A shallow soft soil foundation reinforced masonry revetment structure suitable for fishing boat berthing

By reinforcing the harbor bank on soft soil, and constructing a masonry block revetment structure using precast square piles and rubble foundations, the needs for berthing and landscaping in the harbor were met, achieving both berthing functionality and aesthetic appeal for fishing boats. Furthermore, the construction was highly efficient and resource-saving.

CN224982118UActive Publication Date: 2026-11-17NINGBO CHINA COMM WATER TRANSPORTATION DESIGN & RES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522798865.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-30
Publication Date
2026-11-17
Estimated Expiration
2035-12-30

AI Technical Summary

Technical Problem

Existing vertical or sloping masonry revetments are insufficient to meet the berthing function and landscape performance requirements of fishing ports on soft soil, and the resources are not fully utilized.

Method used

Precast square piles are used to reinforce the soft foundation of the revetment, a rubble bed and a load-bearing cushion layer are laid, a mortar-grouted rubble retaining wall is built and rubber fenders are installed, drainage components and concrete breast walls are set up, and combined with mooring bollards and surface structure, a shallow soft foundation reinforced mortar-grouted rubble revetment structure suitable for fishing boats to berth is formed.

Benefits of technology

It enables fishing boats to berth, meets the landscape requirements of fishing ports, and has the advantages of simple structure, convenient construction, high efficiency, low cost, and resource conservation. It solves the functional and landscape problems of fishing port revetments in soft soil geology.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982118U_ABST
    Figure CN224982118U_ABST
Patent Text Reader

Abstract

This utility model relates to a shallow soft soil foundation reinforcement masonry revetment structure suitable for fishing boat berthing, comprising precast square piles driven into the excavated soft soil foundation, a masonry foundation bed laid on the soft soil foundation, a load-bearing cushion layer laid on the masonry foundation bed, the upper surface of the load-bearing cushion layer being flush with the upper surface of the masonry foundation bed, a concrete foundation being poured on the load-bearing cushion layer, a masonry retaining wall being built on the concrete foundation, a concrete breast wall being poured on top of the masonry retaining wall, a rubber fender being installed in front of the masonry retaining wall, a masonry base layer being backfilled behind the masonry retaining wall, and a drainage component being embedded in the masonry retaining wall communicating with the rubber fender and the masonry base layer, and a surface layer structure being poured between the top of the masonry base layer and the rear end of the concrete breast wall; this utility model has the advantages of simple structure, strong applicability, convenient construction, high construction efficiency, full utilization of stone materials, short construction period, low cost, and conservation of marine resources.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the technical field of masonry revetment for fishing ports, and particularly relates to a shallow soft soil foundation reinforced masonry revetment structure suitable for fishing boats to moor. Background Technology

[0002] In recent years, with the rapid development of fishery infrastructure construction in my country, many coastal areas, such as the Jiangsu and Zhejiang regions, have abundant fishery resources and a high level of fishery development, necessitating the construction and reinforcement of fishing port revetments. Revetments are structures built to protect river and seawalls from the erosion of water flow and waves, typically constructed of masonry blocks and concrete. They are generally vertical or sloping, with sloping revetments often used in areas with abundant land resources, and vertical revetments more commonly used in areas with scarce land resources. While current vertical or sloping revetments can meet the needs of protective engineering, with the development of shoreline resources and the scarcity of good geological resources, constructing new revetments on soft soil presents a new challenge. On the other hand, fishing port revetments also need to consider the function of berthing vessels. This masonry block revetment features berthing and mooring facilities at the front edge, enabling fishing vessels to berth and operate. Additionally, landscaping facilities can be installed behind the revetment to meet the aesthetic requirements of the fishing port. Summary of the Invention

[0003] The purpose of this utility model is to overcome the shortcomings of the existing technology and provide a shallow soft soil foundation reinforced masonry revetment structure suitable for fishing boat berthing, which can effectively solve the problems of berthing function and landscape performance requirements of new revetments in soft soil fishing ports.

