Intelligent water supply system for fog gun
By introducing a water supply pipe and a vent pipe structure into the fog cannon water supply system, combined with electric valves, fully automated control is achieved, solving the safety hazards and management inconvenience in low-temperature environments, and realizing the intelligent and green management of the fog cannon system.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- BAOTOU STEEL GRP DESIGN & RES INST
- Filing Date
- 2025-05-13
- Publication Date
- 2026-05-12
Smart Images

Figure CN224229757U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of water supply system technology, specifically to a fog cannon intelligent water supply system. Background Technology
[0002] According to the requirements of the National Opinions on Promoting the Implementation of Ultra-Low Emissions in the Steel Industry (Environmental Protection and Control
[2019] No. 35), existing industrial enterprises are required to install fixed mist cannons, fixed fog sprayers, and other related dust suppression facilities in areas where raw materials, coal yards, and coke are stored. Currently, most of these raw material storage areas in northern regions lack indoor heating facilities. Therefore, the conventional practice for supplying water to mist cannons is to install electric heating cables on the water supply pipelines for winter insulation. This practice has the following problems:
[0003] 1. The electric heating tape has a power of 380V / 220V. In the event of leakage, there is a risk of electric shock on site.
[0004] 2. The actual performance of electric heating tape is generally poor. After 2-3 years of use, it will stop heating and need to be replaced regularly, which increases operating costs.
[0005] 3. The large number of fog cannons in large storage yards puts a heavy burden on on-site staff, requires extensive equipment maintenance, and is prone to management errors, failing to meet national requirements for intelligent and green industrial projects. Utility Model Content
[0006] (I) Technical Issues
[0007] The present invention aims to at least solve the problem of how to eliminate the safety risks of using heating cables in low-temperature environments, which exists in the prior art.
[0008] (II) Technical Content
[0009] This solution provides an intelligent water supply system for fog cannons, achieved through the following specific technical means, including:
[0010] A water supply pipe connected to the water inlet of the fog cannon; the water supply pipe is used to supply water to the fog cannon.
[0011] A drain pipe, connected to the water supply pipe, is used to drain the water from the pipe after the water supply has stopped.
[0012] Preferred technical solution 1: The water supply pipe includes a main water supply pipe and a branch pipe, and the main water supply pipe is connected to the water inlet of the mist cannon through the branch pipe;
[0013] The drain pipe is fixedly connected to the main and branch water supply pipes.
[0014] Preferred technical solution 2: Install switch valve 1 on the main water supply pipe and switch valve 2 on the vent pipe.
[0015] Preferred technical solution three: Both the switching valve one and the switching valve two are electric valves.
[0016] Preferred technical solution four: The switching valve one and switching valve two are connected to an external control box or remote control from the central control room.
[0017] (III) Technical Effects
[0018] The above structure gives this solution the following advantages:
[0019] 1. Eliminate the use of heating cables to remove safety hazards to on-site workers caused by them;
[0020] 2. By adding a drain pipe and a switch valve to the water supply pipeline, the residual water can be drained in time after the fog cannon is stopped, thus avoiding damage from freezing.
[0021] 3. By connecting the switching valve to a local control box or central control room for remote control, complete automation can be achieved, improving the work efficiency of operators and realizing the intelligent and green transformation of the factory. Attached Figure Description
[0022] The accompanying drawings are provided to further illustrate the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention, but do not constitute a limitation thereof. In the drawings:
[0023] Figure 1 This is a schematic diagram of the overall structure of this solution;
[0024] Figure 2 This is a schematic diagram of the water supply pipe and vent pipe in this scheme.
[0025] Among them, 1. Water supply pipe, 11. Main water supply pipe, 12. Branch pipe, 2. Fog cannon, 3. Drain pipe, 4. Switch valve one, 5. Switch valve two. Detailed Implementation
[0026] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the protection scope of the present utility model.
[0027] Example 1
[0028] Please see Figures 1-2The intelligent water supply system of the fog cannon 2 includes a water supply pipe 1 connected to the water inlet of the fog cannon 2, which is used to supply water to the fog cannon 2; and a drain pipe 3 connected to the water supply pipe 1, which is used to drain the water between the connection between the drain pipe 3 and the water supply pipe 1 and the water inlet of the fog cannon 2 after the water supply pipe 1 stops supplying water.
[0029] Specifically: the water supply pipe 1 includes a main water supply pipe 11 and a branch pipe 12. One end of the main water supply pipe 11 is connected to a water supply device, which supplies water to the main water supply pipe 11. The other end is connected to the inlet of the mist cannon 2 through the branch pipe 12. At the same time, the drain pipe 3 is fixedly connected to the connection between the main water supply pipe 11 and the branch pipe 12. A switch valve 1 4 is installed on the main water supply pipe 11, and a switch valve 2 5 is installed on the drain pipe 3.
[0030] When fog cannon 2 is in normal operation: switch valve 25 is closed and switch valve 14 is open, so that fog cannon 2 can supply water normally.
[0031] When the fog cannon 2 is stopped: first close switch valve 1 4, then open switch valve 2 5, delay for a period of time (e.g., 2 minutes) to drain the residual water in branch pipe 12, then close switch valve 2 5, thereby canceling the installation of the electric heat tracing cable of the original water supply pipe 1.
[0032] Example 2
[0033] Based on Example 1
[0034] Please see Figures 1-2 The fog cannon 2 intelligent water supply system uses electric valves 4 and 5, which are connected to an external control box (using existing technology) or a central control room (using existing technology) for remote control, enabling the fog cannon 2 to operate fully automatically.
[0035] The control box or central control room is used to remotely control the opening and closing of switch valve 4 and switch valve 5, that is:
[0036] When fog cannon 2 is in normal operation: control valve 2 5 is closed and switch valve 1 4 is open to achieve normal water supply for fog cannon 2;
[0037] When the fog cannon 2 is stopped: first control the shut-off valve 4, then open the valve 5. After the residual water in the branch pipe 12 is drained, close the valve 5.
[0038] Example 3
[0039] Based on Example 1 or 2
[0040] Please see Figures 1-2 The Fog Cannon 2 intelligent water supply system also includes a valve well to protect the main water supply pipe 11 from freezing and preventing it from frost heave below the frost line.
[0041] It is worth noting that the specific model of the electric valve mentioned in this embodiment, as well as its matching power supply and control switch, can also be provided by the manufacturer. The circuits, electronic components, and modules involved are all existing technologies, which can be fully implemented by those skilled in the art, and need not be elaborated upon.
[0042] Unless otherwise expressly specified and limited, the terms "set up," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0043] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A fog cannon intelligent water supply system, characterized in that: include A water supply pipe (1) is connected to the water inlet of the fog cannon (2), and the water supply pipe (1) is used to supply water to the fog cannon (2); The drain pipe (3) is connected to the water supply pipe (1) and is used to drain the water in the water supply pipe (1) after the water supply pipe (1) stops supplying water; The water supply pipe (1) includes a main water supply pipe (11) and a branch pipe (12). One end of the main water supply pipe (11) is connected to the water inlet of the fog cannon (2) through the branch pipe (12). The drain pipe (3) is fixedly connected to the connection between the main water supply pipe (11) and the branch pipe (12). A switch valve 1 (4) is installed on the main water supply pipe (11), and a switch valve 2 (5) is installed on the drain pipe (3). Both the first switching valve (4) and the second switching valve (5) are electric valves; The first switch valve (4) and the second switch valve (5) are connected to the machine-side operation box or the central control room for remote control.
2. The intelligent water supply system for fog cannons according to claim 1, characterized in that: It also includes valve wells for protecting the main water supply pipe (11).