Green concrete pole reinforcement cage pouring manufacturing device

By designing protective and fixing components, controllable clamping and loosening of the rebar cage casting device was achieved, solving the problem of pipe deformation caused by excessive clamping force and ensuring casting quality and stability.

CN223952268UActive Publication Date: 2026-02-27LANPING DANENG CEMENT PROD CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520624547.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-03
Publication Date
2026-02-27
Estimated Expiration
2035-04-03

AI Technical Summary

Technical Problem

In the existing technology, the clamping force of the steel cage casting device is prone to be too large when clamping the pipe, which can cause the pipe to deform or break, affecting the casting quality.

Method used

A green cement pole rebar cage casting device was designed. By setting up protective and fixing components, and using the cooperation of knobs, gears, toothed rings and racks, the pipe can be controlled to be clamped and released, avoiding excessive clamping force and preventing pipe deformation.

Benefits of technology

This effectively avoids pipe deformation or breakage caused by excessive clamping force, ensures the quality of pouring, prevents the steel cage from floating, and improves the stability of the pouring process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223952268U_ABST
    Figure CN223952268U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of concrete pole reinforcement cage pouring, and discloses a green concrete pole reinforcement cage pouring manufacturing device which comprises a bottom plate, a hydraulic rod is fixed to the surface of the bottom plate, a lifting frame is fixed to the top of the output end of the hydraulic rod, a feeding pipe is arranged on the surface of the lifting frame, the feeding pipe penetrates through the lifting frame, and the feeding pipe penetrates through the lifting frame. According to the green concrete pole reinforcement cage pouring manufacturing device, through the arranged protection assembly, when a clamping plate clamps a pipe, a rotary knob is continuously rotated, the clamping plate moves close to a movable plate, the movable plate turns over, a clamping plate and a clamping block move upwards, the clamping block enters a clamping groove, and the clamping groove abuts against the side, away from the inclined face, of the clamping block; when the rotary knob is rotated reversely, the inclined face of the clamping block abuts against the inner wall of the clamping groove, the clamping block enters the sliding groove, and normal loosening of the pipe is not affected.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to cement pole reinforcement cage pouring technical field, concretely is a kind of green cement pole reinforcement cage pouring manufacturing device. BACKGROUND

[0002] Building construction refers to the process of actual construction and installation of building in construction site according to design scheme and relevant specification, in building construction, reinforcement cage is a common steel bar processing product, used for reinforcement and support in concrete structure, currently, when installing reinforcement cage, it is generally inserted into hole after punching hole and then pouring concrete operation is carried out.

[0003] According to a kind of building construction reinforcement cage pouring device (publication number: CN222478173U) of publicity, the above application is adjusted position by driving mechanism control two abutment plates mutually far away or close to each other, so that pipe can be inserted into the inner wall of two slot, finally control two abutment plates mutually close to each other, so as to clamp pipe, so set, in the process of pouring in later period, upward floating reinforcement cage will abut on the surface of two abutment plates, so as to not float upward, effectively guarantee the quality of pouring.

[0004] But in the above application, when clamping pipe, if personnel do not stop in time, clamping force will be too large, so that pipe deformation will occur, and serious pipe breakage will affect subsequent pouring. UTILITY MODEL CONTENT

[0005] The utility model aims at providing a kind of green cement pole reinforcement cage pouring manufacturing device to solve the problems raised in the above background.

[0006] To achieve the above object, the utility model provides the following technical scheme: a kind of green cement pole reinforcement cage pouring manufacturing device, including bottom plate, the surface of the bottom plate is fixed with hydraulic rod, the output end top of the hydraulic rod is fixed with lifting frame, the surface of the lifting frame is provided with feed pipe, the feed pipe penetrates lifting frame, and feed pipe is fixedly connected with lifting frame, the bottom of the lifting frame is provided with leak hole, the surface of the lifting frame is provided with fixed assembly and protection assembly, the fixed assembly includes cavity, clamping plate, moving plate;

[0007] The protection assembly includes;

[0008] Connecting hole, connecting hole is used for the normal passage of clamping plate;

[0009] Clamping plate, clamping plate is used to drive clamping block synchronous movement;

[0010] Sliding block, sliding block is used to stabilize the movement of clamping plate.

