Information processing apparatus, information processing method, and program

The information processing device accelerates the creation of equipment plans by forming partial problems and applying conditions to the equipment planning problem, addressing inefficiencies and errors in existing methods.

JP2024134200AActive Publication Date: 2024-10-03KK TOSHIBA
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023044389
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-20
Publication Date
2024-10-03
Estimated Expiration
2043-03-20

AI Technical Summary

Technical Problem

Existing methods for creating equipment plans for multiple facilities are inefficient and take excessive calculation time, especially when considering large-scale, long-term operations and the effects of facility combinations, with approximate solutions leading to significant errors.

Method used

An information processing device that creates partial problems by replacing some facilities with subsets, applies conditions based on partial problem solutions, and solves the equipment planning problem with added conditions to expedite the creation of equipment plans.

Benefits of technology

This approach reduces the time required to create equipment plans by limiting the solution search space and ensuring accuracy, particularly when considering resource consumption and facility combinations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024134200000001_ABST
    Figure 2024134200000001_ABST
Patent Text Reader

Abstract

To provide an information processing apparatus, an information processing method, and a program capable of increasing the speed for preparing a facility plan.SOLUTION: An information processing apparatus includes creation means which is configured to: create, by replacing a plurality of facilities with some of the plurality of facilities in a facility planning problem for creating a facility plan for operating an arbitrary facility selected from the plurality of facilities, a partial problem of the facility planning problem; create a condition to be applied to the facility planning problem based on a solution to the created partial problem; and create the facility plan by solving a facility planning problem with the created condition added thereto.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] An embodiment of the present invention relates to an information processing device, an information processing method, and a program. [Background technology]

[0002] In general, when a plurality of pieces of equipment exist, it is important to select and operate an appropriate piece of equipment from the plurality of pieces of equipment, rather than operating all of the plurality of pieces of equipment.

[0003] Furthermore, there are cases where the evaluation value obtained by an evaluation function such as cost or profit is improved by combining and operating a plurality of pieces of equipment rather than operating the equipment independently.

[0004] Specifically, for example, in truck delivery where trucks are operated as equipment, planning the routes of multiple trucks simultaneously rather than planning the routes of each truck independently (in order) makes it possible to divide the delivery area more efficiently, potentially increasing the number of delivery requests that can be processed (number of deliveries) and reducing the driving distance.

[0005] For this reason, it is useful to create a plan for the selection and operation of the above-mentioned equipment (hereinafter referred to as an equipment plan) and operate multiple pieces of equipment in accordance with the equipment plan.

[0006] In this case, it is necessary to consider an optimization problem for creating an appropriate equipment plan (hereinafter referred to as an equipment planning problem), but it is difficult to solve a large-scale equipment planning problem, such as creating a long-term equipment plan, within a practical calculation time. In addition, when multiple pieces of equipment are combined and operated as described above, the effect of the combination must be considered, which further increases the calculation time.

[0007] Approximation methods such as heuristics are often used to solve such large-scale optimization problems. However, when the cost of the facility is high, the impact of errors in the solution obtained by the approximation method is large, and the approximation method is not suitable for the facility planning problem described above. [Prior art documents] [Patent documents]

[0008] [Patent Document 1] JP 2016-143336 A Summary of the Invention [Problem to be solved by the invention]

[0009] Therefore, an object of the present invention is to provide an information processing device, an information processing method, and a program that are capable of speeding up the creation of facility plans. [Means for solving the problem]

[0010] An information processing device according to an embodiment includes a creation means for creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment, creating conditions to be applied to the equipment planning problem based on a solution to the created subproblem, and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added. [Brief description of the drawings]

[0011] [Figure 1] FIG. 2 is a block diagram showing an example of a functional configuration of the information processing apparatus according to the embodiment. [Diagram 2] FIG. 4 is a diagram showing an example of the functional configuration of an input unit. [Diagram 3] FIG. 4 is a diagram showing an example of the functional configuration of a partial problem creation unit. [Figure 4]FIG. 4 is a diagram showing an example of the functional configuration of a condition creating unit. [Diagram 5] FIG. 4 is a diagram showing an example of the functional configuration of an output unit. [Figure 6] FIG. 2 is a diagram showing an example of a hardware configuration of an information processing apparatus. [Figure 7] FIG. 1 is a diagram for explaining a mathematical model representing a facility planning problem. [Figure 8] 11 is a flowchart showing an example of a processing procedure of the information processing device in the first application example. [Figure 9] 13 is a flowchart showing an example of a processing procedure of an information processing device in a second application example. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0012] Hereinafter, an embodiment will be described with reference to the drawings. The information processing device of this embodiment is an electronic device (equipment plan creation device) configured to select any (appropriate) piece of equipment from a plurality of pieces of equipment and create an equipment plan for operating the selected equipment.

[0013] In this embodiment, the equipment may be a stationary object such as a generator that is operated (driven), or a moving object such as a truck or a person. The selection of equipment may mean selecting equipment to be newly introduced, or selecting equipment to be operated during a predetermined period (planned period) from among equipment that has already been introduced. The introduction of equipment may mean purchasing and installing equipment, or using equipment (for example, renting and hiring equipment).

[0014] In this embodiment, an equipment plan regarding the selection and operation of equipment is created. However, the equipment plan may be a plan regarding only the selection of equipment.

[0015] 1 is a block diagram showing an example of a functional configuration of an information processing device according to the present embodiment. As shown in FIG 1, the information processing device 1 includes an input unit 2, a storage unit 3, a facility plan creation unit 4, and an output unit 5.

[0016] The input unit 2 inputs an equipment planning problem (optimization problem) for creating the above-mentioned equipment plan. The equipment planning problem input by the input unit 2 is stored in the storage unit 3.

[0017] The facility plan preparation unit 4 has a function of preparing a facility plan using the facility plan problem stored in the storage unit 3 , and includes a sub-problem preparation unit 41 , a condition preparation unit 42 , and a solution finding unit 43 .

