Transportation planning creation system and method
Patent Information
- Application Number
- JP2023010836
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-01-27
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2043-01-27
AI Technical Summary
Existing transportation plans for electric vehicles are challenged by unplanned events, such as increased electricity consumption due to higher temperatures, leading to potential battery depletion and resulting in delivery delays, increased operating times, and unequal working hours for drivers, thereby increasing logistics costs.
A transportation plan creation system that recreates plans by combining transportation and charging strategies to ensure electric vehicles do not run out of power, minimizing delivery delays, operating time increases, and deviations in operating hours, using a plan creation unit to evaluate and select optimal combinations based on remaining battery levels and delivery schedules.
The system effectively suppresses logistics costs by creating new transportation plans that maintain delivery schedules, reduce operating time, and equalize driver working hours, thus optimizing operations for electric vehicle fleets.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a transportation plan creation system and method, and is suitably applied to a transportation plan creation device that creates a transportation plan in a transportation business for transporting luggage by electric vehicles, for example. [Background technology]
[0002] In recent years, the electrification of private cars has been progressing, and in the transportation sector, the electrification of transportation vehicles has also been progressing.
[0003] In order to prevent a vehicle moving between points from running out of battery, there is a technique for determining whether to charge, replace, or neither charge nor replace the battery mounted on the vehicle at the first point based on the current time and a predetermined time when the vehicle moves from a first point to a second point, which is the next destination, by a predetermined time. For example, there is a technique described in Patent Document 1. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] Patent Publication No. 2022-59985 Summary of the Invention [Problem to be solved by the invention]
[0005] Let's consider the case where an electric vehicle is used as a transport vehicle in a transport business. In transport business, cargo is usually transported according to a transport plan drawn up on a weekly or daily basis. However, in transport business, unplanned events that are not included in the transport plan can occur, such as when an order (transport request) to transport additional cargo is received on the same day, and a trip to a third location that was not previously scheduled must be made to collect the cargo before moving from the first location to the second location, or when the temperature becomes higher than expected, resulting in more power consumption than expected for cooling the inside of the vehicle.
[0006] When such an unplanned event occurs, if the event involves a customer, driver, or transport vehicle, and especially if the driver is unable to handle the event alone, the driver can contact the transport operations staff of the event, who can then manually modify the transport plan for all or part of the transport operation, including the transport plans for other transport vehicles, and communicate the modified transport plan to the drivers of each corresponding transport vehicle.
[0007] However, when changing the transportation plan for all or part of the transportation work as described above, it is necessary to keep in mind that the driving range of electric vehicles is short, and if the transportation plan is changed carelessly, the transportation vehicle may run out of power, resulting in a state where the remaining charge of the transportation vehicle is zero. Furthermore, if the transportation vehicle runs out of power, there may be a problem of increased logistics costs in order to deal with the transportation vehicle itself that has run out of power and the cargo that was scheduled to be transported.
[0008] In addition, for example, when changing a transportation plan, it is necessary to suppress delays in delivery and also to prevent an increase in the operating hours of transportation vehicles. This is because if a delivery date is delayed, redelivery may be necessary in some cases, which may increase logistics costs, and if the operating hours of transportation vehicles increase, driver overtime costs may be incurred, which may increase logistics costs.
[0009] In addition, for example, when changing a transportation plan, from the viewpoint of the operation of the transport company's drivers, it is desirable to suppress an increase in the deviation in the operation time of each transport vehicle. This is because an increase in the deviation in the operation time of the transport vehicles leads to inequality in the working hours of the drivers, which may result in longer working hours for any of the drivers, leading to a deterioration in the working environment and an increase in logistics costs.
[0010] Therefore, we propose a transportation plan creation system and method that can create a new transportation plan that suppresses increases in logistics costs regarding the transportation of goods by electric vehicles. [Means for solving the problem]
[0011] In order to solve such problems, in the present invention, a transportation plan creation system that recreates a previously created transportation plan for luggage using transport vehicles consisting of electric vehicles is provided with a plan creation unit that creates multiple combinations of luggage transportation plans and transport vehicle charging plans that transport the luggage to be transported and do not cause any of the transport vehicles to run out of power, based on the original transportation plan and the current remaining charge of each of the transport vehicles, and a plan evaluation unit that evaluates at least the delivery date delay of the luggage for each of the created combinations of the transportation plan and the charging plan, and selects the combination of the transportation plan and the charging plan based on the evaluation results.
[0012] In addition, in the present invention, a transportation plan creation method is executed in a transportation plan creation system having a transportation plan creation device that recreates a previously created transportation plan for luggage using transport vehicles consisting of electric vehicles, and includes a first step of creating a plurality of combinations of transportation plans for the luggage and charging plans for the transport vehicles that transport the luggage to be transported and do not cause any of the transport vehicles to run out of power, based on the original transportation plan and the current remaining charge of each of the transport vehicles, and a second step of evaluating at least the delivery delay of the luggage for each of the created combinations of the transportation plan and the charging plan, and selecting the combination of the transportation plan and the charging plan based on the evaluation results.
[0013] According to the transportation plan creation system and method of the present invention, it is possible to select an optimal combination of transportation plan proposals and charging plan proposals that suppresses delays in delivery of goods, increases in operating hours of transport vehicles, and deviations in operating hours as a new transportation plan. Effect of the Invention
[0014] According to the present invention, it is possible to realize a transportation plan creation system and method that can suppress an increase in logistics costs regarding the transportation of luggage by electric vehicles. [Brief description of the drawings]
[0015] [Figure 1]1 is a block diagram showing an overall configuration of a transportation schedule creation system according to an embodiment of the present invention; [Diagram 2] 1 is a block diagram showing a logical configuration of a transportation schedule creation device according to an embodiment of the present invention; [Diagram 3] 13 is a diagram showing an example of the configuration of a package information table; [Figure 4] 4 is a diagram showing an example of the configuration of a vehicle information table; [Diagram 5] 13 is a diagram showing an example of the configuration of a base information table. [Figure 6] 13 is a diagram showing an example of the configuration of a birth information table; [Figure 7] 11 is a diagram showing an example of the configuration of a charging station information table. [Figure 8] 13 is a diagram showing an example of the configuration of a travel cost information table. [Figure 9] 13 is a diagram showing an example of the configuration of a transportation plan information table. [Figure 10] 10 is a diagram showing an example of the configuration of a vehicle current status information table. [Figure 11] 13 is a diagram showing an example of the configuration of an evaluation information table. [Figure 12] 13 is a diagram showing an example of the configuration of a transportation plan information table. [Figure 13] 11 is a diagram showing an example of the configuration of a proposed charging plan information table. [Figure 14] 10 is a flowchart showing the processing steps for creating and evaluating a transportation and charging plan. [Figure 15] 13 is a flowchart showing a processing procedure for a transportation and charging plan proposal creation process. [Figure 16] 13 is a flowchart showing a processing procedure of a plan proposal evaluation process. [Figure 17] FIG. 13 is a diagram showing an example of a screen configuration of a transportation plan display screen. [Figure 18] FIG. 13 is a diagram illustrating an example of a screen configuration of a charging plan display screen. [Figure 19] FIG. 13 is a diagram showing an example of a screen configuration of a transportation schedule display screen. [Figure 20]FIG. 13 is a diagram showing an example of a screen configuration of a base schedule display screen. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] An embodiment of the present invention will now be described in detail with reference to the drawings.
[0017] (1) Configuration of the transportation planning system according to this embodiment In Fig. 1, reference numeral 1 denotes an overall transportation plan creation system according to this embodiment. This transportation plan creation system 1 is configured with a transportation plan creation device 2, an on-board terminal 4 mounted on each transport vehicle 3 consisting of an electric vehicle, and a plan management terminal 6 installed at each base 5 such as a collection and delivery base 5A and a charging base 5B. The electric vehicle is, for example, an electric vehicle (EV).
[0018] The collection and delivery base 5A refers to a base where collection and delivery are performed for the transport vehicle 3, and the charging base 5B refers to a base where a charging stand is installed for charging the transport vehicle 3. However, there are also cases where a charging stand is installed at the collection and delivery base 5A.
[0019] The transportation plan creation device 2 is composed of a general-purpose computer device equipped with a CPU (Central Processing Unit) 10, a ROM (Read Only Memory) 11, a RAM (Random Access Memory) 12, an auxiliary storage device 13, an input device 14, a display device 15, a media reading device 16 and a communication device 17.
[0020] The CPU 10 is a processor that controls the overall operation of the transportation plan creation device 2. The ROM 11 is a non-volatile semiconductor memory that stores programs and the like required to start up the transportation plan creation device 2, and the RAM 12 is a volatile semiconductor memory that is used as a working memory for the CPU 10.