[0011] Preferably, the connecting hole is arranged on the surface and the inner side of the moving plate and the lifting frame, the inner wall of the connecting hole is slidably connected with a sliding block, the end of the sliding block away from the connecting hole is slidably connected with a clamping plate, the clamping plate penetrates through the connecting hole, the top of the clamping plate is provided with a sliding groove, the inner wall of the sliding groove is slidably connected with a clamping block, the bottom of the clamping block is fixedly connected with a second spring, the bottom of the second spring is fixed on the inner wall of the sliding groove, the inner wall of the cavity is provided with a clamping groove at the top, the surface of the clamping plate is hingedly connected with a movable plate, the end of the movable plate away from the clamping plate is hingedly connected with the bottom of the clamping plate, continuously rotating the knob, the clamping plate moves towards the moving plate, the movable plate is turned over, the clamping plate and the clamping block move upwards, the clamping block enters the clamping groove, the clamping groove and the clamping block abut against the side away from the inclined surface, so that the clamping block, the clamping plate and the clamping plate are limited, at this time, the clamping plate cannot continue to clamp the pipe, reversing the knob, the inclined surface of the clamping block abuts against the inner wall of the clamping groove, the clamping block enters the sliding groove, and the pipe is not affected when being loosened.

[0012] Preferably, the cavity is arranged in the inner portion of the lifting frame, the inner wall of the cavity is rotatably connected with a gear ring, the inner wall of the cavity is rotatably connected with a gear, the gear is engaged with the gear ring, the inner portion of the cavity is provided with a rack, the rack penetrates through the lifting frame and is slidably connected with the lifting frame, the rack is provided with two groups, and the two groups of racks are circumferentially arranged with the center of the cavity as an axis, the surface of one group of the two groups of racks is provided with a threaded groove, the inner wall of the threaded groove is threadedly connected with a screw rod, the end of the screw rod away from the rack is fixedly connected with a knob, the surface of the lifting frame is rotatably connected with the knob, the end of the rack close to the center of the cavity is fixedly connected with a moving plate, the side of the moving plate away from the rack is fixedly connected with a first spring, the end of the first spring away from the moving plate is fixedly connected with a clamping plate, the rack is engaged with the gear, the screw rod is rotated by rotating the knob, the rack moves towards or away from the pipe, the two groups of racks are synchronously moved towards or away from each other through the gear and the gear ring, so that the moving plate and the clamping plate clamp or loosen the pipe.

[0013] Preferably, the surface of the bottom plate is provided with a mounting frame, and the surface of the bottom plate is provided with a through hole, so as to facilitate pouring work.

[0014] Preferably, the end of the clamping block away from the second spring is provided with an inclined surface, and when the inclined surface abuts against the inner wall of the clamping groove, the clamping block can move into the sliding groove, and the pipe is not affected when being loosened.

[0015] Preferably, the surface of the clamping plate is fixedly connected with a stabilizing rod, the end of the stabilizing rod away from the clamping plate penetrates through the moving plate and the lifting frame, and the stabilizing rod is slidably connected with the moving plate, so as to stabilize the movement of the clamping plate.

[0016] Compared with the prior art, the green cement pole reinforcement cage pouring manufacturing device has the following beneficial effects:

[0017] 1. The green cement pole reinforcement cage pouring device, through the setting of the protection assembly, when the clamping plate clamps the pipe, continuously rotating the knob, the clamping plate moves close to the moving plate, the movable plate overturns, the clamping plate, the clamping block moves up, the clamping block enters the clamping groove, the clamping groove and the clamping block away from the side of the inclined surface resist, the clamping block, the clamping plate and the clamping plate are limited, the clamping force is too large, the pipe is deformed and damaged, the knob is reversed, the clamping block inclined surface and the clamping groove inner wall resist, the clamping block enters the sliding groove, and the pipe is not affected normal loosening.

