A connection structure between a newly added steel beam and a low-strength original concrete beam.
By combining external steel frame, anchor plate and transition steel plate, the connection problem between the original low-strength concrete beam and the newly added steel beam was solved, realizing a convenient and environmentally friendly construction method, and improving connection strength and construction efficiency.
Patent Information
- Application Number
- CN202522293946.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-29
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-10-29
AI Technical Summary
In the renovation and upgrading of existing buildings, low-strength original concrete beams cannot be directly reinforced by connecting steel beams with anchor bolts, resulting in a large amount of wet construction work, a long cycle, and a significant environmental impact. Furthermore, the method of increasing the cross-section of cast-in-place structures is not applicable.
The new steel beams are connected to the original low-strength concrete beams using a combination of external steel frame, anchor plate structure and transition steel plate. Through bolts and high-strength bolts are used to connect the new steel beams to the original low-strength concrete beams, avoiding wet work and enhancing the connection strength.
This method enables convenient, energy-saving, and environmentally friendly connection between steel beams and low-strength original concrete beams, reducing construction time and environmental impact while improving the structural strength of the connection nodes.
Smart Images

Figure CN224955477U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building construction technology, and in particular to a connection structure between a newly added steel beam and a low-strength original concrete beam. Background Technology
[0002] In the renovation and upgrading of existing buildings, due to adjustments in building function, it is often necessary to reinforce the existing concrete beams beneath the floor slabs of the new walls. To reduce on-site wet work, a steel beam-supported wall reinforcement design is generally adopted. Anchor bolts are typically used to connect the new steel beams to the original concrete beams to improve the reliability of the connection. The new steel beams transfer the load from the superstructure through the anchor bolt structure. The anchor bolt structure includes an anchoring steel plate attached to the original concrete beam and anchor bars inserted into the original concrete beam through the anchoring steel plate. However, according to building reinforcement requirements, anchor bolts cannot be used for building components with concrete strength grades between C13 and C25. In such cases, a dual approach of increasing the cross-section of the original concrete beam combined with anchor bolts is necessary. The drawback is that when using the cast-in-place structure to increase the cross-section of the original concrete beam, it is necessary to reinforce the beam by creating openings in the floor slab and pouring self-compacting concrete. This involves a large amount of wet work, a long construction period, and requires enhanced post-construction curing of the concrete, significantly impacting the on-site environment. Utility Model Content
[0003] The purpose of this utility model is to provide a connection structure between a newly added steel beam and a low-strength original concrete beam, in order to solve the problems of how to avoid wet construction work when connecting the low-strength original concrete beam and the newly added steel beam, so as to avoid the impact of wet construction work on the surrounding environment, as well as the problems of large workload, long construction and maintenance period, and the problem that the original concrete beam with concrete strength grade in the range of C13-C25 cannot be directly connected to the steel beam for reinforcement construction using anchor bolts.
[0004] To solve the above-mentioned technical problems, this utility model provides a connection structure between a newly added steel beam and a low-strength original concrete beam, comprising:
[0005] An external steel frame is constructed on the original concrete beam at the joint with the newly added steel beam. The external steel frame passes through the floor slab, covers the connection joint of the newly added steel beam, and is constructed on the original concrete beam.
[0006] An anchor plate structure is constructed on the original concrete beam at the node with the newly added steel beam. It includes anchor plates distributed on both sides of the original concrete beam. The anchor plates on both sides are installed on the original concrete beam by multiple through bolts that penetrate the original concrete beam. The anchor plates are welded to the outer steel frame of the area they cover.
[0007] The adapter steel plate is located on the outside and is vertically welded to the anchor plate;
[0008] A new steel beam is constructed at the joint with the existing low-strength concrete beam. The end face of the new steel beam is close to or attached to the anchor plate on the side where it is located. The new steel beam is an H-beam or an I-beam. The upper flange of the new steel beam is attached to the floor slab. The new steel beam is anchored to the floor slab through anchors passing through its upper flange. The web of the new steel beam overlaps and is attached to one side of the transition steel plate and is fastened by multiple high-strength bolts.
[0009] Furthermore, the connection structure between the newly added steel beam and the original low-strength concrete beam provided by this utility model includes an outer steel frame comprising a bottom angle steel installed at each of the two corners of the bottom of the original concrete beam, multiple evenly spaced hoop plates installed through the floor slab on the side of the original concrete beam, multiple lower gusset plates welded between the lower surfaces of the two bottom angle steels of the original concrete beam and evenly spaced from the hoop plates, a top steel plate located on the floor slab and welded to each hoop plate, and multiple upper gusset plates welded to the top steel plate and evenly spaced from the hoop plates.