[0018] The subproblem creation unit 41 creates a subproblem that considers some of the multiple pieces of equipment from the equipment planning problem stored in the storage unit 3. In this embodiment, it is necessary to solve the equipment planning problem in order to create an equipment plan for selecting an appropriate piece of equipment from the multiple pieces of equipment, and the subproblem creation unit 41 creates a subproblem of the equipment planning problem by replacing a set of multiple pieces of equipment in the equipment planning problem (hereinafter referred to as an original set) with a subset that represents some of the multiple pieces of equipment. In other words, the equipment planning problem is an optimization problem that considers the original set, whereas the subproblem is an optimization problem that considers a subset different from the original set.

[0019] The condition creating unit 42 solves the sub-problem created by the sub-problem creating unit 41 and acquires a solution to the sub-problem. The condition creating unit 42 creates a condition to be applied to the facility planning problem based on (information relating to) the acquired solution to the sub-problem.

[0020] The processing of sub-problem creating section 41 and the processing of condition creating section 42 may be repeatedly executed while changing the subset to be considered.

[0021] The solution finding unit 43 solves the equipment planning problem to which the conditions created by the condition creating unit 42 have been added, and acquires a solution to the equipment planning problem. The solution to the equipment planning problem acquired by the solution finding unit 43 in this manner corresponds to the equipment plan created by the equipment plan creating unit 4.

[0022] The output unit 5 outputs the facility plan created by the facility plan creating unit 4 as described above.

[0023] Here, the facility planning problem input by the input unit 2 as described above includes, for example, condition information, evaluation function information, facility information, and operation information.

[0024] The condition information indicates constraint conditions for the facility planning problem. The evaluation function information indicates an evaluation function for obtaining an evaluation value when each of the multiple facilities is selected.

[0025] The equipment information is information related to the selection of equipment, and includes, for example, equipment resource information and equipment subset information. The equipment resource information is information related to resources consumed by the selection of equipment. Possible resources consumed by the selection of equipment include a budget (upper limit of costs) for the introduction of equipment. The equipment subset information is information related to the above-mentioned equipment subset, and includes, for example, equipment ranking information. The equipment ranking information indicates the priority order for each equipment subset. Note that the equipment subset may be composed of one equipment, or may be composed of two or more equipment. Furthermore, the equipment planning problem may include multiple pieces of equipment information.

[0026] The operation information is information related to the operation of the facility, and includes, for example, operation resource information. The operation resource information is information related to resources consumed by the operation of the facility. Examples of resources consumed by the operation of the facility include fuel for trucks in truck deliveries and delivery requests. Note that the facility planning problem may include multiple pieces of operation information.

[0027] In this embodiment, the input unit 2 shown in FIG. 1 may be configured to include, as shown in FIG. 2, a condition information input unit 21 for inputting the above-mentioned condition information, an evaluation function information input unit 22 for inputting evaluation function information, an equipment information input unit 23 for inputting equipment information, and an operation information input unit 24 for inputting operation information.

[0028] Also, in FIG. 2, an example is shown in which the input unit 2 includes a condition information input unit 21, an evaluation function information input unit 22, an equipment information input unit 23, and an operation information input unit 24, but at least some of the condition information input unit 21, the evaluation function information input unit 22, the equipment information input unit 23, and the operation information input unit 24 may be omitted (in other words, the input unit 2 may be configured to input some of the various information described above).

[0029] Although omitted in FIG. 2, the input unit 2 may be configured to further include at least some of, for example, a facility resource information input unit for inputting the above-mentioned facility resource information, a facility subset information input unit for inputting facility subset information, a facility ranking information input unit for inputting facility ranking information, and an operation resource information input unit for inputting operation resource information.

[0030] 1 may determine a subset (a part of a plurality of pieces of equipment) to be considered in a subproblem based on the above-mentioned equipment subset information. When a plurality of subproblems are created, subproblem creating unit 41 may determine the order in which the subproblems are created (solved) based on the above-mentioned equipment ranking information. Subproblem creating unit 41 may create a subproblem for each of the plurality of subsets.

[0031] Furthermore, sub-problem creating section 41 may include sub-problem information output section 411 and sub-problem information input section 412, as shown in FIG.

[0032] The sub-problem information output unit 411 outputs at least one of the condition information, the evaluation function information, the facility information, and the operation information included in the facility planning problem described above, for example.

[0033] The sub-problem information input unit 412 inputs information relating to the creation of a sub-problem in response to a user operation based on at least one of the condition information, evaluation function information, facility information, and operation information output by the sub-problem information output unit 411.

[0034] By using such sub-problem information output unit 411 and sub-problem information input unit 412, it becomes possible to create sub-problems interactively with the user.

[0035] Incidentally, some of the constraint conditions and the evaluation function in the subproblem created by subproblem creating section 41 may be different from the constraint conditions and the evaluation function in the facility planning problem.

[0036] Furthermore, the condition creating section 42 shown in FIG. 1 may include a condition information output section 421, a condition information input section 422, an initial value creating section 423, and a limit value creating section 424, as shown in FIG.

[0037] Condition information output section 421 outputs information relating to the solution of a subproblem that is obtained by solving the subproblem created by subproblem creating section 41, for example.

[0038] The condition information input unit 422 inputs information regarding the creation of conditions to be applied to the facility planning problem in response to a user operation based on information regarding the solution of the subproblem output by the condition information output unit 421.

[0039] By using the condition information output unit 421 and the condition information input unit 422, it is possible to interactively create conditions to be applied to a facility planning problem with a user.

[0040] The initial value creating unit 423 creates initial values ​​to be applied to the facility planning problem, based on the solutions of the subproblems created by the subproblem creating unit 41, for example.

[0041] The limit value creating unit 424 creates limit values ​​to be applied to the facility planning problem, for example, based on the evaluation values ​​in the subproblems solved by the condition creating unit 42.

[0042] That is, in this embodiment, the solution finding unit 43 solves a facility planning problem to which the above-mentioned conditions, initial values, and limit values ​​are added (applied).

[0043] 1 solves the subproblems and the solution unit 43 solves the equipment planning problem as described above, and a mathematical calculation solver such as Gurobi Optimizer or CPLEX may be used to solve such equipment planning problems and subproblems, or a metaheuristic solution such as a gradient method, simulated annealing or genetic algorithm may be used. When multiple pieces of equipment information and operation information are given as described above, multiple equipment planning problems based on each of the pieces of information may be solved, or one equipment planning problem based on a combination of the pieces of information may be solved.