[0018] 2. The green cement pole reinforcement cage pouring device, through the setting of the fixing assembly, rotating the knob, the screw rotates, through the gear, the gear ring, the two groups of racks are synchronously close to each other or away from each other, so as to drive the moving plate and the clamping plate to clamp or loosen the pipe, avoid the pipe shaking during pouring, and the moving plate and the clamping plate bottom resist the reinforcement cage, so as to avoid the reinforcement cage floating up. BRIEF DESCRIPTION OF DRAWINGS

[0019] Figure 1 It is a front view structural schematic diagram of the utility model;

[0020] Figure 2 It is a sectional view structural schematic diagram of the utility model;

[0021] Figure 3 It is a fixed assembly, protection assembly bottom view structural schematic diagram of the utility model;

[0022] Figure 4 It is an explosion sectional view structural schematic diagram of part of the fixed assembly, protection assembly of the utility model;

[0023] Figure 5 It is a protection assembly part explosion structural schematic diagram of the utility model;

[0024] Figure 6 It is a clamping plate, movable plate, clamping plate bottom view structural schematic diagram of the utility model.

[0025] In the drawing: 1, bottom plate; 2, through hole; 3, mounting frame; 4, hydraulic rod; 5, lifting frame; 6, feed pipe; 7, fixed assembly; 70, cavity; 71, gear ring; 72, gear; 73, rack; 74, thread groove; 75, screw; 76, knob; 77, moving plate; 78, spring one; 79, clamping plate; 700, stabilizing rod; 8, protection assembly; 80, connecting hole; 81, clamping plate; 82, sliding block; 83, sliding groove; 84, clamping block; 85, spring two; 86, clamping groove; 87, movable plate. DETAILED DESCRIPTION

[0026] As Figures 1-6As shown, the utility model provides a technical scheme: a kind of green cement pole reinforcement cage pouring manufacturing device, including bottom plate 1, the surface of bottom plate 1 is fixed with hydraulic rod 4, the output end top of hydraulic rod 4 is fixed with lifting frame 5, lifting frame 5 surface is provided with feed pipe 6, feed pipe 6 penetrates lifting frame 5, and feed pipe 6 is fixedly connected with lifting frame 5, the bottom of lifting frame 5 is equipped with leak hole, lifting frame 5 surface is provided with fixed assembly 7 and protection assembly 8, fixed assembly 7 includes cavity 70, clamping plate 79, moving plate 77;Protection assembly 8 includes;Connecting hole 80, clamping plate 81, slider 82, sliding slot 83, clamping block 84, spring two 85, card slot 86, movable plate 87.

[0027] Connecting hole 80 is equipped in the surface and inside of moving plate 77, lifting frame 5, the inner wall of connecting hole 80 is slidably connected with slider 82, the end of slider 82 away from connecting hole 80 is slidably connected with clamping plate 81, clamping plate 81 penetrates connecting hole 80, the top of clamping plate 81 is equipped with sliding slot 83, the inner wall of sliding slot 83 is slidably connected with clamping block 84, the bottom of clamping block 84 is fixed with spring two 85, the bottom of spring two 85 is fixed on the inner wall of sliding slot 83, the inner wall top of cavity 70 is equipped with card slot 86, the surface of clamping plate 79 is hinged with movable plate 87, the end of movable plate 87 away from clamping plate 79 is hinged in the bottom of clamping plate 81, the end of clamping block 84 away from spring two 85 is provided as inclined plane, continuously rotate knob 76, clamping plate 79 moves close to moving plate 77, and movable plate 87 overturns simultaneously, drives clamping plate 81 and clamping block 84 to move up, and clamping block 84 enters card slot 86, at this time, card slot 86 and clamping block 84 away from the side of inclined plane abut, i.e. can be positioned to clamping block 84, clamping plate 81, clamping plate 79, at this time, clamping plate 79 cannot continue to clamp pipe, avoid that the pipe is deformed, damaged by excessive clamping force.

