Working platform
By designing a combination of mounting holes, support components, and settlement piles on the working platform, the problems of high difficulty and cost in fixing floating islands or floating platforms in existing technologies have been solved, achieving stable and low-cost platform fixing and transfer.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- 任晋原
- Filing Date
- 2025-06-13
- Publication Date
- 2026-04-28
AI Technical Summary
In existing technologies, the methods for fixing artificial floating islands or floating platforms are difficult to construct and costly. In particular, the anchoring and pile fixing methods have high requirements during construction, making it difficult to achieve precise position control and incurring high costs.
An operating platform design is adopted, including a main body, supporting components and settling piles. The main body is provided with mounting holes, the supporting components pass through the mounting holes and have pile driving holes, and the settling piles pass through the pile driving holes to fix it to the seabed, avoiding underwater anchoring or pile driving operations. The platform is stably fixed by the cooperation of the supporting components and settling piles.
It reduces construction difficulty and cost, ensures the stability of the platform in both horizontal and vertical directions, and facilitates the transfer and installation of the platform, thereby improving construction efficiency and safety.
Smart Images

Figure CN224171141U_ABST
Abstract
Description
Technical Field
[0001] This application belongs to the field of marine engineering equipment technology, specifically relating to an operating platform. Background Technology
[0002] In production operations in fields such as cage aquaculture and marine transportation, artificial floating islands or floating platforms are usually required as operating platforms to provide a place for workers, equipment and goods.
[0003] In related technologies, methods for securing artificial floating islands or floating platforms typically include:
[0004] (1) Anchoring method, which uses metal anchors and cables to fix the floating platform. However, due to the high requirements for the strength of the anchor and the need for the anchor to be dragged to generate tension, it is impossible to achieve precise position control of the platform.
[0005] (2) Pile fixing method, which is to fix the floating platform by driving piles on the seabed. However, the pile fixing method requires strict exploration of the seabed, and the construction difficulty and cost of pile driving are relatively high. The requirements for the bending resistance of the piles are also extremely high. Therefore, the construction cost of the pile fixing method is high. Utility Model Content
[0006] To address the aforementioned technical problems, this utility model provides a working platform, which aims to at least partially solve the technical issues of high difficulty and cost in fixing and constructing working platforms.
[0007] The technical solution of this utility model is as follows:
[0008] A working platform includes: a first platform, the first platform comprising: a main body having at least one mounting hole penetrating the main body; at least one support member corresponding to the at least one mounting hole, the support member being inserted through the corresponding mounting hole, the support member having at least three first piling holes penetrating the support member; and at least three settlement piles corresponding to the at least three first piling holes, the settlement piles being inserted through the corresponding first piling holes.
[0009] In some implementations, the main body includes: a living platform; a floating assembly connected to the living platform and located below the living platform; and a storage component passing through the living platform and disposed within the floating assembly; wherein the mounting hole passes through the living platform and the floating assembly in sequence.
[0010] In some embodiments, the support includes: a cylindrical body, which passes through the mounting hole and has an axial section along the cylindrical body. The cylindrical body contains a receiving layer, a water storage layer, and a first floating layer arranged sequentially from top to bottom. The cylindrical body has a current hole penetrating through it along the radial direction. The first floating layer is located between the current hole and the water storage layer. The cylindrical body has at least three first piling holes penetrating through it along the axial direction.
[0011] In some embodiments, the support further includes a second floating layer disposed within the cylinder; wherein the current hole is located between the second floating layer and the first floating layer.
[0012] In some embodiments, the support further includes a limiting member disposed at the bottom of the cylinder; wherein, along the axial direction of the cylinder, the limiting member has a serrated cross-sectional shape.
[0013] In some embodiments, the working platform further includes: a settlement pile, provided with a second limiting member; wherein, along the axial direction of the cylinder, the cross-sectional shape of the second limiting member is sawtooth-shaped, and the second limiting member engages with the limiting member.
