A prefabricated cover plate structure
The strength of the precast cover plate structure is enhanced by using an angle steel base frame and a steel reinforcement skeleton. The design of a hidden lifting ring assembly and sealing ring solves the problems of easy cracking and protruding lifting rings in traditional precast cover plates, achieving a cover plate structure with high strength, flatness and convenient operation.
Patent Information
- Application Number
- CN202522289280.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-29
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-10-29
AI Technical Summary
Traditional precast cover plates have low structural strength, are prone to cracking, and have protruding lifting rings that affect flatness and are easily damaged, posing safety hazards and making them inconvenient to open and move.
The structure is reinforced with an angle steel base frame and a steel reinforcement skeleton. The lifting ring assembly is designed to be concealed and combined with a sealing ring to prevent dust, ensuring the flatness and sealing of the cover plate.
It improves the load-bearing capacity and service life of the cover plate, avoids safety hazards caused by protruding lifting rings, ensures the flatness and sealing of the cover plate, and facilitates opening and installation.
Smart Images

Figure CN224982242U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the technical field of building engineering, and in particular to a prefabricated cover plate structure. Background Technology
[0002] Building construction projects, such as residential and public buildings, typically include substations, neighborhood substations, and outdoor cable wells. These cable wells require covers for protection, load-bearing capacity, and ease of access. However, traditional precast cable covers present the following problems in practical applications: On the one hand, traditional precast cover slabs are mostly made by casting concrete using simple molds and embedding a small amount of steel reinforcement. Such structures have low strength and are prone to cracking and deformation after bearing large loads for a long time, which seriously affects their service life and safety. They may even cause safety accidents due to structural fractures, increasing the cost of later maintenance. On the other hand, the lifting rings of traditional precast cover slabs are mostly fixed protruding structures, which not only damage the flatness of the top surface of the cover slab, causing pedestrians to trip and fall, but also easily cause damage to the lifting rings due to collisions and friction, affecting the normal opening and handling of the cover slab. Therefore, it is necessary to provide a precast cover slab structure to solve the above technical problems. Utility Model Content
[0003] To solve the above-mentioned technical problems, this utility model provides a prefabricated cover plate structure.
[0004] This utility model provides a precast cover plate structure, including an angle steel base frame and a concrete cover plate body. A steel reinforcement skeleton is provided on the inner side of the concrete cover plate body. The steel reinforcement skeleton is located inside the concrete cover plate body. Two symmetrically arranged receiving grooves are opened on the top of the concrete cover plate body. Two through pipes are symmetrically arranged on the inner side of the receiving grooves. The through pipes penetrate the concrete cover plate body. Each receiving groove is provided with a lifting ring assembly.
[0005] Preferably, the angle steel base frame includes long angle steel and short angle steel, and two of each type are symmetrically arranged. One of the short angle steels is fixedly connected to one end of the two long angle steels, and the other short angle steel is fixedly connected to the other end of the two long angle steels.
[0006] Preferably, the lifting ring assembly includes a lifting ring crossbar, and two vertically arranged lifting ring vertical bars are provided at both ends of the lifting ring crossbar. The lifting ring crossbar and the lifting ring vertical bars are integrally formed. The lifting ring vertical bars are arranged in a one-to-one correspondence with the through pipe. The outer diameter of the lifting ring vertical bar is smaller than the inner diameter of the through pipe. After passing through the through pipe and extending downward, the lifting ring vertical bar is provided with a threaded part, and a nut is threaded onto the threaded part.
[0007] Preferably, a fixing ring is fixedly sleeved on the upper part of the lifting ring vertical rod, and a sealing gasket is fixedly connected to the bottom of the fixing ring, the sealing gasket being in contact with the inner bottom of the receiving groove.
[0008] Preferably, the bottom of the long angle steel and the short angle steel are provided with a square groove, and a square sealing ring is fixedly connected in the square groove.
[0009] Preferably, the main body of the concrete cover plate is cast using C30 fine aggregate concrete.
[0010] Preferably, the height of the long angle steel and the short angle steel is 150-170mm, and the height of the concrete cover plate body is equal to the height of the long angle steel and the short angle steel.
[0011] Compared with related technologies, the prefabricated cover plate structure provided by this utility model has the following beneficial effects: 1. In this utility model, the angle steel base frame is composed of long angle steel and short angle steel fixedly connected to form a stable basic frame structure, providing solid foundation support and outer flatness for the entire precast cover plate. The concrete cover plate body is cast and formed using C30 fine stone concrete, and a steel reinforcement skeleton is set inside. C30 fine stone concrete has high strength, and together with the steel reinforcement skeleton, it can effectively enhance the overall load-bearing capacity of the cover plate and meet the load-bearing requirements of the cover plate in construction projects.
