame, the blowing main pipe can be moved to the inside of the hanging basket, and the blowing branch pipe can be moved to the ideal blowing position. The blowing main pipe covers the metal pipe in the length direction of the base frame. By adjusting the back-and-forth movement of the blowing main pipe in the width direction of the base frame, the blowing process of the metal pipe is completed. By setting the blowing main pipe to move in the height and width directions of the base frame, the blowing main pipe can be moved to the same level as the hanging basket and to the inside of the hanging basket, thereby improving the blowing effect of the blowing branch pipe on the metal pipe.
[0029] (2) By adjusting the two tooth plates to move in opposite directions at the same time through the adjusting component, the first positioning tooth roller is driven to rotate synchronously under the meshing action of the two tooth plates. The first positioning tooth roller drives the blowing head to rotate through the outer connecting block, so that the plurality of blowing heads rotate to one side at the same time, the blowing direction of the blowing head is adjusted and processed, and the use is convenient. BRIEF DESCRIPTION OF DRAWINGS
[0030] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the following will briefly introduce the drawings needed to be used in the embodiment or prior art description. Obviously, the drawings in the following description are only some embodiments of the present application, and for those skilled in the art, other drawings can also be obtained without creative labor on the basis of these drawings.
[0031] Fig. 1 It is a right side view of the metal pipe cleaning and blowing mechanism of the present application.
[0032] Fig. 2 It is a left side view of the metal pipe cleaning and blowing mechanism of the present application.
[0033] Fig. 3 It is a perspective view of the blowing main pipe of the metal pipe cleaning and blowing mechanism of the present application.
[0034] Fig. 4 It is a perspective view of the adjusting component structure of the metal pipe cleaning and blowing mechanism of the present application.
[0035] In the diagram: 11. Base frame; 12. Sliding frame; 121. Longitudinal frame; 122. Transverse frame; 13. Connecting plate; 21. Main purging pipe; 22. Branch purging pipe; 23. Purging head; 24. Sliding block; 31. External connecting block; 32. First adjusting toothed roller; 4. Toothed plate; 5. Adjusting component; 51. Mounting plate; 511. Threaded hole; 53. Screw; 52. Second adjusting toothed roller; 54. Locking nut; 55. Handle. Detailed Implementation
[0036] The technical solutions of this utility model will be clearly and completely described below with reference to the embodiments of this utility model. Obviously, the described embodiments are only a part of the embodiments of this utility model, and not all of them. Based on the embodiments of this utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of this utility model.
[0037] like Figs. 1-4 As shown, the metal pipe cleaning and purging mechanism of this utility model includes a base frame 11, a sliding frame 12, a main purging pipe 21, and purging branch pipes 22. The sliding frame 12 is slidably disposed on the base frame 11 and slides in the height direction of the base frame 11. The main purging pipe 21 is slidably disposed on the sliding frame 12 and slides in the width direction of the base frame 11. The main purging pipe 21 extends in the length direction of the base frame 11. The main purging pipe 21 is connected to a plurality of purging branch pipes 22, which are equidistantly distributed in the extension direction of the main purging pipe 21.
[0038] In practice, an external hoisting mechanism lifts the basket containing the metal pipe and moves it below the main purging pipe 21. The sliding joint 12 is adjusted to move along the height of the base frame 11, allowing the main purging pipe 21 to move inside the basket and the purging branch pipe 22 to the desired purging position. The main purging pipe 21 covers the metal pipe along the length of the base frame 11. By adjusting the back-and-forth movement of the main purging pipe 21 along the width of the base frame 11, the purging process of the metal pipe is completed. By allowing the main purging pipe 21 to move along both the height and width of the base frame 11, it can be moved to be aligned with the basket and then inside the basket, thereby improving the purging effect of the purging branch pipe 22 on the metal pipe.
[0039] In a preferred embodiment, the sliding frame 12 includes two longitudinal frames 121 and one transverse frame 122, wherein the two longitudinal frames 121 are fixedly connected to both ends of the transverse frame 122 and are perpendicular to each other.