[0014] In some implementations, the work platform further includes at least one second platform disposed on the periphery of the first platform and connected to the first platform.
[0015] In some embodiments, the working platform further includes a support assembly comprising: at least one support layer disposed at the bottom of at least one of the support members of the first platform and at least one support member of the second platform, the support layer having at least three second piling holes through which the settlement piles pass; at least two clamping members disposed in at least one of the support layers closest to the support member; and a support base disposed in at least one of the support layers closest to the support member and located between the at least two clamping members; wherein the bottom of the support member abuts against the support base, the circumferential surface of the support member abuts against the at least two clamping members, a first buffer is provided between the clamping members and the support member, and a second buffer is provided between the support base and the support member.
[0016] In some implementations, the support layer includes multiple breeding boxes.
[0017] In some implementations, the work platform further includes a balancing water tank located on the second platform.
[0018] In some implementations, the operating platform further includes a power generation assembly comprising: a support tower disposed on the first platform; at least one generator disposed within the support tower; a radar disposed on top of the support tower; communication equipment disposed on top of the support tower; and a lightning rod disposed on top of the support tower.
[0019] The beneficial effects of this utility model include at least the following:
[0020] Because the main body has at least one mounting hole penetrating through it, and at least one support member corresponds one-to-one with the at least one mounting hole, the support member can limit the main body under the force of wind and / or the force of water impact, ensuring that the main body's position on the horizontal plane remains unchanged and its position is fixed. Furthermore, during high or low tide, the main body can slide on the support member, allowing it to rise and fall on the vertical plane, reducing the impact on the main body and maintaining its balance. When it is necessary to move the first platform, the support member can be separated from the mounting hole to release the limitation on the main body, facilitating the transfer of the first platform.
[0021] Since the support component has at least three first piling holes that penetrate the support component, and at least three settlement piles correspond one-to-one with at least three first piling holes, the settlement piles are inserted into the corresponding first piling holes. Therefore, when it is necessary to fix the support component, the settlement piles can be operated directly on the water so that the settlement piles are inserted into the corresponding first piling holes to fix it to the seabed, thereby achieving the fixation of the support component. Underwater anchoring or piling operations are not required, which reduces the construction difficulty and construction cost.
[0022] Since there are at least three first pile holes and at least three settlement piles, when the settlement piles are installed in the corresponding first pile holes, the support can be limited to prevent the support from shifting or rotating on the horizontal plane, so as to ensure the position of the support is determined and the stability of the support in limiting the main body. Attached Figure Description
[0023] To more clearly illustrate the technical solutions in the embodiments of this application, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0024] Figure 1 These are schematic diagrams of the operating platform in some embodiments;
[0025] Figure 2 for Figure 1 A top view of the dismantling of the power generation components on the central working platform;
[0026] Figure 3 for Figure 1 A schematic diagram of the first arrangement for dismantling the power generation components on the medium-duty work platform;
[0027] Figure 4 for Figure 1 A second schematic diagram of the dismantling of the power generation components on the medium-duty work platform;
[0028] Figure 5 for Figure 1 A schematic diagram of the third arrangement for dismantling the power generation components on the medium-duty work platform;
[0029] Figure 6 for Figure 1 A structural schematic diagram of the support components of the medium-duty working platform;
[0030] Figure 7 for Figure 3 Top view of the central support component;
[0031] Figure 8 for Figure 1 A schematic diagram of the power generation components of the medium-duty platform.
