A bridge pier correction device
The bridge high pier correction device utilizes components such as guide beams, power mechanisms, and limiting beams to achieve precise and safe repositioning of high pier bridges. This solves the problems of cumbersome, time-consuming, and costly correction processes in existing technologies, reduces the risks of high-altitude operations, and improves correction efficiency and safety.
Patent Information
- Application Number
- CN202522619021.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-10
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-12-10
AI Technical Summary
Existing technologies for correcting deviations in high-pier bridges suffer from problems such as cumbersome procedures, long time consumption, high cost, insufficient safety, and inability to effectively prevent re-deviation. In particular, they are difficult to achieve fast, safe, and economical correction under complex terrain conditions.
The bridge pier correction device includes a guide beam, a power mechanism, a sliding component, a push plate component, and a limiting beam. By applying restoring force with jacks, the pier and cap beam are accurately reset, and the limiting device prevents further deviation. Combined with a real-time monitoring system, safety and controllability are ensured.
It enables precise and safe repositioning of high bridge piers, reduces the risk of falls from heights, shortens the correction period, reduces maintenance costs, effectively prevents subsequent misalignment, and improves the utilization rate and safety of the device.
Smart Images

Figure CN224982072U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building construction technology, and in particular to a bridge high pier correction device. Background Technology
[0002] In areas with complex geological conditions, primarily consisting of plateaus, basins, and mountains, the construction of highway bridges in mountainous regions is significantly influenced by the terrain, generally exhibiting characteristics such as numerous curves, steep longitudinal slopes, and high piers. Among these, the misalignment of the pier joints in high-pier bridges (especially flexible high-pier continuous beam bridges with steep longitudinal slopes) has become a common problem on multiple routes. This misalignment occurs when the upper end of the pier (cap beam) is not vertical, causing the T-beam located on the downhill section to tilt downwards.
[0003] Once such misalignment occurs, correction is necessary. Existing correction methods include using steel wire ropes and hand-operated hoists to apply tension to the pier top for forced repositioning. This method requires dismantling the bridge deck system and lifting the precast beams, a cumbersome and time-consuming process. Furthermore, during bridge construction, the superstructure is prone to displacement, resulting in uneven stress on the piers and potential structural safety hazards. After correction, there are no effective measures to prevent recurrence of misalignment, leading to a high risk of subsequent damage. Additionally, the large amount of manual and mechanical input is costly, and there are insufficient safety guarantees for high-altitude operations, making it difficult to meet the needs of rapid, safe, and economical maintenance of high-pier structures on mountainous highway bridges.
[0004] Mechanical correction devices are also used, such as the bridge pier correction and repositioning device disclosed in patent publication number CN112049029A. This device includes a reaction frame mounted on the cap beam, with jacks installed on the reaction frame. The driving ends of the jacks abut against the fixed bridge beam, thus correcting the pier's deviation. In use, the jacks are activated, causing their driving ends to abut against the bridge beam. Since the bridge beam is fixed, it generates a reaction force on the reaction frame, causing the cap beam to move with the reaction frame, thereby moving the bridge pier and repositioning it. This correction and repositioning device does not have a fixed structure on the bridge beam and is only suitable for ordinary highway bridges. For high-pier bridges with complex terrain, additional fixing points need to be added to the T-beams during the correction process. Therefore, this prior art is not suitable for correcting the deviation of high-pier bridges. Utility Model Content
[0005] The purpose of this invention is to provide a bridge pier correction device that enables precise and safe repositioning of bridge piers and solves the problem of subsequent misalignment.
[0006] The technical solution of this utility model is: a bridge high pier correction device, including a guide main beam, a power mechanism disposed on the lower surface of one end of the guide main beam along the longitudinal direction Y, a sliding component disposed on the lower surface of the other end of the guide main beam along the longitudinal direction Y, and a push plate assembly disposed on the upper surface of the other end of the guide main beam along the longitudinal direction Y. The power output end of the power mechanism abuts against the cap beam, the sliding component is placed on the cap beam of the bridge high pier, and the push plate assembly contacts the side of the T-beam located above the cap beam. The guide main beam is provided with a fixed beam extending along the transverse direction X, and the upper surfaces of both ends of the fixed beam are provided with a first limiting beam, which contacts the side of the T-beam in the transverse direction X.
[0007] Preferably, the first limiting beam is positioned away from the push plate assembly.
