Complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles

By using technologies such as outward-expanding positioning wing plates, full-rotation drilling rigs, and irregularly shaped steel cages in the construction of interlocking piles in complex underground pipeline areas, the problems of insufficient positioning accuracy and limited installation of steel cages were solved, achieving high-precision hole formation and reliable water stopping, and improving construction safety and efficiency.

CN224982155UActive Publication Date: 2026-11-17ANHUI HIGHWAY ENG CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522727148.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-23
Publication Date
2026-11-17
Estimated Expiration
2035-12-23

AI Technical Summary

Technical Problem

In the secondary closure construction of interlocking piles in complex underground pipeline areas, there are problems such as insufficient positioning accuracy, difficulty in controlling the verticality of the hole, limited installation of steel cages, poor mechanical adaptability, weak water-stopping reliability, and lack of economical pile body alternatives.

Method used

By employing a combination of technologies including a steel cylinder with outward-expanding positioning wing plates, a full-rotation drilling rig, an irregularly shaped steel reinforcement cage, a retractable threaded rod, an ultrasonic testing instrument, and loose material piles, high-precision positioning, stable hole formation, reliable water stopping, and rapid construction are achieved.

Benefits of technology

It improves the drilling and guiding accuracy of interlocking piles, ensures the stable installation of the reinforcing cage, enhances water-stopping performance, has strong adaptability, is suitable for the flexible construction needs of areas with dense underground pipelines, and improves construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982155U_ABST
    Figure CN224982155U_ABST
Patent Text Reader

Abstract

This utility model provides a complex underground pipeline over-and-underpass secondary closure interlocking pile for road-to-bridge conversion, comprising: a steel cylinder with outwardly expanding positioning wing plates placed in a predetermined hole in the guide wall; a bottom pad plate set at the interlocking pile opening in the guide wall, with a full-rotation drilling rig placed on the pad plate; an irregularly shaped steel cage prefabricated into a semi-circular frame by several welded steel bars, the sides of which are supported at the processing platform by sliding grooves; a bracket installed at the reserved hole opening in the guide wall, passing through the steel cage via a pipe crossbeam and located on both sides of the reserved hole opening in the guide wall to form support; a drill barrel, with several plates and teeth assembled circumferentially at the bottom end of the drill barrel; and sand piles, formed by filling loose material into holes drilled by drilling tools at the original concrete pile positions to form sand piles. This utility model has the advantages of simple and convenient construction steps, good quality interlocking piles, good water-stopping effect, convenient template installation and dismantling, short construction period, effectively improving construction efficiency and saving construction costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of pipeline relocation construction, and in particular to the secondary closure interlocking piles for road-to-bridge conversion using the cut-and-cover method for complex underground pipelines. Background Technology

[0002] In urban road-to-bridge conversion projects, especially those located in areas with complex underground pipelines, high traffic loads, and limited space, cut-and-cover construction often requires the installation of interlocking pile retaining systems to ensure safety and stability during excavation and structural construction. However, under multiple constraints such as deep soft soil, dense pipelines in old urban areas, and uninterrupted traffic management, the construction of interlocking piles becomes significantly more difficult, and traditional technologies have several shortcomings in terms of accuracy, adaptability, and controllability. Traditional interlocking pile drilling relies heavily on pre-drilled holes in ordinary guide walls for positioning. However, in areas with complex underground pipelines, guide walls cannot be extensively dismantled or modified, and pre-drilled holes often suffer from misalignment, large dimensional errors, and difficulty in controlling the centerline, leading to challenges in ensuring pile quality. Simultaneously, the limited space for hoisting the reinforcing cage makes conventional methods of lowering the entire reinforcing cage impossible in low-clearance environments, easily resulting in quality risks such as cage deformation and wall entrapment. Traditional reinforced concrete piles lack flexibility and economy in certain areas, failing to meet the demand for lightweight piles without reinforcing cages in non-load-bearing areas, necessitating the exploration of new granular material pile alternatives.