[0021] The auxiliary storage device 13 is composed of a non-volatile storage device such as a hard disk device or an SSD (Solid State Drive), and stores various programs, data that needs to be stored for a long period of time, etc. The programs stored in the auxiliary storage device 13 are read from the auxiliary storage device 13 to the RAM 12 when the transportation plan creation device 2 is started or when necessary, and the programs read to the RAM 12 are executed by the CPU 10, thereby performing various processes of the transportation plan creation device 2 as a whole, as described below.
[0022] The input device 14 is composed of a mouse, a keyboard, and the like, and is used when a user inputs various information and various instructions to the transportation plan creation device 2. The display device 15 is composed of, for example, a liquid crystal display, an organic EL (Electro-Luminescence) display, and is used to display various information. Note that, instead of the input device 14 and the display device 15, a touch panel in which these are integrated may be applied.
[0023] The media reading device 16 is a reader / writer device that reads and writes data from / to portable storage media such as a USB (Universal Serial Bus) or an SD (Secure Digital) card, etc. The communication device 17 is a communication device that has a function of exchanging information with each of the in-vehicle terminals 4 and each of the planning management terminals 6 via a wired or wireless network 7.
[0024] On the other hand, the vehicle-mounted terminal 4 is composed of a wireless communication terminal device including a communication device 20, which is a wireless communication terminal, and a display device 21 composed of a liquid crystal panel, an organic EL panel, or the like. The vehicle-mounted terminal 4 transmits information such as the current position of the destination transport vehicle 3 and the current charging state of the transport vehicle 3 to the transport plan creation device 2 via the network 7 periodically or in response to a request from the transport plan creation device 2. The vehicle-mounted terminal 4 also displays the information transmitted from the transport plan creation device 2 via the network 7 on the display device 21.
[0025] The plan management terminal 6 is composed of a computer device equipped with a communication device 22, which is a wired or wireless communication terminal, and a display device 23 composed of a liquid crystal display, an organic EL display, or the like. The plan management terminal 6 transmits necessary information about the base 5 at which the terminal 6 is installed to the transportation plan creation device 2 via the network 7 periodically or in response to a request from the transportation plan creation device 2, and displays information transmitted from the transportation plan creation device 2 via the network 7 on the display device 23.
[0026] (2) Transport and charging plan creation and evaluation function according to this embodiment Next, a description will be given of a transportation / charging plan creation and evaluation function according to this embodiment, which is installed in the transportation plan creation device 2. This transportation / charging plan creation and evaluation function is a function that, when an unplanned event occurs in a transportation plan created in advance on a weekly or daily basis, creates multiple combinations of a transportation plan that takes into account the unplanned event and a charging plan (hereinafter, referred to as a charging plan) for charging the necessary transportation vehicles 3 so that each transportation vehicle 3 does not run out of electricity when the transportation plan is executed.
[0027] In addition, in order to prevent each transport vehicle 3 from running out of power, in addition to or instead of charging the battery of the transport vehicle 3, the battery of the transport vehicle 3 may be replaced with a charged battery. The proposed charging plan may include a plan to replace the battery of the transport vehicle 3 in addition to a plan to charge the battery of the transport vehicle 3. A plan that includes at least one of a plan to charge the battery of the transport vehicle 3 and a plan to replace the battery of the transport vehicle 3 may be called a supply plan (or a proposed supply plan). The following explanation will mainly explain an example of creating a proposed charging plan.
[0028] In addition, based on the transportation / charging plan creation and evaluation function, the transportation plan creation device 2 evaluates each combination of the created transportation plan and charging plan for each of the three evaluation items, namely, "delivery delay," "increase in operating time," and "deviation in operating time," and based on the evaluation results for these evaluation items, presents the combination of the transportation plan and charging plan with a higher evaluation as a new transportation plan to users such as the transportation operation staff, the drivers of each transportation vehicle, and the staff at each base station.
[0029] In this case, the "transportation plan proposal" refers to a plan regarding the status of each transport vehicle 3, such as departure, collection, delivery, charging, and arrival at each collection and distribution center 5A, and the "charging plan proposal" refers to a plan regarding charging of each transport vehicle 3 at each charging center 5B.
[0030] Additionally, "delivery delay" here refers to the total time of delivery delay of each package that occurs when transportation work is performed according to the prepared transportation plan and charging plan, and "increase in operating time" refers to the total increased time of each transport vehicle 3 that occurs when transportation work is performed according to the prepared transportation plan and charging plan, relative to the operating time of each transport vehicle 3 in a transportation plan prepared in advance on a weekly or daily basis. Furthermore, "deviation in operating time" refers to the deviation in operating time between transport vehicles 3 when transportation work is performed according to the prepared transportation plan and charging plan.
[0031] When creating a new transportation plan, it is desirable that the values of all of these evaluation items, "Delivery Delay," "Increase in Operating Time," and "Deviation of Operating Time," are small, but it may be difficult to minimize the values of all evaluation items. Therefore, in this transportation plan creation device 2, a desired weight (weighting coefficient) can be set for each evaluation item, and each combination of the transportation plan proposal and the charging plan proposal is comprehensively evaluated based on the total value of the multiplication result obtained by multiplying the value of each evaluation item by the weighting coefficient set for that evaluation item, and the combination with the highest evaluation is selected as the new transportation plan.
[0032] As means for realizing such transportation and charging plan creation and evaluation functions, the transportation plan creation device 2 includes a baggage information table 31, a vehicle information table 32, a base information table 33, a berth information table 34, a charging station information table 35, a movement cost information table 36, a transportation plan information table 37, a vehicle current status information table 38, an evaluation information table 39, a transportation plan information table 40, and a charging plan information table 41, which are each stored in a memory unit 30, as well as a plan creation unit 43 and a plan evaluation unit 44 constituting a control unit 42, as shown in Fig. 2. The memory unit 30 is a conceptualization of the storage areas provided by the ROM 11, the RAM 12, and the auxiliary storage device 13, and the control unit 42 is a conceptualization of the functions of the CPU 10.
[0033] The parcel information table 31 is a table used to manage information on each parcel requested for transportation, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 3, this parcel information table 31 is configured with an order number column 31A, a collection origin base name column 31B, a delivery destination base name column 31C, a quantity column 31D, a possible collection date and time column 31E, and a possible delivery date and time column 31F. In the parcel information table 31, one record (row) corresponds to a transport request for one parcel (hereinafter, this will be simply called an order).
[0034] The order number field 31A stores an identification number (order number) unique to the order that is assigned to the corresponding order. The collection origin base name field 31B stores the name (base name) of the collection and delivery base 5A that is to collect the parcel specified in the order, and the delivery destination base name field 31C stores the base name of the collection and delivery base 5A to which the parcel is to be transported, specified in the order.
[0035] Furthermore, the number of packages requested for transportation in the order is stored in the quantity column 31D. However, instead of the number of packages, the total weight or total volume of the packages may be managed in the package information table 31, and furthermore, a partial or complete combination of the number of packages, total weight, and total volume may be managed in the package information table 31.
[0036] The available collection date and time field 31E is divided into a start field 31EA and an end field 31EB, and the start date and time and the end date and time of the period when the package should be collected are stored in the start field 31EA and the end field 31EB, respectively. Similarly, the available delivery date and time field 31F is divided into a start field 31FA and an end field 31FB, and the start date and time and the end date and time of the period when the package should be delivered are stored in the start field 31FA and the end field 31FB, respectively.
[0037] Therefore, in the example of Fig. 3, an order with an order number of "1" is a request to transport "10" packages from a collection / delivery base 5A with a base code of "Base 1" to a collection / delivery base 5A with a base code of "Base 2." Fig. 3 also shows that the period during which the packages should be collected at the collection / delivery base 5A "Base 1" is from "4 / 1 15:00" to "4 / 1 20:00," and the period during which the packages should be delivered to the collection / delivery base 5A "Base 2" is from "4 / 5 10:00" to "4 / 5 15:00."
[0038] The vehicle information table 32 is a table used to manage transport vehicles 3 that can be used to transport cargo, and is created in advance and provided to the transport plan creation device 2. As shown in Fig. 4, the vehicle information table 32 includes a vehicle name column 32A, a loading capacity upper limit column 32B, an operating time upper limit column 32C, a vehicle unit price column 32D, an operating cost column 32E, a charging amount upper limit column 32F, a charging amount lower limit column 32G, and an electricity cost column 32H. In the vehicle information table 32, one record (row) corresponds to one transport vehicle 3.
[0039] The vehicle name field 32A stores the name (vehicle name) of the corresponding transport vehicle 3, and the loading number upper limit field 32B stores the upper limit number of cargoes (loading number upper limit) that can be loaded on the transport vehicle 3. Instead of the loading number upper limit, a loading weight upper limit indicating the upper limit of the weight that can be loaded on the transport vehicle 3 or a loading capacity upper limit indicating the upper limit of the capacity that can be loaded on the transport vehicle 3 may be managed in the vehicle information table 32. Also, a full or partial combination of the loading number upper limit, loading weight upper limit, and loading capacity upper limit may be managed in the vehicle information table 32. Furthermore, the operating time upper limit field 32C stores the upper limit of the time that the transport vehicle 3 can operate.