[0044] The equipment plan (i.e., the solution to the equipment plan problem) created by the equipment plan creation unit 4 includes equipment to be selected from the multiple equipment (i.e., the appropriateness of the selection of each of the multiple equipment) and an operation plan for the equipment. In this case, the output unit 5 shown in Fig. 1 may be configured to include an equipment selection output unit 51 and an operation plan output unit 52 as shown in Fig. 5.

[0045] The facility selection output unit 51 outputs a facility to be selected from a plurality of facilities included in the facility plan. The operation plan output unit 52 outputs an operation plan included in the facility plan.

[0046] 5, the output unit 5 is described as including the facility selection output unit 51 and the operation plan output unit 52, but the output unit 5 may be configured to include, for example, only the facility selection output unit 51. In other words, the output unit 5 may be configured to output at least the suitability of each of the multiple facilities.

[0047] Furthermore, in the case where the equipment planning problem includes multiple pieces of equipment information or operation information as described above, the suitability of each of the multiple pieces of equipment based on the multiple solutions obtained by solving the equipment planning problem for each piece of equipment information or operation information, statistics of the multiple solutions, etc. may be output.

[0048] As described above, the subproblem creating unit 41 can create a plurality of subproblems, but the subproblem creating unit 41 may not create a subproblem that takes into account all subsets specified by, for example, equipment subset information, or may create a subproblem with different constraint conditions or evaluation functions. Furthermore, the subproblem creating unit 41 may create a subproblem based on information on solutions of subproblems that have already been solved. Furthermore, the condition creating unit 42 may not solve all of the subproblems created by the subproblem creating unit 41. Furthermore, the condition creating unit 42 may solve each of the plurality of subproblems after the plurality of subproblems are created by the subproblem creating unit 41, or may solve the subproblem each time the subproblem is created (that is, the creation and solving of the subproblems may be performed sequentially and repeatedly).

[0049] Fig. 6 shows an example of a hardware configuration of the information processing device 1. As shown in Fig. 6, the information processing device 1 includes a CPU 101, a non-volatile memory 102, a main memory 103, an input device 104, a display device 105, a communication device 106, and the like.

[0050] The CPU 101 is a hardware processor that controls the operation of each component in the information processing device 1. The CPU 101 executes various programs loaded from a non-volatile memory 102, which is a storage device, to a main memory 103. The programs executed by the CPU 101 include an operating system (OS) and a program for creating an equipment plan as described above (hereinafter, referred to as an information processing program), etc.

[0051] The input device 104 is a device configured to input various information, and includes, for example, a mouse and a keyboard, etc. The display device 105 is a device configured to display (output) various information, and includes, for example, a display, etc. The communication device 106 is a device configured to execute, for example, wired or wireless communication with an external device.

[0052] Although only the non-volatile memory 102 and the main memory 103 are shown in FIG. 6, the information processing device 1 may further include other storage devices such as a hard disk drive (HDD) and a solid state drive (SSD).

[0053] In this embodiment, some or all of the input unit 2, the facility plan creation unit 4, and the output unit 5 shown in Fig. 1 are realized by causing the CPU 101 shown in Fig. 6 to execute an information processing program, that is, by software. This information processing program may be downloaded to the information processing device 1 via a network, or may be stored in a storage medium and distributed. In addition, some or all of the input unit 2, the facility plan creation unit 4, and the output unit 5 may be realized by hardware such as an IC (Integrated Circuit), or may be realized by a configuration combining software and hardware.

[0054] 1 is realized by the non-volatile memory 102 shown in FIG. 6 or another storage device.

[0055] Incidentally, in this embodiment, it is assumed that an equipment plan is created that can obtain a higher evaluation value by combining and operating multiple pieces of equipment. However, if, for example, the equipment planning problem does not include resources consumed by selecting equipment (equipment resources) or resources consumed by operating the equipment (operation resources), a subproblem can be created by simply replacing the original set in the equipment planning problem with a subset, as described above.

[0056] On the other hand, when the capital planning problem includes capital resources or operational resources, subproblems may be created and solved by excluding elements related to those resources from the condition information (constraint conditions) and evaluation function information (evaluation function) included in the capital planning problem, or subproblems may be created and solved sequentially (i.e., repeatedly creating and solving subproblems) taking into account the consumption of capital resources or operational resources in partial problems that have already been solved (i.e., the consumed resources).

[0057] Hereinafter, a first and a second application example will be described as application examples to which the information processing device 1 according to the present embodiment is applied.

[0058] First, a first application example will be described. In the first application example, it is assumed that the facility planning is a plan for installing a generator, and partial problems are created and solved by excluding elements related to resources to be consumed from the condition information and the evaluation function information.

[0059] Specifically, in the first application example, a generator is installed as a facility, and electricity generated by the generator is sold in the balancing power market and the spot market. The balancing power market is a market in which balancing power is bought and sold. Balancing power is electricity that is activated in response to commands within a range not exceeding the contract amount from bidders, with power generation capacity equivalent to the contract amount secured on a daily basis in the balancing power market. Since power generation capacity equivalent to the contract amount must be secured at all times, the power generation capacity cannot be used for power generation to be traded in other markets such as the spot market.

[0060] In addition, the time required for the output to be changed from receiving a command to the command value (hereinafter referred to as the response time) is set for the adjustment capability. Generally, it takes time for a stopped generator to respond, so if the set response time is short, the output cannot be changed to the command value even if the stopped generator is operated after receiving a command, and adjustment capability cannot be supplied within that response time.

[0061] Considering the above circumstances, the generator is always operated, and further, the generator is operated not at the maximum generating capacity (rated output) of the generator, but by subtracting an amount equivalent to the regulating capacity. This makes it possible to supply the regulating capacity in a short response time when a command is received.

[0062] Generally, generators are most fuel-efficient when operated at rated output, and the lower the output, the worse the fuel efficiency becomes. However, the fuel efficiency and the degree to which the fuel efficiency worsens differ depending on the type of generator. Therefore, when multiple generators are operated in combination, instead of securing adjustment capability for each generator, it is considered possible to reduce costs by allocating adjustment capability to generators that have relatively good fuel efficiency even when the output is low.