[0032] In the attached image:
[0033] First platform 10, main body 11, living platform 111, floating component 112, floating box 1121, storage component 113, support component 12, cylinder 121, housing layer 122, water storage layer 123, first floating layer 124, ocean current hole 125, second floating layer 126, limiting component 127, settlement pile 13, installation hole 14, first piling hole 15;
[0034] Second platform 20;
[0035] Support component 30, support layer 31, clamping component 32, support base 33, second piling hole 34, first buffer component 35, second buffer component 36;
[0036] Balance water tank 40;
[0037] 50. Power generation components, 51. Support tower, 52. Generator, 53. Radar, 54. Communication equipment, 55. Lightning rod, 56. Horizontal truss beam. Detailed Implementation
[0038] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0039] It should be noted that all directional indications in this utility model embodiment are only used to explain the relative positional relationship and movement of each component in a specific posture. If the specific posture changes, the directional indications will also change accordingly.
[0040] In this utility model, unless otherwise explicitly specified and limited, the terms "connection," "fixing," etc., should be interpreted broadly. For example, "fixing" can mean a fixed connection, a detachable connection, or an integral part; it can mean a mechanical connection or an electrical connection; it can mean a direct connection or an indirect connection through an intermediate medium; it can mean the internal communication of two components or the interaction between two components, unless otherwise explicitly limited. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.
[0041] Furthermore, in this utility model, descriptions involving "first," "second," etc., are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined with "first" or "second" may explicitly or implicitly include at least one of that feature. Additionally, the technical solutions of the various embodiments can be combined with each other, but only on the basis of being achievable by those skilled in the art. When the combination of technical solutions is contradictory or impossible to implement, such a combination of technical solutions should be considered non-existent and not within the scope of protection claimed by this utility model.
[0042] This application is described below with reference to the accompanying drawings and specific embodiments:
[0043] The work platform provided in this embodiment aims to at least partially solve the technical problems of high difficulty and high cost in fixing and constructing work platforms.
[0044] Combination Figure 1 , Figure 2 and Figure 3 The working platform in this embodiment includes a first platform 10, which comprises a main body 11, support members 12, and settlement piles 13. The main body 11 has at least one mounting hole 14 penetrating through it. At least one support member 12 corresponds one-to-one with at least one mounting hole 14, and the support member 12 passes through the corresponding mounting hole 14. Each support member 12 has at least three first piling holes 15 penetrating through it. At least three settlement piles 13 correspond one-to-one with at least three first piling holes 15, and the settlement piles 13 pass through the corresponding first piling holes 15.
[0045] Mounting hole 14 penetrates through body 11 along the height direction of body 11.
[0046] The first piling hole 15 penetrates the support member 12 along the height direction of the support member 12.
[0047] Since the main body 11 has at least one mounting hole 14 penetrating through it, and at least one support member 12 corresponds one-to-one with the at least one mounting hole 14, the support member 12 can limit the position of the main body 11 under the action of wind and / or the action of water, ensuring that the position of the main body 11 on the horizontal plane does not change and guaranteeing the position of the main body 11 is fixed. Moreover, during high or low tide, the main body 11 can slide on the support member 12, allowing the main body 11 to rise and fall on the vertical plane, reducing the impact received by the main body 11 and ensuring the balance of the main body 11. When it is necessary to move the first platform 10, the support member 12 can be separated from the mounting hole to release the limitation on the main body 11, so as to facilitate the transfer of the first platform 10.
[0048] Since the support member 12 has at least three first piling holes 15 penetrating through it, and at least three settlement piles 13 correspond one-to-one with the at least three first piling holes 15, the settlement piles 13 are inserted into the corresponding first piling holes 15. Therefore, when the support member 12 needs to be fixed, the settlement piles 13 can be operated directly on the water so that the settlement piles 13 are inserted into the corresponding first piling holes 15 to be fixed on the seabed, thereby fixing the support member 12. Underwater anchoring or piling operations are not required, which reduces the difficulty and cost of construction.
[0049] Since there are at least three first pile holes 15 and at least three settlement piles 13, when the settlement piles 13 are inserted into the corresponding first pile holes 15, the support member 12 can be limited, preventing the support member 12 from shifting or rotating on the horizontal plane, so as to ensure the position of the support member 12 is determined and the stability of the support member 12 in limiting the main body 11 is guaranteed.