[0040] It also includes a connecting plate 13, wherein the connecting plate 13 is slidably connected to the base frame 11, and both longitudinal frames 121 are fixedly connected to the connecting plate 13, and the two longitudinal frames 121 are symmetrically distributed relative to the middle of the connecting plate 13.
[0041] As a preferred implementation, the blowing head 23 is further included, wherein the blowing head 23 is communicated at the end of the blowing branch pipe 22, and the blowing branch pipe 22 is a blowing hose.
[0042] In this way, the blowing direction can be adjusted.
[0043] As a preferred implementation, the outer connecting block 31, the first positioning tooth roller 32, the tooth plate 4 and the adjusting component 5 are further included, wherein the outer connecting block 31 is fixedly connected with the blowing head 23, and the first positioning tooth roller 32 is arranged on the outer connecting block 31; the two tooth plates 4 are slidably arranged on the length direction of the base frame 11, and are respectively arranged on the two sides of the first positioning tooth roller 32; the tooth grooves, which are engaged with the first positioning tooth roller 32, are arranged on the two tooth plates 4; and the adjusting component 5 is used for adjusting the two tooth plates 4 to move in opposite directions at the same time.
[0044] In the specific implementation, according to the arrangement mode of the metal pipe, when the blowing direction needs to be adjusted, the adjusting component 5 is used to adjust the two tooth plates 4 to move in opposite directions at the same time, and at this time, the first positioning tooth roller 32 is synchronously rotated under the meshing action of the two tooth plates 4, the first positioning tooth roller 32 drives the blowing head 23 to rotate through the outer connecting block 31, so that the plurality of blowing heads 23 are simultaneously rotated to one side, and the adjustment of the blowing direction of the blowing head 23 is completed, which is convenient to use.
[0045] As a preferred implementation, the adjusting component 5 includes the mounting plate 51 and the second positioning tooth roller 52, wherein the sliding block 24 is slidably connected on the cross frame 122, and the sliding block 24 is fixedly connected with the blowing main pipe 21; the mounting plate 51 is fixedly connected with the sliding block 24, and the second positioning tooth roller 52 is rotatably arranged on one side of the mounting plate 51, and the second positioning tooth roller 52 is engaged with the two tooth plates 4.
[0046] In the specific implementation, the second positioning tooth roller 52 is rotated to drive the two tooth plates 4 to synchronously move.
[0047] As a preferred implementation, the adjusting component 5 further includes the screw rod 53 and the locking nut 54, wherein the threaded hole 511 is arranged on the mounting plate 51, the screw rod 53 is threadedly connected with the threaded hole 511 and is fixedly connected with the second positioning tooth roller 52; and the two locking nuts 54 are threadedly connected with the screw rod 53 and are respectively arranged on the two sides of the mounting plate 51.
[0048] In the specific implementation, the screw rod 53 is rotated, and at this time, the screw rod 53 drives the second positioning tooth roller 52 to rotate, so that the positioning of the two tooth plates 4 is completed. After the adjustment of the blowing direction of the blowing head 23 is completed, the two locking nuts 54 are rotated, so that the two locking nuts 54 are tightly attached to the mounting plate 51, and the locking of the screw rod 53 is completed.
[0049] As a preferred implementation, the screw rod 53 is fixedly connected with a handle 55.
[0050] As a preferred implementation, the blowing head 23 is a conical head.
[0051] In this way, the gas pressure of the gas sprayed from the blowing head 23 is increased, thereby improving the blowing effect.
[0052] As a preferred implementation, the bottom of the sliding block 24 is provided with a chuck, and the chuck is clampedly connected with the blowing main pipe 21.
[0053] The working principle of the utility model is introduced as follows:
[0054] The handle 55 is rotated in advance to adjust the blowing direction of the blowing head 23, and the two locking nuts 54 are rotated to make the two locking nuts 54 tightly contact with the mounting plate 51, thereby completing the positioning treatment of the blowing direction of the blowing head 23. The basket containing the metal pipe is lifted by the external lifting mechanism and is moved to the lower side of the blowing main pipe 21, the sliding bracket 12 is adjusted to move in the height direction of the base frame 11, the blowing main pipe 21 is moved to the inside of the basket, and the blowing branch pipe 22 is moved to the ideal blowing position, the blowing main pipe 21 covers the metal pipe in the length direction of the base frame 11, the blowing main pipe 21 is adjusted to move back and forth in the width direction of the base frame 11, and the blowing treatment of the metal pipe is completed.