[0063] In other words, the objective of the generator installation planning problem in the first application example (the optimization problem for creating a generator installation plan) is to select a generator to be installed from a collection of multiple types of generators with different specifications in a way that minimizes costs.

[0064] Below, we will explain the mathematical model that represents the generator installation planning problem in Application Example 1. In the mathematical model that will be explained below, it is assumed that a stopped generator cannot supply adjustment power.

[0065] Figure 7 shows the definition of symbols used to describe the mathematical model. In Figure 7, the subscript i represents a generator, d represents a date, and t represents a time slice. For example, C i and P i etc. correspond to facility information, and C´ dt , O dt , A dt etc. correspond to operational information.

[0066] Here, the following expressions (1) to (5) are some of the constraint conditions indicated by the condition information included in the generator installation planning problem.

number

[0067] Equation (1) expresses the constraint that only installed generators can operate. Equation (2) expresses the constraint that the generated electricity can be used to sell electricity in the spot market or activate the balancing capacity. Equation (3) expresses the constraint that the generating capacity of operating generators can cover the amount of electricity sold in the spot market and the contract amount in the balancing capacity market. Equation (4) expresses the constraint that the amount of activation of the balancing capacity does not exceed the contract amount in the balancing capacity market. Equation (5) expresses the constraint that the activation amount is the total command value for the balancing capacity minus the activation amounts of other bidders.

[0068] Moreover, the following formula (6) is an evaluation function indicated by the evaluation function information included in the generator installation planning problem.

number

[0069] Equation (6) shows an example of an evaluation function that can obtain costs as evaluation values. From the first term onwards, equation (6) shows the installation cost of the generator, fuel cost, sales amount in the spot market, sales amount for the activation of the adjustment power market, and the contract amount in the adjustment power market.

[0070] Hereinafter, an example of a processing procedure of the information processing device 1 in the first application example will be described with reference to the flowchart in FIG.

[0071] First, the input unit 2 inputs a generator installation planning problem as an equipment planning problem (step S1). In this case, the input unit 2 (condition information input unit 21 and evaluation function information input unit 22) inputs condition information indicating constraint conditions such as the above-mentioned formulas (1) to (5) and evaluation function information indicating an evaluation function such as formula (6). Furthermore, the input unit 2 (equipment information input unit 23) inputs, for example, a set of generators, the installation cost of each generator, and performance values ​​such as power generation efficiency for maximum and minimum loads and load factors as equipment information. Furthermore, the input unit 2 (equipment subset information input unit) inputs a subset consisting of one generator each as equipment subset information. Furthermore, the input unit 2 (operation information input unit 24) inputs fuel costs for each time slice and contract prices in the spot market as operation information. Furthermore, the input unit 2 (operation resource information input unit) inputs command values ​​and activation amounts of the entire adjustment power market as operation resource information.

[0072] The generator installation planning problem (the facility planning problem including the condition information, the evaluation function information, the facility information, the operation information, etc.) input in step S1 is stored in the storage unit 3 (step S2).

[0073] Next, the subproblem creation unit 41 creates a subproblem that considers, for example, only one generator based on the above-mentioned equipment subset information (step S3). The subproblem created in this way corresponds to a problem of determining whether or not it is appropriate to install a single generator i when the generator i is operated independently (i.e., whether or not the installation of the generator i is appropriate). In other words, the subproblem is created by replacing the set I of generators in the mathematical model representing the above-mentioned generator installation planning problem with a set consisting of only generators i.

[0074] Here, in this embodiment, it is assumed that if the introduction (selection) of equipment is appropriate when equipment is underestimated in a partial problem, it can be determined that the introduction of the equipment is also appropriate in the equipment planning problem. Note that in this embodiment, in a case where the evaluation improves (or at least does not decrease) by operating multiple pieces of equipment in combination, operating the equipment independently corresponds to the above-mentioned underestimation of the equipment. In other words, if there is an element that may cause an overestimation when operating the equipment independently (i.e., evaluating the equipment individually), a partial problem is created in which the element is excluded.

[0075] In this case, for example, the partial problem information output unit 411 outputs conditions and evaluation functions that span multiple generators including the generator i, conditions and evaluation functions that have a low relationship with the generator i, etc. Note that conditions and evaluation functions that have a low relationship with the generator i include, for example, conditions and evaluation function terms in which the generator i does not explicitly appear (i.e., do not include a subscript for the generator i).

[0076] Specifically, for example, θd in equation (5) among the above equations (1) to (5) is the activation amount of the entire adjustment power market excluding the activation amount of the generator installed by the user, and the actual power generation amount of the generator i is the sum of θd and the power generation amount of the other generators installed by the user subtracted from the command value Adt of the entire market. However, in the partial problem, only the generator i is taken into consideration, and the activation amount of the generator other than the generator i when the user installs a generator is ignored, so the activation amount of the generator i may be larger than the actual amount. In addition, equation (5) is a constraint condition for considering the fuel cost according to the activation amount of the generator i, and if the equation (5) is not adopted as a constraint condition, there is a possibility that the above-mentioned underestimation of the equipment will be violated (i.e., it may be overestimated).

[0077] In this case, by outputting the above-mentioned formula (5) (displayed on display device 105), sub-problem information input unit 412 inputs, for example, in response to a user operation, information regarding the creation of a sub-problem, that formula (5) is adopted as a constraint condition for the sub-problem. In this way, sub-problem creation unit 41 can create a sub-problem including formula (5) as a constraint condition, based on the input information regarding the creation of the sub-problem. Note that although a case where a sub-problem including formula (5) as a constraint condition is created has been described here, depending on the constraint condition, information regarding the creation of a sub-problem that does not adopt the constraint condition may be input by sub-problem information input unit 412, and a sub-problem not including the constraint condition may be created.

[0078] Furthermore, the partial problem information output unit 411 may output the formula (6). Here, for example, the value of the fourth term of the formula (6) may be larger than the profit obtained according to the actual activation amount, so that the fourth term of the formula (6) may be an element that may be overestimated. In this case, the partial problem information input unit 412 inputs, in response to a user's operation, information regarding the creation of a partial problem, for example, that the sales amount for the activation of the adjustment power market in the fourth term of the formula (6) is not included in the evaluation function. This allows the partial problem creation unit 41 to create a partial problem based on an evaluation function that does not include the fourth term of the formula (6).