[0012] 2. When the lifting ring assembly is not pulled up, the lifting ring crossbar is located in the receiving groove, ensuring the flatness of the top surface of the concrete cover plate and avoiding the impact of the overall flatness of the cover plate on the protrusion of the lifting ring assembly. The lifting ring assembly provides convenience for the opening and installation of the cover plate. The lifting ring vertical bar passes through the through pipe and is fixed by the threaded part and nut, which makes installation and disassembly convenient. When it is necessary to open the cover plate, pull up the lifting ring crossbar, and the nut provides support at the bottom, so that the precast cover plate structure can be lifted, making it convenient for operators to open the precast cover plate structure.
[0013] 3. Square sealing rings are fixedly connected in the square grooves at the bottom of the long and short angle steel, which enhances the sealing performance of the prefabricated cover plate structure after it is placed on the installation base and can effectively prevent dust and other impurities from entering the cable well.
[0014] 4. In this utility model, the square sealing ring not only enhances the sealing performance, but also buffers the contact pressure between the long angle steel and the short angle steel and the mounting base, reducing the structural damage to the precast cover plate structure caused by hard impacts and extending the service life of the precast cover plate structure.
[0015] 5. A sealing gasket is connected to the bottom of the fixing ring at the top of the lifting ring vertical rod. The sealing gasket fits against the bottom of the inner side of the receiving groove, sealing the top of the pipe and further preventing impurities from entering the cable well below through the pipe. Attached Figure Description
[0016] Figure 1 A schematic diagram of the overall structure of the prefabricated cover plate structure provided by this utility model; Figure 2 This is a partial sectional view of the present invention; Figure 3 This is a partial sectional view of the present invention; Figure 4 This is a schematic diagram of the structure of the lifting ring assembly in this utility model; Figure 5 This is a schematic diagram of the structure of the lifting ring crossbar in this utility model.
[0017] The following are the labels in the diagram: 1. Angle steel base frame; 101. Long angle steel; 102. Short angle steel; 2. Reinforcing steel skeleton; 3. Concrete cover plate body; 4. Pipe through; 5. Receiving groove; 6. Lifting ring assembly; 601. Lifting ring crossbar; 602. Lifting ring vertical bar; 603. Threaded part; 604. Nut; 7. Square sealing ring; 8. Fixing ring; 9. Sealing gasket. Detailed Implementation
[0018] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0019] Example 1: Please refer to the following: Figures 1 to 4 A precast cover plate structure includes an angle steel base frame 1 and a concrete cover plate body 3. A steel reinforcement skeleton 2 is provided on the inner side of the concrete cover plate body 3. The steel reinforcement skeleton 2 is composed of multiple HRB400 grade hot-rolled ribbed steel bars. In terms of arrangement, the transverse steel bars and longitudinal steel bars are interwoven perpendicularly to form a mesh structure. The steel bars are connected by welding to form a solid whole, which greatly enhances the restraint effect of the steel reinforcement skeleton 2 on the concrete cover plate body, thereby improving the crack resistance and durability of the entire concrete cover plate body 3 structure. The steel reinforcement skeleton 2 is set inside the concrete cover plate body 3. Two symmetrically arranged receiving grooves 5 are opened on the top of the concrete cover plate body 3. Two through pipes 4 are symmetrically arranged on the inner side of the receiving grooves 5. The through pipes 4 are made of PVC pipes and penetrate the concrete cover plate body 3. Each receiving groove 5 is provided with a lifting ring assembly 6.
[0020] The angle steel base frame 1 includes long angle steel 101 and short angle steel 102. Two long angle steel 101 and two short angle steel 102 are symmetrically arranged. One short angle steel 102 is fixedly connected to one end of the two long angle steel 101, and the other short angle steel 102 is fixedly connected to the other end of the two long angle steel 101.
[0021] In the above, the angle steel base frame 1 is fixedly connected by two long angle steels 101 and two short angle steels 102 to form a rectangular stable frame structure. This frame design not only provides solid boundary support for the entire precast cover plate structure and ensures the straightness of the edges of the precast cover plate structure, but also acts as a template during the pouring of the concrete cover plate body 3, ensuring the dimensional accuracy of the concrete cover plate body 3, and enhancing the overall deformation resistance of the precast cover plate structure.
[0022] Furthermore, the bottoms of the long angle steel 101 and the short angle steel 102 are both provided with a square groove, and a square sealing ring 7 is fixedly connected in the square groove. The square sealing ring 7 is a rubber sealing ring and protrudes to the bottom of the square groove.