[0050] In some embodiments, the settling pile 13 is a hollow structure. When not filled with water, the settling pile 13 can float. When water is added to the settling pile 13, it sinks and embeds itself into the seabed for fixation. When it is necessary to move the first platform 10, the water inside the settling pile 13 can be pumped out, allowing the settling pile 13 to float and leave the first piling hole 15. This releases the constraint on the support member 12, allowing the support member 12 to separate from the mounting hole, facilitating the transfer of the first platform 10.
[0051] In some embodiments, the number of mounting holes 14 can be one or more, and the number of support members 12 can also be one or more. When both the number of mounting holes 14 and support members 12 is one, the mounting hole 14 can be a non-circular hole, and the shape of the support member 12 matches the shape of the mounting hole 14 to prevent the platform from rotating on the support member 12 and ensure the stability of the platform installation. When both the number of mounting holes 14 and support members 12 is multiple, the support member 12 mates with the corresponding mounting hole 14 to prevent the platform from rotating on the support member 12 and ensure the stability of the platform installation.
[0052] In some embodiments, to enable the main body 11 to float, the main body 11 includes: a living platform 111, a floating assembly 112, and a storage component 113. The floating assembly 112 is connected to the living platform 111 and is located below the living platform 111. The storage component 113 passes through the living platform 111 and is disposed within the floating assembly 112. A mounting hole 14 passes sequentially through the living platform 111 and the floating assembly 112.
[0053] Under the influence of buoyancy, the floating component 112 allows the living platform 111 to float on the water surface, enabling it to be towed by traction equipment, thus reducing the transportation cost of the living platform 111. The storage component 113 can store materials, such as oil; that is, the storage component 113 can be an oil storage tank.
[0054] In some embodiments, the living platform 111 may consist of a living area and an equipment layer. The living area is located above the equipment layer. Valves, pumps, pipes, and other equipment may be placed within the equipment layer.
[0055] In some embodiments, the floating assembly 112 consists of a plurality of floating boxes 1121, each of which is filled with foam material. When the main body 11 enters the water, the floating boxes 1121 can make the living platform 111 float on the water surface under the action of buoyancy.
[0056] Combination Figure 1 and Figure 6 In some embodiments, to limit the positioning of the first platform 11, the support member 12 includes a cylindrical body 121. The cylindrical body 121 passes through the mounting hole 14 and has an axial section along the cylindrical body 121. Inside the cylindrical body 121, from top to bottom, a receiving layer 122, a water storage layer 123, and a first floating layer 124 are sequentially arranged. Radially along the cylindrical body 121, a current hole 125 penetrates the cylindrical body 121. The first floating layer 124 is located between the current hole 125 and the water storage layer 123. Axially along the cylindrical body 121, at least three first piling holes 15 penetrate the cylindrical body wall.
[0057] When the first platform 11 is to be installed onto the support member 12, the cylinder 121 passes through the mounting hole 14, draining the water from the water storage layer 123. Under the action of buoyancy, the first floating layer 124 causes the water storage cylinder 121 to float. A traction device is used to tow the cylinder 121 and the first platform 11 on the water so that the cylinder 121 reaches the installation position. The presence of the current hole 125 reduces traction resistance.
[0058] When the cylinder 121 reaches the installation position, water is injected into the water storage layer 123 so that the weight of the cylinder 121 is greater than the buoyancy, allowing the cylinder 121 to descend and come into contact with the bottom of the water. At this time, the sinking pile 13 can be operated directly on the water so that the sinking pile 13 passes through the corresponding first pile hole 15 to fix it to the seabed, thereby fixing the support 12. Underwater anchoring or pile driving is not required, which reduces the construction difficulty and construction cost.
[0059] In some embodiments, a fire tank may be arranged within the housing layer 122 for fire fighting.