[0004] The purpose of this utility model is achieved through the following technical solution: This shallow soft foundation reinforced masonry revetment structure suitable for fishing boat berthing includes precast square piles, which are driven into the excavated soft foundation of the revetment. A rubble bed is filled on the soft foundation, and a load-bearing cushion layer is laid on the rubble bed. The upper surface of the load-bearing cushion layer is flush with the upper surface of the rubble bed. A concrete foundation is poured on the load-bearing cushion layer, and a masonry retaining wall is built on the concrete foundation. A concrete breast wall is poured on top of the masonry retaining wall. A rubber fender is installed in front of the masonry retaining wall, and a rubble base layer is backfilled behind the masonry retaining wall. A drainage component is embedded in the masonry retaining wall, which communicates with the rubber fender and the rubble base layer. A surface layer structure is poured between the top of the rubble base layer and the rear end of the concrete breast wall. A mooring bollard is pre-embedded above the concrete breast wall.

[0005] The beneficial effects of this utility model are as follows: Compared with the prior art, by reinforcing the soft foundation of the revetment and building a masonry retaining wall on it, and setting rubber fenders, the function of fishing boats berthing and operating can be realized. In addition, the cast-in-place surface structure can be used to set up landscape facilities to meet the landscape requirements of fishing port revetments. It has the advantages of simple structure, strong applicability, convenient construction, high construction efficiency, full utilization of stone materials, short construction period, low cost, and saving marine resources. It can effectively solve the problems of berthing function and landscape performance requirements of new revetments for fishing ports with soft soil geology.

[0006] Preferably, the top of the precast square pile passes through the bearing capacity cushion layer and is connected to the concrete foundation, and the precast square piles are driven sequentially along the length of the revetment soft foundation; through the above structure, the bearing capacity cushion layer and the bearing capacity cushion layer can achieve further bearing through the precast square piles, thereby greatly improving the bearing capacity.

[0007] Preferably, the bearing capacity cushion layer includes a crushed stone cushion layer and a plain concrete cushion layer, wherein the width of the crushed stone cushion layer is greater than the width of the plain concrete cushion layer, and the bearing capacity cushion layer is laid along the length direction of the revetment soft foundation; through the above structure, not only is the bearing capacity greatly enhanced, but it also has good permeability.

[0008] Preferably, the front of the masonry retaining wall is a vertical surface with a concrete wall surface, and the rear of the masonry retaining wall is an inclined surface, which slopes upward from the bottom end to the top end along the side of the concrete breast wall. With the above structure, water in the masonry base can be discharged to the outside from the rear of the masonry retaining wall through the drainage component, which greatly reduces the water pressure behind the masonry retaining wall.

[0009] Preferably, the concrete wall surface is flush with the concrete breast wall, and the rubber fender is fixed to the concrete wall surface and the concrete breast wall by embedded parts. The rubber fender is provided in several pieces and is distributed at intervals along the length of the revetment soft foundation. The rubber fender mainly reduces the impact of ships on the revetment and transfers the impact force of the ship to the revetment wall through the rubber fender.

[0010] Preferably, the drainage component includes a PVC pipe and a reverse filter unit. The PVC pipe is pre-embedded in the masonry retaining wall and is inclined downward from the rear to the front of the masonry retaining wall. The reverse filter unit is pre-embedded in the masonry base layer and is located at the drainage hole of the PVC pipe. By setting the reverse filter unit, the filler in the masonry base layer can be prevented from being lost with the PVC pipe, and the drainage component can reduce the water pressure behind the masonry retaining wall. Attached Figure Description

[0011] Figure 1This is a schematic cross-sectional view of the shallow soft soil foundation reinforced masonry revetment structure of this utility model.

[0012] Figure 2 This is a side view schematic diagram of the shallow soft soil foundation reinforced masonry revetment structure of this utility model.

[0013] Figure 3 This is a top view schematic diagram of the shallow soft soil foundation reinforced masonry revetment structure of this utility model.

[0014] The labels in the attached diagram are as follows: 1. Precast square pile; 2. Soft foundation for revetment; 3. Rubble foundation; 4. Bearing capacity cushion layer; 5. Concrete cap; 6. Masonry retaining wall; 7. Concrete breast wall; 8. Rubber fender; 9. Rubble base layer; 10. Drainage components; 11. Surface structure; 12. Mooring bollard; 41. Crushed stone cushion layer; 42. Plain concrete cushion layer; 61. Concrete wall surface; 10-1. PVC pipe; 10-2. Inverted filter unit. Detailed Implementation