[0040] Furthermore, the vehicle unit price field 32D stores a vehicle unit price representing the arrangement fee required to arrange for the transport vehicle 3, and the operation unit price field 32E stores an operation unit price representing the usage fee per unit time of the transport vehicle 3.
[0041] Furthermore, the upper limit charging amount field 32F stores an upper limit charging amount, which is an upper limit of the amount of charging to the transport vehicle 3, and the lower limit charging amount field 32G stores a lower limit charging amount, which is a minimum amount of charging required for the transport vehicle 3 to operate. Furthermore, the power consumption field 32H stores a travel distance per unit power consumption of the transport vehicle 3.
[0042] Therefore, in the example of Figure 4, a transport vehicle 3 called "Vehicle A" has an upper load capacity of "50", a vehicle cost per unit of "100" yen, an operating cost per unit of "1" yen / minute, an upper charge capacity limit of "60" kWh, a lower charge capacity limit of "10" kWh, and an electricity cost of "7" km / kWh.
[0043] The base station information table 33 is a table used to manage each base station 5, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 5, this base station information table 33 is configured with a base station name column 33A, a collection / delivery time column 33B, a location column 33C, a number of berths column 33D, and a charging amount upper limit column 33E. In the base station information table 33, one record (row) corresponds to one base station 5.
[0044] The base name field 33A stores the name of the corresponding base 5, and the collection / delivery time field 33B stores the average time required for collection and delivery of one package at the base 5 when the base 5 is a collection / delivery base 5A. However, the average time required for collection and the average time required for delivery may be managed separately in the base information table 33.
[0045] The location column 33C is divided into a latitude column 33CA and a longitude column 33CB, with the latitude of the corresponding location 5 being stored in the latitude column 33CA, and the longitude column 33CB storing the longitude of the location 5. The berth number column 33D stores the number of berths that exist at the location 5, and the charging amount upper limit column 33E stores the charging amount upper limit, which is the upper limit of the amount of electricity that can be charged per unit time at the location 5 when a charging stand is installed at the location 5.
[0046] Therefore, in the example of Figure 5, base 5, called "base 1," is located at latitude "33°36'23" and longitude "130°25'05", base 5 has berth "5," the average time required for collection and delivery is "0.5" min / minute, and the upper limit of charging capacity is "100" kWh.
[0047] The berth information table 34 is a table used to manage berths installed at each base 5, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 6, this berth information table 34 is configured with a base name column 34A, a berth name column 34B, and an acceptance time column 34C. In the berth information table 34, one record (row) corresponds to one berth installed at one of the bases 5.
[0048] The base name column 34A stores the name of the base 5 where the corresponding berth is provided, and the berth name column 34B stores the name of the corresponding berth (berth name). The receiving time column 34C is divided into a start column 34CA and an end column 34CB. The start column 34CA stores the start time of the time period (receiving time period) during which the corresponding berth can receive the transport vehicle 3, and the end column 34CB stores the end time of the receiving time period.
[0049] Therefore, in the example of FIG. 6, for example, it is shown that the reception time period of a berth called "berth A" provided at a base 5 called "base 1" is from "07:00" to "21:00".
[0050] The charging station information table 35 is a table used for managing the charging stations installed at each base 5, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 7, this charging station information table 35 is configured with a base name column 35A, a station number column 35B, a charging amount column 35C, an acceptance time column 35D, a charging mode column 35E, and a parallel work availability flag column 35F. In the charging station information table 35, one record (row) corresponds to one charging station.
[0051] The location name field 35A stores the name of the location 5 where the corresponding charging stand is installed, and the station number field 35B stores a number (station number) assigned to the charging stand that is unique to that charging stand. The charging amount field 35C stores the charging amount per unit time that can be charged at that charging stand.
[0052] The acceptance time column 35D is divided into a start column 35DA and an end column 35DB. The start column 35DA stores the start time of the time period during which the corresponding charging station is available, and the end column 35DB stores the end time of that time period. The charging mode column 35E stores the charging modes that can be used at the charging station. Such charging modes include a normal charging mode for charging at a normal speed and a rapid charging mode for rapid charging.
[0053] Furthermore, the parallel operation flag field 35F stores a flag (parallel operation flag) indicating whether collection or delivery can be performed in parallel with charging when the charging station is installed at the collection / distribution base 5A. The parallel operation flag is set to "Yes" if collection or delivery can be performed in parallel with charging, and is set to "No" if collection or delivery cannot be performed in parallel with charging.
[0054] Therefore, in the example of Figure 7, the charging station with station number "1" installed at site 5 with site name "Site 1" supports only "normal charging" and allows charging up to "3.2" kW per unit time. It also shows that the available time period for this charging station is from "07:00" to "19:00", and that collection or delivery can be performed in parallel with charging.
[0055] The travel cost information table 36 is a table used to manage costs required for travel from one base 5 to another base 5, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 8, the travel cost information table 36 is configured with a departure and arrival point column 36A, a travel time column 36B, a travel distance column 36C, and a power transfer coefficient column 36D. In the travel cost information table 36, one record (row) corresponds to a route from one base 5 to another base 5.
[0056] The departure / arrival point field 36A is divided into a departure point field 36AA and an arrival point field 36AB. The departure point field 36AA stores the base name of the base 5 that is the departure point of the corresponding route, and the arrival point field 36AB stores the base name of the base 5 that is the arrival point of the route.
[0057] The travel time field 36B stores the average travel time required for the transport vehicle 3 to travel from the departure point to the destination on that route while observing the legal speed limit, and the travel distance field 36C stores the travel distance from the departure point to the destination on that route. Furthermore, the power transfer coefficient field 36D stores a power transfer coefficient indicating the power efficiency in that case. For example, in FIG. 4, the power consumption of vehicle A is "7" kw / kWh, but when traveling from "base 1" to "base 2", it travels only "0.8" minutes compared to the standard efficiency, and when traveling from "base 1" to "base 3", it travels "1.0" minutes, which is equivalent to the standard efficiency.
[0058] Therefore, in the example of FIG. 8, it is shown that the distance from "site 1" to "site 2" is "8.4" km, the average travel time is "15" minutes, and the electricity consumption cost is "0.8".
[0059] The transportation plan information table 37 is a table used to manage the transportation plan for the day that has been created in advance on a weekly or daily basis, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 9, this transportation plan information table 37 is configured with a vehicle name column 37A, a base name column 37B, a berth name column 37C, a status column 37D, an order number column 37E, a quantity column 37F, and a time column 37G. In the transportation plan information table 37, one record (row) corresponds to one status of one transport vehicle 3 for which a transportation schedule has been created.
[0060] The vehicle name field 37A stores the name of the corresponding transport vehicle 3, and the base name field 37B stores the name of the base 5 from which the transport vehicle 3 should depart, pick up, deliver, charge, or arrive. The berth name field 37C stores the name of the berth that the transport vehicle 3 should use at the base 5, and the status field 37D stores a "status" that indicates the work that the transport vehicle 3 should perform at the base 5. The "status" in this case includes departure, pick up, delivery, charging, and arrival.
[0061] The order number field 37E stores the order number of the order for which the corresponding work or the like is to be performed, and the quantity field 37F stores the number of packages specified in the order. Note that instead of the number of packages, the total weight or total volume of the packages may be managed in the transport plan information table 37, and further, a combination of some or all of the number of packages, the total weight, and the total volume may be managed in the transport plan information table 37.
[0062] The time column 37G is further divided into a start column 37GA and an end column 37GB. The start column 37GA stores the date and time when the state (task, etc.) stored in the status column 37D should start, and the end column 37GB stores the date and time when the state (task, etc.) should end.
[0063] Therefore, in the example of Figure 9, a transportation schedule has been created for a transport vehicle 3 called "Vehicle A" to "depart" from base 5 called "Base 3" at "4 / 1 8:00", "collect" "8" packages according to order number "5" at berth "Berth A" at base 5 called "Base 4" (here, collection / distribution base 5A) between "4 / 1 9:05" and "4 / 1 9:13", and then "deliver" the packages at berth "Berth A" at base called "Base 7" (here, collection / distribution base 5A) between "4 / 1 10:00" and "4 / 1 10:04".
[0064] The vehicle current status information table 38 is a table used to manage the current status of each transport vehicle 3 that is acquired by the transport plan creation device 2 through notification from each managed transport vehicle 3. As shown in Fig. 10, the vehicle current status information table 38 includes a vehicle name column 38A, a current location column 38B, a remaining charge column 38C, and an information reception date and time column 38D. In the vehicle current status information table 38, one record (row) corresponds to one managed transport vehicle 3.