[0060] In some embodiments, after the cylinder 121 is fixed, the ocean current below the water surface can pass through the current hole 125 to reduce the impact force of the ocean current on the cylinder 121 and ensure the stability of the cylinder 121 installation. At the same time, a generator can be installed in the current hole 125, and the generator blades can be driven to rotate during the ocean current flow to generate electricity.
[0061] Combination Figure 6 In some embodiments, to ensure that the support member 12 can float, the support member 12 further includes a second floating layer 126. The second floating layer 126 is disposed inside the cylinder 121. The current hole 125 is located between the second floating layer 126 and the first floating layer 124. Under the action of buoyancy, the first floating layer 124 and the second floating layer 126 work together to make the water storage cylinder 121 float on the water surface.
[0062] In some embodiments, the first floating layer 124 and the second floating layer 126 have the same structure, both being composed of foamed material.
[0063] In some embodiments, to further ensure the stability of the cylinder 121 installation, the support member 12 further includes a limiting member 127. The limiting member 127 is disposed at the bottom of the cylinder 121. The limiting member 127 has a serrated cross-sectional shape along the axial direction of the cylinder 121.
[0064] After the cylinder 121 reaches the installation position and water is injected into the water storage layer 123, the cylinder 121 descends, allowing the serrated limiting member 127 to insert into the seabed. The serrated limiting member 127 can increase the friction between the cylinder 121 and the seabed, so that the cylinder 121 is stably placed on the seabed under the action of gravity and friction, reducing the requirements for the geological conditions of the seabed and ensuring the stability of the cylinder 121 installation.
[0065] Combination Figure 1 , Figure 2 and Figure 3 In some embodiments, to ensure the stability of the working platform on the water surface, the working platform further includes at least one second platform 20. The at least one second platform 20 is disposed on the circumferential surface of the first platform 10 and connected to the first platform 10. The structure of the second platform 20 is consistent with the structure of the first platform 10.
[0066] The increased overall surface area of the work platform effectively expands its supporting foundation. When the platform is subjected to external forces, such as the impact of waves or the reaction force generated by the equipment, these forces act across the entire platform. This prevents deformation or damage caused by excessive localized stress, allowing the platform to maintain relative stability under external forces, reducing swaying and displacement, and ensuring stability on the water surface, thus improving the accuracy and safety of operations. Furthermore, the increased surface area provides workers with more space to move and work.
[0067] In some embodiments, the number of second platforms 20 can be one or more. When the number of second platforms 20 is multiple, the multiple second platforms 20 are evenly spaced at equal angles on the periphery of the first platform 10.
[0068] Combination Figure 3 , Figure 4 , Figure 5 and Figure 7In some embodiments, to enable the working platform to adapt to different depths, the working platform further includes a support assembly 30, which includes at least one support layer 31, clamping members 32, and a support base 33. At least one support layer 31 is disposed at the bottom of at least one of the support members 12 of the first platform 10 and at least one of the support members 12 of the second platform 20. The support layer 31 has at least three second piling holes 34, through which settlement piles 13 are inserted. At least two clamping members 32 are disposed in the support layer 31 closest to the support member 12. The support base 33 is disposed in the support layer 31 closest to the support member 12 and is located between the at least two clamping members 32. The bottom of the support member 12 abuts against the support base 33, and the peripheral surface of the support member 12 abuts against the at least two clamping members 32.
[0069] In some embodiments, if the seabed at the installation location of the work platform is at a relatively deep position, a support layer 31 is laid on the seabed. The number of support layers 31 is selected according to the usage requirements of the work platform and the depth of the seabed. After the support layer 31 is installed, the support member 12 is placed on the support base 33, which supports the support member 12. At the same time, at least two clamping members 32 clamp the support member 12 to limit its movement and prevent it from shifting under the influence of ocean currents or waves, ensuring that the installation position of the support member 12 is determined and that the installation of the support member 12 is stable. When it is necessary to fix the support member 12, the settlement piles 13 are sequentially driven through the first pile hole 15 and the second pile hole 34 and installed on the seabed to realize the installation of the support member 12.
