Steel structure embedded bolt positioning die

By using a steel structure pre-embedded bolt positioning mold and a positioning template and timber reinforcement design, high-precision positioning and fixing of pre-embedded bolts were achieved, solving the problem of low positioning accuracy of pre-embedded bolts, improving the construction quality of steel structures and reducing costs.

CN224016833UActive Publication Date: 2026-03-20YUNNAN CONSTR & INSTALLATION JOINT STOCK +1
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-03
Publication Date
2026-03-20

AI Technical Summary

Technical Problem

The low positioning accuracy of anchor bolts embedded in the cast-in-place concrete foundation affects the construction quality of the steel structure.

Method used

A steel structure pre-embedded bolt positioning mold is adopted, including a positioning template, an upper reinforcing beam, a lower supporting beam, nails, adjusting nuts, and clamping nuts. Through the design of bolt positioning holes and square holes, combined with the reinforcement of wooden squares and steel pipes, the precise positioning and fixing of pre-embedded bolts can be achieved.

Benefits of technology

It improves the installation accuracy of pre-embedded bolts, ensures the construction quality of steel structures, and the molds can be reused, thus having high economic value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224016833U_ABST
    Figure CN224016833U_ABST
Patent Text Reader

Abstract

The utility model discloses a steel structure embedded bolt rapid positioning die and belongs to the technical field of steel structure construction. The mold comprises a positioning mold plate, an upper reinforcing beam rod, a lower supporting beam rod, iron nails, adjusting nuts and clamping nuts, the positioning mold plate is a solid wood laminate, the beam rods are strip-shaped square timbers, bolt positioning holes are drilled in the positioning mold plate, square holes are formed between the bolt positioning holes, the upper reinforcing beam rod and the lower supporting beam rod are fixed to the upper side and the lower side of the positioning mold plate through the iron nails, and the upper reinforcing beam rod and the lower supporting beam rod are clamped through the clamping nuts. And the lower supporting beam rod is fixed to the concrete foundation formwork, the embedded bolts are installed in the bolt positioning holes, and the clamping nuts and the adjusting nuts are used for fixing the embedded bolts. By means of the mold, construction of the embedded bolt can be rapidly conducted, high stability is achieved, the installation precision of the embedded bolt is high, and meanwhile in construction of the same structural column, the positioning mold can be repeatedly used.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The application belongs to the technical field of steel structure construction, and particularly relates to a steel structure pre-buried bolt rapid positioning mold. BACKGROUND

[0002] The steel structure column and the foundation are connected through pre-buried bolts in the main body of the building steel structure, and the installation precision of the pre-buried bolts directly affects the steel structure construction precision of the entire factory building. Therefore, the pre-buried installation precision of the pre-buried bolts is very high. If the pre-buried deviation exceeds the allowable range, the hole on the steel column foot plate will not correspond to the foundation bolt, affecting the subsequent main body construction quality of the steel structure. Therefore, a positioning mechanism needs to be used to position the pre-buried bolt during the construction and fixing process of the steel structure pre-buried bolt. SUMMARY

[0003] The application provides a steel structure pre-buried bolt positioning mold, and solves the technical problem of low positioning precision during pre-buried foundation bolt installation on cast-in-place concrete foundation.

[0004] A steel structure pre-buried bolt rapid positioning mold, characterized in that: the steel structure pre-buried bolt rapid positioning mold comprises a positioning template, an upper reinforcing beam rod, a lower supporting beam rod, iron nails, an adjusting nut and a clamping nut, the positioning template is a solid wood board, bolt positioning holes are drilled in the positioning template, the diameter of the bolt positioning holes is the outer diameter of the pre-buried bolt plus 2 mm, square holes are opened between the bolt positioning holes, and the size of the square holes is 100 mm*100 mm; the upper reinforcing beam rod and the lower supporting beam rod are both wood squares, the upper reinforcing beam rod and the lower supporting beam rod are respectively fixed on the upper side and the lower side of the positioning template by using the iron nails, the upper reinforcing beam rod and the lower supporting beam rod are both two, the upper reinforcing beam rod and the lower supporting beam rod are perpendicular to each other, and the positions of the upper reinforcing beam rod and the lower supporting beam rod are located on the outer sides of the square holes and the bolt positioning holes; the distance between the iron nails is 70 mm to 100 mm; the pre-buried bolt is installed in the bolt positioning hole, and the pre-buried bolt is fixed by using the clamping nut and the adjusting nut, the adjusting nut is located on the lower side of the positioning template, the clamping nut is located on the upper side of the positioning template, and after the elevation of the pre-buried bolt is controlled in place by using the adjusting nut, the clamping nut is locked.

[0005] Further, the thickness of the positioning template is 18 mm.

[0006] Further, the size of the cross section of the upper reinforcing beam rod and the lower supporting beam rod is 40 mm*60 mm.