[0010] Furthermore, the connection structure between the newly added steel beam and the original low-strength concrete beam provided by this utility model integrates the hoop plate in the anchor plate coverage area with the anchor plate as a single structure.
[0011] Furthermore, in the connection structure between the newly added steel beam and the original low-strength concrete beam provided by this utility model, a tightening steel plate is tightly installed in the gap between the hoop plate of the outer steel frame and the original concrete beam.
[0012] Furthermore, in the connection structure between the newly added steel beam and the original low-strength concrete beam provided by this utility model, a tightening steel plate is tightly installed in the gap between the outer steel frame and the original concrete beam and structural adhesive is filled.
[0013] Furthermore, the connection structure between the newly added steel beam and the original low-strength concrete beam provided by this utility model also includes: laying an anti-crack mesh on the outer steel frame and constructing a cement mortar layer with a strength grade greater than that of the original concrete beam.
[0014] Compared with the prior art, the beneficial effects of this utility model are as follows:
[0015] This utility model provides a connection structure between a newly added steel beam and a low-strength original concrete beam. The newly added steel beam uses H-beams or I-beams and is connected to the original low-strength concrete beam (with a concrete strength grade between C13 and C25) via an anchor plate structure and an outer steel frame. This avoids the adverse environmental impact and the problems of large workload, long construction and maintenance periods associated with wet construction methods that involve enlarging the beam cross-section using cast-in-place structures. At the connection node between the newly added steel beam and the low-strength original concrete beam, the original concrete beam within a predetermined reinforcement range spanning both sides of the newly added steel beam is reinforced using an outer steel frame, thereby improving the structural strength at the node. The anchor plate structure further strengthens the connection between the newly added steel beam and the original concrete beam. The connection end face and anchor plate structure are fixed to the anchor plate by through-beam bolts penetrating the original concrete beam. Compared with the anchoring method of anchoring within the original concrete beam, this improves the structural strength of the anchor plate installation. A transition steel plate is vertically welded to the anchor plate of the anchor plate structure and connected to the web of the new steel beam by high-strength bolts. This allows the new steel beam to be connected to the original concrete beam via the transition steel plate, anchor plate structure, and outer steel frame. This avoids the problem of the new steel beam being unable to be anchored to a low-strength original concrete beam using anchor bolts, and avoids the need to enlarge the cross-section of the low-strength original concrete beam through cast-in-place reinforcement before connecting the new steel beam via anchor bolts. This avoids wet work and has the advantages of short construction period, convenient construction, and energy saving and environmental protection. Anchoring the new steel beam to the floor slab with anchors allows for upward tension on the new steel beam, reducing the shear force on the high-strength bolts at the connection point between the new steel beam and the transition steel plate due to gravity, thus improving the tightness of the connection between the new steel beam and the transition steel plate. Attached Figure Description
[0016] Figure 1 This is a schematic diagram of the elevation structure of the connection node between the newly added steel beam and the original low-strength concrete beam.
[0017] Figure 2 yes Figure 1 Cross-sectional view of AA in the middle;
[0018] As shown in the figure:
[0019] 100. The connection structure between the newly added steel beam and the original low-strength concrete beam;
[0020] 110. Outer steel frame; 111. Beam bottom angle steel; 112. Hoop plate; 113. Lower gusset plate; 114. Upper gusset plate; 115. Beam top steel plate; 116. Tightening steel plate; 117. Filler adhesive.
[0021] 120. Anchor plate structure; 121. Through-beam bolt; 122. Anchor plate;
[0022] 130. Adapter steel plate;
[0023] 140. New steel beams;
[0024] 150. Anchors;
[0025] 160. High-strength bolts;
[0026] 170. Original concrete beam;
[0027] 180. Floor slab. Detailed Implementation
[0028] The present invention will now be described in detail with reference to the accompanying drawings. The advantages and features of the present invention will become clearer from the following description. It should be noted that the drawings are all in a very simplified form and use non-precise proportions, and are only used to facilitate and clarify the illustration of the embodiments of the present invention.
[0029] Please refer to Figures 1 to 2 This utility model embodiment provides a method for connecting a newly added steel beam to an existing low-strength concrete beam, including:
[0030] Step S1: Construct an outer steel frame 110 on the original concrete beam 170 at the connection node with the new steel beam, and wrap the outer steel frame 110 through the floor slab 180 to cover the connection end face of the new steel beam 140 on the original concrete beam 170.