[0003] In summary, existing technologies for secondary closure of interlocking piles in complex underground pipeline areas generally suffer from problems such as insufficient positioning accuracy, difficulty in controlling the verticality of the borehole, limited installation of reinforcing cages, poor mechanical adaptability, weak water-stopping reliability, and a lack of economical alternative pile solutions. Therefore, there is an urgent need for a secondary closure construction system for interlocking piles that can achieve high-precision positioning, highly adaptable borehole formation, and highly reliable water-stopping, in order to improve the overall quality of the retaining structure and construction safety. Utility Model Content

[0004] The purpose of this utility model is to provide a complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles that solves the above-mentioned technical problems.

[0005] To solve the above-mentioned technical problems, this utility model provides a secondary closure interlocking pile for road-to-bridge conversion using a cut-and-cover method for complex underground pipelines, comprising: A steel cylinder with an outwardly expanding positioning wing plate is placed in a predetermined hole in the guide wall. The steel cylinder is fixed to the guide wall, and the outwardly expanding positioning wing plate is used to limit the horizontal and vertical displacement of the steel cylinder. The bottom pad is set at the interlocking pile opening of the guide wall, and the full-rotation drilling rig is placed on the pad. The top of the full-rotation drilling rig is equipped with a guardrail. The full-rotation drilling rig is used to descend along the interlocking pile opening to cut the existing structure. An irregular steel cage is prefabricated into a semi-circular frame by several welded steel bars. The sides of the irregular steel cage are supported at the processing platform by a sliding groove. Jacks arranged on both sides of the irregular steel cage drive the jacking rod to push and form the irregular steel cage. The end of the jacking rod pushes linearly in the sliding groove, so that the irregular steel cage unfolds and forms segment by segment along the guide curve corresponding to the positioning hole. The bracket installed at the reserved opening position of the guide wall passes through the steel cage through the pipe crossbeam and is located on both sides of the reserved opening of the guide wall to form support. The upper and lower sections of the steel cage are connected by reinforcing rings. Ring support bars are arranged on the outside of the reinforcing rings. The spiral hoops and longitudinal main bars together form the main structure of the steel cage. An ultrasonic detector is fixed to a fixed bracket by a limiting block. The bottom of the fixed bracket is equipped with a movable roller and a telescopic threaded rod. The bottom end of the telescopic threaded rod is connected to a fixed support block, and a flap is set on the side of the fixed bracket. The fixed bracket is pushed to the testing area by a handle in conjunction with the movable roller, and the telescopic threaded rod is screwed to make the fixed support block contact the ground. The drill barrel has several teeth mounted around its bottom edge, wear-resistant blocks added to the edges of the teeth, a counterweight plate on the top of the drill barrel, and a suction pipe fixed inside the drill barrel by a fixing rod. Sand piles are formed by drilling holes and filling them with loose materials at the original concrete pile locations. High-pressure jet grouting piles are installed around the sand piles, and grout is injected through the grouting ports to form high-pressure jet grouting piles. This allows the high-pressure jet grouting piles and sand piles to interlock and form a composite load-bearing structure to replace the original concrete piles.

[0006] Furthermore, the outwardly expanding positioning wing plate is manufactured by integral bending and forming, and the outwardly expanding positioning wing plate is circumferentially fixed with the steel cylinder to form an integral frame.

[0007] Furthermore, the bottom pad is made of double-layer steel plate with sand filling, and the top of the full-rotation drilling rig is connected to the guardrail with a detachable structure. A transparent protective plate is installed on the guardrail.

[0008] Furthermore, a drive wheel is installed at the top of the irregularly shaped steel cage, and a follower wheel is arranged at the bottom; after the irregularly shaped steel cage is closed, local reinforcement grouting is performed through the grouting ports set along the circumference of the irregularly shaped steel cage.

[0009] Furthermore, a rubber buffer pad is added to the bottom of the pipe crossarm, and the reinforcing ring and the ring support bar are connected by bolts in a detachable manner.

[0010] Furthermore, the plate teeth adopt a sawtooth-shaped hard alloy structure, and the wear-resistant blocks are replaceable; the inner wall of the suction pipe is coated with a wear-resistant ceramic layer.