[0065] The vehicle name field 38A stores the vehicle name of the corresponding transport vehicle 3. The current location field 38B is divided into a latitude field 38BA and a longitude field 38BB, and the current latitude or longitude of the transport vehicle 3 is stored in the latitude field 38BA and the longitude field 38BB, respectively. The remaining charge field 38C stores the current remaining charge of the transport vehicle 3, and the information received date and time field 38D stores the date and time when the information was received. Note that the information received date and time field 38D may store the date and time when the transport vehicle 3 obtained the information or the date and time when the information was transmitted, instead of or in addition to the date and time when the information was received.
[0066] In addition, instead of latitude and longitude, the information representing the current location of the transport vehicle 3 may be a combination of the name of the base 5 closest to the current location of the corresponding transport vehicle 3, the distance from that base 5, and some or all of the travel time from that base 5.
[0067] Therefore, in the example of Figure 10, according to information received on "4 / 1 11:00", a transport vehicle 3 named "Vehicle A" is located at latitude "33°40'22" and longitude "130°30'06" at that time, and has a remaining charge of "15" kWh.
[0068] The evaluation information table 39 is a table used for managing parameters that indicate the magnitude of the influence that each of the three evaluation items "delivery delay", "increase in operation time", and "deviation in operation time" has on the logistics cost when evaluating the proposed transportation plan and the proposed charging plan, and is created in advance and provided to the transportation plan creation device 2. As shown in Fig. 11, the evaluation information table 39 is configured to include a delivery delay parameter column 39A, an operation time increase parameter column 39B, and an operation time deviation parameter column 39C.
[0069] The delivery date delay parameter field 39A stores a delivery date delay parameter (the weighting coefficient described above for "delivery date delay" when evaluating the proposed transportation plan and the proposed charging plan) that indicates the magnitude of the impact of "delivery date delay" on logistics costs. The operation time increase parameter field 39B stores an operation time increase parameter (the weighting coefficient described above for "increase in operation time" when evaluating the proposed transportation plan and the proposed charging plan) that indicates the magnitude of the impact of "increase in operation time" on logistics costs. The operation time deviation parameter field 39C stores an operation time deviation parameter (the weighting coefficient described above for "deviation in operation time" when evaluating the proposed transportation plan and the proposed charging plan) that indicates the magnitude of the impact of the deviation in operation time between transport vehicles 3 on logistics costs.
[0070] Therefore, in the example of FIG. 11, it is shown that the magnitudes of the delivery delay parameter, the operation time increase parameter, and the operation time deviation parameter are set to "3," "1," and "2," respectively.
[0071] The transportation plan proposal information table 40 is a table used to manage a transportation plan proposal that is created when an unplanned event occurs in a transportation plan that has been previously drawn up on a weekly or daily basis. As shown in Fig. 12, the transportation plan proposal information table 40 includes a vehicle name column 40A, a base name column 40B, a berth name column 40C, a status column 40D, an order number column 40E, a quantity column 40F, and a time column 40G.
[0072] This transportation plan proposal information table 40 has the same configuration as the transportation plan information table 37, and the vehicle name column 40A, base station name column 40B, berth name column 40C, status column 40D, order number column 40E, quantity column 40F and time column 40G store information related to the transportation plan proposal that is similar to the information stored in the corresponding vehicle name column 37A, base station name column 37B, berth name column 37C, status column 37D, order number column 37E, quantity column 37F or time column 37G of the transportation plan information table 37.
[0073] In addition, a plurality of transportation plan proposals may be stored in the transportation plan proposal information table 40, and further, a transportation plan proposal information table 40 may be generated for each transportation plan proposal.
[0074] Furthermore, the charging plan information table 41 is a table used to manage a charging plan for a transport vehicle 3 that requires charging, which is created together with the above-mentioned transportation plan when an unplanned event occurs in a transport plan that has been previously planned on a weekly or daily basis. The charging plan information table 41 is generated for each charging station 5B where charging of any transport vehicle 3 is planned.
[0075] 13, the charging plan information table 41 includes a base name column 41A, a station number column 41B, a vehicle name column 41C, a charging amount column 41D, and a time column 41E. In the charging plan information table 41, one record (row) corresponds to one charging schedule for one transport vehicle 3.
[0076] The base name field 41A stores the base name of the charging base 5B corresponding to the proposed charging plan information table 41. The station number field 41B stores the station number of the charging station installed at the corresponding charging base 5B, and the vehicle name field 41C stores the vehicle name of the transport vehicle 3 to be charged at the charging station.
[0077] Furthermore, the charging amount column 41D stores the charging amount at the charging station that occurs when the created charging plan is followed. Furthermore, the time column 41E is divided into a start column 41EA and an end column 41EB, and the start column 41EA stores the time when the transport vehicle 3 should start charging at the charging station, and the end column 41EB stores the time when the charging should end.
[0078] Therefore, in the example of Figure 13, it is shown that a charging plan has been created at a charging station 5B called "Station 1", for example, at a charging stand with stand number "1", to charge a transport vehicle 3 called "Vehicle 3" at "1.6" kWh between "4 / 1 10:00" and "4 / 1 10:30".
[0079] On the other hand, the plan proposal creation unit 43 (Figure 2) and the plan proposal evaluation unit 44 (Figure 2) are functional units that are realized by the CPU 10 of the transportation plan creation device 2 executing a program stored in the ROM 11 or loaded from the auxiliary storage device 13 to the RAM 12.
[0080] Among these, the plan creation unit 43 has a function of creating a combination of multiple transportation plan proposals and charging plan proposals that take into account an unplanned event that occurs in a transportation plan that has been previously planned on a weekly or daily basis. The plan evaluation unit 44 has a function of evaluating each of the transportation plan proposals and charging plan proposals created by the plan creation unit 43, and proposing the most appropriate combination of the transportation plan proposals and charging plan proposals as a new transportation plan to the user. Specific processing contents of the plan creation unit 43 and the plan evaluation unit 44 will be described later.
[0081] (3) Various processes performed in relation to the creation and evaluation of transportation and charging plans Next, specific processing contents of various processes executed by the plan creation unit 43 and the plan evaluation unit 44 in relation to the transportation / charging plan creation and evaluation function will be described.
[0082] (3-1) Transportation and charging plan creation and evaluation FIG. 14 shows the flow of a series of processes (hereinafter referred to as transportation and charging plan creation and evaluation processes) executed by the plan creation unit 43 and the plan evaluation unit 44 in relation to the transportation and charging plan creation and evaluation function.
[0083] This process of creating and evaluating a proposed transportation and charging plan is triggered when the driver contacts the transportation operations manager to inform him / her that an unplanned event has occurred during the execution of a transportation plan that was previously prepared on a weekly or daily basis, and the operations manager, upon receiving this contact, inputs an instruction to create a proposed transportation plan and a proposed charging plan into the transportation plan creation device 2.
[0084] First, the plan creation unit 43 reads each piece of information stored in each table described above with reference to FIGS. 3 to 11 (S1).
[0085] Next, the plan creation unit 43 creates a transportation plan proposal and a charging plan proposal (S2). At this time, the plan creation unit 43 creates a combination of a plurality of transportation plan proposals and charging plan proposals. In addition, the plan creation unit 43 stores the created transportation plan proposal in the transportation plan proposal information table 40 (FIG. 12), and stores the created charging plan proposal in the charging plan proposal information table 41 (FIG. 13).
[0086] Next, the plan evaluation unit 44 determines whether or not the plan creation unit 43 has been able to create at least one combination of a transportation plan and a charging plan in step S2 (S3).
[0087] Obtaining a negative result in step S3 means that the proposed transportation plan and the proposed charging plan cannot be created under the current conditions (conditions for creating the proposed transportation plan and the proposed charging plan, hereinafter referred to as planning conditions) such as the delivery date of each package and the operating time of each transport vehicle 3. Thus, at this time, the plan proposal evaluation unit 44 changes the planning conditions (for example, delaying the delivery date of packages of customers whose delivery dates can be delayed, or using new transport vehicles 3 that are available on that day) and instructs the plan proposal creation unit 43 to re-create the proposed transportation plan and the proposed charging plan (S4). As a result, the processes from step S2 onwards are executed in the same manner as described above according to the changed planning conditions.
[0088] On the other hand, if a positive result is obtained in step S3, the plan proposal evaluation unit 44 evaluates each of the three evaluation items, namely, "delivery date delay," "increase in operating time," and "deviation in operating time," for each combination of the transportation plan proposal and the charging plan proposal created in step S2, and comprehensively evaluates the combination based on these evaluation results (S5).
[0089] Then, based on the overall evaluation results for each combination of the transportation plan and the charging plan obtained in step S5, the plan proposal evaluation unit 44 selects one combination of the transportation plan and the charging plan with the highest evaluation, creates various screens according to the selected combination of the transportation plan and the charging plan, and outputs the screen data to the display device 15 of the transportation plan creation device 2, the in-vehicle terminal 4 of each transport vehicle 3, and the plan management terminal 6 of each base station 5 (S6).