[0031] In step S2, anchor plates 122 are installed by inserting multiple through bolts 121 through the original concrete beam 170. The anchor plates 122 are distributed on the sides of the original concrete beam 170. The anchor plates 122 are welded to the outer steel frame 110 of the covered area. A transition steel plate 130 is vertically welded to the outside of the anchor plates 122. The figure illustrates the case of four through bolts 121, where each through bolt 121 includes a straight bolt and nuts threaded at both ends.
[0032] Step S3: The end face of the new steel beam 140 is brought close to or attached to the anchor plate 122 on the same side, and the web of the new steel beam 140 is overlapped and attached to the transition steel plate 130. The upper flange of the new steel beam 140 is attached to the floor slab 180, and the new steel beam 140 is anchored to the floor slab 180 through the upper flange using anchors 150. Multiple high-strength bolts 160 are used to fasten the end face of the new steel beam 140 to the transition steel plate 130 through the web of the new steel beam 140 and the transition steel plate 130. The anchors 150 can be chemical expansion bolts or anchor bolts. The figure illustrates the case where six high-strength bolts 160 are used to fasten the new steel beam 140 to the transition steel plate 130.
[0033] Please refer to Figures 1 to 2This utility model also provides a connection structure 100 between a newly added steel beam and a low-strength original concrete beam, employing the aforementioned connection method between the newly added steel beam and the low-strength original concrete beam, including an outer steel frame 110, an anchor plate structure 120, a transition steel plate 130, a newly added steel beam 140, anchors 150, and high-strength bolts 160, wherein:
[0034] An external steel frame 110 is constructed on the original concrete beam 170 at the node with the newly added steel beam 140. The external steel frame 110 passes through the floor slab 180 and covers the connection node of the newly added steel beam 140, and is constructed on the original concrete beam 170.
[0035] An anchor plate structure 120 is constructed on the original concrete beam 170 at the node with the newly added steel beam 140. It includes anchor plates 122 distributed on both sides of the original concrete beam 170. The anchor plates 122 on both sides are installed on the original concrete beam 170 by multiple through bolts 121 penetrating through the beam. The anchor plates 122 are welded to the outer steel frame 110 covering their area. The through bolts 121 are anchored to the holes in the original concrete beam 170 using adhesive.
[0036] The adapter steel plate 130 is located on the outside and is vertically welded to the anchor plate 122.
[0037] A new steel beam 140 is constructed at the joint with the original low-strength concrete beam 170. The end face of the new steel beam 140 is close to or attached to the anchor plate 122 on the side where it is located. The new steel beam 140 is an H-beam or an I-beam. The upper flange of the new steel beam 140 is attached to the floor slab 180. The new steel beam 140 is anchored to the floor slab 180 through the upper flange by anchors 150. The web of the new steel beam 140 overlaps and is attached to one side of the transition steel plate 130 and is fastened by multiple high-strength bolts 160.
[0038] The method and structure 100 for connecting a newly added steel beam to a low-strength original concrete beam provided in this embodiment of the invention uses H-beams or I-beams as the new steel beam 140, which is connected to the low-strength original concrete beam 170 (with a concrete strength grade between C13 and C25) via an outer steel frame 110, an anchor plate structure 120, and a transition steel plate 130. This avoids the adverse environmental impact and the problems of large workload, long construction and maintenance periods associated with wet construction processes used in methods that enlarge beam cross-sections using cast-in-place structures. At the connection node between the new steel beam and the low-strength original concrete beam, the outer steel frame 110 reinforces the original concrete beam 170 within a predetermined reinforcement range spanning both sides of the new steel beam, thereby improving the structural strength at the node between the new steel beam 140 and the original concrete beam 170. The anchor plate structure 120 enlarges the connection end face between the new steel beam 140 and the outer steel frame 110. Furthermore, the anchor plate structure 120 fixes the anchor plate 122 through the original concrete beam 170 via through bolts 121. Compared to the anchoring method of anchoring within the original concrete beam 170, this improves the structural strength of the anchor plate 122 installation. A transition steel plate 130 is vertically welded to the anchor plate 122 of the anchor plate structure 120 and connected to the web of the new steel beam 140 via high-strength bolts 160. This allows the new steel beam 140 to be connected to the original concrete beam 170 via the transition steel plate 130, the anchor plate structure 120, and the outer steel frame 110. This avoids the problem of the new steel beam 140 being unable to be directly anchored to the low-strength original concrete beam 170 using anchor bolts. It also avoids the technical method of increasing the cross-section of the low-strength original concrete beam through cast-in-place reinforcement before connecting the new steel beam via anchor bolts. This avoids wet work and has the advantages of short construction period, convenient construction, and energy saving and environmental protection. By anchoring the new steel beam to the floor slab with anchors, the new steel beam can be pulled upward, reducing the shear force on the high-strength bolts at the connection between the new steel beam and the transition steel plate caused by gravity, and improving the tight connection effect between the new steel beam and the transition steel plate.