[0008] Preferably, the lower surface of the fixed beam is provided with a second limiting beam corresponding to the guide main beam, and two second limiting beams are provided for each guide main beam, with the two second limiting beams sandwiched on both sides of the guide main beam.
[0009] Preferably, the push plate assembly includes a second pad fixed to the guide beam, a hook beam fixed to the second pad, and a push plate disposed on the hook beam and in contact with the T-beam.
[0010] Preferably, a stiffening plate is connected between the hook beam and the second pad.
[0011] Preferably, the sliding assembly includes a third pad placed on the cover beam and a plurality of rollers disposed between the third pad and the guide beam, the rollers making rolling contact with the third pad and the guide beam along the longitudinal direction Y.
[0012] Preferably, the third pad is provided with a plurality of grooves for mounting the roller.
[0013] Preferably, the power mechanism includes a push base and a jack, the push base is fixed to the lower surface of the guide beam, the fixed end of the jack contacts the push base, and the telescopic end of the jack contacts the cover beam.
[0014] Preferably, the telescopic end of the jack is provided with a first pad, which is placed on the cover beam.
[0015] Preferably, a pressure sensor is provided on the telescopic end of the jack.
[0016] Compared with related technologies, the beneficial effects of this utility model are as follows: I. This utility model adds a push plate assembly and a limiting beam that can be clamped on the T-beam. The push plate assembly contacts the T-beam in the longitudinal direction, and the limiting beam is clamped at both ends of the T-beam in the transverse direction, thereby forming a fixed point on the T-beam, which is more conducive to the operation of the jack to push the cap beam on the high pier to reset. Second, during the correction process, the superstructure remains basically still, the cap beam is subjected to uniform stress, and the bridge piers can be accurately and safely repositioned. Third, this utility model is applicable to high-altitude operations. By designing a limit beam and push plate assembly, it effectively reduces the risk of falling from heights and makes the entire operation controllable. Fourth, the correction device of this utility model can be reused and has a high utilization rate. Attached Figure Description
[0017] Figure 1 A schematic diagram of the transverse arrangement of the bridge pier correction device provided by this utility model; Figure 2 This is a schematic diagram of the longitudinal installation of the bridge pier correction device provided by this utility model.
[0018] In the attached diagram: 1. Cap beam; 2. T-beam; 3. Correction device; 31. Guide main beam; 32. Power mechanism; 321. Push seat; 322. Jack; 323. First pad; 33. Fixed beam; 34. First limiting beam; 35. Second limiting beam; 36. Push plate assembly; 361. Hook beam; 362. Stiffening plate; 363. Second pad; 364. Push plate; 37. Sliding assembly; 371. Roller; 372. Third pad. Detailed Implementation
[0019] The present invention will be described in detail below with reference to the accompanying drawings and embodiments. It should be noted that, unless otherwise specified, the embodiments and features described in the embodiments of the present invention can be combined with each other. For ease of description, the terms "upper," "lower," "left," and "right" appearing below only indicate that they correspond to the upper, lower, left, and right directions in the accompanying drawings and do not limit the structure.
[0020] like Figure 1 , Figure 2 As shown, this embodiment provides a bridge pier correction device 3 for correcting the position of the cap beam 1 of the T-beam 2 in the longitudinal Y direction. The bridge pier correction device 3 is made of Q235 steel and includes a fixed beam 33, a first limiting beam 34, a second limiting beam 35, a guide main beam 31, a power mechanism 32 disposed on the lower surface of one end of the guide main beam 31 in the longitudinal Y direction, a sliding assembly 37 disposed on the lower surface of the other end of the guide main beam 31 in the longitudinal Y direction, and a push plate assembly 36 disposed on the upper surface of the other end of the guide main beam 31 in the longitudinal Y direction.
[0021] The guide beam 31 is arranged longitudinally Y-shaped at the upper end of the cap beam 1. The power mechanism 32 includes a pusher 321 and a jack 322. The pusher 321 is fixed to the lower surface of the guide beam 31, the fixed end of the jack 322 contacts the pusher 321, and the telescopic end of the jack 322 contacts the cap beam 1 through a first pad 323. The jack 322 is a 30t jack, and the number is determined according to the number of T-beams 2, with no less than 6 jacks for each half of the bridge. Each telescopic end of the jack 322 is equipped with a pressure sensor (not shown), and the range of the pressure sensor is greater than the tonnage of the jack 322.
