A precast concrete wall panel with lifting and balancing steel pipe

CN224620954UActive Publication Date: 2026-08-11QINGDAO WANRUI NEW CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-08-22
Publication Date
2026-08-11

AI Technical Summary

Benefits of technology

[0011] 1. This utility model uses bolts and threaded holes to install the hoisting plate body onto two pre-embedded steel pipes. Then, the hanger below the wire rope is erected and passes through the hoisting holes on the hoisting plate body. Next, the hanger is leveled and supported at the bottom of the hoisting plate body. Since there are multiple hoisting holes on the hoisting plate body, the hanger is installed on the hoisting holes as needed to ensure that the wall panel is hoisted in a stable state. This achieves the purpose of installing the hoisting plate on the top of the steel pipe and adjusting the hoisting points as needed according to the holes on the hoisting plate to ensure the balance and stability of the wall panel hoisting.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224620954U_ABST
    Figure CN224620954U_ABST
Patent Text Reader

Abstract

This utility model discloses a precast concrete wall panel with a lifting and balancing steel pipe, comprising two symmetrically embedded steel pipes. The tops of the two embedded steel pipes extend to the top of the wall panel, and a lifting plate body is detachably installed on the top of the two embedded steel pipes. A lifting beam is provided on the top of the lifting plate body, and steel wire ropes are installed on both sides of the bottom of the lifting beam. This utility model installs the lifting plate body onto the two embedded steel pipes using bolts and threaded holes. Then, the hangers below the steel wire ropes are vertically inserted through the lifting holes on the lifting plate body. The hangers are then horizontally supported at the bottom of the lifting plate body. Since there are multiple lifting holes on the lifting plate body, the hangers are installed in the holes as needed to ensure the wall panel is lifted stably. This achieves the purpose of installing the lifting plate on top of the steel pipes, adjusting the lifting points according to the holes on the lifting plate, and ensuring the balanced and stable lifting of the wall panel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of building wall panel technology, and in particular relates to a precast concrete wall panel with a hoisting balance steel pipe. Background Technology

[0002] Wall panel hoisting is a crucial step in prefabricated building construction, directly impacting project quality, progress, and safety. The wall panels are transported to the hoisting area and placed stably in the hoisting position using forklifts or cranes, with wooden blocks placed underneath to prevent tilting.

[0003] According to the location of the wall panel lifting points, the lifting tools (such as steel wire ropes and lifting slings) should be properly tied to ensure even force distribution. Soft materials should be padded at the binding points to prevent damage to the wall panel. In order to ensure the balance and stability of the wall panel lifting, we have designed a precast concrete wall panel with a lifting balance steel pipe. The lifting plate is installed on the top of the steel pipe. The lifting points are adjusted as needed according to the holes on the lifting plate to ensure the balance and stability of the wall panel lifting. Utility Model Content

[0004] The purpose of this utility model is to provide a precast concrete wall panel with a lifting and balancing steel pipe, which has the advantages of installing a lifting plate on the top of the steel pipe and adjusting the lifting points as needed according to the holes on the lifting plate to ensure the wall panel is lifted in a balanced and stable manner, thereby solving the above-mentioned technical problems.

[0005] The technical solution of this utility model to solve the above-mentioned technical problems is as follows: A precast concrete wall panel with a lifting balance steel pipe, comprising two symmetrically embedded steel pipes embedded in the wall panel, the tops of the two embedded steel pipes extending to the top of the wall panel, a lifting loading plate body detachably installed on the top of the two embedded steel pipes, a lifting beam provided on the top of the lifting loading plate body, steel wire ropes installed on both sides of the bottom of the lifting beam, a hanger installed on the bottom of the steel wire ropes, and multiple equally spaced lifting holes opened on both sides of the top of the lifting loading plate body, the hanger passing through one of the lifting holes and being hung on the bottom of the lifting loading plate body.