[0070] In some embodiments, if the seabed is a hard reef and cannot be excavated, the seabed is filled with hard stones or concrete blocks mixed with sand and gravel. The top is leveled with sandbags, and then the support layer 31 is installed to ensure its levelness, thereby ensuring the stability of the support frame 12. To prevent sand and gravel from leaking out, the outer perimeter of the support layer 31 is sealed with sandbags, and magnesium-based quick-setting concrete can be poured if necessary.
[0071] In some embodiments, if the seabed is soft, an excavator is used to dig out a flat surface, sandbags are used to level it, and then the support layer 31 is installed to ensure that the support layer 31 is level, thereby ensuring the stability of the support frame 12. To prevent sand and gravel from leaking out, the perimeter of the support layer 31 is sealed with sandbags, and magnesium-based quick-setting concrete can be poured if necessary.
[0072] Combination Figure 3 , Figure 4 and Figure 5In some embodiments, to ensure the safety of the support member 12 and the clamping member 32, a first buffer member 35 is provided between the clamping member 32 and the support member 12. The support member 12 may sway under the influence of ocean currents or waves; the first buffer member 35 cushions this movement, preventing hard contact between the support member 12 and the clamping member 32 and ensuring their safety. The first buffer member 35 can be made of hard rubber.
[0073] In some embodiments, to ensure the safety of the support base 33 and the clamping member 32, a second buffer 36 is provided between the support base 33 and the support member 12. The support member 12 may sway under the influence of ocean currents or waves; the second buffer 36 cushions this movement, preventing hard contact between the support member 12 and the support base 33, thus ensuring the safety of both. The second buffer 36 can be made of hard rubber.
[0074] In some embodiments, in order to make full use of the support layer 31, the support layer 31 includes multiple aquaculture boxes, in which marine organisms such as sea cucumbers can be cultured. That is to say, the support layer 31 not only serves to support the support member 12, but also serves to aquaculture, thus achieving two uses in one piece.
[0075] Combination Figure 1 In some embodiments, to ensure the balance of the work platform, the work platform further includes a balance water tank 40. The balance water tank 40 is located on the second platform 20. By filling or draining water into the balance water tank 40, the center of gravity of the work platform can be changed to ensure the balance of the work platform.
[0076] Combination Figure 1 and Figure 8 In some embodiments, the operating platform further includes a power generation component 50, which includes a support tower 51, a generator 52, a radar 53, a communication device 54, and a lightning rod 55. The support tower 51 is located on the first platform 10. At least one generator 52 is located inside the support tower 51, and under the action of wind, the blades of the generator 52 rotate to generate electricity. The radar 53 is located on the top of the support tower 51 to monitor the external environment. The communication device 54 is located on the top of the support tower 51 to communicate with the outside world. The lightning rod 55 is located on the top of the support tower 51 to avoid lightning strikes and ensure safety. The generator 52 can be a vertical axis micro-wind generator.
[0077] In some embodiments, the support tower 51 may be made of corrosion-resistant materials, such as aluminum alloy, basalt profiles, steel structures, etc.
[0078] In some embodiments, the number of generators 52 can be one or more. When the number of generators 52 is multiple, multiple horizontal truss beams 56 are spaced apart in the support tower 51 along the height direction of the support tower 51. Multiple generators 52 correspond one-to-one with multiple horizontal truss beams 56. The generators 52 are mounted on the corresponding horizontal truss beams 56. The horizontal truss beams 56 support the generators 52, ensuring the stability of the generator installation.
[0079] In some embodiments, the operating platform also includes infrastructure. The infrastructure may be wastewater treatment equipment, seawater desalination equipment, condensate recovery system, solid waste treatment equipment, agricultural equipment, etc., and the infrastructure may be installed on the first platform 10 and / or the second platform 20 depending on the available space.