[0090] Specifically, the plan proposal evaluation unit 44 generates a transportation plan proposal display screen 50, which will be described later with reference to Fig. 17, and a charging plan proposal display screen 60, which will be described later with reference to Fig. 18, and outputs screen data of the generated transportation plan proposal display screen 50 and charging plan proposal display screen 60 to the display device 15. As a result, the transportation plan proposal display screen 50 and the charging plan proposal display screen 60 are displayed on the display device 15 in response to a user operation.
[0091] The plan proposal evaluation unit 44 also generates a transport schedule display screen 70 for each transport vehicle 3, which will be described later with reference to Fig. 19, and a base schedule display screen 80 for each base 5, which will be described later with reference to Fig. 20. The plan proposal evaluation unit 44 then transmits screen data of each generated transport schedule display screen 70 to the in-vehicle terminal 4 of the corresponding transport vehicle 3 via the network 7, and also transmits screen data of each generated base schedule display screen 80 to the plan management terminal 6 of the corresponding base 5 via the network 7.
[0092] As a result, the corresponding transport schedule display screen 70 is displayed on the display device 21 of each vehicle-mounted terminal 4, and the corresponding base schedule display screen 80 is displayed on the display device 23 of each plan management terminal.
[0093] This completes the transportation plan creation and evaluation process.
[0094] (3-2) Transportation and charging plan creation process Fig. 15 shows the contents of a specific process (hereinafter, referred to as a transportation / charging plan creation process) executed by the plan creation unit 43 in step S2 of the transportation / charging plan creation and evaluation process described above with reference to Fig. 14. The plan creation unit 43 creates a transportation plan and a charging plan that meet the plan conditions according to the processing procedure shown in Fig. 15.
[0095] In practice, when the plan creation unit 43 proceeds to step S2 of the transportation and charging plan creation and evaluation process, it starts the transportation and charging plan creation process shown in Fig. 15, and first attempts to create multiple transportation plan proposals and charging plan proposals that can transport all the cargo to be transported without causing any of the transportation vehicles 3 to run out of power, without changing the visit order of the bases 5 of each transportation vehicle 3 in the current transportation plan read from the transportation plan information table 37 (Fig. 9) in step S1 of the transportation and charging plan creation and evaluation process (S10). Specifically, for each transportation vehicle 3 with a risk of running out of power, a position below the lower limit of the charging amount is estimated, and a plan is attempted to add charging work at a base to be visited before that.
[0096] The identification of the "transport vehicles 3 at risk of running out of power" can be performed by identifying the transport vehicles 3 whose charging power falls below the lower limit of the charge amount unless the transport plan is changed, based on the original transport plan stored in the transport plan information table 37 (FIG. 9), the current position and remaining charge amount of each transport vehicle 3 stored in the vehicle current status information table 38 (FIG. 10), the lower limit of the charge amount and the power cost of each transport vehicle 3 stored in the vehicle information table 32 (FIG. 4), the travel distance between each base 5 stored in the travel cost information table 36 (FIG. 8), and the power transfer coefficient. For example, the power consumption amount on the unvisited route when the transport plan is not changed can be calculated by multiplying the power cost of each transport vehicle 3 by the power transfer coefficient on the unvisited route and comparing the result with the travel distance on the unvisited route.
[0097] Next, the plan creation unit 43 determines whether or not the transportation plan proposal and the charging plan proposal have been created in step S10 (S11). If the plan creation unit 43 obtains a positive result in this determination, the plan creation unit 43 stores each of the transportation plan proposals constituting each combination of the transportation plan proposal and the charging plan proposal created at that time in the transportation plan proposal information table 40 (FIG. 12), and stores each of the charging plan proposals constituting each of the combinations in the charging plan proposal information table 41 (FIG. 13) (S12).
[0098] Next, the plan creation unit 43 estimates the location of the transport vehicles 3 at risk of running out of power that is below the lower limit of the charge amount in the original transportation plan, and selects one transport vehicle 3 that is the shortest distance between the collection / distribution base 5A that it will visit next and the charging base 5B nearest to that collection / distribution base 5A, and for which steps S13 and after have not been processed for that collection / distribution base 5A and that charging base 5B (S13).
[0099] Next, the plan creation unit 43 adds a visit to the collection and distribution base 5A and the charging base 5B determined to be the closest in distance in step S13 to the original transportation plan for the transportation vehicle 3 selected in step S13 (hereinafter, this is referred to as the selected vehicle), and attempts to create multiple combinations of transportation plan proposals and charging plan proposals that transport all the packages to be transported and that do not cause the transportation vehicle 3 to run out of power (S14). For example, a plan is attempted in which the amount of power consumed by the selected vehicle 3 from the collection and distribution base 5A to the end of delivery in the original transportation plan is predicted, and the predicted amount of power is charged at the charging base 5B. The transportation plan proposal created at this time may be created so that the increase in the travel time of each transportation vehicle 3 and the difference from the work time are reduced compared to the original transportation plan.
[0100] Thereafter, the plan creation unit 43 determines whether or not at least one combination of a transportation plan and a charging plan has been created in step S14 (S15).
[0101] If the plan creation unit 43 obtains a negative result in this determination, it determines (S16) whether or not the processing from step S13 onwards has been completed for all transport vehicles 3. If the plan creation unit 43 obtains a negative result in this determination, it returns to step S13, and thereafter, in addition to the selected vehicle 3, it selects the transport vehicle 3 to be selected in step S13 from other transport vehicles 3 for which step S14 onwards has not been processed, and repeats the processing from step S13 to step S16 in the same manner as described above.
[0102] If the plan creation unit 43 does not obtain a positive result in step S15 even after repeating the processes of steps S13 to S16 (i.e., if it is unable to create a combination of a transportation plan and a charging plan that transports all of the cargo to be transported and does not result in any transport vehicles 3 running out of power), the plan creation unit 43 proceeds to step S18.
[0103] On the other hand, if a positive result is obtained in step S15 by repeating the processing of steps S13 to S16 (i.e., if at least one combination of a transportation plan and a charging plan can be created that transports all of the cargo to be transported and does not cause any transport vehicle 3 to run out of power), the plan creation unit 43 stores each of the transportation plan proposals that constitute each combination of the transportation plan proposal and the charging plan proposal created at that time in the transportation plan proposal information table 40 (FIG. 12), and stores each of the charging plan proposals that constitute each of the combinations in the charging plan proposal information table 41 (FIG. 13) (S17).
[0104] Next, the plan creation unit 43 selects one transport vehicle 3 with the largest remaining charge (S18). The "remaining charge" here may be the current remaining charge of each transport vehicle 3 obtained from the vehicle information table 32 (FIG. 4), or may be the remaining charge of each transport vehicle 3 at the time of completion of transport when each transport vehicle 3 moves according to the original transport plan, which is estimated based on each piece of information stored in the transport plan information table 37 (FIG. 9) and the travel cost information table 36 (FIG. 8).
[0105] Next, the plan creation unit 43 attempts to create multiple combinations of transportation plan proposals and charging plan proposals that allow the transportation vehicles 3 selected in step S18 (hereinafter referred to as selected vehicles) 3 to preferentially add visiting bases or extend their operating hours, and deliver all cargo without any of the transportation vehicles 3 running out of power (S19). For example, a plan is attempted in which the selected vehicles 3 take on part of the deliveries of the transportation vehicles 3 that are at risk of running out of power in the original transportation plan. The transportation plan proposal created at this time may be created so as to reduce the increase in travel time of each transportation vehicle 3 and the difference from the work time, compared to the original transportation plan stored in the transportation plan information table 37.
[0106] After this, the plan creation unit 43 determines whether or not at least one combination of a transportation plan and a charging plan has been created in step S19 (however, if there are no transport vehicles 3 that need charging in the created transportation plan, a charging plan is not required) (S20).
[0107] If the plan creation unit 43 obtains a negative result in this determination, it determines (S21) whether or not the processing from step S18 onwards has been completed for all transport vehicles 3. If the plan creation unit 43 obtains a negative result in this determination, it returns to step S18, and thereafter, in addition to the selected vehicle 3, it selects the transport vehicle 3 to be selected in step S18 from other applicable transport vehicles 3 for which step S17 onwards has not been processed, and repeats the processing from step S18 to step S21 in the same manner as described above.
[0108] Then, when a positive result is obtained in step S20 by the repeated processing of steps S18 to S21 (i.e., when at least one combination of a transportation plan and a charging plan that transports all the cargo to be transported and does not cause any transport vehicle 3 to run out of power can be created), the plan creation unit 43 stores each of the transportation plan plans constituting each combination of the transportation plan and the charging plan created at that time in the transportation plan proposal information table 40, and stores each of the charging plan plans constituting each of the combinations in the charging plan proposal information table 41 (S22). Then, the plan creation unit 43 then ends this transportation and charging plan creation process.