[0023] In the above, the square sealing ring 7 is installed in the square groove at the bottom of the long angle steel 101 and the short angle steel 102. When the prefabricated cover plate structure is placed on the mounting base surface of the cable well, the square sealing ring 7 will be squeezed and deformed, thus tightly fitting the mounting base surface and effectively blocking dust and other impurities from entering the cable well below. In addition, the rubber square sealing ring 7 can also reduce the hard friction and collision between the angle steel base frame 1 and the mounting base surface during the placement and use of the prefabricated cover plate structure, playing a buffer protection role and extending the service life of the prefabricated cover plate structure.
[0024] Furthermore, the main body of the concrete cover plate 3 is cast using C30 fine aggregate concrete.
[0025] In the above, the concrete cover plate body 3 is cast using C30 fine stone concrete. C30 grade concrete has high compressive strength, while the aggregate particle size of fine stone concrete is small, which makes the concrete casting more compact, reduces internal pores, improves the overall quality and durability of the concrete cover plate body 3, and also helps to better integrate with the internal steel reinforcement skeleton 2, jointly improving the structural strength of the precast cover plate structure.
[0026] Furthermore, the height of the long angle steel 101 and the short angle steel 102 is 150-170mm, and the height of the concrete cover plate body 3 is equal to the height of the long angle steel 101 and the short angle steel 102.
[0027] In the above, the height of the long angle steel 101 and the short angle steel 102 is set at 150-170mm, and the height of the concrete cover plate body 3 is consistent with it. This size design ensures that the cover plate has sufficient thickness to meet the load-bearing requirements, and also enables the angle steel base frame 1 and the concrete cover plate body 3 to form an integral load-bearing structure, avoiding stress concentration caused by the inconsistency in height between the two, which would affect the overall stability of the cover plate.
[0028] Example 2: For further details, please refer to [link / reference]. Figures 1 to 5Based on Embodiment 1, the lifting ring assembly 6 includes a lifting ring crossbar 601. Two vertically arranged lifting ring vertical bars 602 are provided at both ends of the lifting ring crossbar 601. The lifting ring crossbar 601 and the lifting ring vertical bars 602 are integrally formed. The lifting ring vertical bars 602 are arranged one-to-one with the through pipe 4. The outer diameter of the lifting ring vertical bar 602 is smaller than the inner diameter of the through pipe 4. After the lifting ring vertical bar 602 passes through the through pipe 4 and extends downward, it is provided with a threaded part 603. A nut 604 is threaded onto the threaded part 603.
[0029] In the above description, the structural design of the lifting ring assembly 6 makes it easy to install and disassemble. The cooperation between the lifting ring vertical rod 602 and the through pipe 4 ensures that the lifting ring assembly 6 is accurately positioned on the cover plate. The outer diameter of the lifting ring vertical rod 602 is smaller than the inner diameter of the through pipe 4, which facilitates installation and operation. The threaded part 603 and the nut 604 can firmly fix the lifting ring assembly 6 to the concrete cover plate body 3. When it is necessary to open the cover plate, the precast cover plate structure can be easily lifted by pulling the lifting ring horizontal rod 601 upward, which provides convenience for the opening and transportation of the precast cover plate structure.
[0030] Furthermore, a fixing ring 8 is fixedly sleeved on the upper part of the lifting ring vertical rod 602, and a sealing gasket 9 is fixedly connected to the bottom of the fixing ring 8. The sealing gasket 9 is a rubber sealing gasket, and the sealing gasket 9 fits against the inner bottom of the receiving groove 5.
[0031] In the above, the fixing ring 8 and sealing gasket 9 at the upper part of the lifting ring vertical rod 602 play a good sealing role. The sealing gasket 9 fits against the bottom of the inner side of the receiving groove 5, which can effectively prevent dust and other impurities from entering the cable well below through the conduit 4. At the same time, the fixing ring 8 can also play a certain role in limiting the position of the lifting ring vertical rod 602 in the conduit 4.
