A construction template structure for integrally pouring a shock insulation wall

By using symmetrically arranged upper and lower templates and side template box structures, combined with fixing components and support rods, the problem of low efficiency in traditional phased construction is solved, realizing efficient integrated casting of seismic isolation walls, and improving construction efficiency and structural stability.

CN224549613UActive Publication Date: 2026-07-24CHINA CONSTR FIRST GROUP THE FIFTH CONSTR +1
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
CHINA CONSTR FIRST GROUP THE FIFTH CONSTR
Filing Date
2025-08-20
Publication Date
2026-07-24

AI Technical Summary

Technical Problem

Traditional formwork methods require phased construction, resulting in long construction cycles, low efficiency, and difficulty in meeting the seismic requirements of high-rise buildings.

Method used

The upper and lower templates are symmetrically set, and the side templates form a box structure. The upper and lower templates are connected by fixing components to achieve one-time formwork. The structural stability is improved by connecting rods and support rods, and the upper and lower walls can be poured at the same time.

Benefits of technology

This method enables simultaneous pouring of the upper and lower walls, reducing the construction period, improving construction efficiency, lowering formwork erection costs, and enhancing the stability and flatness of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224549613U_ABST
    Figure CN224549613U_ABST
Patent Text Reader

Abstract

The application relates to the technical field of building shock insulation wall construction, and particularly discloses a shock insulation wall integrated pouring construction formwork structure which comprises an upper formwork and a lower formwork, the upper formwork and the lower formwork are symmetrically arranged, side formworks are vertically arranged on the circumferential sides of the upper formwork and the lower formwork, the upper formwork or the lower formwork and the side formworks form a box body structure with one side being in an open shape, a pouring opening for pouring concrete is arranged on the lower formwork, and a fixing assembly for connecting the upper formwork and the lower formwork is arranged between the upper formwork and the lower formwork. The application has the effects of shortening a construction period and improving construction efficiency.