[0039] Please refer to Figures 1 to 2The present invention provides a method and structure 100 for connecting a newly added steel beam to a low-strength original concrete beam. The outer steel frame 110 includes a bottom angle steel 111 constructed at each of the two corners of the bottom of the original concrete beam 170; multiple evenly spaced hoop plates 112 constructed through the floor slab 180 on the side of the original concrete beam 170; multiple lower gusset plates 113 welded to the lower surfaces of the two bottom angle steels 111 of the original concrete beam 170 and evenly spaced from the hoop plates 112; a top steel plate 115 located on the floor slab 180 and welded inward to each hoop plate 112; and multiple upper gusset plates 114 welded to the top steel plate 115 and evenly spaced from the hoop plates 112. At this time, the upper gusset plates 114, lower gusset plates 113, and the hoop plates 112 on both sides form a ring structure with multiple evenly spaced gussets welded to the bottom angle steel 111 and the top steel plate 115. The bottom angle steel 111 is welded to the lower gusset plate 113 and the hoop plate 112, and the top steel plate 115 is also welded to the hoop plate 112 and the upper gusset plate 114. The welding process includes, but is not limited to, chamfer welding. The bottom angle steel 111 and the top steel plate 115 are arranged along the entire length within the reinforcement range, thereby connecting the various hoop structures into a whole and improving the overall structural strength of the outer steel frame 110. The top steel plate 115 and the upper gusset plate 114 are located at the top of the original concrete beam 170. The top steel plate 115 can diffuse the load from the newly added steel beam 140 onto the top of the beam, satisfying the local bearing requirements of the concrete beam. The upper gusset plate 114 is located outside the top steel plate 115. The upper gusset plate 114 can transmit shear force and form a closed force system with the largest lever arm and the most effective constraint on the original concrete beam 170, preventing the top steel plate 115 from becoming unstable. It can also provide sufficient welding space for convenient construction. The upper and lower gusset plates and the hoop plate form a closed hoop to transmit force flow. In order to improve the tightness of the bottom angle steel 111 with the original concrete beam 170 and avoid large gaps, before the bottom angle steel 111 is installed at the corner of the bottom of the original concrete beam 170, the corner of the bottom of the low-strength grade original concrete beam 170 is ground into a rounded corner that matches the inner corner of the bottom angle steel 111. The reinforcement area refers to a section symmetrically distributed across the newly added steel beam 140 on the original concrete beam 170. To improve the stability and reliability of force transmission, the widths and spacing of the hoop plate 112, lower gusset plate 113, and upper gusset plate 114 are the same. Before enclosing the steel frame 110, the concentrated force transmitted from the newly added steel beam to the original concrete beam is used to perform local compression and local shear capacity verification on the original concrete beam to determine the dimensions and reinforcement area of the top steel plate and gusset plate.
[0040] Please refer to Figures 1 to 2The present invention provides a method and structure 100 for connecting a newly added steel beam to a low-strength original concrete beam. The method involves cutting off the overlapping area of the hoop plate 112 within the area covered by the anchor plate 122, and then welding the anchor plate 122 between the cut-off hoop plates 112, thus forming an integral structure between the anchor plate 122 and the hoop plate 112 within its covered area. The method of welding the hoop plate 112 to the anchor plate 122 in a discontinuous manner improves the load-bearing capacity and overall integrity of the anchor plate 112. The load is transferred from the newly added steel beam 140 to the anchor plate 122 via the transition steel plate 130 and high-strength bolts 160, and then to the outer steel frame 110, resulting in a more direct and smooth force transmission. To increase the load-bearing strength of the anchor plate 122, its thickness is greater than that of the hoop plate 112.
[0041] Please refer to Figure 1 To eliminate installation errors, the connection method and structure 100 between the newly added steel beam and the original low-strength concrete beam provided in this embodiment of the invention uses a tightening steel plate 116 to secure the gap between the hoop plate 112 of the outer steel frame 110 and the original concrete beam 170. For example, within the reinforcement range, the top of the original concrete beam 170 uses a -70x5 beam top steel plate 115, the bottom uses an L75x5 beam bottom angle steel 111, and a -50x5@50 hoop plate 112 and upper and lower connecting plates are used. The gap between the hoop plate and the beam can be filled with a -50x5 tightening steel plate 116.