[0079] In the above description, the partial problem is created based on information regarding the creation of the partial problem input by the partial problem information input unit 412. However, the partial problem creation unit 41 may automatically create a partial problem that excludes conditions, evaluation functions, etc. that have a low correlation with the generator i described above.

[0080] Next, the condition creating unit 42 solves the subproblem created in step S3 (step S4). When the subproblem is solved, the appropriateness of the installation of the generator i described above (i.e., whether the installation of the generator i is appropriate or not) is determined.

[0081] When the process of step S4 is executed, the condition creating unit 42 creates conditions, initial values, and limit values ​​to be applied to the generator installation planning problem, based on information related to the solutions of the subproblems (step S5).

[0082] Specifically, the information on the solution of the subproblem includes the solution of the subproblem (i.e., whether the installation of the generator is appropriate) and the evaluation value (evaluation function value) in the subproblem. In this case, for example, for a generator i whose installation is determined to be appropriate in the subproblem, the condition creating unit 42 creates a condition (γ i In addition, for the generator i whose installation is determined to be inappropriate in the partial problem, the condition creating unit 42 (initial value creating unit 423) creates an initial value (γ i =0). Furthermore, the condition creating unit 42 (limit value creating unit 424) creates the sum of the evaluation values ​​in the partial problems as the limit value (upper cost limit). The reason for setting the sum of the evaluation values ​​in the partial problems as the limit value is not only because the partial problems overestimate the amount of adjustment power to be activated (i.e., fuel costs) and do not take into account the sales amount for activation, but also because, as described above, by combining and operating multiple power generators, it is possible to efficiently ensure power generation capacity for adjustment power (i.e., costs can be further reduced), and therefore there exists a solution in the original problem whose evaluation value is smaller than the sum of the evaluation values ​​of the partial problems.

[0083] When a plurality of subproblems are created in step S3, the conditions, initial values, and limit values ​​may be created based on the solutions of the respective subproblems or on statistics of the evaluation values ​​of the respective subproblems.

[0084] Furthermore, the condition information output unit 421 may output solutions to subproblems and evaluation values ​​(or statistical values) for the subproblems, and the condition information input unit 422 may input information regarding the creation of conditions, initial values, and limit values ​​to be applied to the generator installation planning problem in response to user operation, so that the condition creation unit 42 may create the conditions, initial values, and limit values ​​based on the input information.

[0085] In the above description, the conditions, initial values, and limit values ​​are created. However, as will be described later, if the scope of the search for a solution to the generator installation planning problem (equipment planning problem) can be reduced, at least one of the conditions, initial values, and limit values ​​may be omitted.

[0086] The solution finding unit 43 solves the generator installation planning problem (facility planning problem) to which the conditions, initial values, and limit values ​​created in step S5 have been added (step S6). This makes it possible to reduce the range of the solution search, and reduce the time required for the solution search (i.e., solve the problem quickly), compared to solving the generator installation planning problem input in step S1 as is. Specifically, the range of the solution search can be reduced by half each time a condition that indicates that installation is appropriate for one generator is added.

[0087] When the process of step S6 is executed, an installation plan (facility plan) for the generator is created, and the output unit 5 outputs the installation plan for the generator (step S7).

[0088] Here, the generator installation plan (i.e., the solution to the generator installation plan problem) includes the suitability of the installation of each generator (γi) and the operation plan of the generator. In this case, the suitability of the installation of each generator is output by the facility selection output unit 51, and the operation plan of the generator is output by the operation plan output unit 52.

[0089] In addition, when multiple equipment information or operational information is included in the equipment planning problem, the appropriateness of installing a generator (equipment) based on multiple solutions obtained by solving the equipment planning problem for each piece of equipment information or operational information, as well as statistics regarding the multiple solutions, may be output.

[0090] In addition, it is assumed here that, for example, fuel costs, the electricity market contract price and contract amount, and the command value for adjustment capacity are determined, but if multiple pieces of operational information based on multiple scenarios with different reliability of estimation are input, it is also possible to solve an equipment planning problem for each piece of operational information and output statistics such as an expected value for the suitability of installing each generator based on the reliability.

[0091] As described above, in the first application example, the information processing device 1 creates a subproblem while ignoring benefits from resource consumption, and operates to underestimate the solution to the subproblem.

[0092] In the first application example, it is assumed that the equipment planning problem includes resources consumed by the selection of equipment and resources consumed by the operation of the equipment. If such resources are not included, however, a process of creating a subproblem by replacing the original set in the equipment planning problem with a subset can be executed in step S3 shown in FIG. 8.

[0093] Next, a second application example will be described. In the second application example, it is assumed that the facility plan is a truck delivery plan, and subproblems are created and solved sequentially while taking into consideration that facility resources or operational resources are consumed in subproblems that have already been solved.

[0094] Specifically, in the second application example, a truck is rented and used to deliver packages from a collection point to various locations. The location to which the package is to be delivered and the amount of packages to be delivered to that location (i.e., the demand at that location) are referred to as a delivery request. A maximum load (capacity) is set for a truck, and in truck delivery, a reward can be earned by processing delivery requests such that the sum of demands does not exceed that capacity. In addition, fuel costs according to the distance traveled by the truck are required for truck delivery.

[0095] Here, if the cost is the sum of the truck rental fee and fuel cost minus the sum of the reward obtained by processing the delivery request, the objective of the truck delivery planning problem in the second application example (optimization problem for creating a truck delivery plan) is to select the number of trucks to be rented so as to minimize the cost (i.e., maximize the profit obtained by subtracting the sum of the truck rental fee and fuel cost from the sum of the reward). In other words, the truck delivery planning problem is a problem of finding the minimum number of trucks required to process all of the delivery requests. However, if the rental fee for renting the minimum number of trucks exceeds the upper limit of the budget or if there is a route that is not worth the reward because the driving distance is too long, the truck delivery planning problem becomes a problem of finding the combination that maximizes the profit, taking into account the number of trucks possible within the budget and the delivery requests and routes that are worth the reward.