[0011] The beneficial effects of this utility model are as follows: 1. This utility model uses a steel cylinder with outwardly expanding positioning wing plates, along with an adjustable positioning screw and a double-nut locking structure, to maintain a stable position of the cylinder during concrete pouring. The integrally bent positioning wing plates effectively limit the horizontal and vertical displacement of the cylinder, ensuring the precise consistency of the center position of the reserved hole and improving the guiding accuracy of the interlocking pile hole formation; 2. This utility model achieves precise unfolding of the reinforcing cage along the guide curve through a combination of a drive wheel, a follower wheel, and an arc-shaped limiting track. The rolling contact structure between the push rod and the slide reduces frictional resistance, making the reinforcing cage forming process stable and dimensionally controllable. The grouting locking structure enhances the shape retention capability of the reinforcing cage, overcoming the limitations of low efficiency and poor precision in traditional manual unfolding of reinforcing cages; 3. This utility model effectively reduces lifting impact by installing rubber buffer pads on the crossbeams at the pipe openings; the detachable connection between the reinforcing rings and the supporting bars allows for rapid center alignment of the segmented rebar cage, ensuring geometric stability in the opening area. This technology significantly improves the problems of difficult installation and easy tilting of rebar cages in traditional low-clearance areas. 4. This utility model replaces concrete piles with granular material piles, enhances water-stopping performance through external jet grouting piles, and utilizes grouting ports to achieve full diffusion of grout, forming a composite load-bearing pile structure. Compared with traditional concrete piles, this system offers faster construction speed, less ground disturbance, better water-stopping performance, and is suitable for flexible construction needs in areas with dense underground pipelines. Attached Figure Description

[0012] Figure 1 This is a schematic diagram showing the precise positioning of the reserved holes in the concrete guide wall.

[0013] Figure 2 This is a schematic diagram illustrating the processing principle of irregularly shaped stirrups.

[0014] Figure 3 This is a layout diagram of an irregularly shaped steel reinforcement cage.

[0015] Figure 4 This is a schematic diagram of a low-headroom support frame for the segmented installation of the reinforcing cage.

[0016] Figure 5 This is a schematic diagram of an ultrasonic mobile platform.

[0017] Figure 6 This is a schematic diagram of the modification of the drilling tools for a reverse circulation drilling rig.

[0018] Figure 7 This is a schematic diagram of a full-rotation drilling rig.

[0019] Figure 8 This is a schematic diagram of a loose material pile replacing a reinforced concrete pile.

[0020] In the diagram: 1-Guide wall; 2-Single-layer bidirectional reinforcement; 3-Connecting bolt; 4-Adjustable positioning screw; 5-Steel cylinder; 6-Outwardly expanding positioning wing plate; 7-Slide groove; 8-Jack; 9-Push rod; 10-Positioning hole; 11-Drive wheel; 12-Follower wheel; 13-Irregularly shaped reinforcement cage; 14-Grouting port; 15-Welded reinforcement; 16-Spiral stirrup; 17-Longitudinal main reinforcement; 18-Reinforcing ring stirrup; 19-Ring stirrup support reinforcement; 20-Pipe crossbeam; 21- 21-Extendable threaded rod; 22-Fixed support block; 23-Moving roller; 24-Limit block; 25-Ultrasonic detector; 26-Handle; 27-Fixed bracket; 28-Flip plate; 29-Wear-resistant block; 30-Plate teeth; 31-Drill barrel; 32-Counterweight plate; 33-Suction pipe; 34-Fixed rod; 35-Interlocking pile mouth; 36-Bottom pad; 37-Full-rotation drilling rig; 38-Guardrail; 39-Concrete pile; 40-Sand pile; 41-High-pressure jet grouting pile. Detailed Implementation

[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model are within the protection scope of the present utility model.

[0022] Those skilled in the art should understand that, in the disclosure of this utility model, the terms "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, the above terms should not be construed as limitations on this utility model.