[0080] In the description of this application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.
[0081] In the description of this utility model, unless otherwise expressly specified and limited, "above" or "below" the second feature can include direct contact between the first and second features, or contact between the first and second features through another feature between them. Furthermore, "above," "over," and "on top" of the second feature includes the first feature directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature includes the first feature directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.
[0082] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. In addition, those skilled in the art can combine and integrate the different embodiments or examples described in this specification.
[0083] Although preferred embodiments of this application have been described, those skilled in the art, upon learning the basic inventive concept, can make other changes and modifications to these embodiments. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments as well as all changes and modifications falling within the scope of this application.
[0084] Obviously, those skilled in the art can make various modifications and variations to this application without departing from the spirit and scope of this application. Therefore, if such modifications and variations fall within the scope of the claims of this application and their equivalents, this application also intends to include such modifications and variations.
Claims
1. A working platform, characterized in that, Including a first platform, the first platform includes: The main body has at least one mounting hole penetrating through it; At least one support member corresponds one-to-one with at least one mounting hole, the support member is inserted through the corresponding mounting hole, and the support member has at least three first piling holes penetrating the support member; At least three settlement piles are provided, each corresponding to one of at least three first pile holes, with the settlement piles passing through the corresponding first pile holes.
2. The operating platform according to claim 1, characterized in that, The subject includes: Residential platform; A floating component is connected to the living platform and located below the living platform; Storage components are installed on the living platform and located within the floating assembly; The mounting holes pass through the living platform and the floating component in sequence.
3. The operating platform according to claim 1, characterized in that, The support member includes: A cylindrical body is inserted through the mounting hole and has an axial section along the cylinder body. The cylinder body is provided with a receiving layer, a water storage layer and a first floating layer from top to bottom. Along the radial direction of the cylinder, the cylinder has an ocean current hole that penetrates the cylinder, the first floating layer is located between the ocean current hole and the water storage layer, and along the axial direction of the cylinder, the cylinder wall has at least three first piling holes that penetrate the cylinder wall.
4. The operating platform according to claim 3, characterized in that, The support member also includes: A second floating layer is provided inside the cylinder; The current hole is located between the second floating layer and the first floating layer.
5. The operating platform according to claim 3, characterized in that, The support member also includes: A limiting component is provided at the bottom of the cylinder; The limiting member has a serrated cross-sectional shape along the axial direction of the cylinder.
6. The operating platform according to claim 5, characterized in that, The operating platform also includes: The settlement pile is equipped with a second limiting device; Along the axial direction of the cylinder, the cross-sectional shape of the second limiting member is sawtooth-shaped, and the second limiting member engages with the limiting member.
7. The operating platform according to any one of claims 1-5, characterized in that, The operating platform also includes: At least one second platform is disposed on the periphery of the first platform and connected to the first platform.
8. The operating platform according to claim 7, characterized in that, The operating platform also includes support components, which include: At least one support layer is provided at the bottom of at least one of the support members of the first platform and at least one support member of the second platform, and the support layer is provided with at least three second piling holes, and the settlement piles are inserted through the corresponding second piling holes. At least two clamping members are provided in at least one of the support layers closest to the support member; A support base is disposed in at least one of the support layers closest to the support member and is located between at least two of the clamping members; The bottom of the support member abuts against the support base, the circumferential surface of the support member abuts against the at least two clamping members, a first buffer member is provided between the clamping members and the support member, and a second buffer member is provided between the support base and the support member.
9. The operating platform according to claim 8, characterized in that, The support layer includes multiple breeding boxes.
10. The operating platform according to any one of claims 1-5, characterized in that, The operating platform also includes a power generation component, which comprises: A support tower is located on the first platform; At least one generator is located inside the support tower; The radar is located at the top of the support tower; Communication equipment is located at the top of the support tower; A lightning rod is installed at the top of the supporting tower.