[0096] In truck delivery in the second application example, it is necessary to select the number of trucks to be borrowed, and at the same time, to assign delivery requests to the borrowed trucks and determine the order in which the delivery requests are to be processed (i.e., the route to visit the assigned points). If delivery requests are assigned to trucks in order and routes are determined, routes that visit points close to collection points or points with high rewards are selected preferentially, so planning deliveries by multiple trucks at the same time may determine a more efficient route, which may increase the total number of delivery requests that can be processed or reduce the mileage.

[0097] Hereinafter, an example of a processing procedure of the information processing device 1 in the second application example will be described with reference to the flowchart in FIG.

[0098] First, the input unit 2 inputs a truck delivery planning problem as a facility planning problem (step S11). Specifically, the input unit 2 (condition information input unit 21 and evaluation function information input unit 22) inputs, for example, condition information indicating constraint conditions for the number of rented trucks to depart and arrive at a collection point and evaluation function information indicating an evaluation function that can obtain the above-mentioned cost as an evaluation value. Furthermore, the input unit 2 (facility information input unit 23) inputs performance values ​​such as rental fee and capacity for each truck as facility information. Furthermore, the input unit 2 (facility resource information input unit) inputs a budget for renting trucks as facility resource information. Furthermore, the input unit 2 (facility subset information input unit) inputs a subset consisting of one truck each as facility subset information. Furthermore, the input unit 2 (facility ranking information input unit) inputs the priority of each truck assigned based on the ascending order of the ratio of the rented amount to the capacity as facility ranking information. Furthermore, the input unit 2 (operation information input unit 24) inputs, as operation information, fuel costs required for trucks to travel between each point, the point and demand in each delivery request (the point to which the cargo is to be delivered in each delivery request and the amount of cargo to be delivered), and the remuneration obtained by processing each delivery request, etc. Also, the input unit 2 (operation resource information input unit) inputs a set of delivery requests, etc. as operation resource information.

[0099] The truck delivery planning problem (a facility planning problem including condition information, evaluation function information, facility information, operation information, and the like) input in step S11 is stored in the storage unit 3 (step S12).

[0100] Next, the sub-problem creation unit 41 selects one truck with a low rental fee for the capacity based on the facility ranking information, and creates a sub-problem that considers only the selected truck (hereinafter, referred to as the target truck) (step S13). The sub-problem created in this way corresponds to a problem of judging whether it is appropriate to process some requests out of a set of delivery requests by borrowing only one truck of the target request (i.e., whether it is appropriate to borrow the target truck).

[0101] The condition creating unit 42 solves the subproblem created in step S13 (step S14).

[0102] When the processing of step S14 is executed, the remaining budget (new budget) is determined by subtracting the rental fee for the target truck from the budget, and the set of delivery requests excluding the delivery requests assigned to the target truck from the set of delivery requests is determined as the new set of delivery requests.

[0103] Next, it is determined whether a condition for terminating the creation of the subproblem (hereinafter, referred to as the termination condition) is satisfied (step S15). The termination conditions include, for example, that renting a truck is determined to be inappropriate in the subproblem (hereinafter, referred to as the first termination condition), that the rental fee for the next truck to be selected exceeds the remaining budget (hereinafter, referred to as the second termination condition), and that there is no delivery request to be assigned to the truck (i.e., the set of new delivery requests is an empty set) (hereinafter, referred to as the third termination condition).

[0104] If it is determined that none of the first to third termination conditions are satisfied (NO in step S15), the process returns to step S13 and is repeated. That is, in the second application example, in consideration of the fact that resources (here, budgets, delivery requests, etc.) are consumed by sequentially selecting or operating the multiple facilities, a process is executed in which multiple subproblems reflecting the consumed resources are repeatedly created and solved.

[0105] On the other hand, if it is determined that at least one of the first to third termination conditions is satisfied (YES in step S15), the condition creation unit 42 creates conditions, initial values, and limit values ​​to be applied to the truck delivery planning problem based on information regarding the solution of the subproblem (for example, the appropriateness of renting a truck and the evaluation value for that subproblem, etc.) (step S16).

[0106] Specifically, for example, when it is determined that the first termination condition is satisfied, the condition creating unit 42 creates a condition that trucks determined to be suitable for borrowing in each subproblem by repeatedly executing steps S13 and S14 as described above are suitable for borrowing in the truck delivery plan problem (original problem). In addition, the condition creating unit 42 (initial value creating unit 423) creates an initial value that determines that trucks other than those determined to be suitable for borrowing in each subproblem are not suitable for borrowing. Furthermore, the condition creating unit 42 (limit value creating unit 424) creates a limit value that is the sum of the evaluation values ​​in each subproblem.

[0107] On the other hand, if it is determined that the second or third termination condition is satisfied, for example, the condition creating unit 42 (initial value creating unit 423) creates an initial value that indicates that for trucks determined to be suitable for borrowing in each subproblem, borrowing is suitable for the truck delivery plan problem. In addition, the condition creating unit 42 creates a condition that for trucks other than those determined to be suitable for borrowing in each subproblem, borrowing is not suitable for the truck delivery plan problem. Furthermore, the condition creating unit 42 (limit value creating unit 424) creates a limit value that is the sum of the evaluation values ​​in each subproblem.

[0108] In addition, if it is determined that both the first termination condition and the second or third termination condition are satisfied, the processing that would be performed if it was determined that the first termination condition was satisfied is executed (i.e., the first termination condition takes precedence over the second and third termination conditions).

[0109] In addition, the condition information output unit 421 may output solutions to subproblems and evaluation values ​​for the subproblems, and the condition information input unit 422 may input information regarding the creation of conditions, initial values, and limit values ​​to be applied to the truck delivery plan problem in response to user operation, so that the condition creation unit 42 may create the conditions, initial values, and limit values ​​based on the input information.

[0110] In addition, although it has been described here that conditions, initial values, and limit values ​​are created, at least one of the conditions, initial values, and limit values ​​may be omitted if it is possible to reduce the scope of the search for a solution to the truck delivery planning problem (equipment planning problem), as will be described later.