[0023] It is understood that the term "a" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element can be one, while in another embodiment, the number of the element can be multiple, and the term "a" should not be understood as a limitation on the number.

[0024] like Figures 1-8 As described above, this utility model provides a secondary closure interlocking pile for road-to-bridge conversion using a cut-and-cover method for complex underground pipelines, such as... Figure 1As shown, after the reinforcement of guide wall 1 is tied, the steel cylinder 5 with the outwardly expanding positioning wing plate 6 is placed in the predetermined hole position. The spacing between two adjacent steel cylinders 5 is adjusted by the adjustable positioning screw 4, and the outwardly expanding positioning wing plate 6 is connected to guide wall 1 by connecting bolts 3, thereby firmly fixing the steel cylinder 5 to guide wall 1 and maintaining a stable position of the steel cylinder 5 during concrete pouring. The outwardly expanding positioning wing plate 6 is used to limit the horizontal and vertical displacement of the steel cylinder 5, ensuring that the center position of the reserved hole is accurately consistent, and realizing the precise guidance of the interlocking pile drilling equipment.

[0025] The adjustable positioning screw 4 includes two screws with threaded connections at their ends, and the screw ends are rotatably connected to the steel cylinder 5. By rotating the screw, the total length of the two adjacent screws is changed to adjust the distance between the two adjacent steel cylinders 5.

[0026] The positioning wing plate 6 on the outer side of the steel cylinder 5 is made by integral bending and forming. The positioning wing plate 6 is welded to the steel cylinder 5 in a circumferential manner to form an integral frame, which can improve the steel cylinder 5's resistance to lateral deformation during concrete pouring. The adjustable positioning screw 4 adopts a double nut locking structure and cooperates with the steel cylinder 5 to keep the steel cylinder 5 in a stable position during vibration and improve the positioning accuracy of the reserved hole.

[0027] like Figure 2 , Figure 3 As shown, the reinforcing cage frame is prefabricated into a semi-circular frame by several welded reinforcing bars 15 according to the design shape. It is supported on the processing platform by a slide groove 7. The forming of the irregular reinforcing cage 13 is achieved by jacks 8 arranged on both sides driving push rods 9. The ends of the push rods 8 push linearly in the slide groove 7, so that the irregular reinforcing cage 13 unfolds and forms segment by segment along the guide curve corresponding to the positioning hole 10. The irregular reinforcing cage 13 is equipped with a drive wheel 11 at the top and a follower wheel 12 at the bottom. The drive wheel 11 provides traction force and the follower wheel 12 provides guiding support, so that the irregular reinforcing cage 13 is stable in posture and uniform in deformation during the forming process. After the irregular reinforcing cage 13 is closed, local reinforcement grouting is performed through the grouting port 14 arranged around the circumference of the irregular reinforcing cage 13 to lock the frame in shape.

[0028] The drive wheels 11 and follower wheels 12 arranged at both ends of the irregular steel cage 13 are rolled on the arc-shaped limiting track, which can limit the radial displacement of the irregular steel cage 13 during the unfolding and forming process; a rolling contact structure is set between the end of the push rod 9 and the slide groove 7 to reduce frictional resistance, making the unfolding process of the irregular steel cage 13 more stable and the forming accuracy higher.

[0029] like Figure 4As shown, the support is installed at the reserved opening position of the guide wall 1. A crossbeam 20 passes through the reinforcing cage and forms a stable support on both sides of the reserved opening in the guide wall 1, allowing for smooth docking and vertical positioning of the reinforcing cage under low clearance conditions during segmented hoisting. The upper and lower sections of the reinforcing cage are connected by reinforcing hoops 18. Hoop support bars 19 are arranged on the outside of the reinforcing hoops 18 to maintain the geometric stability of the reinforcing cage when crossing the opening and prevent skewing or tilting during hoisting. The spiral stirrups 16 and the longitudinal main bars 17 together form the main structure of the reinforcing cage. When passing through the opening, the crossbeam 20 provides local support, allowing the reinforcing cage to be introduced into the opening segment by segment while maintaining coaxiality.