[0042] Please refer to Figure 1 In order to eliminate the gap between the outer steel frame 110 and the original concrete beam 170 and improve the corrosion resistance of the joint, the connection method and structure 100 between the newly added steel beam and the original low-strength concrete beam provided in this utility model embodiment fills the gap between the outer steel frame 110 and the original concrete beam 170 by a combination of tightening steel plate 116 and structural adhesive filling.
[0043] To protect and prevent corrosion of the outer steel frame 110, extend its service life, and avoid rust, the connection method and structure 100 between the newly added steel beam and the original low-strength concrete beam provided in this embodiment of the invention involves laying a crack-resistant mesh on the outer steel frame 110 and constructing a cement mortar layer with a strength grade greater than that of the original concrete beam 170. The outer steel frame 110 is protected by the cement mortar layer containing the crack-resistant mesh. The thickness of the cement mortar layer is not less than 25mm.
[0044] The method and structure 100 for connecting a newly added steel beam to a low-strength original concrete beam provided in this embodiment of the invention reinforces the low-strength original concrete beam using a newly added steel beam 140. This method is convenient, quick, and effective, avoiding on-site wet concrete work and subsequent curing, saving construction time, and having no impact on the site environment. It can also be used in conjunction with other reinforcement methods, such as externally bonded steel beams or fiber cloth bonding, when the low-strength original concrete beam 170 has insufficient load-bearing capacity.
[0045] This utility model is not limited to the specific embodiments described above. Obviously, the embodiments described above are only some, not all, of the embodiments of this utility model. Based on the described embodiments of this utility model, all other embodiments obtained by those skilled in the art are within the scope of protection of this utility model. Those skilled in the art can make other levels of modifications and variations to this utility model. Therefore, if these modifications and variations of this utility model fall within the scope of the claims of this utility model, this utility model also intends to include these modifications and variations.
Claims
1. A connection structure between a newly added steel beam and a low-strength original concrete beam, characterized in that, include: An external steel frame is constructed on the original concrete beam at the joint with the newly added steel beam. The external steel frame passes through the floor slab, covers the connection joint of the newly added steel beam, and is constructed on the original concrete beam. An anchor plate structure is constructed on the original concrete beam at the node with the newly added steel beam. It includes anchor plates distributed on both sides of the original concrete beam. The anchor plates on both sides are installed on the original concrete beam by multiple through bolts that penetrate the original concrete beam. The anchor plates are welded to the outer steel frame of the area they cover. The adapter steel plate is located on the outside and is vertically welded to the anchor plate; A new steel beam is constructed at the joint with the existing low-strength concrete beam. The end face of the new steel beam is close to or attached to the anchor plate on the side where it is located. The new steel beam is an H-beam or an I-beam. The upper flange of the new steel beam is attached to the floor slab. The new steel beam is anchored to the floor slab through anchors passing through its upper flange. The web of the new steel beam overlaps and is attached to one side of the transition steel plate and is fastened by multiple high-strength bolts.
2. The connection structure between the newly added steel beam and the original low-strength concrete beam according to claim 1, characterized in that, The external steel frame includes a bottom angle steel installed at each of the two corners of the bottom of the original concrete beam, multiple evenly spaced hoops installed through the floor slab on the side of the original concrete beam, multiple lower gusset plates welded between the lower surfaces of the two bottom angle steels of the original concrete beam and evenly spaced from the hoops, a top steel plate located on the floor slab and welded to each hoop, and multiple upper gusset plates welded to the top steel plate and evenly spaced from the hoops.
3. The connection structure between the newly added steel beam and the original low-strength concrete beam according to claim 2, characterized in that, The hoop plate in the anchor plate coverage area is cut off and integrated with the anchor plate as a single structure.
4. The connection structure between the newly added steel beam and the original low-strength concrete beam according to claim 1, characterized in that, The gap between the hoop plate of the outer steel frame and the original concrete beam is tightly filled with a top steel plate.
5. The connection structure between the newly added steel beam and the original low-strength concrete beam according to claim 1, characterized in that, The gap between the outer steel frame and the original concrete beam is tightly fitted with a clamping steel plate and filled with structural adhesive.
6. The connection structure between the newly added steel beam and the original low-strength concrete beam according to claim 1, characterized in that, Also includes: Crack-resistant mesh is laid on the outer steel frame, and a cement mortar layer with a strength grade greater than that of the original concrete beam is constructed.