[0015] The present invention will now be described in detail with reference to the accompanying drawings: as shown in the drawings Figures 1 to 3 As shown, this utility model includes a precast square pile 1, which is driven into the excavated revetment soft foundation 2. A rubble bed 3 is filled on the revetment soft foundation 2, and a bearing capacity cushion layer 4 is laid on the rubble bed 3. The upper surface of the bearing capacity cushion layer 4 is flush with the upper surface of the rubble bed 3. A concrete foundation 5 is poured on the bearing capacity cushion layer 4. A masonry rubble retaining wall 6 is built on the concrete foundation 5. A concrete breast wall 7 is poured on the top of the masonry rubble retaining wall 6. A rubber fender 8 is installed in front of the masonry rubble retaining wall 6. A rubble base layer 9 is backfilled behind the masonry rubble retaining wall 6. A drainage component 10 is embedded on the masonry rubble retaining wall 6, which is connected to the rubber fender 8 and the rubble base layer 9. A surface structure 11 is poured between the top of the rubble base layer 9 and the rear end of the concrete breast wall 7. A mooring bollard 12 is pre-embedded above the concrete breast wall 7.

[0016] The top of the precast square pile 1 passes through the bearing capacity cushion layer 4 and is connected to the concrete foundation 5, and the precast square pile 1 is driven sequentially along the length of the revetment soft foundation 2.

[0017] The bearing capacity cushion layer 4 includes a crushed stone cushion layer 41 and a plain concrete cushion layer 42. The width of the crushed stone cushion layer 41 is greater than the width of the plain concrete cushion layer 42, and the bearing capacity cushion layer 4 is laid along the length of the revetment soft foundation 2.

[0018] The front of the masonry retaining wall 6 is a vertical surface with a concrete wall 61 cast in. The rear of the masonry retaining wall 6 is an inclined surface, which slopes upward along the side of the concrete breast wall 7 from the bottom end to the top end.

[0019] The concrete wall 61 is flush with the concrete breast wall 7, and the rubber fender 8 is fixed to the concrete wall 61 and the concrete breast wall 7 by embedded parts. Several rubber fenders 8 are provided and are distributed at intervals along the length of the revetment soft foundation 2.

[0020] The drainage component 10 includes a PVC pipe 10-1 and a reverse filter unit 10-2. The PVC pipe 10-1 is embedded in the masonry retaining wall 6 and is inclined downward from the rear to the front of the masonry retaining wall 6. The reverse filter unit 10-2 is embedded in the masonry base layer 9 and is located at the drainage hole of the PVC pipe 10-1.

[0021] The construction process of this utility model is as follows: First, precast square piles 1 are driven sequentially along the length of the revetment soft foundation 2. Then, along the length of the revetment soft foundation 2, the rubble foundation bed 3, the bearing capacity cushion layer 4, the concrete foundation 5, the mortar-grouted rubble retaining wall 6, and the concrete breast wall 7 are constructed sequentially upwards. Rubber fenders 8 are installed in front of the mortar-grouted rubble retaining wall 6 and the concrete breast wall 7. Finally, the rubble base layer 9 is filled behind the mortar-grouted rubble retaining wall 6, and the surface structure 11 is poured.

[0022] Precast square pile 1: Precast square pile 1 can be a 300×300mm precast concrete small square pile. This mortar-grouted masonry revetment uses small square piles to reinforce the soft soil foundation. The pile length is selected according to calculations. The reinforcement treatment with small square piles enhances the bearing capacity of the foundation. Concrete small square piles are easy to purchase, reducing costs, meeting environmental protection requirements, and are convenient to construct.

[0023] Rockfill Subgrade 3: Rockfill subgrade 3 can be filled with 10-100kg rocks. First, excavate the surface soft soil of the foundation trench for the revetment soft foundation 2. After excavating to the design elevation, carry out the rockfill subgrade construction. The subgrade should be filled with 10-100kg rocks. When the rockfill subgrade is thick, it needs to be filled in layers. The rockfill subgrade should allow for settlement. After the rockfill subgrade is completed, the subgrade is leveled, including coarse leveling and fine leveling. After leveling, the subgrade is compacted, and then the crushed stone cushion layer 41 is laid.

[0024] Crushed stone cushion layer 41: The crushed stone cushion layer 41 can be laid using graded crushed stone. The graded crushed stone is laid after the subgrade has been compacted. Graded crushed stone has good permeability and stress diffusion, load-bearing transition properties, and is widely available, allowing for local sourcing and facilitating the processing of raw materials and mixtures, as well as mechanical paving operations.