[0030] A rubber buffer pad is added to the bottom of the pipe crossarm 20 to reduce the impact when the steel cage is hoisted and contacted; the reinforcing hoop 18 and the hoop support bar 19 are connected by bolts in a detachable manner, which facilitates the rapid docking and centering of the segmented steel cage and improves the adaptability under low headroom construction conditions.

[0031] like Figure 5 As shown, the ultrasonic testing instrument 25 is fixed to the fixed bracket 27 by a limiting block 24. The bottom of the fixed bracket 27 is equipped with a movable roller 23 and a telescopic threaded rod 21. The bottom end of the threaded rod 21 is connected to a fixed support block 22, and a flap 28 is provided on the side of the fixed bracket 27. The fixed bracket 27 is pushed to the testing area by the handle 26 in conjunction with the movable roller 23. The telescopic threaded rod 21 is turned to make the fixed support block 22 contact the ground, and the roller is locked to achieve stable positioning of the platform. The verticality of the interlocking pile is precisely controlled by the ultrasonic testing instrument 25.

[0032] like Figure 6 As shown, several toothed plates 30 are circumferentially assembled at the bottom of the drill barrel 31, and wear-resistant blocks 29 are added to the edges of the toothed plates 30 to improve durability. A counterweight plate 32 is set on the top of the drill barrel 31 to enhance drilling stability. The slurry suction pipe 33 is fixed inside the drill barrel 31 by a fixing rod 34. During operation, the toothed plates 30 work with the wear-resistant blocks 29 to cut the formation, while the slurry suction pipe 33 simultaneously sucks up the drill cuttings slurry, achieving efficient drilling and cuttings removal, which is suitable for complex geological conditions.

[0033] The plate teeth 30 adopt a sawtooth-shaped hard alloy structure, and the wear-resistant block 29 adopts a replaceable modular design, such as connecting the wear-resistant block 29 and the plate teeth 30 by bolts; the inner wall of the slurry suction pipe 33 is coated with a wear-resistant ceramic layer to reduce long-term slurry transport wear and improve drilling and slag removal capacity; drilling is controlled by external drilling rigs and gear transmission.

[0034] like Figure 7As shown, a bottom pad 36 is installed at the interlocking pile opening 35 of the guide wall 1, and a full-rotation drilling rig 37 is placed on the pad 36. A guardrail 38 is installed on the top of the full-rotation drilling rig 37. The full-rotation drilling rig 37 descends along the interlocking pile opening 35 and uses the rotary cutting force to cut the existing structure to realize the interlocking pile hole formation operation. The guardrail 38 ensures construction safety.

[0035] The working area of ​​the full-rotation drilling rig 37 has a double-layer steel plate with sand-filled bottom pad 36 to absorb drilling rig vibration; the protective railing 38 installed on the top of the drilling rig has a detachable structure and a transparent protective plate is installed on the enclosure.

[0036] like Figure 8 As shown, at the original location of concrete pile 39, a hole is drilled and filled with loose material to form a sand pile 40. High-pressure jet grouting piles 41 are constructed around the sand piles 40 to improve the water-stopping effect. Grout is injected into the high-pressure jet grouting piles 41 through the grouting port 14, so that the high-pressure jet grouting piles 41 and the sand piles 40 interlock to form a composite load-bearing structure to replace the original concrete pile 39. During construction, the drill bucket 31 is used to simultaneously remove slag, and the grouting port 14 ensures that the grout is full, ultimately forming a stable pile force system.

[0037] This utility model is not limited to the above-described preferred embodiments. Anyone can derive other forms of products under the guidance of this utility model. However, regardless of any changes made in their shape or structure, any technical solution that is the same as or similar to this application falls within the protection scope of this utility model.