[0022] like Figure 1 As shown, a correction device 3 is installed between the two T-beams 2. A fixed beam 33 extending in the transverse X direction is provided on the guide beam 31. First limiting beams 34 are provided on the upper surfaces of both ends of the fixed beam 33, and the first limiting beams 34 contact the sides of the T-beams 2 in the transverse X direction. Two guide beams 31 are provided on the fixed beam 33, and each guide beam 31 has a second limiting beam 35 on both sides in the transverse X direction. The upper ends of the second limiting beams 35 are connected to the fixed beam 33.
[0023] The pusher plate assembly 36 contacts the side of the T-beam 2. The pusher plate assembly 36 includes a second pad 363 fixed to the guide main beam 31, a hook beam 361 fixed to the second pad 363, and a pusher plate 364 disposed on the hook beam 361 and in contact with the T-beam 2. A stiffening plate 362 connects the hook beam 361 and the second pad 363.
[0024] The sliding assembly 37 is placed on the cover beam 1. The sliding assembly 37 includes a third pad 372 placed on the cover beam 1 and a plurality of rollers 371 disposed between the third pad 372 and the guide beam 31. The rollers 371 roll in contact with the third pad 372 and the guide beam 31 along the longitudinal direction Y. A plurality of grooves for embedding the rollers 371 may be provided on the third pad 372.
[0025] When using the correction system, it is also necessary to install a device to measure the displacement of the cap beam 1 relative to the T beam 2, as well as a total station (2 units, used to monitor the repositioning of the piers under the bridge) and a strain acquisition box (1 unit, connected to the strain gauge at the bottom of the pier to monitor the stress).
[0026] Based on the principle that action and reaction forces are far apart, T-beam 2, which is continuously constrained in the longitudinal Y direction and runs uphill, serves as the reaction device. A restoring force is applied in the longitudinal Y direction downhill using jacks to reposition the pier and cap beam 1. The specific construction steps are as follows: S1, Construction Preparation: S1.1, accurately measure the deviation of the high pier twice a day for three consecutive days, morning and evening, and track the changes in the deviation; S1.2, check the condition of the cap beam 1 and T beam 2 and their attached parts (such as supports, blocks, etc.), clean the misaligned piers and adjacent expansion joints, and quickly fill the expansion joints with wood, steel, and concrete to prevent displacement of the upper T beam 2 during the correction. S1.3, Erect the construction scaffolding and prepare monitoring equipment; S2, Prestress estimation: S2.1, Calculate the frictional thrust: f = P_1×10×8%×1.1 (P_1 is the self-weight of the beam and bridge deck system, in tons, overload factor 1.1, sliding friction coefficient 8%). S2.2, Calculate the thrust of a single jack: F = X×10×0.8 (X is the rated tonnage of the jack, in tons, with an efficiency coefficient of 0.8). S2.3, Determine the number of jacks: Total thrust P_{total} = S × F (S is the number of jacks), which must satisfy P_{total} > f (the friction coefficient between the rolling steel bar and the steel pad is 3‰~5‰, and the resistance of the device is negligible). S3, Monitoring System Deployment: S3.1, Horizontal thrust monitoring: A pressure sensor is installed at the front end of each jack to monitor the thrust magnitude and uniformity in real time; S3.2, Displacement monitoring: The safety displacement meter on the top of the pier monitors the relative displacement of the cap beam 1 (including the transverse direction), and the total station under the bridge monitors the overall displacement of the high pier; S3.3, Stress monitoring: Strain gauges are attached to the bottom of the high pier and connected to a strain acquisition box to monitor concrete strain and stress in real time; S4, Correction work: S4.1, Synchronous jacking: Use a synchronous jacking system to vertically jack the T-beam 2 by 1-2mm, and install a correction device 3 between the T-beam 2 and the cap beam 1; S4.2, Top-pushing pre-tightening: Apply a load of 10kN to each jack, check the operating status of the device and components, and stop the machine for adjustment if any abnormality is found; S4.3, Step-by-step jacking: Under normal circumstances, apply a load of 10kN per step simultaneously, hold the load for 3~5 minutes per step and monitor, and slowly push the high pier back to its original position; S4.4, Load holding limit: After the high pier is reset, maintain the jack thrust for 48 hours and observe continuously. If there are no abnormalities, install the limit device to complete the correction. If cracks appear in the high pier, reinforce it simultaneously.