[0055] The above is only a preferred implementation of the utility model, and is not used to limit the utility model, and any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model should be included in the protection scope of the utility model.
Claims
1. A metal tube cleaning and purging mechanism, characterized by: Including base frame (11), sliding frame (12), blowing main pipe (21) and blowing branch pipe (22), wherein, The sliding frame (12) is slidably arranged on the base frame (11) and slides in the height direction of the base frame (11); The blowing main pipe (21) is slidably arranged on the sliding frame (12) and slides in the width direction of the base frame (11), and the blowing main pipe (21) extends in the length direction of the base frame (11), and the blowing main pipe (21) is communicated with a plurality of blowing branch pipes (22), and the plurality of blowing branch pipes (22) are equidistantly distributed in the extension direction of the blowing main pipe (21).
2. The metal pipe cleaning and purging mechanism according to claim 1, wherein: The sliding frame (12) comprises two longitudinal frames (121) and a transverse frame (122), wherein, The two longitudinal frames (121) are respectively fixedly connected to the two ends of the transverse frame (122) and are connected to each other perpendicularly to the transverse frame (122).
3. The metal pipe cleaning and purging mechanism according to claim 2, wherein: Further comprising a connecting plate (13), wherein, The connecting plate (13) is slidably connected to the base frame (11), and the two longitudinal frames (121) are fixedly connected to the connecting plate (13), and the two longitudinal frames (121) are symmetrically distributed relative to the middle part of the connecting plate (13).
4. The metal pipe cleaning and purging mechanism according to claim 2, wherein: Further comprising a blowing head (23), wherein, The blowing head (23) is communicated at the end of the blowing branch pipe (22), and the blowing branch pipe (22) is a blowing hose.
5. The metal pipe cleaning and purging mechanism according to claim 4, wherein: Further comprising an outer connecting block (31), a first positioning tooth roller (32), a tooth plate (4) and an adjusting component (5), wherein, The outer connecting block (31) is fixedly connected to the blowing head (23), and the first positioning tooth roller (32) is arranged on the outer connecting block (31); Two tooth plates (4) slide in the length direction of the base frame (11) and are respectively located on the two sides of the first positioning tooth roller (32), and tooth grooves meshing with the first positioning tooth roller (32) are formed in the two tooth plates (4); The adjusting component (5) is used for adjusting the movement of the two tooth plates (4) in opposite directions.
6. The metal pipe cleaning and purging mechanism according to claim 5, wherein: The adjusting component (5) comprises a mounting plate (51) and a second positioning tooth roller (52), wherein, The transverse frame (122) is slidably connected with a sliding block (24), and the sliding block (24) is fixedly connected with the blowing main pipe (21); The mounting plate (51) is fixedly connected with the sliding block (24), and the second positioning tooth roller (52) is rotatably arranged on one side of the mounting plate (51), and the second positioning tooth roller (52) meshes with the two tooth plates (4).
7. The metal pipe cleaning and purging mechanism according to claim 6, wherein: The adjusting component (5) further comprises a screw rod (53) and a locking nut (54), wherein, A threaded hole (511) is formed in the mounting plate (51), the screw rod (53) is threadedly connected with the threaded hole (511) and is fixedly connected with the second positioning tooth roller (52); Two locking nuts (54) are threadedly connected with the screw rod (53) and are respectively located on the two sides of the mounting plate (51).
8. The metal pipe cleaning and purging mechanism according to claim 7, wherein: The screw rod (53) is fixedly connected with a handle (55).
9. The metal pipe cleaning and purging mechanism according to claim 4, wherein: The blowing head (23) is a conical head.
10. The metal pipe cleaning and purging mechanism according to claim 6, wherein: The bottom of the sliding block (24) is provided with a chuck which is clamped and connected with the blowing main pipe (21).
Citation Information
Patent Citations
Metal pipe deburring blowing machine
CN213079377U