Claims

1. A complex underground pipeline cover-excavation road-reconstruction bridge secondary closure engagement pile, characterized in that, include: A steel cylinder (5) is placed in a predetermined hole in the guide wall (1) and has an outwardly expanding positioning wing plate (6). The steel cylinder (5) is fixed on the guide wall (1). The outwardly expanding positioning wing plate (6) is used to limit the horizontal and vertical displacement of the steel cylinder (5). A bottom pad (36) is set at the interlocking pile opening (35) of the guide wall (1), and a full-rotation drilling rig (37) is placed on the pad (36). A guardrail (38) is set on the top of the full-rotation drilling rig (37). The full-rotation drilling rig (37) is used to descend along the interlocking pile opening (35) to cut the existing structure. A semi-circular frame of a non-circular steel cage (13) is prefabricated from several welded steel bars (15). The non-circular steel cage (13) is supported on the processing platform by a sliding groove (7). Jacks (8) arranged on both sides of the non-circular steel cage (13) drive push rods (9) to push and form the non-circular steel cage (13). The end of the push rod (9) pushes linearly in the sliding groove (7), so that the non-circular steel cage (13) unfolds and forms segment by segment along the guide curve corresponding to the positioning hole (10). The bracket installed at the reserved opening position of the guide wall (1) passes through the steel cage through the pipe crossbeam (20) and is located on both sides of the reserved opening of the guide wall (1) to form a support. The upper and lower sections of the steel cage are connected by a reinforcing hoop (18). The hoop support bar (19) is arranged on the outside of the reinforcing hoop (18). The spiral hoop bar (16) and the longitudinal main bar (17) together form the main structure of the steel cage. An ultrasonic detector (25) is fixed to a fixed bracket (27) by a limiting block (24). The bottom of the fixed bracket (27) is equipped with a movable roller (23) and a telescopic threaded rod (21). The bottom end of the telescopic threaded rod (21) is connected to a fixed support block (22). At the same time, a flap (28) is set on the side of the fixed bracket (27). The fixed bracket (27) is pushed to the detection area by the handle (26) in conjunction with the movable roller (23). The telescopic threaded rod (21) is screwed to make the fixed support block (22) contact the ground. A drill barrel (31) is provided with several toothed plates (30) circumferentially mounted at the bottom end of the drill barrel (31). Wear-resistant blocks (29) are added to the edges of the toothed plates (30). A counterweight plate (32) is provided at the top of the drill barrel (31). A suction pipe (33) is fixed inside the drill barrel (31) by a fixing rod (34). Sand piles (40) are formed by drilling holes and filling them with loose materials at the original concrete pile (39) locations. High-pressure jet grouting piles (41) are installed around the sand piles (40) and grout is injected through the grouting port (14) to form high-pressure jet grouting piles (41), so that the high-pressure jet grouting piles (41) and sand piles (40) interlock to form a composite bearing structure to replace the original concrete piles (39).

2. The complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles as described in claim 1, characterized in that: The outwardly expanding positioning wing plate (6) is made by integral bending and forming, and the outwardly expanding positioning wing plate (6) and the steel cylinder (5) are circumferentially fixed to form an integral frame.

3. The complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles as described in claim 1, characterized in that: The bottom pad (36) is made of double-layer steel plate with sand filling structure. The top of the full-rotation drilling rig (37) and the guardrail (38) are made of detachable structure. A transparent protective plate is installed on the guardrail (38).

4. The complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles as described in claim 1, characterized in that: The top of the irregular steel cage (13) is equipped with a drive wheel (11) and the bottom is equipped with a follower wheel (12). After the irregular steel cage (13) is closed, local reinforcement grouting is carried out through the grouting port (14) set along the circumference of the irregular steel cage (13).

5. The complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles as described in claim 1, characterized in that: A rubber buffer pad is added to the bottom of the pipe crossarm (20), and the reinforcing ring (18) and the ring support bar (19) are connected by bolts in a detachable manner.

6. The complex underground pipeline cut-and-cover method for road-to-bridge secondary closure interlocking piles according to claim 1, characterized in that: The plate teeth (30) adopt a sawtooth-shaped hard alloy structure, and the wear-resistant block (29) is replaceable; the inner wall of the suction pipe (33) is coated with a wear-resistant ceramic layer.