[0032] The working principle of the prefabricated cover plate structure provided by this utility model is as follows: When manufacturing the precast cover plate structure of this utility model, a thin film is laid on a flat, hardened site. Then, according to the length, width, and height required for the precast cover plate manufacturing, two long angle steels 101 and two short angle steels 102 of matching size are selected. The long angle steels 101 and two short angle steels 102 are welded and fixed in sequence to obtain the angle steel base frame 1. Square sealing rings 7 are fixed in the square grooves at the bottom of the long angle steels 101 and two short angle steels 102. This not only enhances the sealing performance of the precast cover plate structure after it is placed on the installation base, but also buffers the contact pressure between the precast cover plate structure and the installation base, avoiding structural damage caused by hard collisions. The steel reinforcement cage 2 is tied according to the steel reinforcement configuration. After the steel reinforcement cage 2 is tied, concrete is poured. C30 fine stone concrete is used for pouring. Before initial setting, the ø20 PVC pipe 4 is inserted into the concrete cover plate body 3. At the same time, a receiving groove 5 is pressed out at the lifting ring position so that the depth of the receiving groove 5 is 20mm, ensuring that the lifting ring crossbar 601 of the lifting ring assembly 6 is lower than the top surface of the concrete cover plate body 3. After the C30 fine aggregate concrete has solidified, the concrete cover plate body 3 is formed. After the curing strength of the concrete cover plate body 3 is reached, the lifting ring assembly 6 is installed. The upper part of the lifting ring vertical rod 602 is fixedly connected to the fixing ring 8, and the bottom of the fixing ring 8 is fixedly connected to the sealing gasket 9. The two lifting ring vertical rods 602 of the lifting ring assembly 6 are passed through the through pipe 4, and then the nuts 604 are used to connect and fix them to the threaded part 603. The nuts 604 are kept 30-70mm away from the bottom of the concrete cover plate body 3 so that there is room for movement when the lifting ring vertical rods 602 are pulled up.
[0033] The installation of the lifting rings and the cleaning of the laitance around the angle steel base frame 1 are carried out before the installation of the precast cover plate structure can proceed.
[0034] When the lifting ring assembly 6 is not pulled up, the lifting ring crossbar 601 is located in the receiving groove 5, ensuring that the top surface of the concrete cover plate body 3 is flat. Under the action of its own weight, the lifting ring assembly 6 causes the fixing ring 8 to drive the sealing gasket 9 to press tightly against the bottom of the inner side of the receiving groove 5, sealing the top of the pipe 4 and preventing debris from entering the cable well below through the pipe 4.
[0035] The above description is merely an embodiment of this utility model and does not limit the patent scope of this utility model. Any equivalent structural or procedural transformations made based on the content of this utility model specification and drawings, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of this utility model.
Claims
1. A preformed cover sheet structure, characterized by The system includes an angle steel base frame (1) and a concrete cover plate body (3). A steel reinforcement skeleton (2) is provided on the inner side of the concrete cover plate body (3). The steel reinforcement skeleton (2) is located inside the concrete cover plate body (3). Two symmetrically arranged receiving grooves (5) are opened on the top of the concrete cover plate body (3). Two through pipes (4) are symmetrically arranged on the inner side of the receiving grooves (5). The through pipes (4) penetrate the concrete cover plate body (3). A lifting ring assembly (6) is provided in each of the receiving grooves (5).
2. A preformed cover sheet structure according to claim 1, wherein, The angle steel base frame (1) includes long angle steel (101) and short angle steel (102). Two long angle steels (101) and two short angle steels (102) are symmetrically arranged. One of the short angle steels (102) is fixedly connected to one end of the two long angle steels (101), and the other short angle steel (102) is fixedly connected to the other end of the two long angle steels (101).
3. A preformed cover sheet structure according to claim 1, wherein, The lifting ring assembly (6) includes a lifting ring crossbar (601), and two vertically arranged lifting ring vertical bars (602) are provided at both ends of the lifting ring crossbar (601). The lifting ring crossbar (601) and the lifting ring vertical bars (602) are integrally set. The lifting ring vertical bars (602) are arranged one-to-one with the through pipe (4). The outer diameter of the lifting ring vertical bar (602) is smaller than the inner diameter of the through pipe (4). The lifting ring vertical bar (602) passes through the through pipe (4) and extends downwards, and is provided with a threaded part (603). A nut (604) is threaded onto the threaded part (603).
4. A preformed cover sheet structure according to claim 3, wherein, The upper part of the lifting ring vertical rod (602) is fixedly fitted with a fixing ring (8), and a sealing gasket (9) is fixedly connected to the bottom of the fixing ring (8). The sealing gasket (9) fits against the inner bottom of the receiving groove (5).
5. A preformed cover sheet structure according to claim 2, wherein, The bottom of the long angle steel (101) and the short angle steel (102) are provided with a square groove, and a square sealing ring (7) is fixedly connected in the square groove.
6. A preformed cover sheet structure according to claim 1, wherein, The main body of the concrete cover plate (3) is formed by casting C30 fine stone concrete.
7. A preformed cover sheet structure according to claim 2, wherein, The height of the long angle steel (101) and the short angle steel (102) is 150-170mm, and the height of the concrete cover plate body (3) is equal to the height of the long angle steel (101) and the short angle steel (102).