[0109] In contrast, if the plan creation unit 43 obtains a positive result in step S21 without obtaining a positive result in step S20 even by repeating the processing of steps S18 to S21 (i.e., if the processing of step S19 for all transport vehicles 3 is completed without being able to create a combination of transportation plan proposals and charging plan proposals that transport all of the cargo to be transported and that does not result in any transport vehicles 3 running out of power), the plan creation unit 43 terminates the transportation and charging plan creation and evaluation processing.
[0110] (3-3) Plan evaluation process Fig. 16 shows the details of the specific process (hereinafter, referred to as the plan proposal evaluation process) executed by the plan proposal evaluation unit 44 in step S5 of the transportation plan proposal creation / evaluation process described above with reference to Fig. 14. The plan proposal evaluation unit 44 evaluates the combination of the transportation plan proposal and the charging plan proposal created by the plan proposal creation unit 43 from the above-mentioned three viewpoints of "delivery date delay," "increase in operation time," and "deviation in operation time" according to the processing procedure shown in Fig. 16. Note that, with at least "delivery date delay" as the evaluation item, the evaluation items may be changed, added, or removed.
[0111] In practice, when the plan proposal evaluation unit 44 proceeds to step S5 of the transportation / charging plan proposal creation and evaluation process, it starts the plan proposal creation process shown in Figure 16, and first reads all of the transportation plan proposals and charging plan proposals stored in the transportation plan proposal information table 40 and the charging plan proposal information table 41, respectively (S30).
[0112] Next, the plan proposal evaluation unit 44 selects one combination of the transportation plan proposal and the charging plan proposal for which step S32 and subsequent steps have not been processed, from among the combinations of the transportation plan proposal and the charging plan proposal created by the plan proposal creation unit 43 (S31).
[0113] Next, the plan proposal evaluation unit 44 evaluates the "delivery date delay" of the combination of the transportation plan proposal and the charging plan proposal selected in step S31 (hereinafter, this is referred to as a selected combination) (S32). Specifically, the plan proposal evaluation unit 44 uses various information stored in the baggage information table 31 (FIG. 3) and the transportation plan proposal information table 40 acquired in step S30, and calculates the following equation:
number
[0114] Here, the "deviation from the collection time frame" in formula (1) refers to the time difference between the collection time frame (available collection date and time 31E in the luggage information table 31) and the collection time in the proposed transportation plan (time 40G in the proposed transportation plan information table 40). For example, if the collection time frame is 1:00 to 3:00 p.m. and the actual collection time is 6:00 to 6:15 p.m., the time difference between the end time of the collection time frame and the actual end time of collection, which is 3 hours and 15 minutes, corresponds to the "deviation from the collection time frame."
[0115] Similarly, the “deviation from the delivery time frame” in equation (1) refers to the time difference between the delivery time frame (delivery date and time 31F in the package information table 31) and the delivery time in the proposed transportation plan (time 40G in the proposed transportation plan information table 40).
[0116] However, the delivery delay evaluation value is calculated by the following formula using each piece of information stored in the transportation plan information table 37 (FIG. 9) and the transportation plan information table 40:
number
[0117] Here, the “collection start time of the proposed transportation plan” and the “delivery start time of the proposed transportation plan” in equation (2) are obtained from the start time 40GA of the rows in the proposed transportation plan information table 40 whose statuses are “collection” and “delivery”, respectively, and the “collection start time of the original transportation plan” and the “delivery start time of the original transportation plan” are obtained from the start time 37GA of the rows in the proposed transportation plan information table 37 whose statuses are “collection” and “delivery”, respectively.
[0118] Next, the plan evaluation unit 44 evaluates the "operation time" of the selected combination (S33). Specifically, the plan evaluation unit 44 uses each piece of information stored in the transportation plan information table 37 and the transportation plan information table 40, and calculates the following formula:
number
[0119] Here, the "operating time of the proposed transportation plan" in formula (3) refers to the time difference between the time when the "departure" operation is performed in the proposed transportation plan (start time 40GA of the row with the status "departure" in the proposed transportation plan information table 40) and the time when the "arrival" operation is performed in the proposed transportation plan (start time 40GA of the row with the status "arrival" in the proposed transportation plan information table 40). Similarly, the "operating time of the original transportation plan" refers to the time difference between the time when the "departure" operation is performed in the original transportation plan (start time 40GA of the row with the status "departure" in the proposed transportation plan information table 37) and the time when the "arrival" operation is performed in the original transportation plan (start time 40GA of the row with the status "arrival" in the proposed transportation plan information table 37).
[0120] However, the operating time increase evaluation value is calculated by the following formula using various information stored in the vehicle information table 32 (FIG. 4) and the transportation plan information table 40.
number
[0121] Here, the “operation time of the proposed transportation plan” and the “operation time of the original transportation plan” in the formula (4) are calculated in the same manner as in the formula (3). In addition, the “upper operating time limit” is obtained from the upper operating time limit 32C in the vehicle information table 32.
[0122] Furthermore, the plan evaluation unit 44 evaluates the "deviation of operation time" of the selected combination (S34). Specifically, the plan evaluation unit 44 uses various information stored in the transportation plan information table 37 and the transportation plan information table 40, and calculates the following formula:
number
[0123] Next, the plan evaluation unit 44 calculates the following equation based on the parameters (weighting coefficients) previously set for each evaluation item of "delivery delay," "operation time," and "operation time deviation" stored in the evaluation information table 39 (FIG. 11), the delivery delay evaluation value calculated in step S32, the operation time evaluation value calculated in step S33, and the operation time deviation evaluation value calculated in step S34.
number
[0124] Next, the plan proposal evaluation unit 44 judges whether the overall evaluation value calculated in step S35 is better (smaller) than the current tentative solution (S36). If the plan proposal evaluation unit 44 obtains a negative result in this judgment, it proceeds to step S38.
[0125] On the other hand, if the determination in step S36 is affirmative, the plan proposal evaluation unit 44 stores the selected combination as a provisional solution (S37). Note that if the comprehensive evaluation value calculated in the immediately preceding step S35 is the first one calculated, the plan proposal evaluation unit omits step S36 and stores the selected combination as a provisional solution.
[0126] Furthermore, the plan proposal evaluation unit 44 determines whether or not all combinations of transportation plan proposals and charging plan proposals created up to that point have been completed, with no combinations of transportation plan proposals and charging plan proposals remaining unprocessed after step S32 (S38).
[0127] If the plan proposal evaluation unit 44 obtains a negative result in this judgment, it returns to step S31, and then repeats the processing of steps S31 to S38 while sequentially switching the combination of the transportation plan proposal and the charging plan proposal selected in step S31 to other corresponding combinations of the transportation plan proposal and the charging plan proposal that have not been processed in step S32 and after, until it obtains a positive result in step S38.
[0128] Then, when the plan proposal evaluation unit 44 eventually obtains a positive result in step S38 by completing calculation of the overall evaluation values for all combinations of transportation plan proposals and charging plan proposals created by the plan proposal creation unit 43, it terminates this plan proposal evaluation process.
[0129] (4) Screen layout (4-1) Transport plan display screen Fig. 17 shows an example of the configuration of a transportation plan display screen 50 displayed on the display device 15 by the plan evaluation unit 44 in step S6 of the transportation / charging plan creation and evaluation process described above with reference to Fig. 14. This transportation plan display screen 50 is configured to include a transportation schedule display area 51, a transportation route display area 52, and an evaluation result display area 53.
[0130] The transport schedule display area 51 displays the cargo transport schedule by each transport vehicle 3 in the transport plan that constitutes the combination (hereinafter referred to as the optimal combination) of the transport plan and the charging plan, whose overall evaluation value was finally saved as a provisional solution in step S37 of the plan evaluation process described above in FIG. 16, in a format similar to that of the transport plan information table 40 described above in FIG. 12.
[0131] In addition, the transport route display area 52 is provided with a pull-down menu button 55 and a vehicle name display field 56, and by clicking the pull-down menu button 55, a pull-down menu (not shown) can be displayed that lists the vehicle names of all transport vehicles 3 for which transport schedules have been created in the proposed transport plan that constitutes the optimal combination.
[0132] In the transport route display area 52, a desired transport vehicle 3 can be selected by clicking on the name of the vehicle 3 from among the vehicle names listed in the pull-down menu, and the name of the selected transport vehicle 3 (hereinafter referred to as the selected vehicle) is then displayed in the vehicle name display field 56.
[0133] Furthermore, when the desired transport vehicle 3 is selected as described above, a map (not shown) of the surrounding area of the transport route of the selected vehicle 3 is displayed in the transport route display area 52. Then, on the map, base marks 57 indicating the positions of each base 5 are displayed, and the transport route of the selected vehicle 3 is displayed with arrows 58.