[0028] The cavity 70 is arranged in the interior of the lifting frame 5, the inner wall of the cavity 70 is rotationally connected with the gear ring 71, the inner wall of the cavity 70 is rotationally connected with the gear 72, the gear 72 is engaged with the gear ring 71, the interior of the cavity 70 is provided with the rack 73, the rack 73 penetrates through the lifting frame 5 and is slidingly connected with the lifting frame 5, the rack 73 is provided with two groups, and the two groups of rack 73 are circumferentially arranged with the center of the cavity 70 as the axis, the surface of one group of the two groups of rack 73 is provided with the threaded groove 74, the inner wall of the threaded groove 74 is threadedly connected with the screw rod 75, one end of the screw rod 75 away from the rack 73 is fixedly connected with the knob 76, the knob 76 is rotationally connected with the surface of the lifting frame 5, one end of the rack 73 close to the center of the cavity 70 is fixedly connected with the moving plate 77, one side of the moving plate 77 away from the rack 73 is fixedly connected with the spring one 78, one end of the spring one 78 away from the moving plate 77 is fixedly connected with the clamping plate 79, the rack 73 is engaged with the gear 72, the surface of the clamping plate 79 is fixedly connected with the stabilizing rod 700, one end of the stabilizing rod 700 away from the clamping plate 79 penetrates through the moving plate 77 and the lifting frame 5 and is slidingly connected with the moving plate 77, the knob 76 is rotated, the screw rod 75 is rotated, at this time, the rack 73 close to the pipe is moved, at the same time, the gear 72 is rotated, that is, the gear ring 71 is synchronously rotated, that is, the two groups of rack 73 are synchronously close to each other, so that the moving plate 77 and the clamping plate 79 clamp the pipe.

[0029] The surface of the bottom plate 1 is provided with the mounting frame 3, and the surface of the bottom plate 1 is provided with the through hole 2, so as to facilitate subsequent pouring processing.

[0030] In use, the through hole 2 is sleeved on the surface of the reinforcement cage, is fixed on the ground through the mounting frame 3 and the bolt, the space height of the lifting frame 5 can be lifted by opening the hydraulic rod 4 and moving upward, at this time, the pipe for discharging concrete is inserted into the feeding pipe 6, at the same time, the pipe passes through the leakage hole, at this time, the knob 76 is rotated, the screw rod 75 is driven to rotate, at this time, the rack 73 moves close to the pipe, the gear 72 is driven to rotate, the gear ring 71 is synchronously driven to rotate, the two groups of racks 73 are synchronously driven to move close to each other, the moving plate 77 and the clamp plate 79 are driven to clamp the pipe, the knob 76 is continuously rotated, at this time, the clamp plate 79 moves close to the moving plate 77, the spring one 78 is compressed, the movable plate 87 is turned over, the clamping plate 81 and the clamping block 84 are driven to move upward, the movement of the clamping plate 81 is stabilized through the sliding block 82, when the surface of the clamping block 84 is in contact with the inner wall of the cavity 70, the clamping block 84 moves into the sliding groove 83, the spring two 85 is compressed, when the position of the clamping block 84 is parallel to the clamping groove 86, the spring two 85 is released, the clamping block 84 enters the clamping groove 86, at this time, the clamping groove 86 is in contact with the side of the clamping block 84 away from the inclined surface, the clamping block 84, the clamping plate 81 and the clamp plate 79 are limited, at this time, the clamp plate 79 cannot continue to clamp the pipe, the pipe is prevented from being deformed and damaged due to excessive clamping force, at the same time, the bottom of the moving plate 77 and the clamp plate 79 is in contact with the reinforcement cage, the reinforcement cage is prevented from floating up, when the pipe needs to be loosened, the knob 76 is turned over, the inclined surface of the clamping block 84 is in contact with the inner wall of the clamping groove 86, the clamping block 84 enters the sliding groove 83, the clamp plate 79 and the moving plate 77 are prevented from moving away from the pipe, the pipe can be normally loosened, at the same time, the spring one 78 is released, the clamp plate 79 and the movable plate 87 are reset.

[0031] The above is a detailed description of the utility model, but some modifications or improvements can be made on the basis of the utility model, which is obvious to those skilled in the art. Therefore, the modifications or improvements without departing from the spirit of the utility model are within the protection scope of the utility model.