[0006] Preferably, the top of the pre-embedded steel pipe is provided with a threaded hole, and bolts are provided through both ends of the top of the hoisting plate body. The bolts pass through the hoisting plate body and are threadedly connected to the threaded hole.

[0007] Preferably, the top of the hoisting plate body has long slots at both ends for bolts to pass through.

[0008] Preferably, both ends of the hanger are provided with positioning edges, and the inner side of the positioning edges is in contact with the body of the hoisting plate.

[0009] Preferably, the surface of the pre-embedded steel pipe is welded with multiple round steel plates, which are pre-embedded in the wall panel.

[0010] The beneficial effects of this utility model are:

[0011] 1. This utility model uses bolts and threaded holes to install the hoisting plate body onto two pre-embedded steel pipes. Then, the hanger below the wire rope is erected and passes through the hoisting holes on the hoisting plate body. Next, the hanger is leveled and supported at the bottom of the hoisting plate body. Since there are multiple hoisting holes on the hoisting plate body, the hanger is installed on the hoisting holes as needed to ensure that the wall panel is hoisted in a stable state. This achieves the purpose of installing the hoisting plate on the top of the steel pipe and adjusting the hoisting points as needed according to the holes on the hoisting plate to ensure the balance and stability of the wall panel hoisting.

[0012] 2. By setting positioning edges, when the hanger is supported at the bottom of the hoisting plate body, the positioning edges at both ends of the hanger will fit against the side of the hoisting plate body, effectively limiting the hanger and ensuring that the hanger is in a stable state.

[0013] 3. By setting up a long groove, this utility model can adapt to the slight deviation in the distance between two pre-embedded steel pipes when there is a slight deviation in the distance between the two pre-embedded steel pipes, thus having high adaptability.

[0014] 4. By setting up a round steel plate, this utility model can increase the structural strength of the embedded steel pipe in the wall and effectively prevent the embedded steel pipe from detaching from the wall panel. Attached Figure Description

[0015] The advantages of the present invention, as described above and / or in the following detailed description in conjunction with the accompanying drawings, will become clearer and more readily understood. These drawings are merely illustrative and do not limit the scope of the present invention.

[0016] Figure 1 This is a schematic diagram of one embodiment of the present utility model;

[0017] Figure 2 This is a three-dimensional schematic diagram of the pre-embedded steel pipe and the hoisting loading plate body according to one embodiment of the present invention;

[0018] Figure 3 This is a three-dimensional disassembled schematic diagram of the pre-embedded steel pipe and the hoisting loading plate body in one embodiment of this utility model. Detailed Implementation

[0019] In the following description, embodiments of the precast concrete wall panel with lifting and balancing steel pipe of the present invention will be described with reference to the accompanying drawings.

[0020] Figure 1-3This invention illustrates a precast concrete wall panel with a lifting and balancing steel pipe according to an embodiment of the present invention. It includes two symmetrically embedded steel pipes 1. Multiple circular steel plates 11 are welded to the surface of each embedded steel pipe 1. The circular steel plates 11, embedded in the wall panel, increase the structural strength of the embedded steel pipes 1 within the wall, effectively preventing them from detaching from the wall panel. The tops of the two embedded steel pipes 1 extend to the top of the wall panel. A lifting plate body 2 is detachably installed on the top of the two embedded steel pipes 1. A lifting beam 3 is provided on the top of the lifting plate body 2. Steel wire ropes 4 are installed on both sides of the bottom of the lifting beam 3. Hangers 5 are installed at the bottom of the steel wire ropes 4. Positioning edges 10 are provided at both ends of the hangers 5. The inner side of the positioning edges 10 is in contact with the lifting plate body 2. Through the positioning edges 10, the hangers 5 support… When supported at the bottom of the lifting loading plate body 2, the positioning edges 10 at both ends of the hanger 5 will fit against the side of the lifting loading plate body 2, effectively limiting the hanger 5 and ensuring that the hanger 5 is in a stable state. Multiple equally spaced lifting holes 6 are opened on both sides of the top of the lifting loading plate body 2. The hanger 5 passes through one of the lifting holes 6 and is hung on the bottom of the lifting loading plate body 2. The top of the pre-embedded steel pipe 1 is provided with threaded holes 8. Bolts 7 are installed through both ends of the top of the lifting loading plate body 2. The bolts 7 pass through the lifting loading plate body 2 and are threadedly connected to the threaded holes 8. The top of the lifting loading plate body 2 is provided with long grooves 9 for the bolts 7 to pass through. With the setting of long grooves 9, when there is a slight deviation in the distance between the two pre-embedded steel pipes 1, the long grooves 9 can adapt to the slight deviation in the distance between the two pre-embedded steel pipes 1, and have high adaptability.