[0134] Furthermore, in the evaluation result display area 53, the evaluation values (delivery date delay evaluation value, operation time increase evaluation value, and operation time deviation evaluation value) for each evaluation item ("delivery date delay", "increase in operation time", and "deviation in operation time") for the optimal combination, as well as the values of evaluation parameters (weighting coefficients) that have been preset for these evaluation items, are displayed in a table format.
[0135] Furthermore, on the transportation plan display screen 50, a display switch button 54 is provided to the right of the evaluation result display area 53, and by clicking this display switch button 54, the display screen of the display device 15 can be switched from this transportation plan display screen 50 to the charging plan display screen 60 shown in Figure 18.
[0136] The charging plan display screen 60 is configured to include a charging schedule display area 61 and an evaluation result display area 62. In the charging schedule display area 61, the charging schedule of each transport vehicle 3 that is a target in the charging plan constituting the optimal combination is displayed in a tabular format similar to the charging plan information table 41 described above with reference to FIG.
[0137] However, unlike the charging plan proposal information table 41, which was created for each charging base 5B (including a distribution base 5A having a charging stand), the table displayed in the charging schedule display area 61 has a base name column (a column marked "base name" in FIG. 18) for each record (row), and the base name of the charging base 5B where the corresponding charging stand is installed is displayed in this base name column, which is a difference from the charging plan proposal information table 41.
[0138] In addition, in the evaluation result display area 62, similar to the evaluation result display area 53 of the transportation plan display screen 50, the evaluation values (delivery date delay evaluation value, operation time evaluation value, and operation time deviation evaluation value) for each evaluation item for the transportation plan and charging plan that constitute the corresponding optimal combination, and the values of the evaluation parameters that have been preset for these evaluation items are displayed in tabular form.
[0139] Furthermore, on the charging plan proposal display screen 60, a display switch button 63 is provided to the right of the evaluation result display area 62, and by clicking this display switch button 63, the display screen of the display device 15 can be switched from the charging plan proposal display screen 60 to the transportation plan proposal display screen 50 described above with reference to Figure 17.
[0140] (4-2) Transport schedule display screen On the other hand, Figure 19 shows a transport schedule display screen 70 that is displayed on each of the on-board terminals 4 of each transport vehicle 3 based on the transport schedule transmitted from the plan evaluation unit 44 to each of the on-board terminals 4 of each transport vehicle 3 in step S6 of the transportation and charging plan creation and evaluation process described above with reference to Figure 14.
[0141] This transport schedule display screen 70 displays a transport schedule table 71 in which the transport schedule of the transport vehicle 3 on which the on-board terminal 4 is mounted is registered, from among the transport schedules of each transport vehicle 3 in the proposed transport plan that constitutes the optimal combination.
[0142] The transportation schedule table 71 includes a base name column 71A, a berth name column 71B, a status column 71C, an order number column 71D, a quantity column 71E, a time column 71F, and a progress column 71G. In the transportation schedule table 71, one record (row) corresponds to one status (departure, collection, delivery, charging, arrival, etc.) that the corresponding transportation vehicle 3 should perform at any of the bases 5.
[0143] The base station name column 71A, berth name column 71B, status column 71C, order number column 71D, quantity column 71E and time column 71F display information similar to the information stored in the base station name column 40B, berth name column 40C, status column 40D, order number column 40E, quantity column 40F and time column 40G of the record corresponding to the corresponding transport vehicle 3 in the transportation plan proposal information table 40 described above with reference to Figure 12.
[0144] Furthermore, the progress column 71G displays information indicating whether the corresponding transport vehicle 3 has completed the state corresponding to the record. In the example of Fig. 19, if the transport vehicle 3 has completed the corresponding state, the information "Complete" is displayed, and if the transport vehicle 3 has not completed the corresponding state, the information "Not yet" is displayed.
[0145] By displaying such a transport schedule display screen 70 on the in-vehicle terminal 4 of each transport vehicle 3, the driver of each transport vehicle 3 can easily check the upcoming transport schedule of the transport vehicle 3 he or she is driving and the progress of the transport schedule in real time, even if the transport plan is changed due to the occurrence of an unplanned event.
[0146] (4-3) Location schedule display screen On the other hand, Figure 20 shows a base schedule display screen 80 that is displayed on each of the plan management terminals 6 based on the work schedule of each base 5 transmitted from the plan evaluation unit 44 to the plan management terminal 6 of each base 5 in step S6 of the transportation and charging plan creation and evaluation process described above with reference to Figure 14.
[0147] This base schedule display screen 80 displays a base schedule table 81 in which schedules (hereinafter, referred to as work schedules) of each task (collection, delivery, charging, etc.) that each transport vehicle 3 defined in the transportation plan proposal and charging plan proposal constituting the optimal combination should perform at the corresponding base 5 are registered. Note that "task" here is synonymous with "state" described above.
[0148] This base schedule table 81 is configured with an order number column 81A, a vehicle name column 81B, a time column 81C, a berth name / stand number column 81D, a status column 81E, and a quantity column 81F. In the base schedule table 81, one record (row) corresponds to one operation performed for each transport vehicle 3 at the corresponding base 5.
[0149] The order number column 81A displays the order number of the order that is the subject of the corresponding work, and the vehicle name column 81B stores the vehicle name of the transport vehicle 3 that is the subject of the corresponding work. The time column 81C is divided into a start column 81CA and an end column 81CB, and the date and time when the corresponding work should start is displayed in the start column 81CA, and the date and time by which the work should be completed is displayed in the end column 81CB.
[0150] The berth name / station number column 81D displays the berth number of the berth or the station number of the charging station where the work should be performed, and the status column 81E displays the specific content of the work ("status"). Furthermore, the quantity column 81F displays the number of pieces of luggage for which the work should be performed.
[0151] In addition to or instead of the number of packages, all or part of the weight, volume, length, width, or height may be displayed on the base schedule table 81. Also, on the base schedule display screen 80, the charging schedule and the schedule of other work may be displayed separately.
[0152] By displaying such a base schedule display screen 80 on the planning management terminal 6 at each base, workers at each base can easily check the upcoming schedule for the work they are to perform in real time, even if the transportation plan is changed due to the occurrence of an unplanned event.
[0153] (5) Effects of this embodiment As described above, in the transportation plan creation system 1 of this embodiment, when an unplanned event occurs in a previously created transportation plan, the transportation plan creation device 2 creates multiple combinations of transportation plan proposals and charging plans that take the unplanned event into consideration, evaluates each of the created combinations of transportation plan proposals and charging plan proposals for three evaluation items, namely, "delivery date delay," "increase in operating time," and "deviation in operating time," and based on the evaluation results for these evaluation items, selects a more highly evaluated combination of transportation plan proposals and charging plan proposals as a new transportation plan and presents it to users such as transportation operation personnel, drivers of each transport vehicle, and staff at each base station.
[0154] Therefore, according to the present transportation plan creation system 1, it is possible to create the best new transportation plan (proposed transportation plan and proposed charging plan) that can reduce delivery delays of cargo, and operating times and deviations in operating times of transport vehicles, thereby creating a new transportation plan that reduces increases in logistics costs.
[0155] (6) Other embodiments In the above-described embodiment, the transportation and charging plan creation and evaluation functions of the present embodiment are described as being installed in one computer device constituting the transportation plan creation device 2. However, the present invention is not limited to this, and the transportation and charging plan creation and evaluation functions of the present embodiment may be distributed and installed in multiple computer devices constituting a distributed computing system.
[0156] In addition, in the above-described embodiment, a case has been described in which the proposed transportation plan out of the proposed transportation plan and the proposed charging plan finally selected as a new transportation plan is displayed on the proposed transportation plan display screen 50, and the proposed charging plan is displayed on the proposed charging plan display screen 60. However, the present invention is not limited to this, and the proposed transportation plan and the proposed charging plan may be displayed together on a single screen.
[0157] Furthermore, in the above-described embodiment, the plan proposal evaluation unit 44 selects one transportation plan and one charging plan as a new transportation plan. However, the present invention is not limited to this. A combination of multiple transportation plan proposals and charging plan proposals that are Pareto optimal may be presented to a user such as an operations staff member, and the user may be able to select a desired combination from among these presented combinations of transportation plan proposals and charging plan proposals.
[0158] For example, multiple sets of evaluation parameters for each evaluation item (e.g., delivery delay parameters, operating time increase parameters, and operating time deviation parameters, etc.) may be prepared, and the plan proposal evaluation unit 44 may extract optimal combinations of transportation plan proposals and charging plan proposals for each set of these evaluation parameters, display these extracted optimal combinations of transportation plan proposals and charging plan proposals, and allow the operations staff to select the desired optimal combination.