Claims

1. A kind of green cement pole reinforcement cage pouring production device, including bottom plate (1), it is characterized in that: The surface of the bottom plate (1) is fixed with a hydraulic rod (4), the output end top of the hydraulic rod (4) is fixed with a lifting frame (5), the surface of the lifting frame (5) is provided with a feeding pipe (6), the feeding pipe (6) penetrates the lifting frame (5), and the feeding pipe (6) is fixedly connected with the lifting frame (5), the bottom of the lifting frame (5) is provided with a leakage hole, the surface of the lifting frame (5) is provided with a fixing assembly (7) and a protection assembly (8), the fixing assembly (7) comprises a cavity (70), a clamping plate (79), a moving plate (77); The protection assembly (8) comprises; The connecting hole (80) is used for the normal passing of the clamping plate (81); The clamping plate (81) is used for driving the clamping block (84) to move synchronously; The sliding block (82) is used for stabilizing the movement of the clamping plate (81).

2. The green cement pole reinforcement cage pouring manufacturing device according to claim 1, characterized in that: The connecting hole (80) is arranged on the surface and the inner side of the moving plate (77) and the lifting frame (5), the inner wall of the connecting hole (80) is slidably connected with the sliding block (82), one end, away from the connecting hole (80), of the sliding block (82) is slidably connected with the clamping plate (81), the clamping plate (81) penetrates the connecting hole (80), the top of the clamping plate (81) is provided with a sliding groove (83), the inner wall of the sliding groove (83) is slidably connected with the clamping block (84), the bottom of the clamping block (84) is fixedly connected with a second spring (85), the bottom of the second spring (85) is fixed on the inner wall of the sliding groove (83), the inner wall top of the cavity (70) is provided with a clamping groove (86), the surface of the clamping plate (79) is hingedly connected with a movable plate (87), one end, away from the clamping plate (79), of the movable plate (87) is hingedly connected with the bottom of the clamping plate (81).

3. The green cement pole reinforcement cage pouring manufacturing device according to claim 1, characterized in that: The cavity (70) is arranged in the lifting frame (5), the inner wall of the cavity (70) is rotatably connected with a gear ring (71), the inner wall of the cavity (70) is rotatably connected with a gear (72), the gear (72) is engaged with the gear ring (71), the inside of the cavity (70) is provided with a rack (73), the rack (73) penetrates the lifting frame (5), and the rack (73) is slidably connected with the lifting frame (5), the rack (73) is provided with two groups, and the two groups of rack (73) are circumferentially arranged with the center of the cavity (70) as the axis, the surface of one of the two groups of rack (73) is provided with a threaded groove (74), the inner wall of the threaded groove (74) is threadedly connected with a screw rod (75), one end, away from the rack (73), of the screw rod (75) is fixedly connected with a knob (76), the surface of the lifting frame (5) is rotatably connected with the knob (76), one end, close to the center of the cavity (70), of the rack (73) is fixedly connected with the moving plate (77), one side, away from the rack (73), of the moving plate (77) is fixedly connected with a first spring (78), one end, away from the moving plate (77), of the first spring (78) is fixedly connected with the clamping plate (79), the rack (73) is engaged with the gear (72).

4. The green cement pole reinforcement cage pouring manufacturing device according to claim 1, characterized in that: The surface of the bottom plate (1) is provided with a mounting rack (3), and the surface of the bottom plate (1) is provided with a through hole (2).

5. The green cement pole reinforcement cage pouring manufacturing device according to claim 2, characterized in that: The card block (84) is provided with an inclined surface at one end away from the spring (85).

6. The green cement pole reinforcement cage pouring manufacturing device according to claim 3, characterized in that: The surface of the clamping plate (79) is fixed with a stabilizing rod (700), one end of the stabilizing rod (700) away from the clamping plate (79) penetrates through the moving plate (77) and the lifting frame (5), and the stabilizing rod (700) is in sliding connection with the moving plate (77).

Citation Information

Patent Citations

  • Building construction reinforcement cage pouring device

    CN222478173U