[0007] The utility model discloses beneficial effect lies in: adopt the positioning mould to carry out the positioning to the embedded bolt, adopt the steel pipe and the wood square to carry out the reinforcement to concrete structure column formwork system, carry out the combination connection to the formwork system of positioning mould and structure column with effective reinforcement, install the embedded bolt, and the position monitoring of embedded bolt is carried out after accurate pouring concrete. Adopt this mould can carry out the construction of embedded bolt quickly, and the embedded bolt position is positioned after being positioned by the positioning mould, and the positioning mould and whole concrete structure column formwork system are connected as a whole, have higher stability, and the installation accuracy of embedded bolt is higher, and positioning mould can be repeatedly used in the same structure column construction, and the turnover number can reach 10-15 generally, has higher economic value and popularization and use value. BRIEF DESCRIPTION OF DRAWINGS

[0008] Figure 1 It is a kind of steel structure embedded bolt fast positioning mould plan view.

[0009] Figure 2 It is a kind of steel structure embedded bolt fast positioning mould side sectional view

[0010] Wherein:1-positioning template, 2-bolt positioning hole, 3-square hole, 4-upper reinforcement beam rod, 5-lower support beam rod, 10-embedded bolt, 11-clamping nut, 12-adjusting nut. DETAILED DESCRIPTION

[0011] Example 1: in the construction process of electrolytic workshop steel structure embedded bolt positioning, for the characteristics of many embedded bolts, high precision requirement, use a kind of embedded bolt positioning mould.

[0012] The utility model provides a kind of steel structure pre-buried bolt fast positioning mould, when using, first the longitudinal and transverse axis of concrete structure column cap foundation, structure column template installation boundary line are marked using ink pot, and the midpoint position of concrete structure column is marked using red paint.According to the position of pre-buried bolt 10 on drawing and the relative spacing size between bolt, the processing of positioning template 1 is positioned, and positioning template 1 uses 18mm thick solid wood plywood, and bolt positioning hole 2 is processed using mechanical drilling on positioning template 1, the diameter of bolt positioning hole 2 is pre-buried bolt 10 outer diameter+2mm, square hole 3 is opened in the middle of bolt positioning hole 2, and the size of square hole 3 is 100mm*100mm, and square hole 3 is used for subsequent concrete pouring and vibrating construction.Iron nails are used to fix upper reinforcing beam 4 and lower support beam 5 on the upper side and lower side of positioning template 1 respectively, and upper reinforcing beam 4 and lower support beam 5 are wood square with cross section diameter 40mm*60mm, and upper reinforcing beam 4 and lower support beam 5 are both two, and upper reinforcing beam 4 and lower support beam 5 are perpendicular to each other, and the position is located outside square hole 3 and bolt positioning hole 2, and the distance between iron nails is 70mm~100mm.In the process of steel structure foundation steel bar binding, the position of pre-buried bolt 10 is measured in advance, and the position of pre-buried bolt position conflicts with foundation steel bar is appropriately adjusted to avoid.

[0013] After the installation of pre-buried bolt 10 is completed, the position and elevation are reviewed, and after the review is correct, concrete is poured, and the pouring of concrete is poured from the middle square hole 3 of positioning template 1, and concrete is vibrated during the pouring of concrete to avoid the contact of vibrating rod with pre-buried bolt 10, and if displacement of pre-buried bolt 10 is found during the vibrating process, pre-buried bolt 10 is adjusted, and after adjustment is in place and fixed, concrete is continuously poured.In the process of pouring concrete, plastic sleeve is used to protect the upper thread of pre-buried bolt 10.After the completion of concrete pouring, maintenance is carried out, and after the end of maintenance, positioning template 1 is removed.

Claims

1. A positioning mold for embedded bolts in steel structures, characterized in that: The system includes a positioning template, upper reinforcing beams, lower supporting beams, nails, adjusting nuts, and clamping nuts. The positioning template is made of solid wood plywood with bolt positioning holes drilled in it. The diameter of the bolt positioning holes is the outer diameter of the pre-embedded bolts + 2mm. Square holes with dimensions of 100mm*100mm are made between the bolt positioning holes. The upper reinforcing beams and lower supporting beams are both made of wood and are fixed to the upper and lower sides of the positioning template respectively using nails. There are two upper reinforcing beams and two lower supporting beams, which are perpendicular to each other and located outside the square holes and bolt positioning holes, with nails spaced 70mm to 100mm apart. Pre-embedded bolts are installed in the bolt positioning holes and fixed using clamping nuts and adjusting nuts. The adjusting nuts are located on the lower side of the positioning template, and the clamping nuts are located on the upper side. After the elevation of the pre-embedded bolts is controlled by the adjusting nuts, the clamping nuts are locked.

2. The steel structure pre-embedded bolt positioning mold as described in claim 1, characterized in that... The positioning template has a thickness of 18mm.

3. A positioning mold for embedded bolts in steel structures as described in claim 1, characterized in that... The cross-sectional dimensions of the upper reinforcing beam and the lower supporting beam are 40mm*60mm.