[0025] Plain concrete cushion layer 42: C20 plain concrete can be used for the plain concrete cushion layer 42. It is laid after the crushed stone cushion layer 41. The plain concrete cushion layer 42 is located between the concrete cap 5 and the crushed stone cushion layer 41, used to improve the water stability of the foundation and to distribute loads to reduce foundation deformation. The concrete cap 5 serves as a leveling, isolation, and transition layer. It facilitates construction layout and foundation formwork support. It ensures the effective position of the foundation cap reinforcement and allows for better control of the protective layer; it isolates the bottom reinforcement from soil contamination. It facilitates the application of an anti-corrosion layer to the foundation bottom surface. Leveling, by adjusting the thickness, compensates for errors in earthwork excavation, ensuring the base slab is stressed on a single plane and avoiding waste of high-grade concrete for the foundation.

[0026] Concrete foundation 5: Concrete foundation 5 can be cast using C40 concrete, and the thickness of the foundation is set according to the calculation requirements. Concrete foundation 5 is constructed after the lower foundation bed is completed. Before pouring concrete foundation 5, the rubble foundation bed 3 needs to be leveled and compacted. After the foundation bed is leveled, the concrete foundation is poured in sections, and the section length can be 5~20 m.

[0027] Masonry retaining wall 6: The masonry retaining wall 6 uses M10 masonry blocks. Construction of the masonry retaining wall 6 can only begin after the concrete foundation 5 is completed and the concrete has reached its set age. Stone tenons should be embedded in the top surface of the foundation. The exposed length of the stones should not be less than 150mm, the spacing should be 300mm~500mm, and the embedment depth should be 150mm~200mm. When constructing the masonry on the concrete foundation 5, the base surface should be cleaned and moistened before mortaring. When the retaining wall is constructed in layers or sections, the height difference between adjacent sections should not exceed 1.2m. The masonry retaining wall 6 is poured in sections as needed, with the section length consistent with the concrete foundation 5. During construction of the masonry retaining wall 6, PVC pipes 10-1 for drainage holes are installed. For masonry retaining walls, expansion joints must be provided along the length direction. The spacing of the expansion joints should be determined according to the temperature, foundation conditions and subgrade thickness, and should be 10~30m.

[0028] Concrete wall 61: Concrete wall 61 can be poured using C30 concrete, and the wall thickness is set according to calculation requirements. Concrete wall 61 is poured in sections after the masonry retaining wall 6 is constructed, with the section lengths matching those of the masonry retaining wall 6. Rubber fender embedded parts are installed during the pouring of the concrete wall.

[0029] Drainage component 10: The drainage component 10 uses a 100mm diameter PVC pipe 10-1, with a drainage hole installed every 5m. The drainage component 10 is installed during the construction of the masonry retaining wall 6, and the slope of the PVC pipe 10-1 meets the relevant specifications during installation. The drainage component 10 is mainly used to reduce the water pressure behind the wall.

[0030] Inverted Filter Unit 10-2: Inverted filter unit 10-2 can be constructed using two-piece riprap and geotextile as the inverted filter structure. It is installed after the riprap is poured up to the drainage hole. The number of inverted filter units can be increased appropriately when the cofferdam is high. The main purpose of inverted filter unit 10-2 is to prevent the backfill material from being lost through the drainage hole. The inverted filter layer should be constructed in sections and layers, with each layer staggered by sufficient distance. When using geotextile inverted filter material, non-woven geotextiles and woven geotextiles are preferred. Backfilling should be carried out promptly after the inverted filter layer is constructed.

[0031] Rubber fenders 8: Rubber fenders 8 can be purchased as finished products from rubber fender manufacturers. The spacing of the rubber fenders 8 is set according to the calculations of the designed ship type. Embedded parts are installed in both the concrete breast wall 7 and the concrete wall surface 61 to fix the rubber fenders 8. The rubber fenders 8 mainly mitigate the impact of ships on the shore, transferring the impact force of the ship to the shore wall through the rubber fenders 8.

[0032] Block stone base layer 9: High-quality quarry stone or similar aggregate can be used for the block stone base layer 9. Backfilling behind the wall should only be carried out after the masonry wall has reached its design strength. The bottom layer should be filled with small stones, and the top layer with large stones. When there are block stone prisms behind the wall, the prisms and the inverted filter layer should be constructed first. Backfilling behind the wall should be layered and compacted. The thickness of each layer should be determined based on the type of backfill material, the compaction method, and the mechanical properties.