[0159] 16, a predetermined number of combinations (combinations of transportation plan proposals and charging plan proposals) with the highest overall evaluation values may be selected, not just the combination with the highest overall evaluation value, and these combinations may be displayed on the display device 15 together with their respective evaluation values and overall evaluation values, so that the operation staff may select (decide) the combination to be applied as a new transportation plan / charging plan, using the input device 14 or the like. The combination selected by the operation staff is notified to relevant parties via the screens or the like shown in FIGS. 17 to 20.
[0160] In the above embodiment, a case where a plurality of combinations of a transportation plan and a charging plan are created has been described, but the present invention is not limited to this. A plurality of combinations of a transportation plan and a supply plan for charging or replacing a battery of a transportation vehicle 3 required to prevent each transportation vehicle 3 from running out of power when the transportation plan is executed may be created. Information on a battery to be replaced can be input by, for example, storing a battery identification number in the station number and "replacement" in the charging mode in FIG. 7. In addition, when a plan to replace a battery is created, for example, "replacement" is stored in the state in the transportation plan information table 40 in FIG. 12, and the battery identification number is stored in the station number and the charge amount increased by the battery replacement is stored in the charge amount in the charging plan information table 41 in FIG. 13. Furthermore, an evaluation process and an output process may be performed on the combination of a transportation plan and a supply plan.
[0161] The present invention can be applied to a transportation plan creation system that recreates a previously created plan for transporting luggage using a transport vehicle made up of electric vehicles. [Explanation of symbols]
[0162] 1...transportation plan creation system, 2...transportation plan creation device, 3...transport vehicle, 4...on-board terminal, 5...base, 5A...collection and distribution base, 5B...charging base, 6...plan management terminal, 31...baggage information table, 32...vehicle information table, 33...base information table, 34...berth information table, 35...charging station information table, 36...travel cost information table, 37...transportation plan information table, 38...vehicle current status information table, 39...evaluation information table, 40...transportation plan proposal information table, 41...charging plan proposal information table, 43...plan proposal creation section, 44...plan proposal evaluation section, 50...transportation plan display screen, 60...charging plan proposal display screen, 70...transportation schedule display screen, 80...base schedule display screen.
Claims
1. A transportation plan creation system that recreates a previously created transportation plan for a cargo vehicle using a transportation vehicle including an electric vehicle, a plan creation unit that creates a plurality of combinations of a luggage transportation plan and a charging plan for the transportation vehicles, which transport the luggage to be transported and prevent the transportation vehicles from running out of power, based on the original transportation plan and the current remaining charge of each of the transportation vehicles; a plan evaluation unit that evaluates, for each combination of the created transportation plan and the charging plan, at least one of a delay in delivery of the goods and an increase in operation time of the transport vehicle, and selects a combination of the transportation plan and the charging plan based on an evaluation result; A transportation plan creation system comprising:
2. The plan evaluation unit includes: For each combination of the transportation plan proposal and the charging plan proposal created by the plan proposal creation unit, each evaluation item of a delay in delivery of the cargo, an increase in the operation time of the transportation vehicle, and a deviation in the operation time of the transportation vehicle is evaluated, the combination is comprehensively evaluated based on the evaluation results of each evaluation item, and a combination of the transportation plan proposal and the charging plan proposal is selected based on the comprehensive evaluation result.
2. The transportation planning system according to claim 1 .
3. The plan creation unit A combination of a proposed transport plan for the luggage and a proposed charging plan for the transportation vehicle is created by adding and / or changing a visiting base of the transportation vehicle, so that all of the luggage to be transported is transported and no transportation vehicle runs out of power.
2. The transportation planning system according to claim 1 .
4. The plan creation unit A combination of a transportation plan proposal for the luggage and a charging plan proposal for the transportation vehicle is created taking into consideration a travel cost between the bases in addition to a remaining charge amount of the transportation vehicle.
4. The transportation planning system according to claim 3.
5. The plan creation unit Manage weighting coefficients for each of the evaluation items that are set in advance; For each combination of the proposed transportation plan and the proposed charging plan, an evaluation value for each of the evaluation items is calculated, and a sum of multiplication results obtained by multiplying the evaluation value for each of the evaluation items by the corresponding weighting coefficient is calculated as an overall evaluation value representing an overall evaluation of the combination; A combination of the transportation plan proposal and the charging plan proposal is selected based on the overall evaluation value for each combination of the calculated transportation plan proposal and the charging plan proposal.
3. The transportation planning system according to claim 2.
6. Further comprising a display device for displaying information, The plan evaluation unit includes: Information regarding the selected combination of the transportation plan and / or the charging plan is displayed on the display device.
2. The transportation planning system according to claim 1 .
7. The plan evaluation unit includes: For each combination of the transportation plan proposal and the charging plan proposal created by the plan proposal creation unit, each evaluation item of a delivery delay of the luggage, an increase in operation time of the transport vehicle, and a deviation of the operation time of the transport vehicle is evaluated, the combination is comprehensively evaluated based on the evaluation results of each evaluation item, and a combination of the transportation plan proposal and the charging plan proposal is selected based on the comprehensive evaluation result; The information displayed on the display device includes an evaluation result for each of the evaluation items for the combination of the transportation plan plan and / or the charging plan plan selected as the transportation plan.
7. The transportation planning system according to claim 6.
8. The vehicle further includes an on-board terminal mounted on each of the transportation vehicles, The plan evaluation unit includes: Transmitting a transportation schedule for each of the transportation vehicles included in the selected combination of the transportation plan proposal and / or the charging plan proposal to the in-vehicle terminal of each of the corresponding transportation vehicles; Each of the vehicle-mounted terminals includes: Display the transportation schedule transmitted from the plan evaluation unit 2. The transportation planning system according to claim 1 .
9. The system further includes a planning management terminal installed at each base where the luggage is collected or delivered and / or the transportation vehicle is charged; The plan evaluation unit includes: Transmitting work schedules for each of the base stations included in the combination of the transportation plan proposal and / or the charging plan proposal selected as the new transportation plan to the plan management terminals of the corresponding base stations, Each of the planning management terminals includes: Display the work schedule transmitted from the plan evaluation unit 2. The transportation planning system according to claim 1 .
10. The replenishment plan includes at least one of a plan for charging a battery of the transport vehicle and a plan for replacing a battery of the transport vehicle.
2. The transportation planning system according to claim 1 .
11. A transportation plan creation method executed in a transportation plan creation system having a transportation plan creation device that recreates a previously created transportation plan for a package using a transport vehicle including an electric vehicle, comprising: A first step of creating a plurality of combinations of a proposed transportation plan for the luggage and a proposed charging plan for the transportation vehicle, which transport the luggage to be transported and in which no transportation vehicle runs out of power, based on the original transportation plan and the current remaining charge of each of the transportation vehicles; a second step of evaluating at least one of a delay in delivery of the cargo and an increase in operation time of the transport vehicle for each combination of the created transportation plan proposal and the charging plan proposal, and selecting a combination of the transportation plan proposal and the charging plan proposal based on an evaluation result; A transportation plan creation method comprising:
12. In the second step, the transportation planning system For each combination of the created transportation plan proposal and the charging plan proposal, each evaluation item, i.e., a delay in delivery of the cargo, an increase in the operation time of the transportation vehicle, and a deviation in the operation time of the transportation vehicle, is evaluated, the combination is comprehensively evaluated based on the evaluation results of each evaluation item, and a combination of the transportation plan proposal and the charging plan proposal is selected based on the comprehensive evaluation result. The transportation planning method according to claim 11 .
13. In the first step, the transportation planning system A combination of a proposed transport plan for the luggage and a proposed charging plan for the transportation vehicle is created by adding and / or changing a visiting base of the transportation vehicle, so that all of the luggage to be transported is transported and no transportation vehicle runs out of power. The transportation planning method according to claim 11 .
14. In the first step, the transportation planning system A combination of a transportation plan proposal for the luggage and a charging plan proposal for the transportation vehicle is created taking into consideration a travel cost between the bases in addition to a remaining charge amount of the transportation vehicle. The transportation planning method according to claim 13 .
15. In the first step, the transportation planning system Manage weighting coefficients for each of the evaluation items that are set in advance; For each combination of the proposed transportation plan and the proposed charging plan, an evaluation value for each of the evaluation items is calculated, and a sum of multiplication results obtained by multiplying the evaluation value for each of the evaluation items by the corresponding weighting coefficient is calculated as an overall evaluation value representing an overall evaluation of the combination; A combination of the transportation plan proposal and the charging plan proposal is selected based on the overall evaluation value for each combination of the calculated transportation plan proposal and the charging plan proposal. The transportation planning method according to claim 12 .
16. In the first step, the transportation planning system Displaying information regarding the combination of the transportation plan proposal and / or the charging plan proposal selected as the transportation plan The transportation planning method according to claim 11 .