[0111] The solution finding unit 43 solves the truck delivery plan problem (facility planning problem) to which the conditions, initial values, and limit values ​​created in step S16 have been added (step S17). This makes it possible to reduce the range of solution search compared to solving the truck delivery plan problem input in step S11 as is, and reduces the time required for the solution (i.e., solving the problem quickly).

[0112] When the process of step S17 is executed, a truck delivery plan (facility plan) is created, and the output unit 5 outputs the truck delivery plan (step S18).

[0113] Here, the truck delivery plan (i.e., the solution to the truck delivery plan problem) includes the suitability of renting each truck and the operation plan of the truck (for example, the route that the truck will travel, etc.). In this case, the suitability of renting each truck is output by the facility selection output unit 51, and the operation plan of the truck is output by the operation plan output unit 52.

[0114] In the second application example, multiple subproblems are repeatedly created while subtracting consumed resources, but if the equipment is not the same, the result (solution to the facility planning problem) will differ depending on the order in which the multiple subproblems are solved. For this reason, the second application example is suitable for solving facility planning problems where the equipment is the same or the priority order of the equipment is set.

[0115] As described above, in this embodiment, a subproblem is created by selecting any (appropriate) equipment from a plurality of equipment, replacing the plurality of equipment in an equipment planning problem for creating an equipment plan for operating the selected equipment with some of the plurality of equipment, creating conditions to be applied to the equipment planning problem based on the solution of the created subproblem, and creating an equipment plan by solving the equipment planning problem to which the created conditions have been added.

[0116] In this embodiment, with this configuration, it is possible to limit the scope of the search for a solution to an equipment planning problem by adding conditions to the equipment planning problem (original problem), thereby making it possible to speed up the creation of equipment plans (i.e., the solving of the equipment planning problem).

[0117] In this embodiment, when the equipment planning problem includes equipment resource information or operation resource information, a plurality of subproblems are created that reflect the resources consumed by sequentially selecting or operating a plurality of pieces of equipment. With this configuration, this embodiment makes it possible to create an appropriate equipment plan that takes into account the resources consumed.

[0118] Furthermore, in this embodiment, initial values ​​and limit values ​​to be applied to the capital planning problem are created based on the solutions of the subproblems. In this embodiment, by adding such initial values ​​and limit values, the range for searching for a solution to the capital planning problem can be further limited, so that the capital planning can be created even faster.

[0119] In addition, in this embodiment, when the equipment planning problem includes multiple pieces of equipment information, the equipment planning problem may be solved for each piece of equipment information. Similarly, when the equipment planning problem includes multiple pieces of operation information, the equipment planning problem may be solved for each piece of operation information. With this configuration, it is possible to obtain (output) the suitability of the equipment based on multiple solutions and its statistics.

[0120] Furthermore, in this embodiment, the equipment planning problem may include subset information, and the sub-problem may be created based on the subset information. The subset information may also include equipment ranking information indicating the priority of each subset. With this configuration, it is possible to create a sub-problem by selecting an appropriate subset from a set of multiple equipment (original set) in the equipment planning problem, making it possible to create a highly accurate equipment plan.

[0121] In addition, in this embodiment, the condition information, evaluation function information, equipment information, or operation information included in the equipment planning problem may be output, and a partial problem may be created based on information regarding the creation of a partial problem input in response to a user operation based on the output condition information, evaluation function information, equipment information, or operation information (i.e., a user operation performed after checking the information). Furthermore, in this embodiment, information regarding a solution of the partial problem (a solution to the partial problem and an evaluation value for the partial problem) may be output, and a condition may be created based on information regarding the creation of a condition applied to the equipment planning problem input in response to a user operation based on the output information regarding the solution of the partial problem (i.e., a user operation performed after checking the information). With this configuration, partial problems and conditions can be created interactively with the user.

[0122] In addition, in this embodiment, equipment to be selected from a plurality of pieces of equipment included in an equipment plan created by solving the equipment planning problem is output. In this embodiment, such a configuration allows the user to easily grasp the equipment to be selected from a plurality of pieces of equipment in the equipment planning problem. Note that in addition to the equipment to be selected from a plurality of pieces of equipment, an operation plan for the equipment may be further output.

[0123] Although some embodiments of the present invention have been described, these embodiments are presented as examples and are not intended to limit the scope of the invention. These embodiments can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the spirit of the invention. These embodiments and their modifications are included in the scope of the invention and its equivalents described in the claims, as well as in the scope and spirit of the invention.

[0124] The following supplementary notes are further disclosed regarding the above-described embodiment. [1] An information processing device comprising: a creation means for creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment, creating conditions to be applied to the equipment planning problem based on a solution of the created subproblem, and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added. [2] the facility planning problem includes facility resource information regarding resources consumed by selecting each of the plurality of facilities; The creating means creates a plurality of subproblems reflecting resources consumed by sequentially selecting the plurality of pieces of equipment based on the equipment resource information when the equipment planning problem includes the equipment resource information. [1] An information processing device according to the present invention. [3] the facility planning problem includes operational resource information regarding resources consumed by operating each of the plurality of facilities; The creation means creates a plurality of subproblems reflecting resources consumed by sequentially operating the plurality of facilities based on the operational resource information when the facility planning problem includes the operational resource information. [1] or [2]. [4] The information processing device according to any one of [1] to [3], wherein the creation means creates initial values ​​to be applied to the equipment planning problem based on the solutions of the subproblems, and solves the equipment planning problem to which the created initial values ​​have been added. [5] the facility planning problem includes evaluation function information indicating an evaluation function for obtaining an evaluation value when each of the plurality of facilities is selected, The creating means creates a limit value of the evaluation value to be applied to the equipment planning problem based on the solution of the partial problem, and solves the equipment planning problem to which the created limit value has been added. The information processing device according to any one of [1] to [4]. [6] the facility planning problem includes a plurality of facility information related to the selection of the facility, When the facility planning problem includes a plurality of pieces of facility information, the facility planning problem is solved for each piece of facility information. The information processing device according to any one of [1] to [5]. [7] The facility planning problem includes a plurality of pieces of operation information related to the operation of the facility, When the facility planning problem includes a plurality of pieces of operation information, the facility planning problem is solved for each piece of operation information. The information processing device according to any one of [1] to [6]. [8] the facility planning problem includes subset information regarding a subset representing a portion of the facilities among the plurality of facilities; The creating means creates the sub-problems based on the subset information. The information processing device according to any one of [1] to [7]. [9] The information processing device according to [8], wherein the subset information includes facility ranking information indicating a priority order for each of the subsets.