[0021] Working principle: When using this utility model, the user inserts bolts 7 into the long groove 9 of the hoisting plate body 2 and screws them into the inner cavity of the threaded hole 8 to realize the installation of the hoisting plate body 2 and the pre-embedded steel pipe 1. Then, the hoisting beam 3 is moved above the wall panel. The hangers 5 at the ends of the steel wire ropes 4 on both sides of the bottom of the hoisting beam 3 are adjusted to a vertical state and pass through the hoisting holes 6 on the hoisting plate body 2. Then, they are adjusted to a horizontal state so that the hangers 5 and the positioning edge 10 are fitted on the surface of the hoisting plate body 2. Since there are multiple hoisting holes 6, the hoisting holes 6 through which the hangers 5 pass can be selected as needed to achieve balanced and stable hoisting of the wall panel.

[0022] In summary: This precast concrete wall panel with lifting and balancing steel pipes is installed on two pre-embedded steel pipes 1 by bolts 7 and threaded holes 8. Then, the hanger 5 below the wire rope 4 is raised and passes through the lifting holes 6 on the lifting plate body 2. The hanger 5 is then leveled and supported at the bottom of the lifting plate body 2. Since there are multiple lifting holes 6 on the lifting plate body 2, the hanger 5 is installed in the lifting holes 6 as needed to ensure that the wall panel is lifted in a stable state. This achieves the purpose of installing the lifting plate on the top of the steel pipes and adjusting the lifting points as needed according to the holes on the lifting plate to ensure the balance and stability of the wall panel during lifting.

Claims

1. A precast concrete wall panel with a hoisting balance steel pipe, characterized in that, The system includes two symmetrical embedded steel pipes (1) embedded in the wall panel. The tops of the two embedded steel pipes (1) extend to the top of the wall panel. The tops of the two embedded steel pipes (1) are detachably equipped with a hoisting plate body (2). The top of the hoisting plate body (2) is provided with a hoisting beam (3). Steel wire ropes (4) are installed on both sides of the bottom of the hoisting beam (3). Hangers (5) are installed at the bottom of the steel wire ropes (4). Multiple equally spaced hoisting holes (6) are opened on both sides of the top of the hoisting plate body (2). The hangers (5) pass through one of the hoisting holes (6) and are hung on the bottom of the hoisting plate body (2).

2. The precast concrete wall panel with hoisting balance steel pipe according to claim 1, characterized in that, The top of the pre-embedded steel pipe (1) is provided with a threaded hole (8), and bolts (7) are provided through both ends of the top of the hoisting plate body (2). The bolts (7) pass through the hoisting plate body (2) and are threadedly connected to the threaded hole (8).

3. The precast concrete wall panel with hoisting balance steel pipe according to claim 2, characterized in that, The top of the hoisting plate body (2) has long slots (9) at both ends for bolts (7) to pass through.

4. The precast concrete wall panel with hoisting balance steel pipe according to claim 3, characterized in that, Both ends of the hanger (5) are provided with positioning edges (10), and the inner side of the positioning edge (10) is in contact with the hoisting plate body (2).

5. The precast concrete wall panel with hoisting balance steel pipe according to claim 4, characterized in that, The surface of the pre-embedded steel pipe (1) is welded with multiple round steel plates (11), which are pre-embedded in the wall panel.