[0033] Concrete breast wall 7: Concrete breast wall 7 can be cast using C40 concrete. The construction of concrete breast wall 7 will be carried out after the masonry retaining wall has been constructed to the design elevation. Concrete breast wall 7 mainly serves as a capping structure and a mounting structure for mooring facilities. During the casting of concrete breast wall 7, the mooring bollards 12 and rubber fenders will be embedded.

[0034] Bollard 12: Bollard 12 can be a 150kN bollard. The size of bollard 12 is selected based on the design ship type, and the spacing of bollard 12 is also selected based on the design ship type. Bollard 12 and related embedded components can be purchased as a set from the manufacturer. The bollard embedded components are pre-embedded during the pouring of the breast wall. The main function of the bollard is to secure the mooring lines when the ship is berthed and operating.

[0035] Surface Structure 11: Surface structure 11 can consist of a graded crushed stone base layer, a concrete base layer, and a concrete surface layer. After the rubble is filled to the design elevation, the surface structure construction begins. First, a 100 mm graded crushed stone base layer is laid, followed by a 150 mm C15 concrete base layer, and finally a 200 mm concrete surface layer. Landscape features such as covered walkways can be installed above the surface structure as needed.

[0036] The above are merely specific embodiments of this application, but the scope of protection of this application is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in this application should be included within the scope of protection of this application. Therefore, the scope of protection of this application should be determined by the scope of the claims.

Claims

1. A kind of shallow soft foundation reinforcement mortar block revetment structure suitable for fishing boat berthing, including prefabricated square pile (1), it is characterized in that: The precast square piles (1) are driven onto the excavated revetment soft foundation (2). A rubble foundation bed (3) is filled on the revetment soft foundation (2), and a bearing capacity cushion layer (4) is laid on the rubble foundation bed (3). The upper surface of the bearing capacity cushion layer (4) is flush with the upper surface of the rubble foundation bed (3). A concrete foundation (5) is poured on the bearing capacity cushion layer (4), and a masonry rubble retaining wall (6) is built on the concrete foundation bed (5). The top of the masonry rubble retaining wall (6) is filled with concrete. The earthen breast wall (7) is equipped with a rubber fender (8) in front of the masonry retaining wall (6), and a rubble base (9) is backfilled behind the masonry retaining wall (6). A drainage component (10) is embedded on the masonry retaining wall (6) which communicates with the rubber fender (8) and the rubble base (9). A surface structure (11) is poured between the top of the rubble base (9) and the rear end of the concrete breast wall (7). A mooring bollard (12) is pre-embedded above the concrete breast wall (7).

2. The shore protection structure of the shallow soft ground reinforcement by the block masonry for the fishing boat docking according to claim 1, characterized in that: The top of the precast square pile (1) passes through the bearing capacity cushion layer (4) and is connected to the concrete foundation (5), and the precast square pile (1) is driven sequentially along the length of the revetment soft foundation (2).

3. The shore protection structure of the shallow soft ground reinforcement by the block masonry for the fishing boat docking according to claim 1, characterized in that: The bearing capacity cushion layer (4) includes a crushed stone cushion layer (41) and a plain concrete cushion layer (42). The width of the crushed stone cushion layer (41) is greater than the width of the plain concrete cushion layer (42), and the bearing capacity cushion layer (4) is laid along the length direction of the revetment soft foundation (2).

4. The shallow soft ground reinforced block masonry revetment structure suitable for fishing boat berthing according to claim 1, characterized in that: The front of the masonry retaining wall (6) is a vertical surface with a concrete wall surface (61) poured on it. The rear of the masonry retaining wall (6) is an inclined surface, and it slopes upward along the side of the concrete breast wall (7) from the bottom end to the top end.

5. The shallow soft ground reinforced block masonry revetment structure suitable for fishing boat berthing according to claim 4, characterized in that: The concrete wall (61) is flush with the concrete breast wall (7), and the rubber fender (8) is fixed on the concrete wall (61) and the concrete breast wall (7) by embedded parts. The rubber fender (8) is provided with several pieces and is distributed at intervals along the length direction of the revetment soft foundation (2).

6. The shallow soft ground reinforced block masonry bulkhead structure suitable for fishing boat berthing according to claim 1, wherein: The drainage component (10) includes a PVC pipe (10-1) and a reverse filter unit (10-2). The PVC pipe (10-1) is embedded in the masonry retaining wall (6) and is inclined downward from the rear to the front of the masonry retaining wall (6). The reverse filter unit (10-2) is embedded in the masonry base layer (9) and is located at the drainage hole of the PVC pipe (10-1).