[10] the equipment planning problem includes condition information indicating constraint conditions for the equipment planning problem, evaluation function information indicating an evaluation function for obtaining an evaluation value when each of the plurality of pieces of equipment is selected, equipment information related to the selection of the equipment, or operation information related to the operation of the equipment, The creation means outputs the condition information, the evaluation function information, the facility information, or the operation information, and creates the partial problem based on information regarding creation of the partial problem input in response to a user's operation based on the output condition information, the evaluation function information, the facility information, or the operation information. The information processing device according to any one of [1] to [9].

[11] The information processing device described in any one of [1] to

[10] , wherein the creation means outputs information regarding a solution to the subproblem, and creates the conditions based on information regarding the creation of the conditions input in response to a user operation based on the output information regarding the solution of the subproblem.

[12] Further comprising an output means, the created facility plan includes a facility to be selected from the plurality of facilities, The output means outputs a facility to be selected from the plurality of facilities included in the created facility planning problem. The information processing device according to any one of [1] to

[11] .

[13] An information processing method comprising: creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment; creating conditions to be applied to the equipment planning problem based on a solution of the created subproblem; and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added.

[14] A program for causing a computer to function as a creation means for creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment, creating conditions to be applied to the equipment planning problem based on the solution of the created subproblem, and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added. [Explanation of symbols]

[0125] 1...information processing device, 2...input unit, 3...storage unit, 4...equipment plan creation unit, 5...output unit, 21...condition information input unit, 22...evaluation function information input unit, 23...equipment information input unit, 24...operation information input unit, 41...sub-problem creation unit, 42...condition creation unit, 43...solution finding unit, 51...equipment selection output unit, 52...operation plan output unit, 101...CPU, 102...non-volatile memory, 103...main memory, 104...input device, 105...display device, 106...communication device, 411...sub-problem information output unit, 412...sub-problem information input unit, 421...condition information output unit, 422...condition information input unit, 423...initial value creation unit, 424...limit value creation unit.

Claims

1. An information processing device comprising: a creation means for creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment, creating conditions to be applied to the equipment planning problem based on a solution of the created subproblem, and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added.

2. the facility planning problem includes facility resource information regarding resources consumed by selecting each of the plurality of facilities; The creating means creates a plurality of subproblems reflecting resources consumed by sequentially selecting the plurality of pieces of equipment based on the equipment resource information when the equipment planning problem includes the equipment resource information.

2. The information processing device according to claim 1.

3. the facility planning problem includes operational resource information regarding resources consumed by operating each of the plurality of facilities; The creation means creates a plurality of subproblems reflecting resources consumed by sequentially operating the plurality of facilities based on the operational resource information when the facility planning problem includes the operational resource information.

2. The information processing device according to claim 1.

4. 2 . The information processing apparatus according to claim 1 , wherein the creating means creates an initial value to be applied to the facility planning problem based on the solution of the subproblem, and solves the facility planning problem to which the created initial value has been added.

5. the facility planning problem includes evaluation function information indicating an evaluation function for obtaining an evaluation value when each of the plurality of facilities is selected, The creating means creates a limit value of the evaluation value to be applied to the equipment planning problem based on the solution of the partial problem, and solves the equipment planning problem to which the created limit value has been added.

2. The information processing device according to claim 1.

6. the facility planning problem includes a plurality of facility information related to the selection of the facility, When the facility planning problem includes a plurality of pieces of facility information, the facility planning problem is solved for each piece of facility information.

2. The information processing device according to claim 1.

7. The facility planning problem includes a plurality of pieces of operation information related to the operation of the facility, When the facility planning problem includes a plurality of pieces of operation information, the facility planning problem is solved for each piece of operation information.

2. The information processing device according to claim 1.

8. the facility planning problem includes subset information regarding a subset representing a portion of the facilities among the plurality of facilities; The creating means creates the sub-problems based on the subset information.

2. The information processing device according to claim 1.

9. The information processing apparatus according to claim 8 , wherein the subset information includes facility ranking information indicating a priority order for each of the subsets.

10. the equipment planning problem includes condition information indicating constraint conditions for the equipment planning problem, evaluation function information indicating an evaluation function for obtaining an evaluation value when each of the plurality of pieces of equipment is selected, equipment information related to the selection of the equipment, or operation information related to the operation of the equipment, The creation means outputs the condition information, the evaluation function information, the facility information, or the operation information, and creates the partial problem based on information regarding creation of the partial problem input in response to a user's operation based on the output condition information, the evaluation function information, the facility information, or the operation information.

2. The information processing device according to claim 1.

11. 2. The information processing device according to claim 1, wherein the creation means outputs information relating to a solution of the subproblem, and creates the condition based on information relating to the creation of the condition input in response to a user operation based on the output information relating to the solution of the subproblem.

12. Further comprising an output means, the created facility plan includes a facility to be selected from the plurality of facilities, The output means outputs a facility to be selected from the plurality of facilities included in the created facility planning problem.

2. The information processing device according to claim 1.

13. An information processing method comprising: creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment; creating conditions to be applied to the equipment planning problem based on a solution of the created subproblem; and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added.

14. A program for causing a computer to function as a creation means for creating a subproblem of an equipment planning problem for selecting any equipment from a plurality of equipment and creating an equipment plan for operating the selected equipment by replacing the plurality of equipment in the equipment planning problem with some of the plurality of equipment, creating conditions to be applied to the equipment planning problem based on the solution of the created subproblem, and creating the equipment plan by solving the equipment planning problem to which the created conditions have been added.

Citation Information

Patent Citations

  • Method and device for planning

    JP1995073158A

  • Method and apparatus for optimizing configuration of distributed energy system

    JP2016143336A

  • Operation planning method, operation planning device, and program

    JP2020065407A

  • Operation planning device, operation planning method, and operation planning program

    WO2020225848A1