[0027] The correction device of this utility model has high safety. During the correction process, the upper structure is basically stationary and the high pier is subjected to uniform force. The structural damage is avoided by real-time monitoring (thrust, displacement, stress). The device is designed to be suitable for high-altitude operations. The protective cable and limit device reduce the risk of falling. The operation is controllable throughout.
[0028] The correction device of this utility model is economical. Its material is Q235 steel commonly used in bridge engineering, which is simple to process and moderately priced. Compared with conventional methods, it eliminates the process of dismantling the bridge deck system and raising the beam plate. The correction period for a single high pier is only 9 days (including 3 days for device fabrication, 2 days for preparation, 2 days for construction, and 2 days for load holding), which reduces the construction period by more than 30 days and saves maintenance costs of 300,000 yuan per pier.
[0029] The correction device of this utility model has strong versatility and durability: the number of jacks and the size of the guide beam and the jacking base can be adjusted according to the beam size and the bridge deck weight, and it can be adapted to bridge piers of different structural types; the correction device is modified into a permanent facility after correction, which effectively prevents later deviation. The device has a high material turnover rate and can be reused for multiple bridges.
[0030] The correction device of this utility model is easy to operate: the synchronous jacking system and the step-by-step jacking process simplify the construction process and reduce the intensity of manual labor; the quick installation and disassembly design reduces on-site operation time, facilitates transportation, and is suitable for the construction environment of high piers of bridges in mountainous areas.
[0031] The above description is merely an embodiment of this utility model and does not limit the patent scope of this utility model. Any equivalent structural or procedural transformations made based on the content of this utility model specification and drawings, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of this utility model.
Claims
1. A bridge pier correction device, characterized in that, The structure includes a guide beam (31), a power mechanism (32) disposed on the lower surface of one end of the guide beam (31) along the longitudinal direction Y, a sliding assembly (37) disposed on the lower surface of the other end of the guide beam (31) along the longitudinal direction Y, and a push plate assembly (36) disposed on the upper surface of the other end of the guide beam (31) along the longitudinal direction Y. The power output end of the power mechanism (32) abuts against the cap beam (1), the sliding assembly (37) is placed on the cap beam (1) of the bridge pier, and the push plate assembly (36) contacts the side of the T beam (2) located above the cap beam (1). The guide beam (31) is provided with a fixed beam (33) extending along the transverse direction X. The upper surfaces of both ends of the fixed beam (33) are provided with a first limiting beam (34), and the first limiting beam (34) contacts the side of the T beam (2) in the transverse direction X.
2. The bridge high pier correction device according to claim 1, characterized in that, The first limiting beam (34) is positioned away from the push plate assembly (36).
3. The bridge high pier correction device according to claim 1, characterized in that, The lower surface of the fixed beam (33) is provided with a second limiting beam (35) corresponding to the guide main beam (31), and two second limiting beams (35) are provided for each guide main beam (31), with the two second limiting beams (35) sandwiched on both sides of the guide main beam (31).
4. The bridge high pier correction device according to claim 1, characterized in that, The push plate assembly (36) includes a second pad (363) fixed to the guide beam (31), a hook beam (361) fixed to the second pad (363), and a push plate (364) disposed on the hook beam (361) and in contact with the T beam (2).
5. The bridge high pier correction device according to claim 4, characterized in that, A stiffening plate (362) is connected between the hook beam (361) and the second pad (363).
6. The bridge pier correction device according to any one of claims 1-5, characterized in that, The sliding assembly (37) includes a third pad (372) placed on the cover beam (1) and a plurality of rollers (371) disposed between the third pad (372) and the guide beam (31), the rollers (371) rollingly contacting the third pad (372) and the guide beam (31) along the longitudinal direction Y.
7. The bridge high pier correction device according to claim 6, characterized in that, The third pad (372) is provided with a plurality of grooves for mounting the roller (371).
8. The bridge pier correction device according to any one of claims 1-5, characterized in that, The power mechanism (32) includes a push seat (321) and a jack (322). The push seat (321) is fixed to the lower surface of the guide beam (31). The fixed end of the jack (322) is in contact with the push seat (321), and the telescopic end of the jack (322) is in contact with the cover beam (1).
9. The bridge high pier correction device according to claim 8, characterized in that, The telescopic end of the jack (322) is provided with a first pad (323), which is placed on the cover beam (1).
10. The bridge high pier correction device according to claim 8, characterized in that, A pressure sensor is provided on the telescopic end of the jack (322).